Professional Documents
Culture Documents
WORK PROCESS
Corporate Office
Table of Contents
1. PURPOSE.................................................................................................................
2. DETAILS..................................................................................................................
Step 7.5.1 - Approve and Communicate TA Execution Plan........................................4
Step 7.5.2 - Perform Pre-TA Execution Activities......................................................9
Step 7.5.3 - Conduct Pre-Activity Safety Review (for Shutting Down).......................18
Step 7.5.4 - Perform Plant Shutting Down Activities...............................................22
Step 7.5.5 - Perform TA Mechanical Days Activities................................................34
Step 7.5.6 - Conduct Pre-Activity Safety Review (for Startup)..................................45
Step 7.5.7 - Perform Pre-Startup and Startup Activities..........................................50
3. DOCUMENT HISTORY...............................................................................................
Internal
Page 1 of 61
Downstream
WORK PROCESS
Corporate Office
1. PURPOSE
The Plan & Execute Turnaround is one of the sub work process of Maintain Facility, under
Produce Product.
This document provides the details of steps involves in “7.5 Execute TA” stage.
PETA workflow process diagram in Figure 1 indicates the general order of the steps
(WPL5). The steps can also be accomplished in parallel. Because of the interrelationships
of activities required in a well-planned turnaround, the TA Planning Schedule is more
appropriate tool to use for scheduling a specific turnaround.
Internal
Page 2 of 61
Downstream
WORK PROCESS
Corporate Office
2. DETAILS
2.1 There are seven (7) key steps involved in “7.5 Execute TA” stage
Internal
Page 3 of 61
Downstream
WORK PROCESS
Corporate Office
2.2 The details of steps are tabulated as per the subsequent tables below.
Internal
Page 4 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 5 of 61
Downstream
WORK PROCESS
Corporate Office
Master Plan”.
o TA HSE KPI.
o TA Quality KPI.
o TA Cost KPI.
o TA Operation KPI.
Internal
Page 6 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 7 of 61
Downstream
WORK PROCESS
Corporate Office
Risk Assessment”.
Information MyExplorer
Technology Tools
MyEvents
OPU Intranet
Primavera
Internal
Page 8 of 61
Downstream
WORK PROCESS
Corporate Office
TA Job Packages.
Key
Responsibility Role Responsibility
Internal
Page 9 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 10 of 61
Downstream
WORK PROCESS
Corporate Office
Attend TA trainings.
Internal
Page 11 of 61
Downstream
WORK PROCESS
Corporate Office
Attend TA trainings.
Internal
Page 12 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 13 of 61
Downstream
WORK PROCESS
Corporate Office
TA Quality KPI.
Internal
Page 14 of 61
Downstream
WORK PROCESS
Corporate Office
o Quality training.
o Operation training.
Internal
Page 15 of 61
Downstream
WORK PROCESS
Corporate Office
Scaffolding erection
Insulation removal.
DOSH Engagement:
Internal
Page 16 of 61
Downstream
WORK PROCESS
Corporate Office
Information Primavera
Technology
STEPS
Tools
Internal
Page 17 of 61
Downstream
WORK PROCESS
Corporate Office
Approved TIP.
TA Job Packages.
PASR-SD Report.
Internal
Page 18 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 19 of 61
Downstream
WORK PROCESS
Corporate Office
Information STEPS
Technology
Internal
Page 20 of 61
Downstream
WORK PROCESS
Corporate Office
Tools
Internal
Page 21 of 61
Downstream
WORK PROCESS
Corporate Office
TA Job Packages.
Closure all the action items from TA Governance Risk Register with
due date before TA Execution.
Internal
Page 22 of 61
Downstream
WORK PROCESS
Corporate Office
TA Execution period.
Key
Responsibility Role Responsibility
Internal
Page 23 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 24 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 25 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 26 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 27 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 28 of 61
Downstream
WORK PROCESS
Corporate Office
TA Cost KPI.
Internal
Page 29 of 61
Downstream
WORK PROCESS
Corporate Office
o TA Quality KPI.
o TA Schedule KPI.
o TA Cost KPI.
Internal
Page 30 of 61
Downstream
WORK PROCESS
Corporate Office
“First Product Off” is the date and time the first main plant product
being out of production to indicate the start of P2P duration and TA
Execution period. The “First Product Off” must be clearly captured and
communicated to all stakeholders and the workforce involved.
Safe Handover
Safe Handover indicates the completion of all plant shutting down and
de-commissioning activities for each system package or equipment as
specified in TA Systemization to safely move to step “7.5.4 Perform
Mechanical Days Activities”. Typically, it shall be managed through
closure of all PASR-SD “Medium” findings and Hand-Over of
Equipment for Maintenance (HOEM) certification from Operation to TA
Execution Team.
TA LWR Worklist Freeze Date defines the last date for submission and
registration of the TA LWR Worklist which is declared at the start of
P2P duration and TA Execution period.
Internal
Page 31 of 61
Downstream
WORK PROCESS
Corporate Office
The procurement of services is typically under lump sum price for all
the services rendered to execute the work (but the basis for cost
estimates can be from the available unit rates). The cost impact of the
EWR also must be closely monitored against allocated budget due to
additional cost to expedite the material and services.
New Scope.
Scope Deleted.
Information Primavera
Internal
Page 32 of 61
Downstream
WORK PROCESS
Corporate Office
Technology
Tools
LOTO procedure.
OFWP.
EMWP.
Internal
Page 33 of 61
Downstream
WORK PROCESS
Corporate Office
TA Job Packages.
Internal
Page 34 of 61
Downstream
WORK PROCESS
Corporate Office
TA information and data are analyzed and reported, and actions are
taken to mitigate issues.
All WCS and JICS signed and completed (except for SIS and BLIS de-
blinding work).
Key
Responsibility Role Responsibility
Review EWR.
Internal
Page 35 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 36 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 37 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 38 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 39 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 40 of 61
Downstream
WORK PROCESS
Corporate Office
TA Cost KPI.
o Logistic plan,
o Maintenance activities.
o Operations activities.
Internal
Page 41 of 61
Downstream
WORK PROCESS
Corporate Office
o Inspection activities.
o Project activities.
o TA Quality KPI.
o TA Schedule KPI.
o TA Cost KPI.
o EWR cost.
Internal
Page 42 of 61
Downstream
WORK PROCESS
Corporate Office
Contractor Productivity.
TA Execution Meetings:
Internal
Page 43 of 61
Downstream
WORK PROCESS
Corporate Office
Information Primavera
Technology
STEPS
Tools
PTW procedure.
OFWP.
Internal
Page 44 of 61
Downstream
WORK PROCESS
Corporate Office
Approved TEP.
All WCS and JICS signed and completed (except for SIS and BLIS de-
blinding work).
PASR-SU Report.
Key
Responsibility Role Responsibility
Internal
Page 45 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 46 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 47 of 61
Downstream
WORK PROCESS
Corporate Office
Safe Hand-back
Information Primavera
Internal
Page 48 of 61
Downstream
WORK PROCESS
Corporate Office
Technology
Tools
STEPS
Internal
Page 49 of 61
Downstream
WORK PROCESS
Corporate Office
Description This step describes plant pre-startup and startup activities required to
safely start up the plant for uninterrupted operation. The Pre-startup
activities ensures de-isolation of energy and process safety prior to
introduction of hydrocarbon to the plant.
The startup activities start when the plant feed is introduced to initiate
the processing and produce product. The “Last (On-Specs) On”
indicates the end of P2P duration and TA Execution period.
Internal
Page 50 of 61
Downstream
WORK PROCESS
Corporate Office
Product produced and “Last (On-Specs) Product On” date and time
captured.
Key
Responsibility Role Responsibility
Internal
Page 51 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 52 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 53 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 54 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 55 of 61
Downstream
WORK PROCESS
Corporate Office
Internal
Page 56 of 61
Downstream
WORK PROCESS
Corporate Office
TA Cost KPI.
Plant Pre-Startup activities are critical to ensure safe and timely plant
start-up. Typically, completion of activities is controlled and validated
through Ready-For-Startup (RFSU) checklist and certification.
The Pre-Startup activities include but not limited to the followings and
(for detail descriptions Appendix V-11 - Operations TAMG):
Internal
Page 57 of 61
Downstream
WORK PROCESS
Corporate Office
o TA Quality KPI.
o TA Schedule KPI.
o TA Cost KPI.
Insulation reinstatement
Scaffolding removal
Internal
Page 58 of 61
Downstream
WORK PROCESS
Corporate Office
Ready-For-Startup (RFSU)
“Last (On-Specs) Product On” is date and time the final product
produce by the plant to indicate the end of P2P duration and TA
Execution period. The product shall be tested and confirmed meeting
Internal
Page 59 of 61
Downstream
WORK PROCESS
Corporate Office
Information Primavera
Technology
Tools
LOTO procedure.
OFWP.
EMWP.
Internal
Page 60 of 61
Downstream
WORK PROCESS
Corporate Office
3. DOCUMENT HISTORY
Revision History
0 Document created
Document Authorisation
Internal
Page 61 of 61