Role Objective To receive and asses Labor Reports & Progress reports on a daily basis, to find out if any iss
Function/ Department/
Project Execution & Planning Team / QS Team
BU
Location Bangalore
Date:
ort Template Guideline
asis, to find out if any issues at site or hindrance for executing works as site
DAILY PROGRESS REPORT Date: 02-Nov-20
Weather:
STAR INFRATECH PROJECT NAME :Construction of Medical College, 300 Bed Hospital, Boys and Girls Hostel, Teaching and Non-Teaching Staff Quarters and allied facilities at Chikkaballapura in Chikkaballapura District.
Original Contract Value (Rs Lakhs) 5,081,146,358 Name of the Project Manager : - Anand Bandagi-PM Hospital Block PLANT PRODUCTION DETAILS
Vartion & Additional Works - Contact No :- Location : Chikballapur Medical College Project Current Month Previous Month
Balance
Scope Up to Date
Qtys.
Total Value 5,081,146,358 To day Month to Date Up to Previous Month Cum. Achieved till date Total scope Balance as on date MATERI TODAY Up to Previous Day Current Month Up to Previous Month
TURNOVER PLANTS
Project Start Date AL
19-Feb-20 Structure Finishes Structure Finishes Structure Finishes Structure Finishes Structure Finishes Structure Finishes No. of No. of
(appointment date : ) No. of Working Qty in No. of Working Qty in Qty in No. of Working Qty in
Qty in Mt./Cum. Qty in Mt./Cum. Working Working Qty in Mt./Cum.
Hours Mt./Cum. Hours Mt./Cum. Mt./Cum. Hours Mt./Cum.
Project Duration ( Months) 36 Target in Rs Hours Hours
(Lakhs) 59 52 119 104 4,951 4,741 5,069.4 4,845
Project Duration ( days) 1,095 BATCHING PLANT Conc. 1,660.85 2945.69 4,606.54 30291.40 - 34,897.94 (34,897.94)
Scheduled Completion Date
(subject to revised appointment date) 18-Feb-23 20546.82 13,470 19,482 12,937 5466.54 5,466.54 8886.67 - 14,353.21 (14,353.21)
Completion 63% 18% 61% 77% 20% 10% 21% 11% 95% 96%
Expected date of Completion 18-Feb-23 - - - -
Non availability of
Machinery Break Down Report Aggreagte 20mm - - approved Drawings DRG Shortage of Materials SOM Semiskilled 0
Chikkaballapura Medical College Shortage of Sub
Excavator Aggreagte 10mm #REF! #REF! #REF! Contractors SSC Shortage of Labour SOL Unskilled
35,000 completed balance 32,419 Land Acquisition
Hitachi Fine Aggregates - - Fund shortage FS Problem LAP
30,000
Tipper Cement - - TODAY Shortfall Amount
25,000
20,000 19,482 Tractor Pozzolonic material 586.06 586.06 586.06 BDPM SOM SOL LAP RAIN DRG SSC FS Total
15,000
Admixtures - - % Effected 75% 10% 5% 90%
12,937
10,000 #REF! - #REF! #REF! Value Effected - 48 6 - - - 3 - 58
5,000
Concrete Produced - - - 39178.07 39,178.07
1,065 533 1,597
-
Structures Finishes Total
Total (Structural+Finishes) 3,401,633,343.1 11,109,653 4,705,025 22,219,306 15,282,665 969,199,368 144,437,693 991,418,674 159,720,358 - - 6,285,269 6,697,923
1 A
Carpenter
Barbenders
0
2 B
0
3 C On NMR
Cook
Mess
Survey
Batching plant
Ballies unloading
Dewatering
0
4 D
Ballies unloading
0
5 E On NMR
Office water pump
Soil Levelling
Backfilling
Material shifting
0
TOTAL 0
Prepared by Reviewed by
Name & Designation Name & Designation
Date: 11/2/2020
0
0
0
0
0
0 0 0
0
0
0
0 0 0
2 2
1 1
1 1
1 1
2 2
5 5
1 1
0 13 13
0
0
0 0 0
0
1 1
3 3
7 7
3 3
0 14 14
0 27 27
Approved by
Name & Designation
1
3
2
5
4
3
2
1
1
SI No.
Tower C
Tower D
Total Qty
Drive ways
Club house
2 Description of Component
Project Office
Total Labours
Retaining wall
/Hospital Block
-
-
3 Carpenter
-
-
4 Carpenter Helper
-
-
5 Barbender
-
-
6 Barbender Helper
-
-
7 Block work Mason
-
-
8 Block work Mason Helper
-
-
9 Int / Ext Plastering Mason
Daily Labor Report ( Month Year)
-
-
10 Int / Ext Plastering Mason Helper
-
-
11 Tile Mason (flr / dadoo)
-
-
12 Tile Mason (flr / dadoo) Helper
-
-
13 Granite Mason
-
-
14 Granite Mason Helper
-
-
15 Water proofing Mason
-
-
16 Electrician
-
-
17 Electrician Helper
Page 8 of 22
-
-
18 Plumber
Tower Area/Building
19 Plumber Helper
-
-
20 FPS
-
-
21 FPS Helper
-
-
22 Painter
-
-
23 Painter Helper
-
-
24 Joinery works
-
-
26 Breaker / chipping
-
-
27 Unskilled
-
-
-
-
29 W/P,STP / Others
-
-
31 Mechanic
-
-
32 Mason
-
-
33 M/C
NMR
-
-
34 F/C
-
35 Grand Total
Works carried out qty
6 Compound wall
Total Labours - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Total Qty - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
MEP/External development etc
1 STP-02
2 U.G.Tank-02
Total Labours - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Total Qty - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
GRAND TOTAL
LABOURS - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
NOTE:- The above bifurcation can be modify as per your convinence but seggregation should be mandatory
Page 9 of 22
STAR
Daily Progress Report (Nov -2020) Date:
INFRATECH
Project:
Contractor:
Daily Progress Report (Please modify as per your site condition BOQ items/scope of works and vendors on board)
Today's Qty
Sl Vendor BOQ BOQ Executed Qty Planned qty
Building /Block WO no Description of work Unit Drawing ref no Remarks
No Name Item No Qty till date Planned qty Achieved Qty for Next day
Shuttering of Column
Column rebar
Slab/Beams
Shuttering of Column
Column rebar
1 Any Hindrance: (Please specify the problems or issues if any at site in terms of labours, materials, drawings, payments etc )
Contractor
Machinery/ End Total HSD WO
Sl.No Name / Star Work order No Type Vehicle No. Unit Start time End time Start Reading Amount
Vehicle Reading hour/KM issued Rate
Infratech
Diesel
HR/Day/Month/
1 GRV Contractor Job JCB KA-xxxx 9:00AM 6:00AM 6780.0 6789.8 9.8 10.00 750.0 7350.0
KM
Remarks/
Work details
Receipt Qty Diesel Issue qty Petrol issue qty Balance stock
Sl.N Remarks/
Date Unit Vehicle No./ Any Total Diesel Any Total Petrol Diesel Petrol
o Diesel Petrol Millers DG Bikes Work details
Name Others Consumed Others Consumed closing closing
Opening Stock 10 10
1 01/09/2020 0 0 10 10
2 02/09/2020 0 8 8 10 2
3 03/09/2020 0 0.0 0.0 10 2
4 04/09/2020 0 0.0 10 2
5 05/09/2020 0 0.0 10 2
6 06/09/2020 0 0.0 10 2
7 07/09/2020 0 0.0 10 2
8 08/09/2020 0 0.0 10 2
9 09/09/2020 0 0.0 10 2
10 10/09/2020 0 0.0 10 2
11 11/09/2020 0 0.0 10 2
12 12/09/2020 0 0.0 10 2
13 13/09/2020 0 0.0 10 2
14 14/09/2020 0 0.0 10 2
15 15/09/2020 0 0.0 10 2
16 16/09/2020 0 0.0 10 2
17 17/09/2020 0 0.0 10 2
18 18/09/2020 0 0.0 10 2
19 19/09/2020 0 0.0 10 2
20 20/09/2020 0 0.0 10 2
21 21/09/2020 0 0.0 10 2
22 22/09/2020 0 0.0 10 2
23 23/09/2020 0 0.0 10 2
24 24/09/2020 0 0.0 10 2
25 25/09/2020 0 0.0 10 2
26 26/09/2020 0 0.0 10 2
27 27/09/2020 0 0.0 10 2
STAR INFRATECH Fuel Consumption Report for Month of Sep 2020
Project: Date:
Petrol & Diesel: Issued to Vehicles / Equipments of Company and Contractors report
Receipt Qty Diesel Issue qty Petrol issue qty Balance stock
Sl.N Remarks/
Date Unit Vehicle No./ Any Total Diesel Any Total Petrol Diesel Petrol
o Diesel Petrol Millers DG Bikes Work details
Name Others Consumed Others Consumed closing closing
28 28/09/2020 0 0.0 10 2
29 29/09/2020 0 0.0 10 2
30 30/09/2020 0 0.0 10 2
Total 10 10 0 0 0 0 8 8 10 2
0
0
0
0
Any Hindrance:
1 (Please specify the problems or issues if any at site in terms of materials, drawings, payments etc )
etc
3-Nov 4-Nov 5-Nov 6-Nov 7-Nov 8-Nov 9-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov 15-Nov
16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov 22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov
29-Nov 30-Nov
STAR INFRATECH Daily Attendance List (Nov -2020)
Project:
Attendance Staff attendance Details
Month: Nov-20