You are on page 1of 13

Project : SLF Extention 2

Location : Brgy San Jose Sico


Subject : Gantt Chart For Existing and New SLF Extention

JANUARY 2020 FEBRUARY 2020


Item Description No. of days 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Existing SLF
2 Site Clearing Plan 5 1 1 1 1 1
Actual 5 1 1 1 1 1
3
Excavation of SLF Plan 41 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Actual 21 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Excavation of SLF Proposal Plan 12 1 1 1 1 1 1 1 1 1 1 1 1


1 Cell and Clearing Area 840 cu.m. / day Actual 0

Target Full Capacity of Existing SLF will be on Feb 29, 2020 #REF! days Target Plan 12 days @ February 11, 2020
Target Finished of Excavated Cell atleast 1 of 20x20x20m and right of way and
hustling of materials 20.00 days Equipement Needed
Backhoe 4.00 nos.
For the Hustling of Soil 20 cbm capacity 34.00 trips / day Bulldozer w/ Reefer 1.00 no.
Soil that need to haul 680.00 cu.m. / day Trucks 20 cbm / 7 trips/day 6.00 nos. say 42 trips / day
840.00 cu.m./DAY
Equipement Needed 10,080.00
Backhoe 3.00 nos.
Bulldozer 2.00 nos.
Trucks 20 cbm / 7 trips/day 5.00 nos. Base on Actual Hauling = 40 trips / 1 Truck of 20CBM

Existing Volume of SLF (existing) 58.5 x 102 x 35m 208,845.00 cu.m.

Capacity Total
Trucks Trips cu.m. Volume Cu.m/Day Days @ 10800 cu.m.
Volume Hauled September 12 - Jan 13 2020 135,866.00 cu.m.
Existing SLF as of January 13 2020 72,979.00 cu.m. 1 40 20 800 840 1.05 13.5
Total Volume per day including Metro Waste (1,095 cu.m. + 450 cu.m.) 47.2355987 days = say 48 days 2 40 20 1600 840 0.525 6.75
3 40 20 2400 840 0.35 4.5
4 40 20 3200 840 0.2625 3.375
New SLF 1 Cell ( 20x20x20) 8,000.00 cu.m. 5 40 20 4000 840 0.21 2.7
Site Clearing 2,000.00 cu.m. 6 40 20 4800 840 0.175 2.25
Rough Estimate 10,000.00 cu.m.
Truck ( 20 CBM capacity ) 20.00 cu.m.
sub-total 500.00 Trips
Target Plan 15.00 days
sub-total 33.33 Trips / day
say 34.00 Trips / day Prepared by : JAY GENER
8,000.00 5.18
9.16

Phase 2 16,858.13
Description Area Depth Total cbm/dy
Phase 2A 3,663.09 20.00 73,261.80 800.00
Phase 2B 4,786.90 20.00 95,738.00 800.00
Phase 2C 3,492.96 20.00 69,859.20 800.00
Phase 2D 4,915.18 20.00 98,303.60 800.00
16,858.13 337,162.60

Phase 2 16,858.13
Description Area Depth Total cbm/dy
Phase 2A 3,663.09 20.00 73,261.80 1,200.00
Phase 2B 4,786.90 20.00 95,738.00 1,200.00
Phase 2C 3,492.96 20.00 69,859.20 1,200.00
Phase 2D 4,915.18 20.00 98,303.60 1,200.00
16,858.13 337,162.60

Phase 2 16,858.13
Description Area Depth Total cbm/dy
Phase 2A 3,663.09 20.00 73,261.80 1,800.00
Phase 2B 4,786.90 20.00 95,738.00 1,800.00
Phase 2C 3,492.96 20.00 69,859.20 1,800.00
Phase 2D 4,915.18 20.00 98,303.60 1,800.00
16,858.13 337,162.60
Dumping
Description Area Depth Total cbm/dy
Phase 1 existing 7,611.00 20.00 152,220.00 800.00
7,611.00 15.00 114,165.00 800.00
7,611.00 266,385.00

Actual 135,866.00 9/12/19 to 1/13/2020


88.00
1,543.93

130,519.00
84.48 days
29.00 january 13 - feb 23
55.48 days 172.48
6.52

172.48
117.00
55.48
15.53

Day Say 12 hrs


91.58 92.00 Backhoe 4
119.67 120.00 Bulldozer w reefer 1
87.32 88.00 Loader 1
122.88 123.00 Trucks 6
421.45 423.00 days
1.15 1.16 year

Day Say 24 hrs


61.05 62.00 Backhoe 4
79.78 80.00 Bulldozer w reefer 1
58.22 59.00 Loader 1
81.92 82.00 Trucks 6
280.97 283.00 days
0.77 0.78 year
2 8000

Day Say 24 hrs


40.70 41.00 Backhoe 6
53.19 54.00 Bulldozer w reefer 1
38.81 39.00 Loader 1
54.61 55.00 Trucks 6 800 400
187.31 189.00 days 2400
0.51 0.52 year
2 8000
47.418640776699
Day Say 1545
190.28 191.00
142.71 143.00
332.98 334.00
32000
1600

19,739.00

8,000.00
144,000.00
480,000.00

8000 20 400

480.00
12.00

1.04
9,600.00
10,000.00
9,600.00
1.04
Development 10,000.00 sq.m.
Target Completion 3.00 months
Hours of Work 8.00 hrs.
Backhoe Capacity per day 400.00 cu.m/day
Height 25.00 l.m.
Volume 250,000.00 cu.m.

@ 3months 2,777.78 cu.m./day


@ 400 cu.m./day 6.94 no. of backhoe
say 7.00 backhoe

Backhoe 7.00 400.00 2,800.00 cu.m./ day


233.33333
@ 40 Trips per day 5.8333333
Dumptruck say 6 nos.

Equipment Needed
Buldozzer 2.00 nos
Backhoe 7.00 nos 2 RG 1 WCI
Dumptruck 6.00 nos

AAM 1
RG 2
Caguioa 1
RGY 1
Development 20,000.00 sq.m.
Target Completion 3.00 months
Hours of Work 8.00 hrs.
Backhoe Capacity per day 400.00 cu.m/day
Height 25.00 l.m.
Volume 500,000.00 cu.m.

@ 3months 5,555.56 cu.m./day


@ 400 cu.m./day 13.89 no. of backhoe
say 13.00 backhoe

Backhoe 13.00 400.00 5,200.00 cu.m./ day


433.33333
@ 40 Trips per day 10.833333
Dumptruck say 11 nos.

Equipment Needed
Buldozzer 4.00 nos
Backhoe 13.00 nos
Dumptruck 11.00 nos
Development 30,000.00 sq.m.
Target Completion 3.00 months
Hours of Work 8.00 hrs.
Backhoe Capacity per day 400.00 cu.m/day
Height 25.00 l.m.
Volume 750,000.00 cu.m.

@ 3months 8,333.33 cu.m./day


@ 400 cu.m./day 20.83 no. of backhoe
say 20.00 backhoe

Backhoe 20.00 400.00 8,000.00 cu.m./ day


666.666667
@ 40 Trips per day 16.6666667
Dumptruck say 16 nos.

Equipment Needed
Buldozzer 4.00 nos
Backhoe 20.00 nos
Dumptruck 16.00 nos
Development 30,000.00 sq.m.
Target Completion 3.00 months
Hours of Work 8.00 hrs.
Backhoe Capacity per day 400.00 cu.m/day
Height 30.00 l.m.
Volume 900,000.00 cu.m.

@ 3months 10,000.00 cu.m./day


@ 400 cu.m./day 25.00 no. of backhoe
say 25.00 backhoe

Backhoe 25.00 400.00 10,000.00 cu.m./ day


833.33333333
@ 40 Trips per day 20.833333333
Dumptruck say 21 nos.

Equipment Needed 8 hrs 16hrs


Buldozzer 4.00 nos
Backhoe 25.00 nos 12
Dumptruck 21.00 nos
Target Area 8,100.00 sqm

Development 2,025.00 sq.m.


Target Completion 1.00 month
Hours of Work 8.00 hrs.
Backhoe Capacity per day 400.00 cu.m/day
Height 20.00 l.m.
Volume 40,500.00 cu.m.

@ 1month 1,350.00 cu.m./day


@ 400 cu.m./day 3.38 no. of backhoe
say 4.00 backhoe

Backhoe 4.00 400.00 1,600.00 cu.m./ day


133.33333333
@ 40 Trips per day 3.3333333333
Dumptruck say 6 nos.

Equipment Needed
Buldozzer 1.00 nos
Backhoe 4.00 nos
Dumptruck 6.00 nos
Development 2,025.00 sq.m.
Target Completion 25.00 days
Hours of Work 8.00 hrs.
Backhoe Capacity per day 400.00 cu.m/day
Height 20.00 l.m.
Volume 40,500.00 cu.m.

@ 1month 1,620.00 cu.m./day


@ 400 cu.m./day 4.05 no. of backhoe
say 5.00 backhoe

Backhoe 5.00 400.00 2,000.00 cu.m./ day


166.66666667
@ 40 Trips per day 4.1666666667
Dumptruck say 6 nos.

Equipment Needed
Buldozzer 1.00 nos
Backhoe 5.00 nos
Dumptruck 6.00 nos

You might also like