You are on page 1of 5

NIGHT SHIFT REPORT (08.01.21 – 08.02.

21)
CCAD – ONCOLOGY CENTRE
Page 1|5
A. NIGHT SHIFT MANPOWER (01.08 – 02.08)

Trade Numbers
DBB
Site Engineer 1
Safety Officer 1
Male nurse. 1
Foreman. Absent-Sickness
Security. 2
SSH Inspector. 1 1
Labours (Mason & Helpers) 33
BK GULF
Supervisor (Electrical) 1
Electricians 12

Total Manpower 52

B. ACTIVITIES:

1. Stiffener Beam and Column Casting at Level 06 and Level 05


2. Stiffener Beam and Column Casting at Level P1 and P1
3. Plinth casting at P1
4. Material shifting i.e. blocks and cement from P2 to Level 06.
5. Rubbish removal from P2
6. General Housekeeping

Notes:
Concreting: Start Time: 08.01.2021; 8:30 PM I End Time: 08.02.2021; 5:15 AM
Total Concrete Quantity: 11 cum = (3 Truck Mixers: 1st truck: 5 cum; 2nd Truck: 3 cum; 3rd Truck: 3 cum)

C. QUALITY OBSERVATIONS:

1. Cast Stiffener Column without Core Shear links despite previous Site observation made on 07.21.2021
CCAD – Oncology Centre
Night Shift Report 08.01.21 – 08.02.21
Rev 01/ Page 2|5

2. Stiffener beams and columns Non-compliant to approved reinforcement details

As per approved Shop Drawings:

As per site condition:

Main Longitudinal Bars: T10

Lateral Ties/Stirrups: T8
CCAD – Oncology Centre
Night Shift Report 08.01.21 – 08.02.21
Rev 01/ Page 3|5

3. QA Concrete testing i.e. slump test is not being conducted. Time of arrival of concrete at site must be
validated against the batching time. Upon arrival, the slump and temp must be checked immediately. This
is crucial especially if the concrete placement is at higher levels using concrete pump where slump lost is
susceptible.

4. No proper consolidation method of concrete being done during placement

5. No concrete cover blocks placed to ensure sufficient concrete cover is achieved during concreting
CCAD – Oncology Centre
Night Shift Report 08.01.21 – 08.02.21
Rev 01/ Page 4|5

6. No reference grid line or plumb line to ensure the aluminium Curtain Wall bracket Installation is aligned and
as per the correct setting out.

7. HDG Steel Aluminium brackets – Quality Issues: Zinc coating must be verified upon delivery through MIR. DFT
o be randomly done to ensure minimum of 85 microns is achieved as per BS EN ISO 1461/ASTM A 153.

Mottling Oxidation/White Rust Dross Inclusions

8. Missing bolts (Quality & Safety Non-compliance). Verify the termination between the face of the wall/slab
with the bracket. No notching/cut-out was done.
CCAD – Oncology Centre
Night Shift Report 08.01.21 – 08.02.21
Rev 01/ Page 5|5

9. Unsafe fixation of the mullion to the bracket. Some mullions don’t have any fixation and some only have a
single scree as shown in the picture.

D. SAFETY OBSERVATIONS:

1. Refer to No. 8 and No. 9 in the above Quality Observations – Major Risk

2. Concrete Pump (boom pipe and hose) – Lack of Isolation Measures

E. GOOD PRACTICE

1. Illumination at site exceeds the minimum 50 lux requirement

SIGNATURES
Signature: Julius Sanorjo
HSEQ Engineer
Ellisdon