1) The document discusses a case in Hong Kong regarding whether a government must disqualify bids that do not comply with the requirements in a Request for Tenders document.
2) It focused on the wording used in the Request for Tenders, specifically whether the word "may" regarding non-compliant bids should be interpreted as "must".
3) The court ultimately found that "may" gave the government discretion to consider non-compliant bids, and they were not required to disqualify them.
Original Description:
Original Title
Disqualification from the Tendering Process - 'May' vs 'Must'
1) The document discusses a case in Hong Kong regarding whether a government must disqualify bids that do not comply with the requirements in a Request for Tenders document.
2) It focused on the wording used in the Request for Tenders, specifically whether the word "may" regarding non-compliant bids should be interpreted as "must".
3) The court ultimately found that "may" gave the government discretion to consider non-compliant bids, and they were not required to disqualify them.
1) The document discusses a case in Hong Kong regarding whether a government must disqualify bids that do not comply with the requirements in a Request for Tenders document.
2) It focused on the wording used in the Request for Tenders, specifically whether the word "may" regarding non-compliant bids should be interpreted as "must".
3) The court ultimately found that "may" gave the government discretion to consider non-compliant bids, and they were not required to disqualify them.
DISQUALIFICATION KEY POINTS SCT–2 stated that the tenderer
FROM THE TENDERING • For owners/governments, ‘shall price’ the works so that the careful drafting of tender formula ‘is’ complied with, and PROCESS—‘MAY’ VS requirements is essential. stated that ‘failure to price the ‘MUST’ tender in accordance with the • Bidders must carefully Stuart Cosgriff, Senior above condition may invalidate the analyse what constitutes a Associate tender’. ‘conforming tender’ in the tender documentation. China Harbour and four other Katherine Mallik, Lawyer tenderers tendered for the When does a ‘process contract’ Clayton Utz, Sydney contract. China Harbour’s tender require the Government to was the only tender that complied disqualify bidders from a with the formula contained tendering process if their in SCT–2. Another tenderer, tenders do not comply with the Leightons, however achieved the requirements of a Request for highest score. The scoring system Tenders? A recent Hong Kong awarded points for many different case1 illustrates that it depends factors, including pricing. If all on the wording of the Request for three works (a), (b) and (c) went Tenders. ahead, Leightons’ bid was the BACKGROUND highest scoring bid. If only (a) and In 2002, the Government of Hong (c) went ahead, China Harbour Kong sought tenders for a large was the highest scoring bid. construction project comprising: At the time that the winning bid (a) an 18 hectare area of was chosen, it seemed likely reclamation of the harbour to the Government that the CWB works would go ahead (b) a 500m tunnel (the ‘CWB and the Government felt that Tunnel’); and was desirable that the same (c) a 40m extension overrun contractor carried out the works tunnel (the ‘40 metre EOT’). for (a), (b) and (c). The contract Only the reclamation referred was therefore awarded to to in (a) was guaranteed to be Leightons. awarded to the successful bidder. THE ACTION AND The tender document provided SUBMISSIONS that the CWB Tunnel and 40 China Harbour sued the metre EOT referred to in (b) and Government, claiming breach of (c) could be excised from the contract and arguing that as the works at a future date. Although only compliant tenderer, it should the tenders had to include prices have been awarded the contract. for all three components, all It further submitted that the use tenderers knew that (b) and (c) of ‘shall’ and ‘is’ in SCT–2 made may be excised from the project. compliance with the formula The excisable status of (b) was mandatory and invalidated all important because if the CWB non–compliant tenders. This Tunnel component went ahead, claim relied on a submission that it would form a large part of the word ‘may’ where used in the project. To avoid price SCT–2 should be read as ‘must’. manipulation of the various The Government argued that the components by the tenderers, word ‘may’ gave the Government the Government included a a discretion not to invalidate non– provision, SCT–2, in the tender, compliant tenders and that the which set out a formula for price word ‘may’ meant that a tenderer calculation so that the price who chose not to comply with the for (b) had to represent at least formula ran a risk of having its 33.7 percent of the overall price. tender disqualified.
38 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #118 JANUARY/FEBRUARY 2008
THE DECISION THE APPEAL for success. If a bidder is Justice Burrell found that there China Harbour appealed, claiming in doubt about the effect of was a process contract arising that: particular tender requirements, from the Request for Tenders. He clarification should be sought • it was a term of the process rejected China Harbour’s claim at the earliest opportunity. contract that only conforming and found that if the word ‘may’ tenders would be assessed; was read as ‘must’, the final sentence of SCT–2 would serve • it made the only conforming REFERENCE no purpose. Rather, ‘the message tender; and 1. China Harbour Engineering to tenderers is— do your sums • the underlying rationale of the Company (Group) v The Secretary according to this equation, if you approved marking scheme was for Justice of the Hong Kong do not you run the risk of being to compare like with like and as Special Administrative Region disqualified however good the there was only one conforming HCCT 44/2004 and China rest of your bid is.’ Justice Burrell tender, the Government acted in Harbour Engineering Company found that SCT–2 had a clear and breach of contract by comparing Limited (formerly known as unambiguous meaning that was it to the non–conforming tenders China Harbour Engineering interpreted by every tenderer and awarding the contract to a Company (Group)) v The but China Harbour in the same non–conforming tenderer. Secretary for Justice of the Hong way, and that if China Harbour Kong Special Administrative had been confused it could have The Court of Appeal dismissed Region CACV 138/2006 sought confirmation that bids that the appeal. It agreed with Justice did not comply with the formula Burrell that if the word ‘may’ in Stuart Cosgriff and Katherine would not be invalidated. the final sentence of SCT–2 was Mallik’s article was previously read as ‘must’, that sentence published in Clayton Utz’s Justice Burrell also found that would be useless. If the word there were many other examples Project Insights—December ‘may’ was read as ‘may’, the 2007. Reprinted with permission. in the process contract of the effect would be to confer on tenderers being directed that the Government a discretion to they ‘shall’ do something and invalidate any tender that did not that if they fail to do so, their bid comply with the pricing formula. ‘may’ be disqualified. He said that Unless and until a tender that it was desirable that the word otherwise complied with all of the ‘may’ should consistently mean requirements was invalidated by the same thing in the process an exercise of the Government’s contract and that it would be discretion, it would remain a valid confusing for one occurrence of and conforming tender. ‘may’ to mean ‘must’. Justice Burrell also pointed out that IMPLICATIONS OF THE there were many examples DECISION in the tender documents of Although this decision may not mandatory provisions where be binding in Australia, there are non–compliance would have two key messages arising from inevitable consequences so that if this case which have universal compliance with the formula was application: to be mandatory, SCT–2 would • for owners/governments, have been drafted accordingly. careful drafting of tender Justice Burrell also took into requirements is essential to consideration that all the ensure that any desired flexibility tenderers were big players in in decision–making is retained; the Hong Kong construction and industry, and that they were highly • for bidders, careful experienced and regular bidders analysis of what constitutes a for Government contracts. China ‘conforming tender’ in the tender Harbour’s decision to take a documentation is essential to conservative approach to the ensure that tenders submitted bidding process did not mean have the maximum prospects there was an unlevel playing field. AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #118 JANUARY/FEBRUARY 2008 39