Table of Contents
1.2 – Planning………………………………………………………………………………………………………………………7
1.3 – Implementation……………………………………………………………………………………………….……..…17
Change requests……………………………………………………………………………………………………….……17
Issues log ........................................................................................................................................................18
Project brief
The purpose of this project is to achieve the highest returns for our clients and to
deliver a client experience that is second to none in the industry in order to establish,
within five years, the MLR brand the highest ethical standards with best-in-breed
performance for clients.
Project title
Business plan
Project purpose
To achieve the highest returns for our clients and to deliver a client experience that is
second to none in the industry.
Max Lionel Realty was founded in 2008 by property developer Max Lionel. The
company currently employs approximately 100 people, 80 of whom are licensed real
estate agents.
Through its client agents, the organisation manages property sales and rentals (both
residential and commercial) on behalf of a range clients. The organisation also
separately engages in investment activities, such as property and land development.
The strategic context in which Max Lionel Realty will achieve its mission and vision is
through:
• engaging with customers and clients
• building goodwill and reputation for integrity
• supporting innovative thinking, management and leadership skills.
• creating a high-performing, highly profitable organisation.
Priority
None
Related projects
Project client/owner
The person who is providing the funds and has the ultimate authority over the
project.
Project manager
The project managers have responsibilities to manage the project on a day-to-day
basis.
Project status
The business has done on the WHS policy, the anti-discrimination policy and
procurement policy.
Special provisions
• A New Tax Systemſ Goods and Services Tax) Act 1999 Cwlth)
Project approvals
Add any signatures that are required for approval to proceed to the next phase.
Stakeholder analysis
consultancy fees
Wastage and
associated expenses
Paul Employee Managers/ staffs The increase of
incentives for numbers
performance in all of operational that
areas relevant to related
operational and training programs
strategic goals. completed
Wong Training need Managers/ staffs The decrease of
analysis and numbers
training on WHS of injuries
and
implementation of
recently launched
MLR WHS
management
system.
Jeep Regular coaching Managers/ staffs The increase of
numbers
of coaching sessions
completed.
Suree Manager, staffs Agents, clients and
Agents, clients and tenants understand
tenants the
policy of the
business
Mac Research potential Manager, staffs The cost can be
new suppliers. reduced
Project Title: Business Plan Project Client: Date: 6 Nov
2020
Version:
Project Sponsor: Project Manager: File Name: Page x of Y
Scott Haung John Lee
Communication plan
Project snapshot
Project snapshot
Name of project: Business Plan
Project purpose:
To achieve the highest returns for our clients and to deliver a client experience that
is second to none in the industry.
Deliverables with timeframes Stakeholders
The project will be held for 1 month William Son, Scott Haung, John Lee, Tom
Lee and Ammy
Resources Risks
• Cash flow • Resource limitations
• People • Deadlines
• Equipment • Budget
• Facilities • Technology
• software • legal and other constraints
Interdependencies Success criteria
Business will measure in each task by the
measurement that business provided
above to know about the successful of
business
Project Title: Business Plan Project Client: Date: 6 Nov
2020
Version:
Project Sponsor: Project Manager: File Name: Page x of Y
Scott Haung John Lee
1.2 - Planning
Project plan
Project title:
Business Plan
Project purpose
To achieve the highest returns for our clients and to deliver a client experience that is
second to none in the industry
Background and strategic context
The strategic context in which Max Lionel Realty will achieve its mission and vision is
through:
• engaging with customers and clients
• building goodwill and reputation for integrity
• supporting innovative thinking, management and leadership skills.
• creating a high-performing, highly profitable organisation.
Project objective
The purpose of this project is to achieve the highest returns for our clients and to
deliver a client experience that is second to none in the industry in order to establish,
within five years, the MLR brand the highest ethical standards with best-in-breed
performance for clients.
Assumptions
The company achieves the highest returns for our clients and to deliver a client
experience that is second to none in the industry
Constraints
Governance
Board of Directors
and CEO
Max Llanel
Project Manager
Accountable for the success of the project. Has the authority to commit resources.
Running the project on a day-to-day basis within defined authorities for cost and
schedule as agreed with the project sponsor/board.
Key stakeholders
Business needs to follow-up the process that has been done on this project. If there
are still some unsuccessful outcome, the business will need to solve that issue again
by considering working on another way
Schedule
Controls
Monitoring is only useful if it is built into the execution phase at the beginning. There
is no point to a monitoring activity of all the work has been completed already and all
the resources wasted. A system needs to be set in place for this during the planning
phase and followed up on strongly.
If the monitoring framework if clearly defined, then there may not be any need for
huge amounts of data collection. Too much irrelevant data will only create confusion
and add no value. Quality of data to ensure relevance needs to be the focus of any
data collection efforts.
Decide initially all acceptable methods of data collection. A wide variety can be used
including questionnaires, surveys and focus groups.
Those tagged with reporting should be told clearly who they are to report to. Reports
are tailored according to the management level they are being reviewed by.
A senior management team may only need high level timelines, results and resource
consumption data, while a middle management group or project team itself may
need minute details of each task achieved or delayed
Appendices
Business needs to follow-up the the process that has been done an this project. If
there are still some unsuccessful outcome, the business will need to solve that issue
again by considering to work on another way
Project approvals
Add any signatures that are required for approval to proceed to the next phase.
Gantt chart
Activity/task 1 2 3 4 5 7 8 9 10 11 12 13 14 15 16
Generate and gather
ideas
Collect feedbacks &
select
project topic
Working on Project
Proposal
Submit project proposal
Submit Report
Legend
If there are many tasks or stages in your project, you can identify them with a key or legend.
Task1 Task5
Task2 Task6
Task3 Task7
Task4 Task8
Activities schedule
Budget
Project Name:
Income Inc. GST Ex. GST
Sold houses 4,000,000
rent 800,000
Subtotal 4795050
Contingency (+10%) 479505
TOTAL 5274555
Project Title: Project client: Date:
Version:
Project Sponsor: Project File Name: Page of x of y
Manager:
John Lee
Risk register
Project details
Project Name: Project Name Business plan
Project Manager: John Lee
Risk details
Risk ID: 7
Raised by: Staffs
Date raised: 14 Nov 2012
Description of risk:
Loss of knowledge and capability through departing staff.
Likelihood of risk: Low Impact of risk: High
Risk mitigation
Preventative actions recommended:
Business should create appropriate HR policies and procedures in place.