RISK ASSESSMENT
Page 1 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
2. Mobilization of Over speeding, Collision between vehicles / plants / Operator, 4 3 12 Project traffic management plan shall be communicated to drivers /vehicle 4 1 4
manpower, equipment / pedestrians at site users.
leading to major injury; fatality and Workers, Vehicle operators must have valid drivers license,
Page 2 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
materials, tools and Unsecured load, property damages, Staff, All personnel involved must be inducted prior to activities,
equipment Fall of load leading to minor/ major Only vehicles fit enough/road worthy for activities shall be mobilized for
injury or fatality, Other contractors activities with valid licenses, TPC’s (if required) and any other relevant
Vehicle overturning, documents
Highly unstable road terrain, Equipment/materials
Page 3 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Collapse of unfit vehicle Maximum speed limit of 30Km/H and as per WEBAG site speed limits shall be
operators/workers caused by adhered to at all times in site
Incompetent driver, unstable health situation. Mobilization and vehicular movements shall heed to approved mobilization
Collision with neighboring route at all times
contractors’ assets leading to
Page 4 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Improper work coordination and damage of equipment/injury/fatality Ensure good traffic/pedestrian management
supervision Environmental pollution via dust Ensure that vehicle operators fasten seatbelts at all times during operations
creation caused by over speeding Ensure loads are properly secured and tied off,
Ensure banksman is present wherever applicable during movement,
Page 5 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Deviation from approved MS/vehicle Ensure the road / area is well compacted and graded to prevent the truck from
routes, skidding and stuck in soft spot.
Medical fitness test to be conducted for workers
Page 6 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 7 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Unfit/unhealthy vehicle
operators/workers
Page 8 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 9 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Cables/cable drums, Fall of cables and materials on Workers, Truck shall be parked at a safe place and wedged to avoid moving.
accessories and worker Experienced workers to be used for loading& unloading of materials.
Incorrect equipment and Pedestrian, Loading/unloading must be carried out as per approved procedure,
tools Crush injuries
accessories, Activities must be supervised by authorized competent person,
Trip and fall
Page 10 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Equipment, Materials. Banks man shall be appointed to control all vehicular movements during
activities
Rolling cable drums Only a certified equipment operator shall be deployed for all forms of
lifting activities,
Page 11 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
A certified rigger by third Party will assist the crane and forklift operator
during and operation.
Unsecured cable drums Ground stability shall be ensured prior to positioning lifting equipment,
loading and unloading
Page 12 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 13 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 14 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Lack of supervision,
Page 15 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Loading/unloading on unstable
grounds,
Page 16 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 17 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
4. Lifting Operation Improper lifting procedure Fatality Personnel 4 4 16 Relevant PTW system shall be applied and adhered to at all times 3 2 6
Boom truck / crane and other lifting equipment and accessories (lifting
gears) shall be third party certified,
Fall of equipment All mobile equipment shall have valid license as required by Qatar
Page 18 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 19 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Lifting load above persons Materials fall from height Materials All lifting activities shall be supervised by a competent person,
All equipment to be used must be fit for purpose; no obsolete equipment
shall be allowed on site,
Struck by moving equipment Banksman shall be appointed for all mobile operations
Page 20 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Unstable lifting equipment Operators shall be competent, trained, experienced, qualified and third
party certified
Approved lifting plan shall be adhered to at all times during operations
No personnel shall be allowed to stand under any load or lifting radius
Page 21 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Striking adjacent structure Lifting activities shall be cordoned off during operations
Lifting shall be done with clear distance from adjacent structures
Provide awareness posters and signage.
All lifting activities shall be carried out under favorable weather
Page 22 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 23 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
High wind
Page 24 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 25 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 26 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Lack of supervision
Page 27 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Incompetent personnel
Page 28 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 29 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 30 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
arrangements of HV Fatality Materials Storage of cables shall be done without cable rolling over.
11KV cables, Trips and falls All accessories shall be segregated according to type/size and stored in open
Rolling cable drum Cable rolling over workers racks.
accessories and
Activity shall be supervised by a competent person.
Page 31 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 32 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 33 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 34 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
6. Working at height Positioning, scissors lift, (MEWP) on Fall from height, Workers, 4 4 16 Relevant PTW shall be obtained prior to WAH activities 3 2 6
Activity unstable grounds, Fall of materials, Task briefing to be conducted before activity,
Ground stability shall be ensured prior to the use of MEWPs and ladders
Page 35 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Equipment topple/overturn, Equipment, All MEWP’s shall be TP inspected and visually inspected daily before
Fall of tools use
Collapse of scaffold / MEWP’s Only trained and certified personnel shall be permitted to operate
equipment
Page 36 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Tool Where necessary, safety harness shall be used to prevent fall from
height
Improper or lack of supervision, Work at height activities shall be supervised by competent and
authorized person
Page 37 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
During work at height activities, workers are only allowed to use and
place tools on the work platform andnot to be thrown from person to
Poor guardrail system person.
Scaffold capacity shall not be exceeded
Page 38 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 39 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 40 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
working activities
Adequate illumination during activities
Untrained work-at-height personnel, Ensure 100% tie off safety harness on scaffold where applicable.
All relevant PPE must be worn.
Page 41 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 42 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 43 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
7. Installation of HV Sharp edges on cable tray Bruises Workers 4 3 12 Follow all PTW system for working in excavation and confined space entry. 4 1 4
Cable Cuts Task briefing and TBT shall be conducted prior to activity.
Fall of material Ensure no sharp edges on cable ladder / cable tray to avoid damage to cable
Page 44 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 45 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Respiratory problems Observe correct techniques and posture for lifting/manual handling.
Crush / body Injuries Seek assistance whenever required/team lifting
Rolling cable drum Falls from height Materials Train workers on correct manual handling techniques.
Material and equipment falling into trench Ensure cable ladder and tray are secured firmly prior to pulling by a
Page 46 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
competent person
Personnel shall ensure good grip (coupling multiplier factor) during pulling.
Uncalibrated test equipment Adequate spacing shall be ensured during manual handling to prevent strike
(Megger) against, trips and falls, entrapment hazards
Page 47 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 48 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 49 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 50 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 51 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 52 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 53 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 54 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 55 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 56 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 57 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Open trench
Page 58 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 59 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Improper grip
Page 60 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 61 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
open trench
Page 62 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Loose soil
8. Cable Termination Incompetent worker Fire Workers 4 4 16 Cable termination shall be done according to MS and shop drawing. 3 2 6
Trip and fall Cable termination shall be done by a competent and experience person.
Page 63 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Poor termination Electric shock Client Earthing shall be properly by a competent person with experience
Burns All trailing cable shall be removed from access.
Obtain relevant PTW.
Heat gun shall be off when not in use.
Page 64 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
HV Cable Testing Electric heater/Heat gun Heat gun shall be used by a trained and competent person.
All test equipment shall be calibrated and certificate obtained.
Suitable fire extinguisher shall be in place.
All relevant PPE shall be used.
Page 65 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Improper earthing
Page 66 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 67 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
9.. HV Cable Jointing Incompetent worker Fire Workers 4 3 12 Train workers on cable jointing procedures. 4 1 4
Supervision shall be done by a competent person
Page 68 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Improper jointing Material damage Tools Jointing shall not be done on carriageway.
SDS of chemicals shall be obtained and information given to workers for safe
Skin irritation use.
PPE (hand gloves, safety goggles, hard hat, safety boots, reflective vest) shall
Page 69 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 70 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Compound / resin)
Page 71 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 72 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
10. Work at night Inadequate lighting Slips, trips and falls, Personnel 4 4 16 Relevant PTW to be obtained prior to night activities, 3 2 6
Struck by, Night activities shall be carried out with strict monitoring and supervision,
Tools
Strike against, Adequate lighting system shall be provided on site during all night
Striking objects, activities,
Page 73 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Trailing cables Collapse of personnel Equipment Proper work rotation to be ensured (workers on day shift shall not be
allowed in night shifts),
Proper housekeeping shall be maintained prior to commencement of
night activities,
Page 74 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Poor house keeping Buddy system to be ensured at all times during night activities,
Ensure adequate rest periods for inspection teams and repair
technicians,
Ensure that all personnel are well aware of emergency access/egress at
Page 75 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 76 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Stress
Page 77 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
11. (if applicable) Cuts/Nips/trapping of fingers Tools 3 4 12 Adequate PPE shall be used at all times during activities 2 1 2
Tools shall be inspected daily
Incompetent personnel Tools shall be used for their correct purposes
Quarantine or dispose of any tool that is damaged or not of required
Page 78 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
standard
No-horseplay policy shall be maintained
Lack of adequate PPE
Hot Season
Page 79 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
12. Work under Working under hot weather/high Heat stress, Personnel 4 4 16 Strict monitoring and supervision 3 2 6
unfavorable humidity Heat exhaustion, Heat index chart and MOL regulation to be maintained,
Dehydration, Materials
weather conditions Work rest balance to be ensured,
Heat Rash, Personnel hydration to be consistently maintained,
Page 80 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Working under very cold Heat Stroke, Adequate rest and rotation to be implemented.
weather/humidity Chilblains, Activities to be scheduled according to weather conditions,
Hypothermia, Weather monitoring chart to be monitored effectively,
Damage to materials (rust, cracks), Emergency procedures and preparedness to be communicated to
Page 81 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 82 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Cold Season
Page 83 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
weather conditions,
Workers advised to take warm water when necessary,
Health conditions shall be monitored regularly.
Page 84 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Cold Season
Personnel body temperature to be monitored,
Winter jackets to be provided if work is to be carried out in extreme cold
Page 85 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
weather conditions,
Workers advised to take warm water when necessary,
Strict monitoring of health conditions of workers
Page 86 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
13. Poor Housekeeping Improper arrangement of tools and Workers/ staff and visitor 3 4 12 Container for Construction Waste and other Rubbish/unwanted materials 3 1 3
materials on site, Fire shall be provided and disposed daily/regularly.
Slip, trip and fall Separate waste skip shall be used to accumulate food waste at the site
Struck by / strike against objects or and it shall be disposed at the end of each day’s work.
Page 87 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Stacking of incompatible material/ materials Ensure work area is clean and unwanted / discarded tools / equipment
cables on site, disposed of properly.
Body part puncture/injury
Proper cable management must be ensured on site
Impalement Ensure the walkway and emergency exits are free at all times.
Page 88 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Improper waste segregation, Environmental degradation / Good Housekeeping and cleaning must be followed/maintained and carried
out at regular intervals throughout the work activities on site
contamination
Disposal bins for different wastes should be marked clearly and used correctly
Wastes should be segregated and disposed of in respective
Page 89 of 90
Project CP837- Rehabilitation of Doha South Sewage Treatment works (DSSTW)
TASK: INSTALLATION OF HV CABLE, JOINT AND TERMINATION Date: 7th Feb, 2021
Residual
Activity Risk Initial Risk Controls
Risk
Consequence
Consequence
Risk Rating
Risk Rating
Likelihood
Likelihood
Description of Task Who or What
S/N Risk Effect Control Measures and / or Recovery Measures
Step Might be Harmed?
Hazard Description
Obstructed access/egress
Page 90 of 90