Professional Documents
Culture Documents
GOVERNMENT OF KERALA
KANHANGAD
-KASARGOD(DIST)
2010-2011
SADGURU NITHYANANDA ASHRAMAM
GURUVANAM
A Survey camp report submitted in partial fulfilment for the award of
diploma in civil engineering
Submitted by
1. SUDHEESH K.P
2. SARATH V.V
3. SIRIL SHAHANAS
4. DIVYA V.V
5. VEENA K.V
6. SOUMYA K.P
7. NIMISHA M
8. ANEESH K
Page 1
Survey Camp Report S N P T C Kanhangad
CERTIFICATE
This is to certify that this survey camp report has prepared and
submitted by Sri./kum………………………………………
……………………………Reg . No………………………….of
second year student of Civil Engg. Under our guidance. This survey
camp conducted at Sadguru Nithyananda
Ashramam,Guruvanam,during the academic year 2011-2012
M.JAYACHANDRAN K.P.S.SUBHASH
Lecturer in Civil Engg. Head of department
S.N.P.T.C.Kanhangad Department of Civil Engg.
Page 2
Survey Camp Report S N P T C Kanhangad
ACKNOWLEDGEMENT
Page 3
Survey Camp Report S N P T C Kanhangad
INSTRUMENTS USED
2. DUMPY LEVEL
3. LEVELLING STAFF
4. PRISMATIC COMPASS
5. CHAIN
6. RANGING RODS
7. CROSS-STAFF
8. PEGS
9. ARROWS
Page 4
Survey Camp Report S N P T C Kanhangad
CONTENTS
1 Introduction……………………………………… - 6
2 Need and scope ……………………………….. - 7
3 Procedure for surveying……………………. - 8
4 Key plan……………………………………………. - 10
THEODOLITE TRAVERSING
1 Reference sketch…………………………………….. - 11
2 Stations & Included angles………………………. - 14
3 Corrected Included angles………………………. - 16
4 Calculation of bearings……………………………. - 18
5 Calculation of consecutive co-ordinates…… - 20
6 Correction for consecutive co-ordinates….. - 24
7 Corrected for consecutive co-ordinates…… - 26
8 Independent co-ordinates………………………. - 32
9 Gales traverse table………………………………… -
10 Area computation…………………………............ - 34
11 External area of the traverse…………………… - 35
CONTOURING
12 Introduction………………………………........ - 39
13 Tabulation & RL calculation……………… - 40
14 Contour Details………………………………… - 42
17 Camp diary……………………………………….. - 45
Page 5
Survey Camp Report S N P T C Kanhangad
INTRODUCTION
Page 6
Survey Camp Report S N P T C Kanhangad
Page 7
Survey Camp Report S N P T C Kanhangad
1. RECONNAISSANCE SURVEY
Page 8
Survey Camp Report S N P T C Kanhangad
4. REFERENCE SKETCHES
5 .TRAVERSING
In the survey camp traversing was done by using theodolite.This
method is used in land surveying, were great accuracy is required. in
this, the bearing of the first line is measured using prismatic compass. An
included angle at each traverse station is measured using theodolite by
using general method with face left conditions.
Our batch started works from station no:42 the work is proceded
in anticlockwise direction. The instrument is set up at '9.30am' and the
included angle between line 42-55 and 42-43is measured by face-left
readings. The distance between the instrument stations are measured
accurately with chain and tape. Readings was entered in tabular columns.
Page 9
Survey Camp Report S N P T C Kanhangad
KEY PLAN
Page
10
Survey Camp Report S N P T C Kanhangad
REFERANCE SKETCHES
E P- ELECTRIC POST
C- COMPOUND WALL
Page
11
Survey Camp Report S N P T C Kanhangad
L = Latitude or departure
Page
12
Survey Camp Report S N P T C Kanhangad
Page
13
Survey Camp Report S N P T C Kanhangad
Page
14
Survey Camp Report S N P T C Kanhangad
CHECK
Sum of measured angle = 3240˚16’25”
= 2 x (20-4) x 90
= 3240˚00’00”
= 00˚16’25”
Permissible error = c √n
= 20” √20
= 00˚01’29.44.7”
= 00˚00’49.25”
Correction = -00˚00’49.25”
Page
15
Survey Camp Report S N P T C Kanhangad
<55F,42,43 = 85°5’20”
<42,43,44 = 230°53’31”
<44,45,46 = 161°14’11”
<45,46,47 = 181°15’11”
<46,47,48 = 126°30’31”
<47,48,49 = 161°26’11”
<48,49,50 = 204°36’11”
<49,50,51 = 140°59’11”
<50,51,52 = 96°48’11”
<51,52,53 = 199°59’11”
<52,53,54 = 173°7’36”
<53,54,55 = 161°50’11”
Page
16
Survey Camp Report S N P T C Kanhangad
<54,55,55A = 18°12’31”
<55,55A,55B = 209°8’11”
<55A,55B,55C = 166°10’31”
<55B,55C,55D = 181°38’11”
<55C,55D,55E = 230°49’11”
<55D,55E,55F = 176°11’31”
<55E,55F,42 = 194°59’11”
Page
17
Survey Camp Report S N P T C Kanhangad
CALCULATION OF BEARINGS
Page
19
Survey Camp Report S N P T C Kanhangad
Page
20
Survey Camp Report S N P T C Kanhangad
Page
21
Survey Camp Report S N P T C Kanhangad
Page
22
Survey Camp Report S N P T C Kanhangad
TRANSIT RULE -
Page
23
Survey Camp Report S N P T C Kanhangad
Page
24
Survey Camp Report S N P T C Kanhangad
Page
25
Survey Camp Report S N P T C Kanhangad
Page
26
Survey Camp Report S N P T C Kanhangad
287.88
Page
27
Survey Camp Report S N P T C Kanhangad
Corrected latitudes:-
Page
28
Survey Camp Report S N P T C Kanhangad
Corrected departure:-
Page
29
Survey Camp Report S N P T C Kanhangad
Page
30
Survey Camp Report S N P T C Kanhangad
INDEPENDENT CO-ORDINATES
Independent co-ordinates of first point is assumed as 250,250
Lattitude:-
Independent co-ordinates of 42 = 250.00
DEPARTURES:-
Independent co-ordinates of 42 = 250
Page
31
Survey Camp Report S N P T C Kanhangad
Page
32
Survey Camp Report S N P T C Kanhangad
AREA COMPUTATION
Area of traverse using independent co-ordinates
X=250 221.20 205.00 175.08 148.72 125.80 114.13 109.82 103.77
248.70 250.00
261.77 250.00
2Δ = 1258133.79 - 1225540.92
= 32592.87
Δ = 16296.43
= 16296.43/4047
= 4.03 acre
Page
33
Survey Camp Report S N P T C Kanhangad
Where s = a+b+c
2 34
Area of trapezoid = 1 (a+b)h
2 13.5
1.TRIANGLE
Area = √37.25(37.25-34)(37.25-13.5)(37.25-27) 27
= 171.67m2
2.TRIANGLE
Area = √12.75(12.75-3.5)(12.75-12.5)(12.75-9.5)
3.TRIANGLE 12.5
Area = √49.75(49.75-3.5)(49.75-30)(49.75-34) 34
= 450.92m 30 3 .5
4.TRAPEZOID 13
Area = 1(13+12)30
2 12
2
= 375m
5 .TRAPEZOID 12
Page
34
Survey Camp Report S N P T C Kanhangad
Area = 1(10+12)27.5
2
= 324.5m2 10
6. TRAPEZOID 13.5
Area = 1(10+13.5)31.5
2
= 370.124m2 10
7. TRAPEZOID 12
Area = 1(10+12)35
2 10
= 385m2
8. TRAPEZOID 10
Area = 1(10+3.5)62.5
2 3.5
= 421.875m2
9. TRAPEZOID
= 560m2
8.5
10. TRAPEZOID 15
Page
35
Survey Camp Report S N P T C Kanhangad
Area = 1(15+12.5)37.5
= 515.625m2
12.5
11. TRAPEZOID 15
Area = 1(15+17.5)33.5
2
= 544.375m2 17.5
12. TRAPEZOID 23
Area = 1(23+17.5)34.5
2
= 698.525m2 17.5
171.67+97.88+450.92+375+324.5+370.124+
385+421.875+560+515+544.375+698.525
TOTAL = 4827.49m2
Page
36
Survey Camp Report S N P T C Kanhangad
PROFILE LEVELLING
CROSS SECTION
point to right are be plotted to Cross sections are run at right angle to the
fixedline along which the profile leveling is done .these sections are taken on
eitherof the center line .These sections are taken usually plotted with the
samehorizontal and vertical scale. A suitable datum line is drawn and
perpendicularlines are drawn to mark the levels of the various points on the
cross-section. Thepoint on the line is plotted to the left of the center point &
the right.
CONTOURING
Page
37
Survey Camp Report S N P T C Kanhangad
INTRTODUCTION
Page
38
Survey Camp Report S N P T C Kanhangad
Page
39
Survey Camp Report S N P T C Kanhangad
Page
40
Survey Camp Report S N P T C Kanhangad
CONTOUR DETAILS
DISTANCE
BS IS FS HI RL REMARK
STATION L M R
Line 42-43
42 2.325 77.665 75.34
0 0.445 77.22
Chainage at 12.5
0 1.15 76.515
8.8 2.46 75.205
7.6 3.545 74.12
Chainage at 20.7
0 2.495 75.17
CP 11.4 1.345 3.68 76.515 72.835
4.6 2.875 73.64
Line 43-44
43 0.995 74.155 76.66
Chainage at 13.7
0 0.255 73.9
CP 7.7 0.99 2.485 75.82 73.335
CP 6.6 1.92 3.05 75.255 72.205
4.1 3.445 71.81
6 3.2 72.055
Line 44-45
44 0.155 72.315 72.16
Chainage at 15.4
0 0.14 2.65 72.3 69.65
10.1 1.98 70.32
6 0.075 3.44 70.395 66.955
CP 14.4 1.55 1.78 68.505 66.725
CP 9.5 1.19 2.315 67.915 65.6
10.3 3.305 64.61
7.4 2.66 65.255
6.2 1.735 66.18
Line 45-46
45 1.12 67.765 66.645
Chainage at 23.2
0 0.395 67.37
7.3 1.71 66.055
5.9 2.975 64.79
11.4 2.92 64.845
CP 12.7 0.58 2.81 65.425 62.615
9.9 2.48 62.945
9.3 2.115 63.31
7.7 0.14 65.285
CP 10.9 1.69 3.49 66.975 63.485
7.9 0.39 66.585
11 3.9 63.075
Line 47-48
47 3.8 56.36 52.56
Chainage at 16.7
Page
41
Survey Camp Report S N P T C Kanhangad
0 1.18 55.18
12.4 2.93 53.43
9 3.275 53.085
Line 48-49
48 0.465 53.025 52.56
Chainage at 7.9
0 2.69 50.335
CP 11.2 1.46 2.8 48.765 50.225
8.5 0.6 48.165
7.6 2.7 46.065
3.7 3.57 45.195
6.9 3.155 45.61
Line 49-50
49 0.41 47.385 46.975
Chainage at 8.4
0 1.43 45.995
9.5 3.04 44.345
Line 50-51
50 1.805 45.88 44.075
Chainage at 15.2
0 0.52 45.36
6.7 2.65 43.23
Line 51-52
51 0.18 44.255 44.075
Chainage at 22.8
0 3.75 40.505
6 2.165 3.92 42.67 38.75
13 1.97 40.7
12.2 1.475 41.195
5.5 0.85 41.82
1.1 3.54 39.13
16.3 0.59 42.08
1 -0.3 42.97
2 0.85 41.82
3 -0.3 42.97
Line 52-53
52 1.795 40.899 39.095
Chainage at 68
0 3.115 37.784
4.5 2.87 38.029
2 -0.6 41.499
Line 53-54
53 1.39 42.415 41.025
Chainage at 1.9
0 0.75 41.665
3.6 0.74 41.675
2 0.12 42.295
Chainage at 22.9
0 0.88 41.535
1.9 0.82 41.595
Chainage at 41.7
0 -1.6 44.015
Page
42
Survey Camp Report S N P T C Kanhangad
Line 54-55
54 1.665 42.69 41.025
Chainage at 22.5
0 0.67 42.02
3.7 0.27 42.42
CP 2 3.18 -2.75 48.62 45.44
Chainage at 31.3
0 1.53 47.09
0.85 47.77
Line 55-55A
55 -0.05 49.11 49.16
Chainage at 2.3
0 2.82 46.29
4.7 2.67 46.44
1 -0.1 49.21
Chainage at 8.01
0 0.935 48.175
3.8 0.575 48.535
Line 55A-55B
55A 3.78 54.405 50.625
Chainage at 5.45
0 1.96 52.445
Chainage at 11.65
0 0.75 53.655
Line 55B-55C
55B 2.745 58.57 55.825
Chainage at 9.7
0 1.055 57.515
7 2.945 55.625
9.7 2.08 56.49
Line 55C-55D
55C 2.25 62.75 60.465
Chainage at
0 0.74 62.01
2.8 3.93 58.82
Line 55D-55E
55D 2.39 65.4 63.01
Chainage at
0 0.33 65.07
1.2 3.35 62.05
Line 55E-55F
55E 0.3 69.805 69.505
Chainage at
0 1.29 68.515
3.4 3.29 66.515
Line 55F-42
55F 0.02 74.81 74.79
Chainage at
0 1.03 73.78
4.5 2.96 71.85
Page
43
Survey Camp Report S N P T C Kanhangad
CAMP DIARY
First day
Camp work started at 10.00am. A reconnaissance survey was conducted
and key plan was drawn 52 traverse stations were fixed in the given plot.
Reference sketch of allpossible points were prepared work was closed at 5.00 pm
Second day
Theodolite traversing
After submission of key plan necessary instrumentswere issued and our batch
reached the given plot from 01-02 at 9.00am. the theodolite traversing was
started from station 51and it is preceeded in anticlockwise direction.For this the
instrument was set up over the station and all temporary adjustments are made.
The magnetic bearing offirst line is taken with the help of trough compass .The
horizontal included angle at each of the traverse stationand the help of
theodolite.All the distances are also measured by using chain. The work was not
completed.How even it wasclosed at5.pm.
Third day
The work was restarted at 9a.m and it is continued up to 5p.m
Fourth day
Being the angular error is within the permissible limit. We prepared the
Gale’s traverse table. The traverse is plotted by using independent co-ordinates
to a scale of 1:400. The area of traverse is calculated work is finished 5.00pm.
Page
44
Survey Camp Report S N P T C Kanhangad
Fifth day
Contouring
Sixth day
The work was restarted at 9 am and it is continued.It is closed at
5pm.
Seventh day
We reach the plot at 9.am and the remaining work in
continued. We stop the work at 5pm.
Eighth day
We continued the work from 9.to5pm.
Ninth day
Profile leveling
Page
45