You are on page 1of 10

Paper 1d

Incidents in Ammonia Plants at


IFFCO Aonla Unit
The paper describes three separate incidents in Ammonia plants of IFFCO Aonla Unit. These
incidents involved leakage of corrosive GV solution, sudden shifting and twisting of pipeline and its
supports and leakage of ammonia synthesis gas from valve body. Extent of damage due to these
leakages, efforts to contain the leakage and remedial measures to avoid such incidents in future are
also highlighted in the paper.

Rajiv Srivastava
IFFCO Aonla Unit, Bareilly, INDIA

Tarun Kaushik
IFFCO Aonla Unit, Bareilly, INDIA

Introduction Three separate incidents which occurred in these


Ammonia plants and could have been
FFCO Aonla unit operates two ammonia- catastrophic are described in this paper.

I urea plants in the state of Uttar Pradesh,


India. Ammonia plant I and II were
commissioned in 1988 and 1996 respectively. A. Damage to 20” GV rich
Both the ammonia plants are 1740 MTPD solution pipeline at exit of GV
capacity plants based on M/s. Haldor Topsoe
technology. Absorber
The carbon dioxide removal system in both the
plants is Giammarco Vetrocoke (GV) two-stage
regeneration system. The GV solution contains The Incident
27 wt% potassium carbonate along with
diethanolamine (DEA) and glycine as activators, This incident occurred in the GV system of
and 0.4 wt% vanadium pentoxide as corrosion Ammonia plant II. The Ammonia-II plant was
inhibitor. shut down on Feb 04, 2007 to attend other plant
maintenance jobs. As a practice, the GV
The only difference between the two plants’ absorber exit rich solution line emergency shut
carbon dioxide removal systems is the number off valve 33 USV-101 was closed by actuating
of hydraulic turbines. The Ammonia plant I has the trip group (IS-5). This was done to prevent
one hydraulic turbine, while Ammonia plant II liquid flow from absorber bottom.
has two hydraulic turbines.

2009 37 AMMONIA TECHNICAL MANUAL


The GV absorber was depressurized in order to This reset of IS-5 trip group should have opened
work on the passing of the inlet isolation valve the 33USV-101 valve, but in the field it did not
of hydraulic turbine (see Figure 9) of semi lean open. Two more attempts were made at resetting
pump. After replacing the passing valve, the GV the USV, as past experience has found the
system was kept ready for start up. USV’s some times tend to get stuck closed and
would not open on the 1st or 2nd attempt.
On Feb 06, 2007, start-up activities were being However the USV did not move to open
initiated and the GV circulation was to be condition.
established in preparation for vanadation and
process gas purification. At this time the instrument department was
informed and they were working on the solenoid
At this time the following events occurred: and instrument air tubing when the 33USV-101
suddenly snapped “Open”.
• A liquid level was established in the absorber
bottom sump and at about 15:00 hrs, the GV This sudden and fast opening movement of the
absorber was pressurized to 15 kg/cm2g (213 33USV-101 was accompanied with a loud
psig) using natural gas NG, as per sound, vibration and movement of the down
conventional practice for GV section start- stream piping. At this instant the GV system
up. The lean GV solution pump was started start up activities were immediately suspended
and flow of lean solution into the GV and 33USV-101 was closed immediately.
absorber was initiated through the lean
solution flow control valve. It is worthy to note that 33 USV-101 is designed
for “Slow Opening” and “Fast closing”. This
• At about 90 % absorber level, lean solution “effect” is realized in the actuator by inbuilt
flow to absorber was stopped, the three design.
absorber level control valves were closed
from operating panel and IS-5 (trip interlock The Damage
permitting opening of the 33 USV-101 valve,
which is 20” pneumatically operated ball It was observed that the 20” SS-321 piping
valve shown in Figure 1 at the rich solution down stream the 33 USV-101 and leading to the
outlet from GV absorber bottom) was reset. two hydraulic turbines (see Figure 9) had
moved by almost 300 mm (1.0 ft). The supports
of the three level control valves had broken but
not moved much. One of the 2” drain lines from
this line to the underground GV solution tank
had twisted significantly. The 20”x14” reducing
tee and the 14” elbow on the 14” GV solution
lines to the two hydraulic turbines had twisted.
The entire hydraulic turbines inlet pipe
assembly, incorporating both inlet closing
valves, had moved significantly from its
supported position. Pipeline supports were also
dislodged. See Figures 2 and 3.

Figure 1. 33USV-101 installed at Absorber


bottom rich solution outlet line

AMMONIA TECHNICAL MANUAL 38 2009


drained and flushed with demineralized water
(DMW).

The 20” common line leading to hydraulic


turbines inlet was cut and a blind plug made
from 60 mm thick SS-304 plate was placed
inside the 20” line at down stream of last elbow
(see Figure 9) and welded with full NDT
procedures. These actions were done to isolate
the damaged line for future inspection and
repairs. Absorber level control valves supports
were checked and rectified.
Figure 2. The 20” down stream piping that
suffered most damage GV circulation was established after removing
blind from 33USV-101 downstream flange and
plant was further started up. The normal start up
procedure was followed for starting GV
circulation.

The Analysis

a) For normal GV system start-up, the usual


practice was to first take the absorber
bottom liquid seal, then pressurize the GV
absorber up to 15 kg/cm2g, close the three
absorber level control valves and thereafter
open the 33 USV-101. This time also this
Figure 3. Hydraulic turbine inlet line with practice was followed.
moved supports b) The 33 USV-101 was repaired around 6
months back for passing. Since then there
had been around 3-4 occasions when it was
Actions closed and opened during plant shut down
and start-up.
c) When draining the 33 USV-101 downstream
Reviewing the damage to the piping and their
lines, it was observed that both the isolation
support system, it was decided to isolate the 20”
valves of each of the three level control
piping (see Figure 9) leading to the hydraulic
valves were passing even at minimum back
turbines. This piping had suffered the most
pressure from the down stream side (towards
damage due to sudden line movement.
the necklace line leading to the top of the
HP regenerator).
Subsequently the absorber was de-pressurized
d) During draining and de-pressurizing of the
and the line downstream of 33 USV-101 was
damaged pipeline, even at 0.2 kg/cm2g (2.84
drained of GV solution. The hydraulic turbine
psig) and 51 % level in absorber, the
inlet lines were also drained. A blind was
33USV-101 could not be operated. This
inserted in the downstream flange of 33USV-
indicated a specific problem not related to
101. This downstream line was thoroughly
the differential pressure across the valve.

2009 39 AMMONIA TECHNICAL MANUAL


e) Sometimes GV solution has a tendency to B. Damage to 16” Butterfly
crystallize which might have resulted in
temporary jamming of the internal ball of Valve in the Ammonia
the USV. Synthesis Loop
f) After the replacement of the inlet isolation
valve of the hydraulic turbine during the
plant shutdown, and subsequent preparation The Process
of the GV system for startup, a portion of
the solution inlet line to the hydraulic This incident occurred in the ammonia synthesis
turbine might not have got primed fully. section of Ammonia plant-I. The plant
Thereafter when the 33USV-101 valve originally had a conventional S-200 ammonia
snapped open, a sudden movement of liquid synthesis converter. As part of a plant upgrade,
plug inside the pipeline leading to the a new S-50 converter was installed down stream
hydraulic turbine might have caused the of the existing S-200 converter (see Figure 10).
damage.
A new HP waste heat boiler (WHB) was also
g) The actuator of 33USV-101 is designed to installed downstream of the S-200 converter to
permit slow opening and fast closing of the utilize the reaction heat generated in the S-200
valve by controlled instrument air filling and converter.
bleeding rate. When 33USV-101 was not
opening by jogging the valve, the valve was Normal operating pressure and temperature in
then tried to open by directly forcing air to the ammonia synthesis loop are 200 kg/cm2g
the actuator. This increased air pressure and (2845 psig) and 440 ºC (825 ºF) at the inlet of
air filling rate might have caused the stuck the new WHB. In order to regulate gas flow
valve to snap open. through this WHB during plant start-up, a 16”
manual butterfly valve (BUV 648, see Figure 4)
has been installed at the inlet of WHB. This
Conclusions valve was procured as per M/s Haldor Topsoe
data sheet from M/s Bohler Hochdrucktechnik,
To avoid recurrence of such problem in future, Germany. The valve material is A 182 F347 H.
the following has been envisaged:

- Installation of a 20” valve on the common


line to hydraulic turbines, as close as possible
to 33 USV-101 to avoid long length of empty
line in case of draining.

- A DMW filling connection and a high point


priming vent has been provided at the down
stream of 33USV-101 for the line going to
hydraulic turbines. A filled line would
dampen the effect of sudden opening of
33USV-101.

AMMONIA TECHNICAL MANUAL 40 2009


Figure 4. The 16” butterfly valve at the inlet of Figure 5. The butterfly valve under the platform
the WHB. with broken grating

Actions
The Incident
The plant people working in the immediately
On Jan 14, 2008, when the Ammonia-I plant vicinity rushed to a safe distance keeping the
was under start-up after a brief shutdown, this leak under observation. The Fire & Safety team
butterfly valve on the gas inlet line of WHB was put a water curtain around the leaking gas jet.
tried to open, but the valve remained stuck Simultaneously, the synthesis loop was
closed and would not open by the actuator. So depressurizing through process vent valve. The
the valve actuator was dismantled and the system was depressurized to positive pressure
maintenance crew tried to force open the valve (~10 mmWC) in about two hours. Fortunately,
by a chain block arrangement. During these no fire occurred, and due to favorable wind
efforts for opening the valve, with the system direction, ammonia vapors were dissipated
pressure around 100 kg/cm2 (1422 psig), the top without causing much panic.
portion of the valve spindle sheared off at the
location of the upper locking pin of the spindle After depressurizing, the system was purged
and flew up breaking the structural platform with inert gas, and the damaged valve was
gratings above it (see Figure 5). Synthesis gas replaced with inert gas blanketing on upstream
containing hydrogen, ammonia and other and downstream side. The plant was then
explosive gases started coming out of the started normally.
system to the atmosphere at high pressure and
temperature. This heavy leakage of synthesis
gas could have led to a catastrophic fire and Problem Faced in these Butterfly
casualty leading to shut down of the plant for valves
several months.
A similar valve was also installed in Ammonia
plant-II. Since commissioning, these valves
have presented problems of gas leakage from
glands and flanges. Despite tightening, the
leakage could not be stopped completely. Once

2009 41 AMMONIA TECHNICAL MANUAL


during opening and closing of the valve, the turbine are installed in parallel to each other.
actuator connecting rod (valve stem) sheared off The GV solution from outlet of level control
from its pin joint and actuator became valves and hydraulic turbine is sent to the top of
inoperable. The other actuator was installed in Regenerator.
its position to operate the valve and the matter
was taken up with the supplier, M/s Bohler The hydraulic turbine is provided with manual
Hochdrucktechnik. In response, the supplier inlet (20”) and outlet isolation valves (24”). At
supplied some spare items (stem, connecting the downstream of the 20” inlet isolation valve
rod, etc.) to repair the actuator. The actuator another pneumatically operated valve is
was repaired and reinstalled in Ammonia-I provided to stop the hydraulic turbine remotely
valve. (see Figure 11). The first manual inlet isolation
valve is a SS ball valve with carbon steel body.
After sometime the slot in the stem in which In order to keep the level control valves in
actuator was fitted was found broken and the operating range, the inlet isolation valve of
actuator had become in operable. So to operate hydraulic turbine was always kept in throttled
the valve, the actuator was removed and the condition.
valve was operated manually by a chain block
arrangement.
The Incident
Conclusion On the night of Oct 07, 2008, the GV system of
Ammonia plant–I was running normally.
These butterfly valves continue to be Suddenly at 22:30 hrs, a lot of steam with liquid
problematic with continuous leaks from glands spray was observed near the bottom area of
and flanges despite repeated tightening. We are absorber. Due to night hours and the steam
still looking for solutions in order to have a surrounding the area, it was difficult to sight and
valve in such process conditions that will be free pinpoint the source of leakage, however it was
from leakages. Meanwhile, the manufacturer is obvious that there was a big leak of GV solution
supplying modified valve spindle arrangement from absorber bottom. Concurrently a fast drop
with locking arrangement which will ensure that in the level of absorber was also observed in the
the spindle does not blow off in any condition. main control room.

Actions Taken

C. Failure of Isolation Valve In order to isolate the leakage point, the trip
Body in Potassium Carbonate valve 13USV-101 at the absorber bottom rich
solution outlet line was closed from the control
Service room leading to a plant shutdown. Process gas
was vented to the flare stack from upstream of
the absorber. The absorber gas inlet isolation
The Process valve which is a motor driven valve, was also
closed remotely. The pneumatically operated
In Ammonia plant-I the rich GV solution from valve on the absorber outlet gas line was also
absorber bottom is let down through two closed to completely isolate the absorber. GV
absorber level control valves and a hydraulic solution pumps feeding solution to absorber
turbine. The level control valves and hydraulic were also stopped.

AMMONIA TECHNICAL MANUAL 42 2009


Despite closing the low-level trip valve 13 Once the absorber was depressurized and almost
USV-101, the level in absorber continued to fall all GV solution was drained from it through
due to 13USV-101 passing. Gradual permanent drains to GV storage tanks, the GV
depressurizing of absorber was started to flare to solution leakage was stopped. With no leakage,
stop explosive gas escaping from absorber the leaking valve was inspected after removing
bottom under high pressure. Meanwhile the body insulation. A large hole, about 2” in size,
outlet isolation valves of hydraulic turbine and was observed on the valve body from which
level control valves were closed manually in leakage had occurred (see Figure 7).
order to minimize the leakage.
After completely draining the upstream and
In spite of all these efforts, the GV solution downstream lines, the valve was removed. A
continued to leak out in the form of a jet stream. new gate valve (see Figure 6) which was
The leaking GV solution soon flooded the entire available was installed in its place and normal
nearby floor, the under ground GV effluent plant start up operation was resumed.
tank, and the open surface drains beside the
Ammonia plant-1. It even overflowed the small
dyke wall provided in the GV area. With falling
pressure and level in the absorber, the extent of
leakage was reduced to some extent, allowing a
clear view of the leaking point. From a
distance, it appeared as if the leakage was from
the downstream flange of the inlet isolation
valve of hydraulic turbine. With great caution
the inlet isolation valve was also closed
manually but GV solution leakage continued
unabated.

Mean while a full work force swung into action Figure 6. The new gate valve installed
in order to stop GV solution finding its way out downstream of 13USV-101
of factory through plant surface drain. The GV
solution is not environment friendly and must be
stopped from going to surface drains. The extent of leakage was such that 40.0 MT of
potassium carbonate (~ 20 % of total inventory
GV solution was flowing into the surface drains of GV system) was required to bring up the
near the Ammonia plant-1 and moving towards normal GV solution concentration on restart of
the offsite main surface drains. Many bunds the plant. Normal annual plant consumption of
were quickly placed at various locations of the potassium carbonate is 20.0 MT.
drain using makeshift obstacles. GV solution
was pumped from the over flowing underground
GV effluent tank to large offsites effluent guard The Damage
ponds. Portable dewatering pumps were pressed
into service to empty the surface drains (near The ruptured valve was later dismantled and its
Ammonia plant-1) full of GV solution into a SS ball was taken out from the CS body. There
readily available large GV storage tank in the was no damage found to the SS ball, however,
Ammonia plant-1. With these efforts, GV the CS body of the valve was found heavily
solution was prevented from going outside of eroded and corroded from inside (see Figure 8).
the ammonia-urea complex premises. The material loss from valve body was so

2009 43 AMMONIA TECHNICAL MANUAL


extensive that the wall of body was reduced to Analysis
only about 1.0 mm thick in many places. It was
surprising that such a thin walled body could During operation this isolation valve was kept in
hold GV solution pressure for so long. The a throttled condition (i.e. it was not kept opened
thinning was so wide spread that valve body fully) to control the liquid flow to the hydraulic
could have ruptured in a more violent way turbine. Another hydraulic inlet control valve
which could have been catastrophic. which was provided originally, was removed
much earlier due to damage. The throttling of
the valve, allowed the hot, corrosive CO2 rich
GV solution to flash and impinge continuously
on the inside of valve body while at the same
time flowing turbulently through the partial
opening of the ball of the valve. This continuous
impingement of hot and corrosive solution
eroded and corroded the valve body over a
period of time which ultimately culminated in
failure of the valve body.

The Conclusion

It was not a regular practice to check the valve


Figure 7. The ruptured valve showing the hole body thickness during the plant operation. With
and thinning of valve body. regular thickness measurements, the problem
could have been identified much earlier and
leakage could have been prevented. The
incident also underlines the significance of
proper valve operation. This particular valve
was not meant for flow control and thus should
not have been kept throttled. Now all such
valves have been checked with regular
inspection of valve body thickness
measurements.

The newly installed gate valve is now kept full


open, and a new control valve has been installed
at the inlet of the hydraulic turbine at the
location where the earlier control valve had got
damaged. This control valve is modulated as per
process requirement so as to let a major portion
of the absorber outlet rich GV solution flow
Figure 8. Inside of the ruptured and eroded through the hydraulic turbine and a relatively
valve body small flow is letdown through the absorber level
control valves for control of absorber bottom
level.

AMMONIA TECHNICAL MANUAL 44 2009


Figure 9. Schematic of Ammonia plant-II GV system showing 33USV-101 and the
hydraulic turbines.

Figure 10. Schematic of Ammonia plant-II synthesis loop showing the energy saving
modification and the butterfly valve at gas inlet to new WHB .

2009 45 AMMONIA TECHNICAL MANUAL


Figure 11. Schematic of Ammonia plant-I GV system showing 13USV-101, the hydraulic
turbine and the ball valve which leaked.

Authors

Rajiv Srivastava, JGM (P)


IFFCO Aonla Unit

Tarun Kaushik, DGM (Ammonia)


IFFCO Aonla Unit

AMMONIA TECHNICAL MANUAL 46 2009

You might also like