You are on page 1of 13

HAZID REPORT FORM

Project: BZNA Date: 12/02/2001 Sheet No: 1 of


Drawing Nos
Area or System: Attendees:

Pre Drilling See Attendance List

GUIDEWORD EVENT DESCRIPTION CONSEQUENCES SAFEGUARDS No ACTION RECOMMENDED

Blowout Problems during appraisal Potential fatalities with significant  Normal drilling precautions 2/2  Evaluate drilling program to
drilling with loss of circulation loss of asset  Awareness of potential include loss of circulation
suggest risk of blow out during problems problems
the development drilling  Pre-drilling seismic site survey  Conduct peer review on drilling
of Gas Group 1 Projects

Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 2 of


Drawing Nos
Area or System: Attendees:
BZNA-M-PLR-002
See Attendance List
Construction of New Platform and 6” – 0.5 mile Pipeline

GUIDEWORD EVENT DESCRIPTION CONSEQUENCES SAFEGUARDS No ACTION RECOMMENDED

Platform Potential defficiemcy in piling  Platform subsidence  Plan to do a site survey with 1/2
Installation  Potential capital cost the EPCI contractor after
implication on project contract award
 Provided document from
neighboring area
Potential mishandling of platform  Platform damage Normal precaution 1/2
in transit or during installation  Schedule delay
Poor quality of fabrication Failure in service BP quality assurance and quality 1/2
control
Pipelaying Mishandling of 6” pipeline Potential damage to 12” line Part of bidding appraisal will 1/2 A complete evaluation of contractors
include consideration of the and subcontractors personnel during
competence and experience of BLEQ and technical bid evaluation.
subcontractors and adequacy of
vessel and equipment
Anchor handling Potential damage to 12” line (and  Normal precaution 1/2  Pre-construction meeting with
other lines in the area?)  Properly updated drawings parties involved
 Update pipeline drawings
following the seabed survey
Tie-in Loss of containment Potential hydrocarbon release Depressurizing and degassing by 1/3  Ensure that SCA and BZZB
water flushing platforms are shut-in and
positively isolated
 Develop procedure for
depressurising and degassing
Lifting to cut the 12” line Damage due to overstressing of the Part of bidding appraisal will 1/3  Evaluate competency of
12” line include consideration of the contractor’s pipeline installation
Previous incindent of 6” pipeline competence and experience of procedure. This should be
cracking (LLF-LLD). subcontractors and adequacy of approved by company’s pipeline
Condition of pipeline is not known vessel and equipment. specialist.
in detail, pressure test has been  Consider use of SMART PIG to
done. determine the condition of the
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 3 of


Drawing Nos
Area or System: Attendees:
BZNA-M-PLR-002
See Attendance List
Construction of New Platform and 6” – 0.5 mile Pipeline

pipe early after contract award


 The preffered method of subsea
tie in is without lifting the
pipeline, using smart flanges.
When pipe is cut, it may spring  Hazard to divers Pipecutting device does not require 1/3 As above
apart  Pipeline misalignment diver operation/presence
Pipehandling barge will handle re-
alignment of pipeline

Normal diving hazards Normal precautions 1/3

Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 4 of


Drawing Nos
Area or System: Attendees:
BZZB-MD-200
Construction on Existing Facility (BZZB) See Attendance List

GUIDEWORD EVENT DESCRIPTION CONSEQUENCES SAFEGUARDS No ACTION RECOMMENDED

Loss of Breaking into line containing Import gas line will be


containment hydrocarbon depressurised and degassed for 6”
subsea tie-in
Separator will be depressurised and
water discharge line flushed
Hotwork Potential ignition source Ignition of any hydrocarbon Consider replacing the control
releases from the operating plant assembly with a prefabricated spool
to minimize hotwork on the platform
Arrange for all hotwork to be done
during plant shutdown and
depressurization

Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 5 of


Drawing Nos
Area or System: Attendees:
BZNA-P-PFD-0001
Operation of New Facility (BZNA) See Attendance List

GUIDEWORD EVENT DESCRIPTION CONSEQUENCES SAFEGUARDS No ACTION RECOMMENDED

Blow out during  Expected frequent well  Potential fatalities Normal well intervention procedure 2/2
workover intervention  Major damage
 Increases possibility of well
blowout
Rig moving into position and As above Both wells will be shut-in by 2/2 Compare with best BP world-wide
potential impact on operating well SCSSV during rig positioning for practice on rig approach.
major workover involving a towed
vessel
(All pipelines also shut-in and
depressurised) as required by NWJ
SIMOPS procedure
However, for wirelining and coiled
tubing involving self-propelled
vessel, normal production is
maintained. Vessel procedures will
define weather limitations that will
apply with agreement with BP rep.

Blow out during Potential problem of stuck drill  Cost and schedule impact  Reduce mud weight 2/2
drilling a third pipe due to pressure depletion  Radioactive source stuck  Redesign casing point to cover
well downhole both gas and depleted zone
 Rig moving into position and  Potential fatalities  Producing wells are shut in
potential impact on operating  Major damage until BOP is in place
well
 Heavy lift associated with
drilling activity
Potential damage  Dropped objects Major damage due to gas release  Rig orientation such that 2/2
to export pipeline  Drilling rig jackup legs from pipeline pipeline is away from drilling
 Anchor handling rig approach
 All potentially causing  Conduct SIMOPS meeting
damage to export line
Loss of Process leak from Manifold  Major damage to the platform,  Means of leak detection limited 2/2  Consider use of ultrasonic leak
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 6 of


Drawing Nos
Area or System: Attendees:
BZNA-P-PFD-0001
Operation of New Facility (BZNA) See Attendance List

containment if ignited to low pressure (decreasing detector


 Potential fatality if the platform pressure?) detection  Procedure for boarding platform
is manned  Open well ventilated platform shall include gas detection as a
 Potential escalation to pipeline will help disposed gas released first priority
riser  Fusible plugs in instrument gas  Check with HSE dept on
system to initiate shut down procedure/criteria for offshore
 Two means of escape to evacuation
boatlanding platform  Procedure of detection and
 (Boat maybe 1-2 miles away at evacuation for injured people
another platform) (buddy system?)
 Platform operator carries  Main isolation valve need to be
personal radio with 13 miles operable in the event of possible
range fire exposure for 15 minutes
Riser leak outboard of the ESDV Uncontrolled release from pipeline  Host platform has an isolation 2/2  Ensure that there is appropriate
valve but no means of protection of the riser from
detection of release other than impact damage (e.g. supply boat)
low pressure at BZZB  BZZB platform needs to be
 Splash zone will have modified to send a signal to the
protection coating nearest manned platform
(BRAVO Flow station)
Pipeline leak  Uncontrolled release from  Fortuitous detection during 1/2  Chemical injection arrangement
Corrosion as the leak source pipeline routine travel between should include at least 2 times
 Gas and some condensate platforms 50% pumps on line
release to the environment  Corrosion inhibitor injection at  Chemical storage should be
 Hazard to passing ships/boats BZNA sufficient to allow continuous
 Valve isolation of 12” static operation between platform
line to avoid static line & water service
buildup  Consider high quality metallurgy
 6” line not pigable for 6” short line due to potential
 No means of detecting a leak pitting corrosion or line sizing to
directly. avoid water accumulation
 Regional emergency response  Consider the advantages of
plan & procedures in place pigging 12” line and ensure that
with the equipment at Citra new valve in the line is piggable
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 7 of


Drawing Nos
Area or System: Attendees:
BZNA-P-PFD-0001
Operation of New Facility (BZNA) See Attendance List

Ayu terminal located in the  Review the realistic pipeline


vicinity of Bravo area. leaks and the potential effect on
 Collaboration with MAXUS the environment (local fish and
(neighbouring PSC) for shrimp farm, etc.) for all pipeline
additional support of spillage locations (note that JJA and KKA
handling are very close to shore,
approximately 2 miles for JJA)
Leak from instrument gas system  Potentially up to 2” failure of  Maximum size 2” 1/3 Consider the merits of gas powered
production gas system  Potential escalation to main hydrolic system
 Increased frequency of gas production system
releases  ESDV on instrument gas
system
Normal venting of instrument gas Environmentally impact  Project requirement to 1/3 Consider the merits of gas powered
system minimize hydrocarbon venting hydrolic system
Leak of scale inhibitor or Hazard to personal and  Spill containment of the 1/3
corrosion inhibitor environment chemical skid is directed to the
slop tank
Structural failure Corrosion Structural collaps  Sacrificial anode protection 15 2/1 Anode should be welded to the
years design life structure
 Increased corrosion allowance
by 1/8” in the splash zone
 Major inspection of the
platform every 2-3 years,
topsides and subsea
Wind & waves Structural collaps  Design criteria is 2/1
simultaneously 100 years wind
and waves
 10 years wave occurrence,
fatigue design life 15 years
Seismic, earthquake  Structural collaps Ductility criteria 800 years 2/1 Consider providing seismic detector
 Potential failure of well recurrence interval and 0.2 g peak system to initiate shut down
conductors and loss of contain ground acceleration
hydrocarbon
Seabed foundation failure Structural subsidence  Previous problem with KL area Consider design detail to take into
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 8 of


Drawing Nos
Area or System: Attendees:
BZNA-P-PFD-0001
Operation of New Facility (BZNA) See Attendance List

platforms associated with account possible future sudsidence


reservoir depletion. This new (eg. relative movement between riser
platform areof similar geology and platform)
but of smaller reservoir
depletion hence risk of
subsidence can not be
discounted with risk relatively
low
 Current foundation design
based on typical soil data and it
is intended to carry out site
specific survey during detailed
engineering phase.
Ship Impact Attendant vessel Structural damage Design caters for potential energy 2/1
of attendant vessel impacts
Riser impact Riser currently shown as outside the 2/2 Consider pre-installing riser inside
platform structure the jacket structure
Passing vessel Structural failure  Platform is outside normal 2/1
shipping route
 No radar monitoring of
shipping traffic on manned
platform
Dropped objects Normal platform crane lift eg. Potential damage to hydrocarbon Crane, boat unloading area and 2/1 Confirm this is the case for the
chemical tote tanks equipemnt laydown area such that thereis no instrument gas skid
lifting over the main hydrocarbon
process area
Transport People arriving by boat Personal injury with potential  Life jacket is worn 2/2  Only trained personnel is allowed
fatality  Training available to embark/disembark the
 2-meter wave and 30-knot wind platform
limitations  Consider improvements to
 Water survival training landing space on the boat
 Consider medical certification as
a requirement for offshore visit
 Review of incident data on such
activities with a view to
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 9 of


Drawing Nos
Area or System: Attendees:
BZNA-P-PFD-0001
Operation of New Facility (BZNA) See Attendance List

investigating any improvement


that could be made
Security Platform equipment subject to Loss/damage to equipment. Consider the means of making the
damage and loss due to theft from platform facilities less
the facility (particularly in Potential threat to the vulnerable/accessible to theft.
consideration of its close integrity/safety of the installation. Consider also ensuring that any such
proximity to the shore) activity will not threatent the integrity
of the installation.
Other Uncertainty in BZNA gas Possible under prediction of Review data and consider impact of
composition condensate production higher condensate production
Shutdown philosophy ESD shutdown (including sub There is no means of remote shut
surface safety valve) of the down; consider the merits of remote
platforms is by the following shutdown in the context of
means: earthquake risk etc ?
Fusible plugs
Manual local push button initiation.

Process shutdown (without sub


surface valve) is also initiated by:
High & low pressure trips
High & low
Lifting equipment loss of power Suspended load or dropped object Review arrangement for safe load
during lifting handling in the event of loss of power
(for shallow water facilities, the
power supply is from the attending
supply boat which may be more
liable to cable damage in use)

Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 10 of


Drawing Nos
Area or System: Attendees:
BZNA-P-PFD-0001
Operation of New Facility (BZNA) See Attendance List
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 11 of


Drawing Nos
Area or System: Attendees:
BZZB-MD-200
Operation on the Existing Facilities (BZZB, BZZA, B2C, BC, B Process) See Attendance List

GUIDEWORD EVENT DESCRIPTION CONSEQUENCES SAFEGUARDS No ACTION RECOMMENDED

HP/LP InterfacesBetween wellhead and the Catstrophic failures of manifold 2 x 100% relief valve size for block 2/1
manifold system capacity
Slugging @ BZZB Arrival of slugs through pipelines  Process Shutdown on high  Vessel design pressure exceeds 1/2  Evaluate that B2C compressor
@ Test and Production Separator level normal running pressure of slug catcher is capable to handle
 Liquid carry-over into gas pipeline the liquid carry-over
export line  Compressor slug catcher and  Provide all drawings of receiving
inlet scrubber facilities to EPCI contractor
 Shutdown on BZZB should be
transmitted to host platform
Loss of Release from BZZB Process area Small increase of release because of As per BZNA (fusible plugs) 1/2 Some additional leak detection such
containment the additional control valve and the as sonic detection
piping as well as the small increase
of gas that could be released due to
the increase gas through-put
(although less than original
capacity)
Release from BZZB riser which is  Major gas release from pipeline Frequent inspection of riser 2/2  Review adequacy of riser splash
currently empty  Potential major damage to zone protection
platform  Inspection of riser prior to
recommisioning and establish an
on-going inspection program
BZZB Gas line to BZZA/B2C Uncontrolled release of gas PSLL pressure trip will initiate 1/2  Consider the impact of increasing
(no change to the existing condition shutdown but only for major gas flow rate from 2 MM to 10
other than the increase of gas pipeline failure MM (potenial for initial large
through-put from 2 MM to 10 MM) volumeof liquid slugs)
 Start-up procedure should
include consideration of such
effect on existing facilities
 BZNA gas is low molecular
weight; impact on compressor
should be evaluated
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 12 of


Drawing Nos
Area or System: Attendees:
BZZB-MD-200
Operation on the Existing Facilities (BZZB, BZZA, B2C, BC, B Process) See Attendance List

BZZB Liquid line to BC/B BZNA producing mainly water


Process liquid. The main impact is a small
increase in water separation load at
Junction

Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION
HAZID REPORT FORM

Project: BZNA Date: 31/08/2021 Sheet No: 13 of


Drawing Nos
Area or System: Attendees:

Abandonment See Attendance List

GUIDEWORD EVENT DESCRIPTION CONSEQUENCES SAFEGUARDS No ACTION RECOMMENDED

Wellhead abandonment – All


production casing will plugged
and abandoned (P&A).
The casing will be cut about 10
feet below the mudline
Remove the jacket and return it to
fabrication yard for reuse or
refurbishment
Remove pipeline from seabed and
dispose

Note that under SAFEGUARDS & ACTIONS consider in descending order of priority means of PREVENTION, CONTROL & MITIGATION

You might also like