Professional Documents
Culture Documents
Itatech Report 2019 Rebuild
Itatech Report 2019 Rebuild
Depending on the requirements of the 2.1 Application of the different 2.1.1 Mixed application of the different
individual future project (e.g. tunnel length, rebuild levels rebuild levels
anticipated duration of use or geological
conditions) different options for tunnelling During the project development process, Both, the remanufacturing or refurbishment
machinery specifications are available. the minimum requirements for the tunnelling level can be applied to different subassemblies
machinery are established to assure a safe and within the same machinery rebuild depending
Machinery can be specified to be all new or reliable excavation process. In many cases on the project specific requirements and
rebuilt tunnelling machinery, which could be the allowance for the use of rebuilt tunnelling associated potential technical, schedule
an alternative, with corresponding benefits for machinery with its associated benefits for and economic risks. A future project with a
environment, economy and schedule. environment, economy and schedule can short tunnel length in very abrasive ground
be a viable option, whereas the rebuild conditions may for example require the
In light of the intended future use it may not level is depending on the specific project higher level remanufacturing requirements
always be necessary to specify the highest and requirements. for cutterhead and screw conveyor while the
therefore most expensive level of rebuild. For • Remanufacturing is typically applicable lower level refurbishment requirements for
that reason, two levels of the rebuild process for future projects or applications where full gantry structures or hydraulic power packs can
are established, going back to different stages component lifetime and a “state-of-the-art” be sufficient.
of the product life cycle (Figure 1). set of requirements for the machinery exist.
Systems or sub-assemblies are employed 2.1.2 Combined configurations
The two levels of rebuild : at a different future project in the original
•R
emanufacturing (higher level establishing a configuration or with modifications. Common practice in the industry is also
full new live cycle for the product) to combine the allowance for the use of
• Refurbishment is typically applicable for
remanufactured tunnelling machinery with
•R
efurbishment (lower level extending the future projects or applications without special
the requirement of new condition for clearly
useful life of the product) challenges that can employ machinery that
specified sub-assemblies or components of
successfully completed a project with at least
a TBM or MTBM. This may be the result of
The minimum requirements for each of these comparable requirements. Systems or sub-
an assessment of the predicted geological
two rebuild levels are given within the guideline. assemblies are employed at a comparable
conditions or an operation risk analysis.
Individual manufacturers or rebuilders may future project in their predominantly original
offer additional measures to achieve a specific configuration.
Note : The term “new” means components
warranty. are of new manufacture and have
never previously been used. This can
also include new components of older
Raw material End of manufacture taken from the spare part
Manufacture Use
processing project stock of previous projects. For new
components from stock that are subject to
aging (e.g. seals, hydraulic hoses etc.) the
remaining life span should be a minimum
Refurbishment of two times the anticipated future project
duration.
the contract specifications or supply offer for a as separation of components that are generally 2.3 Refurbishment
machine. not reused such as seals.
The refurbishment is considered to be a “full
Such combined configurations are typically Step 2 : Cleaning includes removal of muck/ maintenance” and “repair or replace defective
applicable for “high profile” projects where soil/debris, de-greasing, draining of fluids, de- functions or parts” procedure, followed
extended component lifetime is needed and a rusting as well as removing of old paint. by a final functional test including full test
special set of requirements for the machinery documentation as per original build.
exists. Note : Depending on the previous use
of the tunnelling machinery additional The basic philosophy behind the refurbishment
2.2 Remanufacturing measures may be required for disassembly process is to extend the useful life of the
and cleaning (e.g. previous use in ground product.
The basic philosophy behind the conditions containing asbestos)
remanufacturing process is to establish a full
new life cycle for the product with sufficient life Step 3 : Inspection of single parts depends
to complete the intended future project. on the nature of the part and is either a
purely visual inspection or an inspection by
2.2.1 The remanufacturing process dimensional measurement or other testing (e.g.
crack testing methods, electrical test, pressure
The general remanufacturing process loss or leakage test etc.). The sorting of parts
consists of five major process steps into reusable, able to be reconditioned or not
(Figure 2) accompanied by a pre-defined reusable as a result of the inspection has to
Quality Assurance / Control procedure. be based on predetermined and documented
The remanufacturing process is in most criteria.
aspects, similar to the original process of first
Figure 4 : Gripper TBM after refurbishment ready to be
manufacturing. Step 4 : Reconditioning of parts may involve
used for the Erstfeld contract of the Gotthard tunnel after
similar or identical manufacturing steps to completing the Amsteg section of the Gotthard tunnel
those applied during manufacture of the new
Quality Assurance
part. Upgrades or improvements to more
1 - Complete disassembly down to the single part level recent technical solutions as well as structural
reinforcement may be part of the process
including replacement of individual parts by
2 - Cleaning of all parts
new ones.
3 - Inspection and sorting of all parts Step 5 : The reassembly process is identical
to the process of original first assembly
4 - Reconditionning of parts or replacement by new parts including using the same procedures and
tools. The final testing after reassembly
5 - Reassembly follows the identical procedure, test criteria
and documentation requirements as after the
original first assembly.
FINAL TESTING
Hydraulic, electric and pneumatic systems for face pressure control as well as soil conditioning systems for EPBs are considered to be of major
importance for a reliable and safe function of the tunnelling machinery.
REFURBISHMENT REMANUFACTURING
Oil reservoirs Visual inspection, cleaning Disassembly, cleaning, new seals, reassembly
REFURBISHMENT REMANUFACTURING
Cables > 1000 V Visual inspection, insulation test Visual inspection, insulation test
Cables < 1000 V Visual inspection, insulation test Visual inspection, insulation test
Cable drums > 1000 V Visual inspection Disassembly, cleaning, reassembly, electrical test
High voltage switchgear Visual inspection Disassembly, cleaning, reassembly, electrical test
Low voltage switchgear Visual inspection Disassembly, cleaning, reassembly, electrical test
Disassembly, cleaning, reassembly,
Transformers Disassembly, cleaning, reassembly, electrical test
electrical test
Disassembly, new bearings, reassembly,
Electrical motors Visual inspection, electrical test
electrical test
PLC hardware Functional test Replace obsolete parts, functional test
PLC software Functional test New, newest update
Sensors Visual inspection , functional test Visual inspection , functional test
Safety related parts Functional test New, functional test
For Slurry-TBMs, the compressed air regulation system for the air bubble is an integral part of the excavation and face support process. Its capacity
and status is of importance for the full functionality and control of the excavation process.
REFURBISHMENT REMANUFACTURING
3.4 Soil Conditioning Systems for EPB-TBMs (Earth Pressure Balance TBMs)
For EPB-TBMs, the installed soil conditioning system is an integral part of the excavation and face support process. Its capacity and the status is of
importance for the full functionality and control of the excavation process.
The layout and dimensioning of a soil conditioning system is depending on the anticipated ground conditions of the intended future use. Its suitability
has to be checked by the rebuilder.
REFURBISHMENT REMANUFACTURING
Visual inspection, new wear parts, Disassembly, new seals, new wear parts, reas-
Water supply system
functional test sembly, functional test
Visual inspection, new wear parts, Disassembly, new seals, new wear parts,
Air supply system
functional test reassembly, functional test
Disassembly, new pumps, controls and piping;
Conditioning materials supply system Visual inspection, cleaning, new wear parts
reassembly; functional test
Foam generators Visual inspection, cleaning, new wear parts New
The specific requirements set out in their design life in their first application, multiple 4.4 Cutterhead, excavation
Sections 4.1 to 4.6 shall be respected for use of a main bearing is acceptable given the tools and muck handling
both, the remanufacturing as well as for the following requirements : equipment
refurbishment level. •T
he operating hours of the main bearing
have not yet reached an estimated 50% of Parts and sub-assemblies of TBMs that
4.1 Shield Structures and the original design life of the bearing. are primary elements of the TBM – ground
parts of machinery acting as interaction, excavation and primary muck
•A
new lifetime calculation, that takes into
temporary ground support transport are highly project specific elements
account the “as experienced” load conditions
with an exposure to abrasive wear. Therefor
and hours of operation in previous use
Shield structures and parts of machinery (e.g. such elements are less suitable for multiple
taken from the TBM data recording system
roof support structures) acting as temporary uses on different projects.
and in addition to that, the anticipated
ground support during tunnelling operations •E
xcavation tools are considered to be
load conditions of the intended future use
must be checked by calculation (e.g. FEA) for consumable wear parts and should be
confirms the usability for the estimated hours
their ability to withstand the loads imposed by replaced by new for tunnelling machinery
of future use operation
the ground and groundwater for the intended rebuilds (refurbishment and remanufacturing),
future use taking into account information •A
full main bearing inspection and
unless a specific OEM rebuild procedure is
on future tunnel alignment and ground / reconditioning as required by the original
applied, as it is common practice for disc
groundwater conditions as provided by the bearing manufacturer or an equally qualified
cutters.
user. organization confirms the “ready to use”
condition. •C
utterhead structures are subject to abrasive
wear and high loads affecting the base
Specific test and reconditioning plans and
The minimum requirements for main bearing structure itself as well as the excavation
procedures for shield structure accompanied
inspection are : tool sockets which typically are integrated
by a written documentation are mandatory
into the base structure. Specific test and
minimum requirements. •M
easurement of axial and radial bearing
reconditioning plans and procedures for
clearance
the cutterhead structure accompanied by
4.2 Ground Support Installation •T
otal dismantling of the main bearing and a written documentation are mandatory
cleaning of all parts minimum requirements. Fixed wear
For unshielded tunnel boring machines where
•V
isual inspection of all main bearing elements protection elements should be replaced
equipment for rock support installation is
(raceways, rollers, cages, bolting threads and depending on their condition and considering
provided, the existing type and installation area
bull gear if an integrated part of the bearing) the intended future use or in any case when
of the rock support elements must be checked
rack testing of all raceways and bull gear if
•C 50% of the wear limit has been reached. In
to ensure it is in accordance with the intended
an integrated part of the main bearing addition the design of cutterhead structures
future use.
is strongly related to the anticipated ground
•D
ocumentation of results and conditions of the specific project. Ground
For shielded tunnel boring machines with recommendation of required remedial related design considerations such as
precast segment installation capability the measures if any excavation tool types and arrangement, disc
shield to lining interface (arrangement, stroke
cutter size and spacing, opening ratio, muck
and pad size of thrust cylinders) as well as As a minimum all seals (lip seals, O-rings) have flow, distribution of conditioning or flushing
the handling capacities and ergonomics of to be replaced when reassembling the main ports all have a major influence on the overall
the segment installation equipment must be bearing. Care has to be taken for appropriate structure. Therefore cutterhead reuse has to
checked to be in accordance with the intended corrosion protection. be justified by a qualified comparison of the
future use and segment design.
ground conditions of previous use and the
Note : A feasible option for main bearing intended future use.
4.3 Main Bearing reconditioning is regrinding of the
raceways and the installation of new •E
lements for primary muck processing and
The main bearing of a TBM is a high value core rollers. As a maximum value, 0.5mm is transportation such as stone crushers, screw
component of TBM or MTBM with a long lead typically considered to be the limit for conveyors, TBM belt conveyors or shield
time for replacement. Typical design life of a regrind depth. The readjustment of the slurry piping systems are subject to abrasive
TBM main bearing is 10.000 hours or more correct bearing clearance is part of the wear. Specific test and reconditioning plans
based on assumed loadings established from reconditioning process. Such operations and procedures for the individual structures
the anticipated operational conditions of the have to be done by a qualified bearing accompanied by a written documentation
intended TBM use. manufacturer and preferably by the original are mandatory minimum requirements. Fixed
However, due to the fact that the majority of bearing manufacturer. wear protection elements should be replaced
main bearings do not approach the limit of depending on their condition and considering
4.6 Documentation
5.2 WARRANTY
ITA Secretariat - c/o MIE2 – Chemin de Balexert 9 - CH-1219 Châtelaine (GE) - Switzerland
Tel: + 41 22 547 74 41 - Email : secretariat@ita-aites.org - Web : www.ita-aites.org