Professional Documents
Culture Documents
A Mobilization works Ls 1
B Demobilization works Ls 1
C Demolition charge Ls 1
Excavation
Labor cost
Substructure
Plain in situ concrete with characteristic strength as specified
A 100 mm thick blinding grade slab at garage and second floor open terrace m3 3
B Wall footings m3 1
Formwork to;
C Sides of wall Tie beam (pynolic board 1/2" thick pcs 3
D Cocolumber assorted bdft 50
E Tie wire no. 16 roll 1
F Common nail assorted kg 3
G Hardwares lot 1
Superstructure
Reinforced in situ concrete with characteristic strength as specified
A Columns m3 1
B Column Footings m3 1
C Floor beams m3 1
D Second floor beams m3 1
F Suspended slab and second floor slab, 100mm thick (150mm thick) m3 2
G Staircase m3 2
H Canopy m3 1
High yield steel bar reinforcement with yield stress as specified
Various diameters in superstructure RCC elements
Formwork to;
A Side of Columns pynolic board 1/2 thick pcs 5
B Sides and runner of beams pynolic board 1/2 thick pcs 2
C Staircase system pcs 1
D Canopy pcs 1
E Cocolumber assorted bdft 70
F Tie wire no. 16 roll 1
G Common nail assorted boxes 1
H Hardwares lot 1
TOTAL
Mate
La
Total for Bill No. 3 - Carried to General Summary
A Structural channel bar 2" x 4" x 1/4" , cee purlins 2" x 4" x 1.5mm m2 130
B Pre-painted multi r sapan 0.50mm thick,stainless gutter 24" and facia cover m2 130
C Staircase railings lm 6
D Balcony railings lm 7
E Steel window stainless grills, 1" x 2" x 1.8mm, 1" x 1" x 1.8mm tubular ft2 300
F Steel gate stainless steel 2" x 4" x 1.8mm ft2 80
G Fence stainless steel grills ft2 60
A Anti-termite m2 100
B Roof water proofing as per specifications
C Terrace water proofing as per specifications
D Waterproofing system to outside walls perimeter m2 6
Wet areas water proofing as per specifications
Floor
A Cement sand screed to receive floor tile finishes m3 3
Walls
B Cement sand plaster to receive internal wall paint m2 60
C Cement sand plaster to receive external wall paint m2 60
Floor Finishes
Floor finishes including polishing, joint, grouting, pointing, glue,
sealant, coating, etc., complete
Internal Common Areas
D Floor tiles 164m2 pcs 500
E CR tiles 54m2 pcs 200
F Step & riser staircase sytem tiles pcs 80
G Adhessive cement bags 50
H Granite slab for kitchen lavatory, pantry, and counter top pcs 5
I Tile trim and staircace nosing lot 1
External Areas
Ceiling Finishes
Ceiling System maretials are metal furring and hardiflex with elegant
design
A Ceiling estimated cost m2 200
Finishing cabinet
Finishing cabinet maretials are made up of laminated plyboard materials
and kitchen cabinets are made up of powdered white aluminum and
glass
A Bedroom cabinets and kitchen cabinet ls 1
Common area
A Mirror to three rooms toilet and four bedrooms no. 7
Sanitary wares and accessories including testing, providing guarantee,
features, finishes, accessories, systems, complete as per drawings and
specifications
RENOVATION OF TWO STOREY RESIDENTIAL BUILDING WITH PROPOSED GARAGE AND SECOND
FLOOR OPEN TERRACE
BLK 3 LOT 21, SUMMERFIELD SUBDIVISION, PASIG CITY
ITEM ITEM DESCRIPTION
NO.
GENERAL SUMMARY
KAGE
TIES
2,000.00 2,000.00
5,000.00 5,000.00
50,000.00 50,000.00
57,000.00
280.00 2,800.00
250 3,750.00
600.00 18,000.00
TOTAL 29,460.00
5,000.00 5,000.00
170.00 1,700.00
270.00 1,350.00
750.00 2,250.00
35.00 1,750.00
1,700.00 1,700.00
80.00 240.00
2,000.00 2,000.00
TOTA 30,990.00
L
5,000.00 5,000.00
5,000.00 5,000.00
5,000.00 5,000.00
5,000.00 5,000.00
5,000.00 5,000.00
5,000.00 10,000.00
5,000.00 10,000.00
5,000.00 5,000.00
180.00 2,700.00
260.00 3,120.00
380.00 7,600.00
750 3,750.00
750 1,500.00
750 750.00
750 750.00
30.00 2,100.00
1,700.00 1,700.00
1,600.00 1,600.00
2,000.00 2,000.00
TOTAL 77,570.00
Substructure 30,990.00
Superstructure 77,570.00
Material cost 108,560.00
Labor cost 54,280.00
TOTA 162,840.00
L
12 720
16 320
600 9000
240 7200
1000 1000
180 5400
Material 23,640
cost
Labor cost 11,820
35,460.00
1200 156,000.00
1500 195,000.00
5000 30,000.00
5000 35,000.00
650 195,000.00
750 60,000.00
560 33,600.00
986,440.00
50 5,000.00
120 720.00
2000 2,000.00
7,720.00
MAIN WORKS PACKAGE
QTY. RATE AMOUNT
(PHP) (PHP)
15000 15,000.00
7500 30,000.00
4000 12,000.00
20000
40,000.00
7500 15,000.00
6000 6,000.00
450 126,000.00
292,800.00
RATE AMOUNT
(PHP) (PHP)
5500 16500
350 21000
350 21000
380 190,000.00
250 50,000.00
380 30,400.00
380 19,000.00
12000 60,000.00
10000 10,000.00
170 59,500.00
620,620.00
MAIN WORKSPACKAGE
140 70,000.00
110 27,500.00
800 160,000.00
70000 70,000.00
1,234,620.00
700 4,900.00
8000 24,000.00
2000 6,000.00
6500 19,500.00
1500 4,500.00
650 1,950.00
300 900.00
450 1,350.00
4000 8,000.00
8000 24,000.00
5500 16,500.00
10000 30,000.00
141,600.00
25,000.00
25,000.00
30,000.00
30,000.00
20,000.00 20,000.00
120000 120,000.00
24000 24,000.00
219,000.00
MAIN WORKS 0
PACKAGE
TOTAL AMOUNT
(in PHP Pesos)
1
57,000.00
29,460.00 2
162,840.00 3
35,460.00 4
986,440.00 5
7,720.00 7
292,800.00 8
1,234,620.00
141,600.00
219,000.00
3,166,940.00