DAFTAR KUANTITAS DAN HARGA

Pengadaan dan Pemasangan Lampu PJU Bandara

RINCIAN PERHITUNGAN HARGA


No. URAIAN VOL JUMLAH (Rp)
JML SATUAN
1 2 3 6 7 8 9=(7x8)
I Pekerjaan Persiapan
1 Penjilidan Dokumen Kontrak 7 7 set x 1 kali 7.00
2 Pembersihan dan Pengukuran Lokasi Kerja 30 30 titik x 1 kali 30.00
3 Shop Drawing dan As Built Drawing 5 5 set x 1 kali 5.00
4 Pembuatan PAS Bandara 10 10 org x 1 kali 10.00
II Pekerjaan Pengadaan dan Pemasangan
A AREA CENDRAWASIH - HANGGAR LION
1 Lampu LED 70 Watt, 5700K, 220 VAC, Efficacy 128-140 lm/watt 19 19 bh x 1 kali 19.00
2 Tiang Lampu Octagonal 11 M, Hot Dip Galvanis, Single Arm Parabole 19 19 bh x 1 kali 19.00
3 Pondasi Tiang Lampu 19 19 titik x 1 kali 19.00
4 MCB 1 Phase 6A/4.5 kA 19 19 bh x 1 kali 19.00
5 Kabel NYFGbY 4x4mm 760 760 m x 1 kali 760.00
6 Kabel NYFGbY 4x10mm 245 245 m x 1 kali 245.00
7 Kabel NYMHY 3 x 1,5 mm 219 219 m x 1 kali 219.00
8 Galian Jalur Kabel 838 838 m x 1 kali 838.00
9 Booring Kabel Dengan Pipa Diameter 2" 6 6 m x 1 kali 6.00
10 Panel Outdoor OLP Berikut Pondasi 1 1 unit x 1 kali 1.00
11 Grounding System Tiang Lampu Baru Dan Panel OLP 20 20 titik x 1 kali 20.00
B AREA RUMAH POMPA
1 Lampu LED 70 Watt, 5700K, 220 VAC, Efficacy 128-140 lm/watt 11 11 bh x 1 kali 11.00
2 Tiang Lampu Octagonal 11 M, Hot Dip Galvanis, Single Arm Parabole 11 11 bh x 1 kali 11.00
3 Pondasi Tiang Lampu 11 11 titik x 1 kali 11.00
4 MCB 1 Phase 6A/4.5 kA 11 11 bh x 1 kali 11.00
5 Kabel NYFGbY 4x4mm 427 427 m x 1 kali 427.00
6 Kabel NYFGbY 4x10mm 7 7 m x 1 kali 7.00
7 Kabel NYMHY 3 x 1,5 mm 127 127 m x 1 kali 127.00
8 Galian Jalur Kabel 334 334 m x 1 kali 334.00
9 Booring Kabel Dengan Pipa Diameter 2" 6 6 m x 1 kali 6.00
10 Panel Outdoor OLP Berikut Pondasi 1 1 unit x 1 kali 1.00
11 Grounding System Tiang Lampu Baru Dan Panel OLP 12 12 titik x 1 kali 12.00
C AREA GEDUNG ABC
1 Lampu LED 70 Watt, 5700K, 220 VAC, Efficacy 128-140 lm/watt 4 4 bh x 1 kali 4.00
2 Pondasi Tiang Lampu 4 4 titik x 1 kali 4.00
3 MCB 1 Phase 6A/4.5 kA 4 4 bh x 1 kali 4.00
4 Kabel NYFGbY 4x4mm 140 140 m x 1 kali 140.00
5 Kabel NYFGbY 4x10mm 7 7 m x 1 kali 7.00
6 Kabel NYMHY 3 x 1,5 mm 46 46 m x 1 kali 46.00
7 Galian Jalur Kabel 115 115 m x 1 kali 115.00
8 Booring Kabel Dengan Pipa Diameter 2" 6 6 m x 1 kali 6.00
9 Panel Outdoor OLP Berikut Pondasi 1 1 unit x 1 kali 1.00
10 Grounding System Tiang Lampu Baru Dan Panel OLP 5 5 titik x 1 kali 5.00
D AREA PARKIRAN BELAKANG GEDUNG A2B
1 Lampu LED 90 Watt, 5700K, 220 VAC, Efficacy 128-140 lm/watt 4 4 bh x 1 kali 4.00
2 Tiang Lampu Octagonal 11 M, Hot Dip Galvanis, Single Arm Parabole 4 4 bh x 1 kali 4.00
3 Pondasi Tiang Lampu 4 4 titik x 1 kali 4.00
4 MCB 1 Phase 6A/4.5 kA 4 4 bh x 1 kali 4.00
5 Kabel NYFGbY 4x4mm 190 190 m x 1 kali 190.00
6 Kabel NYFGbY 4x10mm 30 30 m x 1 kali 30.00
7 Kabel NYMHY 3 x 1,5 mm 46 46 m x 1 kali 46.00
8 Galian Jalur Kabel 187 187 m x 1 kali 187.00
9 Booring Kabel Dengan Pipa Diameter 2" 6 6 m x 1 kali 6.00
10 Panel Outdoor OLP Berikut Pondasi 1 1 unit x 1 kali 1.00
11 Grounding System Tiang Lampu Baru Dan Panel OLP 5 5 titik x 1 kali 5.00
GRAND TOTAL
PEMBULATAN
Terbilang :

……………., ……………… 2021


PT/CV ……………………….

………………………………
DIREKTUR