Professional Documents
Culture Documents
Blowout Problems during appraisal Potential fatalities with significant Normal drilling precautions 2/2 Evaluate drilling program to
drilling with loss of circulation loss of asset Awareness of potential include loss of circulation
suggest risk of blow out during problems problems
the development drilling Pre-drilling seismic site survey Conduct peer review on drilling
of Gas Group 1 Projects
Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM
Platform Potential defficiemcy in piling Platform subsidence Plan to do a site survey with 1/2
Installation Potential capital cost the EPCI contractor after
implication on project contract award
Provided document from
neighboring area
Potential mishandling of platform Platform damage Normal precaution 1/2
in transit or during installation Schedule delay
Poor quality of fabrication Failure in service BP quality assurance and quality 1/2
control
Pipelaying Mishandling of 6” pipeline Potential damage to 12” line Part of bidding appraisal will 1/2 A complete evaluation of contractors
include consideration of the and subcontractors personnel during
competence and experience of BLEQ and technical bid evaluation.
subcontractors and adequacy of
vessel and equipment
Anchor handling Potential damage to 12” line (and Normal precaution 1/2 Pre-construction meeting with
other lines in the area?) Properly updated drawings parties involved
Update pipeline drawings
following the seabed survey
Tie-in Loss of containment Potential hydrocarbon release Depressurizing and degassing by 1/3 Ensure that SCA and BZZB
water flushing platforms are shut-in and
positively isolated
Develop procedure for
depressurising and degassing
Lifting to cut the 12” line Damage due to overstressing of the Part of bidding appraisal will 1/3 Evaluate competency of
12” line include consideration of the contractor’s pipeline installation
Previous incindent of 6” pipeline competence and experience of procedure. This should be
cracking (LLF-LLD). subcontractors and adequacy of approved by company’s pipeline
Condition of pipeline is not known vessel and equipment. specialist.
in detail, pressure test has been Consider use of SMART PIG to
done. determine the condition of the
HAZID REPORT FORM
Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM
Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM
Blow out during Expected frequent well Potential fatalities Normal well intervention procedure 2/2
workover intervention Major damage
Increases possibility of well
blowout
Rig moving into position and As above Both wells will be shut-in by 2/2 Compare with best BP world-wide
potential impact on operating well SCSSV during rig positioning for practice on rig approach.
major workover involving a towed
vessel
(All pipelines also shut-in and
depressurised) as required by NWJ
SIMOPS procedure
However, for wirelining and coiled
tubing involving self-propelled
vessel, normal production is
maintained. Vessel procedures will
define weather limitations that will
apply with agreement with BP rep.
Blow out during Potential problem of stuck drill Cost and schedule impact Reduce mud weight 2/2
drilling a third pipe due to pressure depletion Radioactive source stuck Redesign casing point to cover
well downhole both gas and depleted zone
Rig moving into position and Potential fatalities Producing wells are shut in
potential impact on operating Major damage until BOP is in place
well
Heavy lift associated with
drilling activity
Potential damage Dropped objects Major damage due to gas release Rig orientation such that 2/2
to export pipeline Drilling rig jackup legs from pipeline pipeline is away from drilling
Anchor handling rig approach
All potentially causing Conduct SIMOPS meeting
damage to export line
Loss of Process leak from Manifold Major damage to the platform, Means of leak detection limited 2/2 Consider use of ultrasonic leak
HAZID REPORT FORM
Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM
HP/LP InterfacesBetween wellhead and the Catstrophic failures of manifold 2 x 100% relief valve size for block 2/1
manifold system capacity
Slugging @ BZZB Arrival of slugs through pipelines Process Shutdown on high Vessel design pressure exceeds 1/2 Evaluate that B2C compressor
@ Test and Production Separator level normal running pressure of slug catcher is capable to handle
Liquid carry-over into gas pipeline the liquid carry-over
export line Compressor slug catcher and Provide all drawings of receiving
inlet scrubber facilities to EPCI contractor
Shutdown on BZZB should be
transmitted to host platform
Loss of Release from BZZB Process area Small increase of release because of As per BZNA (fusible plugs) 1/2 Some additional leak detection such
containment the additional control valve and the as sonic detection
piping as well as the small increase
of gas that could be released due to
the increase gas through-put
(although less than original
capacity)
Release from BZZB riser which is Major gas release from pipeline Frequent inspection of riser 2/2 Review adequacy of riser splash
currently empty Potential major damage to zone protection
platform Inspection of riser prior to
recommisioning and establish an
on-going inspection program
BZZB Gas line to BZZA/B2C Uncontrolled release of gas PSLL pressure trip will initiate 1/2 Consider the impact of increasing
(no change to the existing condition shutdown but only for major gas flow rate from 2 MM to 10
other than the increase of gas pipeline failure MM (potenial for initial large
through-put from 2 MM to 10 MM) volumeof liquid slugs)
Start-up procedure should
include consideration of such
effect on existing facilities
BZNA gas is low molecular
weight; impact on compressor
should be evaluated
HAZID REPORT FORM
Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM
Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION