Professional Documents
Culture Documents
NSSPU-GP 44-40-1
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Contents
Paragraph Page
1 Introduction 1
2 Use of Language 1
3 Scope 2
5 General 4
5.1 Self-regulation and Audit 4
5.2 Isolating Authority Training and Competency 4
5.3 Modifications and New Facilities 5
Contents (cont’d)
Paragraph Page
Contents (cont’d)
Paragraph Page
9.6 Removal of Sludge, Scale and Hard Deposits 32
9.7 Removal of Trapped Oil or Vapour 32
9.8 General Ventilation 33
9.9 Artificial Lighting 33
Contents (cont’d)
Table Page
1 ETP/STP Approval Levels for Non-conformance 1
2 Minimum Recommended Isolation Standards for Predetermined
Risk Levels 9
3 Permitted Limits for Confined Space Entry and Work 28
Figure
1 Leak Testing Checklist 34
Addendum 1 Definitions
Addendum 2 Typical Valve Isolations Integrity Tests
Addendum 3 Safe Isolation and Reinstatement of Plant Flowchart
Addendum 4 TAR and Planned Intervention Pre-startup
Assurance Checklist
Addendum 5 Workplace Assessment Plan Template
Addendum 6 Assurance Protocol
1 Introduction
This is the first issue of Site Technical Practice (STP) 44-40-1. This Guidance on Practice (GP) is
based on Safe Isolation and Reinstatement of Plant (UKCS-SSW-001).
The purpose of this document is to define BP operating policy and procedures for the safe
isolation and reinstatement of plant or equipment from sources of hydrocarbons and other fluids.
A glossary of the terms used in the document is given in Addendum 1.
This document satisfies the requirements of BP Integrity Management (IM) Standard Element 6
Practices and Procedures; minimum requirements 6.1 and 6.2.
2 Use of Language
BP Group ETPs and North Sea STPs make use of should and shall terminology to communicate
the requirements of the practice. A non-conformance (or deviation) from these requirements
requires approval in accordance with Table 1 below.
There are 81 Defined Group, Segment and Strategic Performance Unit (SPU) ETPs, all of which
are represented as STPs. This STP is classed as a Segment Defined STP.
Each operating unit or project is required to maintain a register of approved deviations from ETPs
and North Sea STPs as described in North Sea SPU STP Development, Conformance and Control
(NSSPU-GP 00-0001).
All the requirements in the parent ETP are addressed in this STP, with exceptions recorded in the
ETP Change Register.
All text displayed as italic and coloured blue is termed commentary text and is supplementary
guidance to the requirements of the standard.
3 Scope
This practice applies to the preparation for isolation, mechanical isolation, reinstatement and leak
testing of process utility and drilling systems. It shall be followed at all BP UK upstream operated
sites, both onshore (excluding Grangemouth) and offshore, and applies to all process systems
including subsea pipelines and facilities.
For Drilling Operations, making and breaking of drill string and OCTG connections are
exceptions to this practice.
Special requirements for subsurface isolation of the hydrocarbon reservoir are detailed
in Breaking Containment (NSSPU-GP 10-36-1) and Zonal Isolation (NSSPU-GP 10-60-1).
This means that for any work on a xmas tree valve, the upstream isolation requirements (well)
shall be governed by NSSPU-GP 10-36-1, NSSPU-GP 10-60-1 and the downstream (topsides)
isolation requirements by this document.
For the isolation and reinstatement of plant and equipment from sources of electrical energy refer
to Electrical Procedures (UKCS-SSW-003).
5 General
5.1 Self-regulation and Audit
Periodic review of isolation-related activities including review of individual isolations
and review of overall isolation processes shall be undertaken. Such reviews may also include:
General compliance with this document and any local procedures
The assessment of non-compliant isolations and the extent of any approved deviations
Registers of competent Area and Isolating Authorities
The competency requirements for process isolations for the key positions within this document are
as follows:
Isolating Authorities
Initial training Classroom-based CBT and practical (2 days) in SIRP
Workplace Assessment: Before being deemed competent
to carry out process isolating duties, the IA shall have been assessed at
the workplace by a qualified CMAS Assessor.
The IA shall demonstrate by practical example that he is competent in
defining and implementing process isolations.
The process for carrying out workplace assessments is described in the
Safe Isolation and Reinstatement of Plant Workplace – Assessment
Plan (refer to Addendum 5)
Refresher training As defined in CMAS
Certificate (ICC)
Amendments shall not normally be made to isolations in place other than to allow testing of
equipment prior to return to service. Amendments may be made to improve the integrity of the
isolation with the approval of the AA. The reason for the amendment shall be recorded and the
PA advised of the change
Pressure relief valves shall only be isolated following the provision of an alternative means of
pressure relief
For short-term operational tasks such as corrosion coupon retrieval or filter replacements, where no
positive isolation is practicable or where the job duration is shorter than the time to install positive
isolation, then the ‘V’ value from Table 2 can be considered as
the minimum recommended isolation standard. These tasks shall be conducted using
a WCC and a local operating procedure.
Operating Pressure
Fluid Type
10barg >10barg <55barg 55barg
Process fluids and V = SVI V = SVI+B V = DBB+A
hazardous utilities I = SVI+A I = DBB+B I = DBB+B
Non-hazardous utilities V = SVI V = SVI+A V = SVI+B
I = SVI I = SVI+B I = SVI+B
Note: Pipework, including instrument lines of 3/4in nominal bore and below, can be treated
as for pressures less than 10barg.
V Valving required to permit the installation of blank flanges and spades (positive
isolation)
I Valving required to permit carrying out intrusive maintenance without positive
isolation (where positive isolation presents a greater risk)
A Use mandatory safeguards as on List A
B Use mandatory safeguards as on List B
SVI Single valve isolation
DBB Double block and bleed
Category A Category B
Mandatory Safeguards
(Low Risk) (High Risk)
Continuous gas monitoring (for hydrocarbon y y
systems only)
Pressure buildup to test valve integrity y y
Regular monitoring of isolation integrity y y
Control and prevent nearby work y y
Isolating Authority in attendance1 y y
Radio link to control room when breaking y
containment
Develop contingency plan against leakage y
Identify backup isolation valves, shutdown y
systems etc
Minimise task time y
Portable firefighting equipment available y
(for hydrocarbon systems only)
Minimise possibility of plant disturbance y
Table 2 Minimum Recommended Isolation Standards for Predetermined
Risk Levels
1
For Drilling system isolations the Rig Toolpusher or delegate shall perform this role.
Vessel nozzles should normally be left open to assist with free ventilation. Air movers or ducted
fans may also be used to create a flow of clean air through the vessel. If there is any likelihood of
fumes, water or other contaminant entering the vessel from sources other than the isolated
pipework while persons are inside, the need to blank off any affected nozzles shall be considered.
Blanks used for this purpose do not need to be pressure-rated. However non-pressure rated blanks
shall be clearly identified by either
a tag, painted circumference or other marking. In the case of tanks with ‘swan necks’, mechanical
plugs may be an option to prevent ingress of fumes etc.
The manway doors on a vessel being prepared for entry shall be removed last and reinstalled first
to reduce the risk of unauthorised entry.
Further details on confined space entry are given in Paragraphs 9.1 to 9.4.
Records bleed points for checking valve integrity. The operation of the bleed valves
to check integrity need not be recorded as an amendment on the ICC
Confirms that the isolations have been effected
Authorises any temporary de-isolations and isolations necessary for testing
Authorises and records de-isolation on completion of the task
The ICC shall show a complete list of isolations and valve tag numbers. A marked-up Piping and
Instrumentation Diagram (P&ID) or other suitable drawing shall be attached to the ICC, together
with a record of the Level 2 Isolation Risk Assessment where required.
Once work is in progress and subsequent Work Control Certificates are applied
for within the recognised framework of the Boundary Isolation, they can be added providing it is
clearly established that the existing isolation is appropriate for the task. However, this should be
avoided if possible and it is preferable to identify all activities when the Boundary Isolation is
being planned. Integrity of isolations within the boundary cannot generally be proven and, if this
is the case, the ICC should record this eg valve integrity not proven, this document is a record of
the valve status only.
Entry to a confined space within a Boundary Isolation requires separate Isolation and Entry
Certificates to be raised, and the implementation of additional security measures.
Boundary Isolations shall not be removed until all applicable WCCs have been cancelled.
If for any reason work on a particular piece of plant within the Boundary Isolation needs to be
suspended (eg whilst awaiting spares) then a separate isolation shall be implemented and an ICC
raised before the Boundary Isolation can be cancelled.
Where the de-isolation of Boundary Isolations is proposed, the AA shall ensure that all associated
WCCs have been cancelled and that equipment within the Boundary Isolation is in a safe
condition or adequately isolated.
When using a low-pressure gauge (<10 barg) to accurately measure Pressure Buildup (PBU) on an
isolation on a high-pressure system, a snubber (also referred to as a gauge saver) should be fitted
between the gauge and the system. Thus, if there is an unexpected pressure build-up, there is no
risk of overpressuring the gauge.
Typical valve isolation integrity tests for DBB and single valve isolations are described
in Addendum 2. It is important that all bleeds (vents/drains) are checked free from obstruction
prior to testing. It is also important to realise that a bleed which is hard-piped to a closed drain or
flare line will only provide single valve isolation from the drain/flare line (refer to Addendum 2).
On completion of checking valve integrity, a bleed valve should be left in the closed position,
unlocked to allow regular monitoring. A pressure gauge may be fitted to the bleed valve to
monitor for pressure buildup.
An isolation can only be considered to be of DBB standard if the integrity of both valves has been
proven.
If zero pressure buildup is not achievable when checking integrity of a valved isolation,
consideration shall be given to carrying out an assessment of risk to determine whether it is
acceptable to proceed. Additional precautions such as including additional isolation valves,
maintaining or exercising isolation valves or installing positive isolation may be required to
reduce the risk to an acceptable level.
Alternative methods of valve integrity testing may be considered where there are practical
difficulties in using the conventional method, providing that they have been endorsed by the
relevant Technical Authority.
Once the AA is satisfied with the integrity of the valved isolation and that the system is
depressurised, drained and purged if necessary, containment may be carefully broken either to
effect positive isolation or to perform the required task (taking into account all precautions
regarding HS, pyrophoric scale, Low Specific Activity (LSA) scale, Naturally Occurring
Radioactive Material (NORM) and residual nitrogen).
The extra security of untested but witnessed positive isolation, in addition to the valved isolation
used to effect it, is normally acceptable for most confined space entry tasks. However, for longer
term positive isolations (eg a week or more), or where the valved isolation used to effect the
positive isolation needs to be removed for operational reasons, then integrity testing of the positive
isolation is required. This shall be done by service leak testing or formal leak testing of the joint,
depending on the level of risk.
Where a single flare or vent valve forms part of an isolation it may not be possible to fully test
integrity. In this situation the valve cannot be considered as a reliable barrier and therefore an
isolation risk assessment shall be carried out to determine whether the task should proceed. In
some situations, carrying out a pressure fall off test on
the process side of such valves can help in assessing valve integrity depending on the valve type.
On sites where single valve isolation to the flare system is a common occurrence,
the OIM/Site Manager may chose to approve a generic risk assessment that outlines
the conditions and precautions required.
NUIs
It is recognised on NUIs that there may not be a permanent presence on the Installation whilst an
isolation is in place and that it may not be practicable to monitor on a shift basis. In this case on
first return to the NUI the isolation integrity shall be confirmed before continuing work on the
isolated equipment.
Gaskets containing asbestos which shall be handled and disposed of in accordance with the
guidance identified in Asbestos Management and Work with Asbestos (UKCS-SOP-010)
Explosions and fires caused by the sudden mixing of water with hot oil, either during steam
cleaning or on the admission of hot oil into systems which have just been steamed or flushed
with water and which have not been thoroughly drained and dried
Static electricity as an ignition source or electric shock during steam cleaning or high -pressure
water jetting if equipment is not earth bonded
Possible asphyxiation through personnel exposure to nitrogen
Accidental spillage and freezing effects of nitrogen
Before a tank or vessel is flooded with water, it shall be confirmed that its supporting structure is
capable of sustaining the weight. In addition, adequate run-down and draining facilities shall be
provided, as large volumes of water are usually necessary for these operations.
To avoid a buildup of a static charge when this method is used, water shall be added from the base
of the tank or vessel. If a hosepipe is used, the velocity shall be kept low until the end is
submerged, and the nozzle shall be electrically earthed. Flooding with water shall not be relied
upon to remove all petroleum vapour, liquid or solid residues.
It is possible to carry out hot work on the external surface of a water-flooded tank
or vessel without further removal of internal hydrocarbon residue providing the work is below the
water level and an appropriate level of risk assessment has been conducted.
Water used for displacing and removing liquid hydrocarbons will be heavily contaminated after
use. It shall be disposed of in an environmentally-responsible manner.
8.3.3 Steam
At onshore sites, steam may be available in sufficient quantities to permit its use for purging and
cleaning vessels, tanks and pipework. Steam is the most effective of the common media for this
purpose. It should be used at low pressure, not exceeding
1bar maximum.
Two methods of steaming may be employed; open or closed steaming:
Open steaming is used where the tank, vessel and its associated system is fully open to the
atmosphere
Closed steaming is used for closed vessels and their associated equipment.
During this operation, the temperature is raised allowing volatile liquids to vaporise and
disperse together with the bulk of the steam via a condensing system. The heavy constituents
can flow freely and be drained off with the condensed steam from the base of the system
For all but the largest vessels and tanks, sufficient steam should be available to raise the external
surface temperature to at least 95°C. Steaming should be continued until the condensate flowing
from the vessel is substantially free of hydrocarbon.
Steam may be used in the case of process vessels, small storage tanks and medium sized insulated
tanks. It is essential that following a period of closed steaming, adequate provision is made to
prevent damage due to a vacuum being drawn by condensation of steam. In large tanks, the rate of
condensation of steam is such that adequate purging is not possible.
After steaming, it is normal practice to cool down the equipment with copious quantities of water,
this gives an additional wash to help remove residual hydrocarbons.
Where residual material is left on the tank or vessel surface after prolonged steaming, such
residual material may still evolve vapour on application of heat, eg burning or welding. In such
cases, cold cutting may be employed or the internal surface kept thoroughly wet during the heating
operation.
All temporary steam hoses used shall be electrically bonded and earthed.
8.3.4 Air
Where it is not possible or practicable to use any of the foregoing methods, it may be necessary to
use air directly to ventilate equipment and remove hydrocarbon vapour.
When a decision is made to use this technique, every effort shall be made to pump out as much oil
and sludge as possible before opening the tank or vessel. Where practicable, forced ventilation shall
be used so that flammable vapour is cleared in the shortest possible time. During this purging
operation, the flammable range will be passed through, presenting an explosion hazard if an ignition
source is nearby. All electrical equipment used shall therefore be suitable for use in a Zone 1
Hazardous Area. Other equipment within the hazard range of flammable vapour shall be effectively
isolated.
Air movers shall be fitted at the roof or top manhole so as to pull air in at low level. Temporary
trunking may be needed to achieve high-level disposal. In order to minimise the emission of
gas/vapour when the lower manhole door is opened, the air movers shall be started up first to
obtain a slightly negative pressure before the lower manhole is opened.
Vapour issuing from shell manholes may give rise to a dangerous concentration in a bunded or
confined area and, under such conditions, no kind of ignition source is allowed. Removal of
vapour by air movers attached to the roof manhole is the recommended safe practice.
Care shall be taken when using natural draught ventilation during periods of calm weather at
onshore sites, since vapour released from tanks can travel considerable distances without being
dispersed. Due regard shall be taken of wind direction and the risk to adjacent premises or to the
public.
Owing to the possible presence of pyrophoric scale within tanks or vessels which have contained
sour crude or products, provision shall be made for continuous wetting of the internal surfaces by
means of water from one or more water fog nozzles inserted into the roof opening. The nozzles
shall be turned on first and the air movers opened immediately afterwards. A shell manhole shall
be opened after approximately 5 minutes operation, when the internals are thoroughly wet. With
the air movers still in operation, the fog nozzles shall then be removed and loose scale dislodged
with high-pressure water streams.
CAUTION: WHEN THIS METHOD IS EMPLOYED, THE WATER NOZZLES SHALL BE
EARTHED.
9.2 Planning
9.2.1 Introduction
Prior to planning any confined space entry all alternatives to avoid entry shall be considered.
Planning for confined space entry shall include the following:
Confined space hazard identification and Level 2 Risk Assessment (mandatory)
Gas testing and confined space inspection
Entry Certificate issue and validity
Procedures for control of work and non-compliance
Procedures for any non-compliance based on Level 2 Risk Assessment
Emergency response arrangements
Emergency response arrangements shall cover rescue, resuscitation and treatment of casualties.
Entry into confined spaces shall be strictly controlled to prevent persons being exposed to risks
associated with toxic and/or flammable fumes and vapours in the atmosphere, and with
atmospheres which may be deficient (or enriched) in oxygen.
The number of personnel entering a combined space shall be limited by the resources available to
deal with any potential emergency that may arise.
Prior to any entry into a confined space, the atmosphere shall be tested to determine the
precautions necessary, and an Entry Certificate issued. An Entry Certificate is not
a work permit and for all work a relevant Work Control Certificate is required.
Gas tests required for hot work may be carried out by the same person but shall be carried out
separately (ie the tests done for entry are not valid for the Work Control Certificate).
Access and egress should be considered in the event that a casualty may need to be evacuated in
an emergency. It would require a winch to vertically hoist an average person from a space below.
Wearing a harness and lifeline shall only be considered practicable if the nature of the confined
space is such that the attendant could hoist or drag out the person from the space if the latter were
immobilised, and if the rope would not impede an unassisted exit. Wearing only the harness
should also be considered.
A rescuer could attach the lifeline to effect evacuation of the person.
Procedures for entering confined spaces with and without Breathing Apparatus (BA) are described
in Paragraphs 9.3 and 9.5.
Awareness of this document and in particular the need to avoid entry into a confined space
whenever possible
Awareness of the site layout and the site emergency procedures
An understanding of the work to be undertaken, the hazards and the necessary precautions of
the WCC and associated paperwork. Where practicable all personnel involved in the work
should take part in the Level 2 Risk Assessment
Familiarisation with the site emergency procedures for the rescue and recovery of Entrants
Instruction in the communication methods to be used between the Attendant and Entrant
working in the confined space
The AA shall ensure that the Entry Attendant understands his duties and is competent to perform
them.
Entrants shall be briefed by the PA, Supervisor or Entry Attendant to ensure that they understand
the hazards of the task in hand, the signs, symptoms and consequences of exposure to those
hazards, and are aware of the emergency signal to be used by the attendant if evacuation becomes
necessary.
The Rescue Team Members shall receive approved Personal Protective Equipment (PPE) and
rescue equipment (including BA sets) and be trained in its use. They should be trained fire team
members.
New personnel shall not be assigned to the above tasks, unless under training and accompanied by
a competent person who is familiar with the hazards of confined space entry.
Note: Such assistance shall consist of readily available rescue and resuscitation
equipment and personnel trained in its use.
(4) Ensure that an adequate supply of respirable air is maintained whilst Entrants are inside the
confined space.
The Entry Attendant has a vital function to perform. Under no circumstance may the Entry
Attendant enter the confined space or leave his post whilst there are personnel inside.
9.3.2 Entrants
Entrants to the confined space shall:
Wear suitable PPE
Wear a harness and lifeline, if specified on the WCC
According to the type of work and the risk, take adequate rest periods out in the open air
Continuously monitor for oxygen, hydrocarbons and HS
This may be achieved by one of the Entrants wearing a Crowcon Triple meter
(or similar) to warn of hazardous conditions. If this should occur, the space should be vacated,
ventilated and re-tested until conditions have improved to within the limits set out on the Entry
Certificate.
9.5 Additional Procedure for Entry into Confined Spaces with Breathing Apparatus
9.5.2 Entrants
Entrants shall perform the duties listed in Paragraph 9.3.2. In addition, they shall wear approved
positive pressure BA and be trained in its use.
Notes: (1) Canister respirators shall not be used in any circumstances. Air-supplied
apparatus shall be used.
(2) All personnel expected to wear BA and carry out work at the same time shall
have passed a face shield fit test with the recommendation that they should be
clean shaven.
equipment and piping constructed from non-impact tested carbon steel materials with nominal
thickness of >3/4in (19mm),
(ie API 5L, A 106, A 105, A 216, etc). For non-impact tested carbon steel materials
with nominal thickness >3/4in, a Competent Person shall specify the minimum metal
temperatures for leak testing, based on requirements of either RP 42-1 or BS 5500. Sites are
advised to identify any systems containing non-impact tested carbon steel and prepare the
appropriate local test procedures.
Introducing nitrogen to a system introduces a large energy source, far greater than the energy stored
in an equivalent liquid leak test. To minimise this stored energy, vessels which normally operate
with a liquid level shall be water filled (ensure water filling of
the vessel is acceptable with respect to corrosion and scaling) prior to pressurising
with nitrogen.
Full flow pressure relief shall be available via Pressure Safety Valves (PSVs). It is acceptable and
appropriate for the PSVs on the Installation system/plant to be used for this purpose. However, if
full flow pressure relief is not available via a plant system,
then temporary PSVs shall be used. If full flow pressure relief is not provided then
a Level 2 Risk Assessment shall be undertaken to demonstrate that sufficient control
is in place to manage the HP/LP interface.
When a specialist contractor is contracted to carry out nitrogen leak testing rather than leak testing
with nitrogen quads or low volume pumps the following additional measures apply:
There will be a Pump Operator who will be in radio contact with the Leak Test Supervisor who
will monitor system pressure. The pumping unit will be manually shut down on the instruction
of the Leak Test Supervisor. The leak test crew shall have a written procedure for radio
protocol
There will be an automatic pump trip (Overpressure Protection Device (OPPD)) that will shut
down the pumping unit. The OPPD will be located close to the injection point so that it can
monitor the highest pressure that will be seen in the Installation system. Where the OPPD is
installed on a vessel, consideration should be given to the effect the vessel internals, ie the
demister pads, may have on the indicated pressure
If it has been identified that the leak test contractor will have to supply PSVs, consideration
should be given to the location that these PSVs would vent to in an emergency. The vent
location should be surveyed and approved by the Installation AA with guidance from the leak
test contractor on expected nitrogen plume
Acceptance of leak rates in the range between target and maximum allowable leakage
is by exception only and review by the appropriate Technical Authority. The review shall take
into account fluid type, location of joint and ventilation and subsequent monitoring programme.
If a bolted joint fails a leak test, the procedure and Leak Test Decision Tree in Hydrocarbon
Release Reduction (UKCS-SOP-012) should be followed.
10.8 Planning
A checklist summarising the key steps in planning and implementing a test is shown in Figure 1.
All leak testing shall be subject to Level 2 Risk Assessment unless conducted under a risk
assessed and approved Maintenance Routine or Operating Procedure.
When risk assessing the leak testing activity, as a minimum the following should
be considered:
Any parts inside the proposed envelope which may be adversely affected by the test pressure
(eg the maximum static pressure on a balanced pump seal)
Any interfaces with lower pressure systems or equipment (positive or double blocks and bleed
isolation shall be used with consideration given to locking open a vent path to prevent
overpressurisation)
The location and condition of screwed fittings within the test envelope
The stability of components such as expansion joints and spring hangers
The ability to control the rate of pressure rise and the ability to depressurise quickly
Connected high-pressure equipment such as accumulators or pulsation dampers
Need for additional piping support (and its subsequent removal after reinstatement) when items
are removed
The implications of Non-return Valves (NRVs) in the system in relation to pressurisation and
depressurisation
The provision of an emergency depressurisation route for large volume tests. This will ideally
be a remote operated blowdown valve which is an integral part of the leak test envelope and
which will operate automatically on an Installation trip and blowdown event. If this is not
possible, a manual blowdown route shall be identified and both the BP IA and the leak test
contractor shall be aware of its location
Whenever the test envelope extends beyond one site (eg pipelines), effective communication
including formal procedures shall be established between each site.
During turnarounds where a boundary isolation provides the isolation from the process (eg
reservoir and export line) the isolation standard used to carry out nitrogen leak testing within the
boundary may be relaxed to single valve isolation, subject to Level 2 Risk Assessment of the
hazards to work on the adjacent systems.
10.9 Preparation
The site shall be inspected by the PA to confirm that:
The equipment to be tested is free from any obvious flaws
All low-pressure attachments have been removed or effectively isolated
Pressure-indicating and pressure relief devices are secure and online, calibrated and set to the
appropriate pressure as necessary
Any temporary restraints are in place and sufficient to restrain movement on system failure
Vent and drain valves are in the correct position
The pressuring equipment and all associated fittings and connections are secure,
in sound condition and free from contaminants (eg diesel oil)
A maximum safe practicable distance should be maintained in all circumstances given the nature
and location of the pressurising medium.
Access will be prohibited for all personnel during pressurisation periods. Following pressurisation,
access to the test area will be prohibited until the pressure has stabilised. Access for leak detection
shall be restricted to essential personnel (minimum of two),
as specified on the WCC.
10.13 Depressurising
On completion of the test, the pressure should be reduced gradually and under controlled
conditions until atmospheric or desired operational pressure is reached.
The pressure shall be recorded following completion of the test and when isolation from the
pressure source and depressurisation/venting has taken place, prior to any other work starting on
the system.
Vents shall be opened at high points before draining liquids, to ensure that a vacuum is not drawn.
Where possible inert gases should be vented to the Installation flare and vent system or if this is
not practical, to a safe area where they will not affect personnel. Pressuring fluid may sometimes
be decanted into another test envelope in order to conserve pressuring medium. If it is necessary to
vent large volumes to atmosphere, a risk assessment of this activity shall be conducted and a
procedure developed detailing how personnel will be protected during such a depressurisation
event.
Clamps or bolts on bolted flanges shall not be loosened while the system is still under pressure.
Clamps shall only be removed by competent persons who have been trained in the appropriate
procedures.
Checks shall be made to ensure that no part of the envelope retains any trapped residual pressure,
eg behind non-return valves or check valves.
NUIs
It is recognised that for NUIs where a permanent presence does not exist, the ability to monitor
will depend on the length of stay and timing of subsequent visits. The flange tagging process
(refer to Paragraph 7.3) shall still be applied and the monitoring process followed as far as is
practicable, with a final check and removal of the flange tags being made at least on the next
return visit to the site.
A management of change assessment involving the appropriate TA shall be used to assess the
risks, review and capture deviations from piping specifications, and ensure that the joints are
recorded on a reverse integrity test joints register. Factors to consider in the risk assessment
include:
The locations of pipe support arrangements and joints adjacent to those being assembled
Any history of system leak test failures due to leaks from joints other than those for
which the leak test was performed
Addendum 1
Definitions
Term Definition
Blank/Blanking The installation of a piping specification rated device such as a blind flange,
spade (blind) or spectacle blind (reversible spade) for the purpose of
achieving positive isolation.
Boundary Isolations A set of isolations which define the boundaries of a discrete process
envelope.
Breaking Containment The opening up of process/utility systems for any reason, including
inspection, repairs or modifications, where there is a risk from egress of
toxic, flammable or otherwise dangerous materials.
Breathing Apparatus A device which ensures that the wearer has a continuously available supply
of uncontaminated air through a face mask, helmet or mouthpiece.
Canister Respirator Respiratory equipment consisting of a face piece attached to a canister
which contains a filter absorber to remove specific contaminants. It has no
separate supply of air.
Cold Work The carrying out of any task, or the use of any tool or equipment which will
not produce a source of ignition (refer also to Hot Work). It includes the use
of tools for erection, dismantling and cleaning, which are not liable to
produce incendive sparks, and operations such as drilling, tapping and
cutting carried out in such a way as to limit the heat produced and keep the
temperature of the tools and work below 100°C.
Combustible Gas An instrument designed to measure the concentration of
Indicator flammable gas.
Competent Person A person who, by reason of his or her training, knowledge, experience and
judgement is considered by management to be capable of carrying out a
specific task or activity.
Containment Systems Systems (eg transmission pipelines, pipework generally, tanks and vessels)
either pressurised or atmospheric, used for the storage and/or conveyance of
gases, liquids, slurries or mixtures thereof.
Flammable (synonymous Refers to any substance, solid, liquid, gas or vapour, which is
with Inflammable) easily ignited. The addition of the prefix ‘non’ indicates that the
substances are not readily ignited but does not necessarily indicate that they
are non-combustible.
Flammable Limits The limits of combustibility of flammable vapours when mixed with air
(refer to Upper Flammable Limit and Lower Flammable Limit).
Definitions
May 2009 Issue 1 Add 1-1
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Term Definition
Flash Point The lowest temperature to which a liquid can be heated to give off sufficient
vapour to form a mixture with air that can be ignited momentarily in
prescribed laboratory apparatus.
Gas Free A tank is considered to be gas free when the concentration of flammable
gases is within safe prescribed limits. The term gas free does not imply
absence of toxic gases or sufficiency of oxygen for vessel entry.
Hazardous Area An area in which there exists, or may exist, a hazardous atmosphere.
Hazardous Atmosphere An atmosphere containing flammable gas or vapour in a concentration
capable of ignition. (The term refers exclusively to hazards arising from
ignition. Where there is hazard from other causes such as toxicity,
asphyxiation or radioactivity, this is specifically mentioned.)
Hazardous Utility Corrosive, toxic or irritant chemical fluid, nitrogen, steam or hot water,
drilling mud, diesel oil, Aviation Turbine Kerosene (ATK) and other fluids
that could have an environmental impact.
Hot Work This includes welding or the use of any flame or electric arc or the use of
any equipment likely to cause heat, flame or incendive spark. It also
includes caulking, chipping, drilling, riveting and any other heat-producing
operation, unless it is carried out in such a way as to keep the temperature
below 100°C and unable to create or ignite a flammable atmosphere (refer
to Cold Work).
Incendive Spark A spark of sufficient temperature and energy to ignite a flammable gas.
Isolation A method of preventing the passage of fluids through connecting pipework
in order to allow safe access to vessels or other intrusive equipment
maintenance.
Leak Testing The application of a pressure differential to detect leakage paths or leakage
rates. The pressure applied, liquid or gaseous, may be much less than the
maximum service pressure eg vacuum tests, search gas tests, air tests, and
water or service fluid tests.
Local Procedures Site-specific procedures which address the arrangements in place for the
implementation of SMS procedures.
Lower Flammable Limit The lowest concentration of flammable gas in air at atmospheric pressure
(LFL) capable of being ignited. The figure is expressed as percentage by volume.
MAWP Maximum Allowable Working (Operating) Pressure should normally be
taken to mean the design pressure. It is the basis for the pressure setting
relieving device.
Non-hazardous Utility Cold water, air.
Definitions
Add 1-2 May 2009 Issue 1
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Term Definition
Positive Isolation Isolation by means of a fixed barrier, such as a blank flange (following
spool removal), blind plate or spectacle plate, bolted or clamped in place
and conforming to the pipework specification, which provides an equivalent
standard of containment to the pipework in which it is installed.
Process Fluid Well fluids, live crude, stabilised crude, gas, NGL or any other produced
fluid containing hydrocarbon gas or liquid. H 2S, LSA scale/NORM
(Naturally Occurring Radioactive Material) or hydrates may also be present.
Pyrophoric Scale or Usually finely divided ferrous sulphide formed inside a tank, pipeline or
Deposits equipment, in the presence of mercaptans or hydrogen sulphide. It is
capable of such rapid oxidation on exposure to air that heating
to incandescence can occur.
Reasonably Practicable This term implies that an evaluation of costs versus benefits should be
made. Where the cost or difficulty of a precaution is grossly
out of proportion to the reduction in risk likely to be achieved
by implementing the precaution, the precaution can be considered not
reasonably practicable.
Any additional risks which may arise while installing or removing
the precaution shall also be taken into consideration in determining what is
reasonably practicable.
Source of Ignition Naked lights, fires, certain electrical equipment, hot surfaces above ignition
temperature or a spark or flame produced by any other means.
Tanks Within the context of this document, the majority of the tanks referred to
are located onshore and consist of the following types:
(a) Atmospheric fixed roof, normally used for the storage of water,
chemical or heavy oils, ie materials that do not give off vapour at
normal ambient temperature.
(b) Atmospheric floating roof, where the floating roof can be of the pan,
pontoon or double deck design. The roof floats on the tank contents.
These tanks are mainly used for the storage
of materials which have a flashpoint at or below normal atmospheric
temperatures.
(c) Pressure storage tanks, eg for the storage of liquefied petroleum gas
(propane, butane etc). These tanks may also be refrigerated.
Above ground tankage is contained within a bunded area;
ie surrounded by walls of earth, concrete or other impermeable material of
appropriate height so as to completely contain any spillage or rupture within
the bunded area.
Definitions
May 2009 Issue 1 Add 1-3
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Term Definition
Test Pressure Except where it is required to meet design code or statutory requirements
for strength testing (ie 150% of design pressure), the test pressure shall be
limited to not more than 110% of Maximum Allowable Working Pressure
(MAWP).
Upper Flammable Limit The concentration of flammable gas in air at atmospheric pressure above
(UFL) which combustion will not occur. The figure is expressed
as a percentage by volume.
Definitions
Add 1-4 May 2009 Issue 1
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Addendum 2
Typical Valve Isolations Integrity Tests
Paragraph Page
Key
V1 First (upstream) isolation valve from live system.
M1 Live side monitoring point (pressure gauge or vent/drain).
V2 Second (downstream) isolation valve from live system.
M2 Monitoring point between valves and break point (pressure gauge or vent/drain).
B Bleed point between the isolation valves.
(1) If possible, ensure that tappings at M1, M2 and B are not blocked and that pressure gauges,
where installed, are operating.
(2) Close downstream valve V2 and secure in closed position.
(3) Note pressure at monitoring points M1 and M2.
(4) Vent/drain section of line to be broken into and monitor at M2 until the pressure
is near zero.
(5) Close vent/drain at break point and monitor at M2 for a minimum of 10 minutes. No
pressure buildup at M2 indicates the integrity of the downstream valve V2.
(6) Close upstream valve V1 and secure in closed position.
(7) Note pressure at M1 and B.
(8) Vent/drain between V1 and V2 (B) and monitor at B until pressure is near zero.
(9) Close vent/drain (B) and monitor at M1 and B for a minimum of 10 minutes.
(No pressure buildup at B indicates integrity of upstream valve V1.)
(10) Leave vent/drain (B) in closed position to allow further monitoring.
Note: The two block valves are now closed and secured. The bleed valve is closed but not
locked. It is possible for pressure to build up between the two block valves therefore
regular monitoring of the isolation is essential; a suitable pressure gauge may be
fitted to the vent to monitor the pressure.
Key
M1 Live (upstream) side monitoring point.
M2 Monitoring point between valve and break point (downstream).
C Cavity drain (between seals).
(1) If possible, ensure that tappings at M1, M2 and C are not blocked and that pressure gauges,
where installed, are operating.
(2) Close isolation valve and secure in closed position.
(3) Note pressure at M1, C (in cavity) and M2.
(4) Vent/drain downstream section of line to be broken into and monitor pressure
at M2 until pressure is near zero.
(5) Close vent/drain at break point and monitor at M2 and C for a minimum of
10 minutes. (No pressure buildup at M2 and no pressure fall-off at C indicates integrity of
downstream seal.)
(6) Note pressure at M1 and C.
(7) Vent/drain off fluid in cavity (between seals) and monitor at C until the pressure
is near zero.
(8) Close cavity vent/drain (C) and monitor at M1 and C for a minimum of 10 minutes. (No
pressure buildup at C indicates integrity of upstream seal.)
(9) Leave vent/drain (C) in closed position to allow further monitoring.
Note: The double sealed, single block valve is now closed and secured. The bleed valve is
closed but not locked. Any fluid passing through the upstream seal will be detected
at the cavity drain (C). Regular monitoring of the isolation
is therefore essential and a suitable pressure gauge may be fitted to the vent to
monitor the pressure.
Key
M1 Live (upstream) side monitoring point.
M2 Monitoring point between valve and break point (downstream).
(1) Ensure that tappings at M1 and M2 are not blocked and that pressure gauges, where
installed, are operating.
(2) Close isolation valve and secure in closed position.
(3) Note pressure at M1 and M2.
(4) Vent/drain downstream section of line to be broken into and monitor at M2 until pressure is
near zero.
(5) Close downstream vent/drain and monitor at M2 for a minimum of 10 minutes.
(No pressure buildup at M2 indicates integrity of single valve.)
(6) Leave downstream vent/drain at break point in closed position to allow further monitoring.
Note: The single isolation valve is now closed and secured, and the downstream
vent/drain is closed. Any fluid passing through the single valve seal would be
monitored by means of the mandatory additional safeguards listed
in Table 2.
Addendum 3
Safe Isolation and Reinstatement
of Plant Flowchart
Addendum 4
TAR and Planned Intervention
Pre-startup Assurance Checklist
Pre-startup Checklist
The pre-startup checklist or equivalent shall be used for all plant startups following turnarounds or
extended plant outages. For plant startups within 24 hours the Offshore Installation Manager (OIM) may
decide not to make this a requirement.
The pre-start assurance checklist has been developed to manage risks around plant restart.
This process is not designed to manage the risks of executing the tasks. Execution risks and Management
of Change (MoC) will continue to be managed through existing systems.
Procedure Sequence
At each of the points identified, the technician must check the following has been carried out:
All locked valves are returned to the normal operating position and locked
All temporary bleed arrangements, hoses and gauges must be disconnected and returned
to storage
All purge, drain, vent, bleed and transmitter vent valves must be closed
All plugs and caps must be fitted securely
The technician must sign for each point to verify the above.
Addendum 5
Workplace Assessment Plan Template
Paragraph Page
1 Introduction 1
2 Objectives 1
3 Underpinning Knowledge 1
4 Assessment Methodology 2
4.1 Field Assessment Requirements 2
4.2 Observation, Demonstration and Questioning 3
4.3 Simulation 3
4.4 Guidance on the Assessment Process 3
1 Introduction
The following assessment plan consists of four components which make up the unit Safe
Isolations and Reinstatement of Plant:
Process isolations
Breaking containment
Confined space entry
Pressure/leak testing
It provides the framework for the workplace qualified Competence Management Assurance
System (CMAS) Assessor to carry out the assessment.
2 Objectives
This assessment plan sets a common standard for assessing an individual as a competent BP
process isolator. It shall be applied to all candidates, however, the extent of the assessment
process will depend on the previous experience of the individual (refer to Paragraph 4.4).
Successful assessments will be recorded within the CMAS system by a qualified CMAS Assessor
with the appropriate comments.
3 Underpinning Knowledge
Prior to the workplace assessment the candidate shall complete the following training:
SIRP Training Course (refer to Paragraph 5.2 of the main body of this document)
Permit to Work or Integrated Safe System of Work (ISSOW) training to at least Performing
Authority level
4 Assessment Methodology
Assessing competence will be carried out by observation, practical demonstration and questioning.
Plant availability and practicality may dictate an element of simulation.
4.3 Simulation
Where the opportunity does not exist to assess the candidate either by observation
or demonstration on complex isolations, the competence can be assessed by the use of simulated
scenarios.
Simulation can involve:
Detailed description of all aspects of applying isolations to a specific system or section of
plant and equipment. The exercise shall include all documentation required, marked up
diagrams and the application of locks and tags
Answering questions or participating in desktop scenarios, which show the depth of
knowledge gained
Note: Complex isolations which cannot be readily applied and therefore lend themselves to
simulated exercises may include such topics as:
Confined space and vessel entry
Actions on not being able to obtain integrity of isolation
Breaking containment, drain flush and purge
Leak test and reinstate plant and equipment
Addendum 6
Assurance Protocol
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-1
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-2 December 2009 Issue 1/AM02
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-3
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-4 December 2009 Issue 1/AM02
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-5
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-6 December 2009 Issue 1/AM02
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-7
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-8 December 2009 Issue 1/AM02
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-9
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-10 December 2009 Issue 1/AM02
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-11
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-12 December 2009 Issue 1/AM02
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-13
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-14 December 2009 Issue 1/AM02
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-15
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-16 December 2009 Issue 1/AM02
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-17
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-18 December 2009 Issue 1/AM02
Guidance on Practice for
Safe Isolation and Reinstatement of Plant NSSPU-GP 44-40-1
Assurance Protocol
December 2009 Issue 1/AM02 Add 6-19
Guidance on Practice for
NSSPU-GP 44-40-1 Safe Isolation and Reinstatement of Plant
Assurance Protocol
Add 6-20 December 2009 Issue 1/AM02