Modify the numbers in the blue cells with your own production information and your OEE will

calculate automaticaly.

Shift structure :
No of days 5
Tot hr/shift 8
No of shift (ex : day, evening = 2) 3

Total production hr 120

Planned Downtimes (h/ week)


Sanitations 5
C/O 10
Breaks n Lunches 25

Total Planned DT 40

Available production opening time 80

Unplanned Downtimes (h/week)


Breakdowns 3
Missing product 1
Missing employees 4
Adjustments 4
Others 4

Total Unplanned DT 16

Availability % 80%
Efficiency

Machine Standard Speed (theorical max) (u/min) 1200


Estimated actual speed (u/min) 875

Efficiency % 73%
Quality %
Estimated percentage of reject 1.50%

Quality % 98.50%

OEE 57.5%
Modify the numbers in the blue cells with your own production information and your OEE will calculate automaticaly.

Best of class manufacturer OEE score is 80%


Number of production hours lost per week (available production opening time x OEE): 34