Elective: Assignment 4
Elective: Assignment 4
ASSIGNMENT 4
Submitted To:-
Ar. Veena Ekbote Ma’am
Ar. Anklesh Kumawat Sir
Submitted By:-
Prajakta Sushil Vaidya.
EXAMPLE 1
A Excavation _____ 2
B Foundation A 4
C Rough Wall B 10
D Roof C 6
E Exterior Plumbing C 4
F Interior Plumbing E 5
G Exterior Siding D 7
H Exterior Painting G 9
I Electrical Work C 7
J Wallboard F ,I 8
K Flooring J 4
L Interior Painting J 5
M Exterior Fixtures H 2
N Interior Fixtures K ,L 6
CRITICAL PATH CHART
Earliest Time Diagram
START
ES=0
2 EF=2 4 ES=2 10 ES=6
EF=6 EF=16
A B C
6 4 7
ES=16 ES=22
ES=16
D EF=22 E EF=26 I EF=23
7 5
ES=22
ES=26 8
G EF=29
EF=31 ES=25
F J EF=33
9 4 5
ES=29
ES=31 ES=33
H EF=38 K EF=35
L EF=38
2
ES=38
M EF=40
6
N ES=38
EF=44
FINISH
Latest Time Diagram
START
LS=0
2 LF=2 4 LS=2 10 LS=6
LF=6 LF=16
A B C
6 4 7
LS=20 LS=16
LS=18
D LF=26 E LF=20 I LF=25
7 5
LS=26
LS=20 8
G LF=33
LF=25 LS=25
F J LF=33
9 4 5
LS=33
LS=34 LS=33
H LF=42 K LF=38
L LF=38
2
LS=42
M LF=44
6
N LS=38
LF=44
FINISH
Earliest & Latest Time Diagram
START
ES=0 LS=0
EF=2 LF=2 ES=2 LS=2
2 4 EF=6 10 ES=6 LS=6
LF=6
EF=16 LF=16
A B C
6 ES=16 4 ES=22
7
EF=22 ES=16 LS=18
EF=26
D LS=20 E LS=16 I EF=23 LF=25
LF=26 LF=20
7
ES=22 LS=26
5 ES=26 8
G EF=29 LF=33 EF=31 ES=25 LS=25
F LS=20 J EF=33 LF=33
LF=25
9 ES=29 5
4 ES=31
EF=38 EF=35 ES=33 LS=33
H LS=33 K L EF=38 LF=38
LF=42 LS=34
2 LF=38
M
ES=38 LS=42 6
EF=40 LF=44 N ES=38 LS=38
EF=44 LF=44
FINISH
EXAMPLE 2 -Sequence of Activities for House construction Project
Name Of the Starting and Finishing Description of activity Predecessor Time Duration
Activity event (Days)
1 Preaparatory Works A 3 -
2 Excavation Works B 5 A
3 Foundation Works C 10 B
5 Sloof Works E 6 C
10 Plaster Works J 25 F ,H
11 Floor Works K 18 I
13 Painting Work M 30 J ,K
14 Fencing Work N 10 L
15 Complementary Work O 6 M ,N
CRITICAL PATH CHART
Earliest Time Diagram