LATITUDE-DEPARTURE AND AREA OF A TRAVERSE

FIELD WORK 4

DATE: 09/22/21 SCORE:

SCHEDULE: MWF INSTRUCTOR: Luzmirasol Domondon

A. DETERMINE THE LATITUDE-DEPARTURE OF THE TRAVERSE, LINEAR ERROR OF


CLOSURE, BEARING OF THE SIDE OF ERROR, RELATIVE PRECISION, AREA OF
THE TRAVERSE.

LINE LENGTH ADJUSTED LATITUDE DEPARTURE DMD/DPD DA


BEARINGS
AB 46.50-m S 30° 40’ W -

40M -23.72m
-
23.72m 948.8m
BC 75.15-m S 83° 45’ E -
8.18m 74.70M 27.26m -222.99m
CD 117.35-m N 01° 10’ W 117.33m -2.39M 99.57m 11672.69m
DE 74.92-m S 89° 20’ W -
0.87m -74.91m 22.27m -19.37m

EA 60.25-m S 28° 05’ E -


53.16m 28.36m 24.28m 1290.72m
SUM of DA = 13669.7359m
AREA = 6834.8759m

Bh.
D
E

C
E-B-qz.fr
COMPUTATION:

COMPUTATION:
LAT ab = 46.50m cos(30°40’) = -40m
LAT bc = 75.15m cos(83°45’) = -8.18m
LAT cd = 117.35m cos(1°10’) = 117.33m
LAT de = 74.92m cos(89°20’) = -0.87m
LAT ea = 60.25m cos(28°05’) = -53.16m

15.12m
DEP ab = 46.50m sin(30°40’) = -23.72
DEP bc = 75.15m sin(83°45’) = 74.70
DEP cd = 117.35m sin(1°10’) = -2.39
DEP de = 74.92m sin(89°20’) = -74.91
DEP ea = 60.25m sin(28°05’) = 28.36

2.04m
LEC =√(15.12)² + (2.04)² = 62.92m
Tan ϴ = -2.04 / -0.93 = 65°29’
RP = 62.92/374.17 = 0.17m
DMD Method
DMD-AB= -23.72m
DMD-BC= -23.72 + -23.72 + 74.70 = 27.26m
DMD-CD = 27.26 + 74.70 + (-2.39) = 99.57m
DMD-DE = 99.57 + (-2.39) + (-74.91) = 22.27m
DMD-EA = 22.27 + (-74.91) + 28.36 = -24.28m
DA-AB = -23.72 (-40) = 948.8
DA-BC = 27.26 (-8.18) = -222.99
DA-CD = 99.57 (117.23) = 11672.59
DA-DE = 22.27 (-0.87) = -19.37
DA-EA = -24.28 (-53.16) = 1290.72

DA =13669.73 sqm
Area = 0.5(13669.73)
= 6834.87sqm