08 Hse Monthly Report - Samanea Project - August 2021
08 Hse Monthly Report - Samanea Project - August 2021
3 NEARMISS 3 0 0 0
5 FATALITIES 0 0 0 0
8 VEHICLE ACCIDENT 0 0 0 0
9 FIRE CASE 0 0 0 0
10 PROPERTY DAMAGE 0 0 0 0
11 ENVIRONMENTAL IMPACT 0 0 0 0
12 FREQUENCY RATE 0
13 SEVERITY RATE 0
16 HSE INDUCTION - 7 3 10
18 HSE TRAINING - 0 0 0
24 HAZARD REPORT 2 10 1 11
27 HSE REWARD - 2 0 2
36 PROVIDE & SOCIALIZE EMERGENCY LAY OUT OFFICE - Need to install Emergency Evacuation Signs
38 PROVIDE & INSTALL SAFETY SIGNS FIELD - Need more installation & improvement
39 PROVIDE & INSTALL EMERGENCY SIGNS OFFICE & FIELD - Need more installation & improvement
40 PROVIDE FIRE EXTINGUISHER OFFICE & FIELD - Need more Fire Extinguishers installed in the field
41 PROVIDE FIRST AID BOX OFFICE & FIELD - There is only one and not complete
42 PROVIDE A TRASH CAN OFFICE & FIELD - Need more trash bins
52
53
54
55
CONSTRUCTION MANAGEMENT CONSULTATION SERVICES FOR SAMANEA
MIXED USE PROJECT, CIKUPA TANGERANG - INDONESIA
WORKING HOURS / DAY TOTAL OVERTIME / DAY TOTAL TOTAL WORKING TOTAL WORKING
NO DAY DATE LOST TIME
HOURS HOURS HOURS PER DAY HOURS
TOTAL WORKER WORKING HOURS TOTAL WORKER WORKING HOURS
1 Sunday 1-Aug-21 0 8 0 0 3 0 0 0 -
2 Monday 2-Aug-21 12 8 96 0 3 0 0 96 96
(1) + (2)
UP TO THIS MONTH 11,860 1466
CONSTRUCTION MANAGEMENT CONSULTATION SERVICES FOR SAMANEA
MIXED USE PROJECT, CIKUPA TANGERANG - INDONESIA
WORKING HOURS / DAY TOTAL OVERTIME / DAY TOTAL TOTAL WORKING TOTAL WORKING
NO DAY DATE LOST TIME
HOURS HOURS HOURS PER DAY HOURS
TOTAL WORKER WORKING HOURS TOTAL WORKER WORKING HOURS
1 Sunday 1-Aug-21 0 8 0 0 3 0 0 0 -
2 Monday 2-Aug-21 5 8 40 0 3 0 0 40 40
3 Tuesday 3-Aug-21 5 8 40 0 3 0 0 40 80
(1) + (2)
UP TO THIS MONTH 6,144 768
CONSTRUCTION MANAGEMENT CONSULTATION SERVICES FOR SAMANEA
MIXED USE PROJECT, CIKUPA TANGERANG - INDONESIA
WORKING HOURS / DAY TOTAL OVERTIME / DAY TOTAL TOTAL WORKING TOTAL WORKING
NO DAY DATE LOST TIME
HOURS HOURS HOURS PER DAY HOURS
TOTAL WORKER WORKING HOURS TOTAL WORKER WORKING HOURS
(1) + (2)
UP TO THIS MONTH 548,057 50,710
CONSTRUCTION MANAGEMENT CONSULTATION SERVICES FOR SAMANEA
MIXED USE PROJECT, CIKUPA TANGERANG - INDONESIA
NO DESCRIPTION UNIT UP TO LAST MONTH OWNER CONST. MANAGEMENT CONTRACTOR THIS MONTH UP TO THIS MONTH REMARKS
2 Nearmiss Cases - - - - - -
5 Fatalities Cases - - - - - -
14 Frequency Rate 0
15 Severity Rate 0
Note :
Manhours : Number of working hour
Nearmiss : The number of conditions or situations where an accident nearly occurred
Lost Time Injury (LTI) : Number of accidents that cause lost work days (Unable to work again after 2 x 24 hours)
Non Lost Time Injury (Non-LTI) : Number of work accidents that do not cause loss of working days / victims can immediately work before 2x 24 hours
Fatalities : The number of occurrences of accidents causing death
Total Workdays Lost (TWL) : The number of days lost due to an accident at work
Medical Treatment Cases (MTC) : The number of work accidents handled with the help of paramedics, for example actions at the clinic or hospital
First Aid Cases
First(FAC)
Aid Cases (FAC) : The number of work accidents handled only with first aid measures
Illness Due To Work : Occupational diseases such as people working in the generator room have decreased hearing ability
Vehicle Accident : Number of vehicle accidents in the project area
Fire Cases : Number of fire case occured
Property Damage : The number of work accidents that cause property damage without human casualties
Environment Impact : The number of work accidents that cause environmental damage
Frequency Rate : To identify the number of injuries that caused the inability to work
Formula : Frequency Rate = (number of work accidents with lost work time x 1,000,000) / Total Manhours
If the number of workers> 500 people, use a coefficient of 1,000,000, if the number of workers <500 people, use a coefficient of 200,000
The total workforce of 500 people, the number of working hours reached 1,150,000 hours, causes a loss of work time of 70 days, due to 46 work accidents. Then the Frequency Rate = (46 x 1,000,000)
Example :
/ 1,150,000 = 40
ENVIRONMENTAL PERFORMANCE
PERIOD : AUGUST 2021
CONSTRUCTION MANAGEMENT
NO DESCRIPTION UNIT UP TO LAST MONTH OWNER PMC CONTRACTOR THIS MONTH UP TO THIS MONTH REMARKS
5 Use of Water m 3
- - - - - - No data
10
11
12
13
14
15