You are on page 1of 1

1 2 3 4 5 6 7 8 9 10 11 12

FINGER PACKS
AS REQUIRED A B GRIDLINES ARE FOR ORIENTATION REFERENCE ONLY
SF100 PLT15*150 AND REFER TO MSL GA's ONLY.
SF101 PLT10*150 STUB **THESE DO NOT RELATE TO ANY SITE GRIDLINES**
SF102 PLT5*150 101 UB203*133*25
102 UB203*133*25
H 1 H

A B
175 175
1A 1A
103 UB178*102*19 FINGER PACKS
AS REQUIRED
125 125
SF100 PLT15*150
SF102 PLT5*150 1B 2A 1B
SF101 PLT10*150 HIGH LEVEL CANOPY

120
101 UB203*133*25

70
108 RSA80*80*8
102 UB203*133*25
+9685

50

50
108 RSA80*80*8

100

100
110 CHS60.3*3.2 +9.635

230
1910

280
TOP HOLE
111 CHS60.3*3.2

107 RSA80*80*8
107 RSA80*80*8

110 CHS60.3*3.2
G
1B 1B G
1D 1D

107 RSA80*80*8

107 RSA80*80*8
107 RSA80*80*8

107 RSA80*80*8

107 RSA80*80*8

107 RSA80*80*8
EXG RAIL
EXG4 PLT1.5*5992 15mm THK PLATE

BASEPLATE 'TYPE 1'


4No M16 RESIN ANCHORS
25mm GROUT
104 UB178*102*19 SITEWORKS!
REDUNDANT DTW's FROM
447 600 600 600 600 600 600 600 448 LOWER LEVEL TO BE REUSED
CL RSA TOP FACE

2000
597 5095 300 175 175
SF100 PLT15*150
F SF101 PLT10*150 F
125 125
HIGH LEVEL CANOPY PLAN SF102 PLT5*150

TOS +9.685 LOW LEVEL CANOPY


2C 1B 2C
1B

50
102 UB203*133*25
+6850

50

50
FINGER PACKS

100

100
AS REQUIRED
A B +6.800

400

300
SF100 PLT15*150 STUB
SF101 PLT10*150 101 UB203*133*25 EXG2 PLT1.5*5992
SF102 PLT5*150 1B EXG RAIL BEHIND 1B
102 UB203*133*25
1

50
15mm THK PLATE

2000
E
105 UB178*102*19
E

BASEPLATE 'TYPE 1'


4No M16 RESIN ANCHORS
25mm GROUT
3.2
0.3*
C HS6
10 9 1
2B 2B

1671
SITEWORKS!
311
SITEDRILL 4No
116 PFC-125*65*15 116 PFC-125*65*15 1 22mm DIA HOLES IN EXG
*3.2 COLUMN WEB AS SHOWN
60.3
CHS (4No LOCATIONS)
109 80
112 135 EXG4 PLT1.5*5992
C HS6
0.3* EXG RAIL 20
3 .2
106 UB178*102*19

EXG COLUMN
D D
+9685

100 50
2000
597 5095 300

SURVEY DIMS TO
UNDERSIDE OF
LOW LEVEL CANOPY PLAN EXG RAILS (TYP)

TOS +6.850 2B 2B
1C

SECTION 1C - 1C
115 PFC-125*65*15
SECTION 1B - 1B
115 PFC-125*65*15
EXG3 PLT1.5*5992
45

A B TOP OF EXG BLKWK


1*

SITEWORKS!
17

1C EXG RAIL
+1.990
6*

C 5992
5

35

C
*4

HATCHED AREA OF
UB
71

RAILS TO BE REMOVED
*1

1
G
56

SEE SECTIONS 2B & 2C.


EX
B3

VERTICAL STRUTS TO
U
1

BE REMOVED UPTO
G

LOWER CANOPY LEVEL


EX

5989
1 WEB - WEB

2720
610

610

314
REF
5

25
*2

C01 09/09/21 TOC FINALISED. ISSUED FOR CONSTRUCTION


33

3*
13
*1

P01 03/09/21 ISSUED FOR COMMENT/ APPROVAL


3*
03

20
B2

Rev Date Description


UB
1532

1532
U
7

0
11

10

EXG1 UB356*171*45

EXG1 UB356*171*45
B B

Project Title.
300

300

+0
FARADAY CLOSE - WORTHING
CANOPY
-470 Drawing Title.

CANOPY PLANS & ELEVATION


597 5095 300 B 2A
SECTION 1A - 1A
448 300
ELEVATION ON EXG CLADDING
FOUNDATION LEVEL PLAN +9.775 Drawing Status.
108 RSA80*80*8
90

A TOC -470mm A
+9685
DWG Scales.
Drawn By RC 09/09/21 Checked By DO 09/09/21 1:10 1:15 1:25

MSL DWG No. Rev.


/
Tekla Structures

C821 GA-001 C01


SECTION 1D - 1D Client Drawing No. Rev.

DO675_MIDDLETON_FARADAY CLOSE CANOPY


1 2 3 4 5 6 7 8 9 10 11 12

You might also like