Professional Documents
Culture Documents
•If there is a fault on the same feeder, the customer will experience a
voltage sag during the fault followed by an interruption when the breaker
opens to clear the fault.
•It will usually require about 5 or 6 cycles for the breaker to operate,
during which time a voltage sag occurs.
•Note that to clear the fault shown on the transmission system, both breakers A
and B must operate.
•The distribution fault on feeder 4 may be cleared either by the lateral fuse or the
breaker, depending on the utility’s fuse saving practice.
Example of fault locations that caused
misoperation of sensitive production equipment
at an industrial facility (the example system
had multiple overhead distribution feeders and
an extensive overhead transmission system
supplying the substation).
•The system was restored Utility short-circuit fault event with two fast trip
after the second operation. operations of utility line recloser.
3.2 Estimating Voltage Sag Performance
1. Determine the number and characteristics of voltage sags that result from
transmission system faults.
2. Determine the number and characteristics of voltage sags that result from
distribution system faults (for facilities that are supplied from distribution systems).
3. Determine the equipment sensitivity to voltage sags. This will determine the
actual performance of the production process based on voltage sag performance
calculated in steps 1 and 2.
The latter term is defined as the minimum voltage magnitude a piece of equipment
can withstand or tolerate without misoperation or failure.
This is also known as the equipment voltage sag immunity or susceptibility limit.
The loads will be subject to faults on both the transmission system and the
distribution system.
3.2.2 Equipment
sensitivity to voltage sags
•On the other hand, for a customer Typical equipment voltage sag ride-
supplied from the distribution system, the through capability curves.
voltage sag performance will depend on
•the fault performance on both the
transmission and distribution systems.
•Most utilities have detailed short-circuit models of the
interconnected transmission system available for programs such
as ASPEN* One Liner (Fig.).
•The area of vulnerability describes all the fault locations that can
cause equipment to misoperate.
• ONLINE UPS
• OFFLINE/STANDBY UPS
• HYBRID UPS
ONLINE UPS
•The load is always fed through
the UPS. The incoming ac
power is rectified into dc power,
which charges a bank of
batteries. This dc power is then
inverted back into ac power, to
feed the load.
•If the incoming ac power fails,
the inverter is fed from the
batteries and continues to
supply the load.
•However, the on-line operation
increases the losses and may
be unnecessary for protection
of many loads.
OFFLINE/STANDBY UPS
•A standby power supply is
sometimes termed off-line UPS
since the normal line power is
used to power the equipment until
a disturbance is detected and a
switch transfers the load to the
battery backed inverter.
•The transfer time from the normal
source to the battery-backed
inverter is important.
If full-voltage starting is used, the sag voltage, in per unit of nominal system
voltage, is
where V(pu) = actual system voltage, in per unit of nominal ; kVALR = motor
locked rotor kVA ; kVASC = system short-circuit kVA at motor
3.7 Utility System Fault-Clearing Issues
3.7.1 Overcurrent coordination principles
3.7.2 Fuses
3.7.3 Reclosing
>> UD cables
>> Line arresters
Jussi Ahola, ABB Oy
Divide the
network into
zones based on Control room
protection zones
and control Distributed
zones generation
Limit the effects
of disturbances Communication
to smaller areas
Disconne
brings less
ctor
consumers
Station
affected and
revenue lost
Get improved
voltage quality
(light substations
and shorter lines)
Get improved
use of the
distribution
network
investments
heals higher
degree of
utilization, less
stress on the
network and
improved asset
Recloser station Switching
management
Substation Pole mounted Pole
recloser mounted Station
Adapts to
changes in the
switch-
operational
disconnect
environment
or
which can be
implemented
step by step and
grows with the
requirement
© ABB Group
March 10, 2018 | Slide 51
A self-healing power system
Intelligent Zone concept components
Distribution
Management
System
© ABB Group
March 10, 2018 | Slide 52
A self-healing power system
Intelligent Zone concept components
REF615
Bay level
Protection
algorithms
for short
Distribution
circuits and
Management
earth fault
System
Disturbance
data
recording,
COMTRAD
E
Enable
prediction
of non-
permanent
earth faults
Fully
automated
fault
localization
© ABB Group
March 10, 2018 | Slide 53
A self-healing power system
Intelligent Zone concept components
RER601, Protection
REC603 Zone level
Wireless
Gateway Reclosers
enable
Distribution
automatic
Management
isolation
REC523 System
Indicators
transmit the
fault status
Recloser OVR3
SECTOS
Fault Indicator
© ABB Group
March 10, 2018 | Slide 54
A self-healing power system
Intelligent Zone concept components
M2M Communicati
Gateway on
Secure end-
to-end
Distribution
communicati
Management
on utilising
System
M2M VPN
technology
and built-in
firewall
Precise,
real-time
data
acquisition
from your
distribution
network with
standardized
protocols
IEC 60870-
5-104
(GPRS)
© ABB Group
March 10, 2018 | Slide 55
A self-healing power system
Multiple levels of security
APN TUNNELING
Private IP address on
equipment level: not visible to
public, only through M2M
gateway
GPRS radio signals are crypted
with multiple algorithms
Equipment has in-built firewalls:
COMMS EQUIPMENT
accepts traffic only from M2M
gateway
A self-healing power system
Intelligent Zone concept components
COM600 Substation
level
Grid
Automation
Distribution
Controller
Management
Generates
System
the fault
report to
DMS
© ABB Group
March 10, 2018 | Slide 57
A self-healing power system
Intelligent Zone concept components
MicroSCAD
A Pro DMS
Distribution
600 Management
level
DMS
Distribution
analyzes the
Management
fault report
System
Locates the
fault on
geographical
map
Network
reconfigurati
on
Generates
restoration
sequence
Possibility to
run the
sequence
automaticall
y through
SCADA
Fault
reporting
even for
© ABB Group
non-
March 10, 2018 | Slide 58 permanent
faults
A self-healing power system
Advanced fault reporting
Where to start
SAIDI > 200min
Fault location and isolation based on ”trial and error”-
method - increase also SAIFI, specially at the end of
feeders
Only 15% of fault could be located, overcurrent faults
Target
Improve the reliability - reduce SAIDI by 50%
Verify the functionality of the concept
© ABB Group
March 10, 2018 | Slide 60
Pilot Case
Fortum Oy, Masala
Zone Concept
2 feeders
4 protection zones
20 remote zones
The pilot scope
Disconnectors with
fault indication 4 pcs
ABB RER601
KOHU + REC523
Overhead reclosers 2
pcs
Total feeder length
100km
© ABB Group
March 10, 2018 | Slide 61
Pilot Case
The results and the conclusion
© ABB Group
March 10, 2018 | Slide 62
Minimizing Plant Interruption
Caused by Line Disturbances Using
Active Voltage Conditioners
IEEE Canada – Webinar Presentation
May 21, 2008
www.ieee.ca
Presentation Overview
• Telecommunications
• Robotics
What is the Primary Problem ?
• Voltage Sags have been identified as being the
Single Most Expensive Power Quality Event
Interruption
New ITI (CBEMA) Curve
Accident Happens !
Birds Nest
A bad day for this driver
Electrical Dist. System – Spaghetti Design
Causes of Voltage Sags
• External (Utility System)
- Bad Weather
- Equipment Failure
- Human Error,
- Animals & Birds,
- Vehicle, etc.
HRG
600V 3Ø 3W
Voltage Sag TO 50% for 4 Cycles- UPS System
Crashed due to Bad Battery Cell in each of the four
strings. Disturbance caused by a fault on 230 KV line
UPS Alarm History
0123 05/12/01 14:00:09.11.1 sbs on
0124 05/12/01 14:00:09.11.1 inverter off
0125 05/12/01 14:00:09.10.2 dc low shutdown
0126 05/12/01 14:00:09.10.2 dc voltage low
0127 05/12/01 14:00:09.10.1 input voltage normal
0128 05/12/01 14:00:09.09.2 battery voltage low
Supply
load
Rectifier Inverter
Key Features
• Provides rated % protection for 30 Seconds
• It is an On Line device so no switching threshold
• Fast response < ¼ ms to initiate correction
• Complete correction to ±1% in 6 ms (< 1/2 cycle)
• Continuously variable control (no step changes in
output)
• Very efficient (typically > 98.5%)
• High speed microprocessor controlled solution
• Continuous +/-10% voltage correction
Inverter controlled power conditioning
for high power applications
AVC Ratings
25 kVA to 5 MVA 1 MVA to 50 MVA
(Low Voltage 208V-600V) (Medium Voltage 2-36kV)
Ref. Sag/Swell AVC Output (L-L)
3- phase symmetrical sags – A 109%, 109%, 109% 100%, 100%, 100%
AVC Response B 68%, 69%, 69% 99%, 99%, 100%
C 49%, 50%, 49% 80%, 81%, 81%
C
Ref. Sag/Swell AVC Output (L-L)
1- ph. Unbalanced sags – A 80%, 100%, 100% 100%, 100%, 100%
AVC Response B 49%, 100%, 100% 97%, 99%, 99%
C 39%, 100%, 100% 93%, 98%, 98%
EPRI Factory Test 70% 71%
A 99% 100%
70% Sag
71% C 100%
93
%
61
%
A 92.7% 97.4% EPRI Tests
CH2 V L-G, 40% Sag on
92 C 99.2% 480V system
%
CH2
Storage
Battery
Ultra-Capacitors Flywheel
AVC front panel - Run
AVC front panel - Events
AVC front panel - Features
IP Addressable
MODBUS TCP
AVC Maintenance
LCD touch screen Modular design Modules in cabinets
c/w diagnostics
Use of AVC in conjunction with UPS
Facility Supply Bus - Voltage independant
Essential
Production systems
U PS
10-50kVA
Critical Loads
M PLC's, Controls
etc
Large non critical loads
AVC Installed Base
30,000.00
V1 V2 V3
AVC 25,000.00
20,000.00
Output 15,000.00
10,000.00 L-N Volt
V1=97 %
5,000.00
Voltage 0.00
V2=98 %
-5,000.00
-10,000.00
V3=97 %
-15,000.00
-20,000.00
-25,000.00
Can correct the voltage sags close to your critical equipment and
prevent unplanned stoppages
Field Measurements – Case 1
L-N Volt
V1=87%
V2=92%
V3=34%
L-N Volt
V1=100%
V2=100%
V3=80%
L-L Volt
V1=100%
V2=90%
V3=90%
Field Measurements – Case 1
L-N Volt
V1=62%
V2=64%
V3=96%
L-N Volt
V1=87%
V2=98%
V3=92%
L-L Volt
V1=90%
V2=91%
V3=91%
Field Measurements – Case 1
L-N Volt
V1=78%
V2=78%
V3=92%
L-N Volt
V1=100%
V2=100%
V3=100%
Case 1 - Installation
High Voltage compartment (26kV)
Injection Transformer
Case 2 – Polyethylene Plant
•115kV Utility supply
•8 -10 process upsets per year,
most caused by lightning and birds
•Plant restart and recoveries in
some cases took several days
•Lost production and damage to
equipment were they the largest
cause of loss
Solution - Polyethylene
• Customer originally requested 60MVA AVC
protection but this was not cost effective
• Protected Extruders, Cutters and agitators only
• 5 AVCs each 2MVA at 480V installed - 2007
• To date averted 5 potential shutdowns
• Customer reported full project payback in first 4
events (Less than 6 months)
Case 3 - Solar Cell Manufacturer
Thank You