EXAMPLE 1

Name Of the Activity Description of activity Predecessor Time Duration


(Days)

A Excavation _____ 2
B Foundation A 4
C Rough Wall B 10
D Roof C 6
E Exterior Plumbing C 4
F Interior Plumbing E 5
G Exterior Siding D 7
H Exterior Painting G 9
I Electrical Work C 7
J Wallboard F ,I 8
K Flooring J 4
L Interior Painting J 5
M Exterior Fixtures H 2
N Interior Fixtures K ,L 6
CRITICAL PATH CHART
Earliest Time Diagram
START

ES=0
2 EF=2 4 ES=2 10 ES=6
EF=6 EF=16
A B C

6 4 7
ES=16 ES=22
ES=16
D EF=22 E EF=26 I EF=23

7 5
ES=22
ES=26 8
G EF=29
EF=31 ES=25
F J EF=33

9 4 5
ES=29
ES=31 ES=33
H EF=38 K EF=35
L EF=38
2
ES=38
M EF=40
6
N ES=38
EF=44

FINISH
Latest Time Diagram
START

LS=0
2 LF=2 4 LS=2 10 LS=6
LF=6 LF=16
A B C

6 4 7
LS=20 LS=16
LS=18
D LF=26 E LF=20 I LF=25

7 5
LS=26
LS=20 8
G LF=33
LF=25 LS=25
F J LF=33

9 4 5
LS=33
LS=34 LS=33
H LF=42 K LF=38
L LF=38
2
LS=42
M LF=44
6
N LS=38
LF=44

FINISH
Earliest & Latest Time Diagram
START

ES=0 LS=0
EF=2 LF=2 ES=2 LS=2
2 4 EF=6 10 ES=6 LS=6
LF=6
EF=16 LF=16
A B C

6 ES=16 4 ES=22
7
EF=22 ES=16 LS=18
EF=26
D LS=20 E LS=16 I EF=23 LF=25
LF=26 LF=20
7
ES=22 LS=26
5 ES=26 8
G EF=29 LF=33 EF=31 ES=25 LS=25
F LS=20 J EF=33 LF=33
LF=25
9 ES=29 5
4 ES=31
EF=38 EF=35 ES=33 LS=33
H LS=33 K L EF=38 LF=38
LF=42 LS=34
2 LF=38

M
ES=38 LS=42 6
EF=40 LF=44 N ES=38 LS=38
EF=44 LF=44

FINISH
EXAMPLE 2 -Sequence of Activities for House construction Project

Name Of the Starting and Finishing Description of activity Predecessor Time Duration
Activity event (Days)

A (0,1) Preaparing Working Drawings _____ 2 Weeks

B (1,2) Clean the Site A 2 Weeks

C (2,3) Excavate B 2 Weeks

D (3,4) Lay the Foundation C 5 Weeks

E (4,5) Column and Beam placement D 3 Weeks

F (5,6) Construction of rough wall E 3 Weeks

G (5,7) Put up the Slab/ roof E 3 Weeks

H (7,8) Plumbing Work G 2 weeks

I (6,9) Ceiling Work F 2 Weeks

J (9,10) , (7,10) Plastering Work G ,I 2 weeks

K (5,11) Do the electrical work E 1 Weeks

L (8,12) , (11,12) Put up the doors and Windows H ,K 1 Weeks

M (12,13) , (12,14) Install the flooring L 2 Week

N (13,16) , (14,16) Painting Work M 2 week

O (10,15) Compound fencing Work J 2 week

P (15,0) , (16,0) Complementry works N ,O 1 week


CRITICAL PATH CHART
ES=0 ES=14 ES=19
S EF=0 ES=0 1 L 1 EF=20
2 EF=15
T 0 EF=2 12 ES=20
A 1 ES=2 11 2 EF=22
R
A 2 EF=4 ES=17
2 L M 14
T B EF=19
2
K 8 M N
ES=20 ES=22
ES=4
C ES=6 H EF=22 EF=23
EF=6 2 5 EF=11
3 ES=11 2 1
EF=14 3 ES=14 16
3 4 5 7 EF=17 13
D E G N
A. Prepare the Drawings
J P F
B. Clean the site F ES=14 I
EF=17 N
C. Excavate ES=19 ES=21 I
D. Lay the Foundation
6 3 ES=17 EF=21
2 EF=23 S
H
E. Column & Beam Placement I EF=19 2 15
F. Construction of Rough Wall 2 J P
G. Put up the slab / Roof
9 10 O
H. Plumbing Work
I. Ceiling Work
J. Plastering Work
K. Do the Electrical Work
L. Put up the Doors & Windows
M. Install the flooring
N. Painting Work Earliest Time Diagram
O. Compound Fencing Work
P. Complementary Works
LS=0 LS=18 LS=19
S LF=0 LS=0 1 L 1 LF=20
2 LF=19
T 0 LF=2 12 LS=20
A 1 LS=2 11 2 LF=22
R
A 2 LF=4 LS=17
2 L M 14
T B LF=19
2
K 8 M N
LS=20 LS=22
LS=4
C LS=6 H LF=22 LF=23
LF=6 2 5 LF=11
3 LS=11 2 1
LF=14 3 LS=14 16
3 4 5 7 LF=17 13
D E G N
A. Prepare the Drawings
J P F
B. Clean the site F LS=14 I
LF=17 N
C. Excavate LS=19 LS=21 I
D. Lay the Foundation
6 3 LS=17 LF=21
2 LF=23 S
H
E. Column & Beam Placement I LF=19 2 15
F. Construction of Rough Wall 2 J P
G. Put up the slab / Roof
9 10 O
H. Plumbing Work
I. Ceiling Work
J. Plastering Work
K. Do the Electrical Work
L. Put up the Doors & Windows
M. Install the flooring
N. Painting Work
O. Compound Fencing Work Latest Time Diagram
P. Complementary Works
ES=0 LS=0 ES=14 LS=18 ES=19 LS=19
EF=0 LF=0 ES=0 LS=0 1 1 EF=20 LF=20
S
T 0 2 EF=2 LF=2
EF=15 LF=19 L 12 ES=20 LS=20
1 2 EF=22 LF=22
A 11 L
R
A 2 ES=2 LS=2
2 ES=17 M 14
T B EF=4 LF=4
2 M
K 8
EF=19 N
LS=17 ES=22
ES=11 H ES=20
C LF=19 1 EF=23
ES=4 2 5 3 EF=14 2 EF=22
LS=22
EF=6 LS=11 LS=20
LF=14 3 ES=14 16 LF=23
LS=4 3 4 5 7 EF=17 13 LF=22
LF=6 D E G LS=14 N
ES=6 LS=6 LF=17
EF=11 LF=11 P F
F ES=14 LS=14 J I
EF=17 LF=17 N
ES=19 LS=19 ES=21 LS=21 I
3 2 EF=23 LF=23 S
6 ES=17 LS=17 EF=21 LF=21 H
EF=19 LF=19 2 15
P
I 2 10
9 O
J

Earliest & Latest Time Diagram


EXAMPLE 2 -Sequence of Activities for House construction Project

No. Description of activity Code Time (Days) Predecessors

1 Preaparatory Works A 3 -

2 Excavation Works B 5 A

3 Foundation Works C 10 B

4 Column Structure Works D 12 C

5 Sloof Works E 6 C

6 Wall & Frame Works F 12 E

7 Roof Truss Works G 10 D

8 Roof (Ceilings & Tiles) Works H 17 G

9 Sanitary Works & Electrical Installations I 20 F ,H

10 Plaster Works J 25 F ,H

11 Floor Works K 18 I

12 Installation Works (Lamps, Glass, Doors, Windows, L 15 F


Switches, Outlets, Locks, Sanitation)

13 Painting Work M 30 J ,K

14 Fencing Work N 10 L

15 Complementary Work O 6 M ,N
CRITICAL PATH CHART
Earliest Time Diagram

ES=30 ES=40 ES=57


ES=18 EF=40 EF=57 EF=77
EF=30
G H I ES=77
5 8 9 10 EF=95
10 17 20
ES=0 ES=3 ES=8
D 12 J K
EF=3 EF=8 EF=18 ES=57 ES=95
EF=82 EF=125
A B C 10
11 M 13 O
1 2 3 4 6 14
3 5 30
10 ES=125
ES=18 EF=131
EF=24 6 10
E N
F L ES=51
6 7 12 EF=61
12 15
ES=24 ES=36
EF=36 EF=51
Latest Time Diagram

LS=30 LS=40 LS=57


LF=40 LF=57 LF=77
LS=18
LF=30 G H I LS=77
5 8 9 10 LF=95
10 17 20
LS=0 LS=3
LF=3 LF=8 LS=8 D 12 LS=70
J K LS=95
LF=18 LF=125
LF=95
A B C 10
11 M 13 O
1 2 3 4 6 14
3 5 30
10
LS=125
6 10 LF=131
E N
LS=52
LF=58 F L LS=85
6 7 12 LF=95
12 15
LS=58 LS=70
LF=70 LF=85
Earliest & Latest Time Diagram

ES=18 ES=30 LS=30 ES=40 LS=40 ES=57 LS=57


EF=30 EF=40 LF=40 EF=57 LF=57 EF=77 LF=77
LS=18
LF=30 G H I ES=77 LS=77
5 8 9 10 EF=95 LF=95
ES=8 10 17 20
ES=0 LS=0 EF=18
ES=3 LS=3
EF=3 LF=3 EF=8 LF=8 LS=8 D 12 ES=57 LS=70 J K ES=95 LS=95
LF=18 EF=82 LF=95
10 EF=125 LF=125
A B C
11 M 13 O
1 2 3 4 6 14
3 5 30
10
ES=125 LS=125
ES=18 EF=131 LF=131
EF=24 6 10
E N
LS=52
LF=58 F L ES=51 LS=85
6 7 12 EF=61 LF=95
12 15
ES=24 LS=58 ES=36 LS=70
EF=36 LF=70 EF=51 LF=85