Complex problem
COMPLEX PROBLEM
Pakistan is among the most urbanized countries of South Asia. As challenges mount, urban
planning is gradually finding space in the policy discourse. It causes the pace of urbanization and
the major problems associated with it. From which one of the problem caused by the
urbanization is housing.
The State Bank of Pakistan has estimated that across all major cities, urban housing was
approximately 4.4 million units short of demand in 2015. If current trends continue, Pakistan’s
five largest cities will account for 78 percent of the total housing shortage by 2035. Even if
urban population remains stagnant, the growing trend of nuclear families who seek housing
separate from larger families will increase pressure on housing supply.
When provided, housing is often low quality. Pakistan ranks eighth among the ten countries
that collectively hold 60 percent of substandard housing across the world. Karachi, one of
the world’s fastest growing megacities with an estimated 17 million people, ranks second
lowest in South Asia and sixth lowest in the world on the Economist Intelligence Unit’s 2015
livability index.
Page 2 of 20
Complex problem
This initiative would mean doubling the capacity at least of all construction related
industry.
This initiative would also mean another one to three hundred thousand jobs in the service
industry that is banking, security, maintenance, insurance etc.
Subtotal of those
which will be built
150000 400000 500000 500000 500000
under APNA
Housing Authority
This was the planning that is given by the government of Pakistan. As an emerging civil
engineer, it’s our duty to provide a solution which would be sustainable and socioeconomically
viable and culturally acceptable in the designated locality and this was basically our project.
Page 3 of 20
Complex problem
Assignment problem:
We have to design a house which will comply all applicable statutory regulations related with
house construction. The area of house may range from three to five Marla; one floor to three
floors. State the materials, machinery, labor and methodology to be used in construction of above
said house. We take the inputs from others disciplines involved in the construction mechanical,
sewerage and plumbing; electrical: wirings and conduits. And we have made proper project
initiation, management and planning for this project.
Adjust the relative locations of various parts of house according to specified region of Pakistan
(e.g. Lahore & Peshawar may be different) By laws of LDA, DHA, Fazia Housing and Bahria
Town may be assumed for your house, if not available You are encouraged to prepare drawings
in AutoCAD format You should write final report in proper technical and academic English and
final Power Point presentation is also preferable.
Procedure contents
Location:
Facilities
Construction materials
Cost estimation
Methodology:
Solutions
Map of house
Electrical installation
Plumbing
Sewerage
Page 4 of 20
Complex problem
Location
We have chosen Lahore city for our project the reason for this:
Population Population
Rank City Change Province
2017 Census 1989 Census
As we can see that the Lahore is the city in which population increases up to 113.59%
which is the most in all of them. So this one reason that this city needs housing.
Lahore has seen various mega-infrastructure projects in the past few years. The other side of
these developments is the increase in the number of slum settlements. Because of a lack of
availability of affordable housing, a large part of the city’s population is left with no option but
to settle in slums where they lack basic utilities needed for a dignified life
Page 5 of 20
Complex problem
Facilities:
Further in Lahore I select area Johar town as a role model for society and build
house in this type of society because a poor person Urban poor left with no option other than
informal means of living. It is only way out to most poor to live in inadequate housing
settlements near the city centers to fulfill their need for accommodation and employment.
This is a kind of area from where every kind of basic facility is near then whether it is hospitals,
educational centers, banks, markets, shopping centers, patrol pumps, general stores basically we
need to facilitate the poor with every basic need.
Page 6 of 20
Complex problem
Grey structure:
The major items required for the construction of a grey structure include cement, bricks, gravel,
sand, rebar, and piping for electrical and plumbing work. Being the most important part of any
construction project, labor cost is one of the major expenses. Here is the expense breakdown for
all items and labor:
Sample project:
5 Marla house construction cost (250 sq. yd). Covered area 2125 sq. ft. Item wise per square
foot cost calculations
Calculation:
2. Crush 60 Rs/sq.ft
Calculation:
60 Rs x 2125 sq.ft=127500Rs
Page 7 of 20
Complex problem
Calculation:
5. Sand 35 Rs/sq.ft:
Calculation:
35 Rs x 2125 sq.ft=119000 Rs
Calculation:
Page 8 of 20
Complex problem
Calculation:
Other items
10.Electricity items 20 Rs/sq.ft
Calculation:
Calculation:
15.Bitumen 4 Rs/sq.ft
Calculation:
17.Mud 3 Rs/sq.ft
Calculation:
Calculation:
19.Taxes 5 Rs/sq.ft
Calculation:
Page 10 of 20
Complex problem
Calculation:
15 Bitumen 4 8500
16 Polythene sheet 3 6375
17 Mud 3 6375
18 Chips 4 8500
19 Taxes 5 10625
20 Electric bills 5 10625
21 Boring 4 8500
22 Random 10 2125
Page 11 of 20
Complex problem
Main gate:
Calculation:
-Windows surface area rate in any good brand 1.3 gauge with clear 5 mm glass in silver color up to Rs 330/sq.ft
Granite 40 Rs/sq.ft
Calculation:
Page 12 of 20
Complex problem
-Bathroom accessories (towel rod, soap dish, tissue holder etc) imported brand up to Rs 4000/set
-Other indoor and outdoor plumbing hardware (bottle traps, waste pipes, covers, taps etc.)
Paints:
Calculation:
Page 13 of 20
Complex problem
Let us see what will be the total house construction cost of finishing works:
Cost Total
S# Item per approximate
sq.ft price(Pak Rs)
1 Paint 90 191250
3 Granite 40 85000
Aluminum
4 42 89250
windows
Page 14 of 20
Complex problem
Page 15 of 20
Complex problem
Methodology
Designing of the house:
We take an idea from the internet and then we sketch our plan of house on auto cad, and we also
drew this sketch on the sheet on which first we draw the ground floor then second floor and the
top floor. We also draw the elevation and sectional cutting drawing of our design of house .We
made this design keeping in mind the rules which were given by Lahore development authority.
Page 16 of 20
Complex problem
Our design:
Page 17 of 20
Complex problem
Page 18 of 20
Complex problem
Page 19 of 20
Complex problem
The above map shows our foundation denser height of wall, area of every room kitchen and
bathroom. We have already discussed the materials used in construction and cost estimation for
this has already done. We will make a plan of proper sewage electrical resistance and mechanical
installation and all o]the facilities that should have given to a society and home.
Page 20 of 20