You are on page 1of 5

PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1

(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

HSE Inspection Team: Date of Inspection:- 11-Aug-2021 Time:- 8:15 AM


Saqib Noveed - Altorath HSE Engineer

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Observation:
During site visit it is observed that Permit requester and Permit
issuer information and signature are missing, incomplete crane
lifting permit found.

Location:
Package-2
Contractor has breached:
Method Statement:
N/A
OSHAD-SF :
COP-21.0 Permit to Work System
01 Approved HSE Plan- Rev 01:
5.09 PTW-System
Musanada HSE Requirements
Musanada Key HSE requirements section-5.15
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
UAE Federal Law No. 08 of 1980
Ministerial Order no. 32 of 1982 A.D. on determining prevention means
and measures to protect workers from occupational hazards,

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 1

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Observation:
Poor welfare facilities at site,
Contractor clean & cool rest area with clean & cold drinking water.

laborers rest area is poorly built and managed at site.


Location:
Package 02
Contractor has breached:
Method Statement:
N/A
02
OSHAD-SF :
OSHAD SF COP-8
Approved HSE Plan- Rev 01:
Project HSE Plan section -5.15
Musanada HSE Requirements
Musanada Key HSE requirements section-5.18
Legal:
Ministerial Order 32 section -5(f) m

03 Observation:
Excavation observed without appropriate barricading and
signage, traffic coming from Asab Mazra side can be affected.
Insfficent awareness signage.
Location:
Package-02
Contractor has breached:
OSHAD-SF :
AD OSHAD- CoP 29.0 – Excavation, AD

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 2

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES

OSHAD- CoP 22.0 - Barricading of Hazards & AD


OSHAD-CoP 17.0 Safety Sign & Signals
Approved HSE Plan- Rev 01:
Traffic Management Plan
Musanada HSE Requirements
Musanada Key HSE requirements section-5.18
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
UAE Federal Law No. 08 of 1980
Ministerial Order no. 32 of 1982 A.D. on determining prevention
means and measures to protect workers from occupational
hazards
04 Observation:
Appointed rigger does not hold any rigging certificate/card to qualify
him as a competent person for the crane lifting operation.
Location:
Package-02
Contractor has breached:
OSHAD-SF :
OSHAD SF COP -34 , OSHAD SF COP -36
Approved HSE Plan- Rev 01:
Project HSE Plan section -5.14
Musanada HSE Requirements
Musanada Key HSE requirements section-5.11

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 3

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

SN OBSERVATION OBSERVATION PICTURES CLOSE OUT PICTURES


Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
Ministerial Order 32 section -20
Observation:
Poor inspection of fire extinguishers at site. All portable fire extinguishers shall
be inspected at least monthly to ensure their existence in their locations and that
their safety seals are not broken and there are no damages or defects.
Location:
Package-01 (Man lift)
Contractor has breached:
OSHAD-SF :
CoP 33.1 (General 3.1.1 (f)) , CoP 43
Approved HSE Plan- Rev 01:
05
HSE - CONSTRUCTION MANAGEMENT PLAN , HSE Officer
Responsibilities (7) , 14. Fire Fighting Equipment
Musanada HSE Requirements
Musanada Key HSE requirements section-5.9
Musanada SOP:
IMS SOP 8 Hazard and Risk
Legal:
VOLUME 3 SPECIFICATIONS 3A - General Specifications : 1.16.7 Health
and Safety (R & S) Fire protection & Prevention:
Ministerial Resolution No. (32) for 1982 A.D article (8)
Prepared by: Closed by: Accepted By:
Consultant HSE Engineer: Main Contractor HSE Contractor’s PM
Saqib Noveed Delowar Hussain Baha Al Awar

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 4

Site Visit Report for Construction of Shah Link Road: Package-1 & 2
PROJECT: Construction of the New Link Road between Shah Gas Field & Mezairaa Area Phase-1
(Packages 1 & 2)
HEALTH, SAFETY AND ENVIRONMENT
Weekly Site Observation Report

Close-Out Checked by: Closeout approved by:


Consultant HSE Engineer: Resident Engineer
Saqib Noveed Awan Muhammad Ibrahim Soomro

HSE DEPARTMENT: CLOSEOUT REPORT SHALL BE FOLLOWED BY APPROVED CORRECTIVE ACTIONS 5

Site Visit Report for Construction of Shah Link Road: Package-1 & 2

You might also like