You are on page 1of 2

CONTRACTS

DISQUALIFICATION KEY POINTS SCT–2 stated that the tenderer


FROM THE TENDERING • For owners/governments, ‘shall price’ the works so that the
careful drafting of tender formula ‘is’ complied with, and
PROCESS—‘MAY’ VS requirements is essential. stated that ‘failure to price the
‘MUST’ tender in accordance with the
• Bidders must carefully
Stuart Cosgriff, Senior above condition may invalidate the
analyse what constitutes a
Associate tender’.
‘conforming tender’ in the tender
documentation. China Harbour and four other
Katherine Mallik, Lawyer
tenderers tendered for the
When does a ‘process contract’
Clayton Utz, Sydney contract. China Harbour’s tender
require the Government to
was the only tender that complied
disqualify bidders from a
with the formula contained
tendering process if their
in SCT–2. Another tenderer,
tenders do not comply with the
Leightons, however achieved the
requirements of a Request for
highest score. The scoring system
Tenders? A recent Hong Kong
awarded points for many different
case1 illustrates that it depends
factors, including pricing. If all
on the wording of the Request for
three works (a), (b) and (c) went
Tenders.
ahead, Leightons’ bid was the
BACKGROUND highest scoring bid. If only (a) and
In 2002, the Government of Hong (c) went ahead, China Harbour
Kong sought tenders for a large was the highest scoring bid.
construction project comprising: At the time that the winning bid
(a) an 18 hectare area of was chosen, it seemed likely
reclamation of the harbour to the Government that the
CWB works would go ahead
(b) a 500m tunnel (the ‘CWB
and the Government felt that
Tunnel’); and
was desirable that the same
(c) a 40m extension overrun contractor carried out the works
tunnel (the ‘40 metre EOT’). for (a), (b) and (c). The contract
Only the reclamation referred was therefore awarded to
to in (a) was guaranteed to be Leightons.
awarded to the successful bidder. THE ACTION AND
The tender document provided SUBMISSIONS
that the CWB Tunnel and 40 China Harbour sued the
metre EOT referred to in (b) and Government, claiming breach of
(c) could be excised from the contract and arguing that as the
works at a future date. Although only compliant tenderer, it should
the tenders had to include prices have been awarded the contract.
for all three components, all It further submitted that the use
tenderers knew that (b) and (c) of ‘shall’ and ‘is’ in SCT–2 made
may be excised from the project. compliance with the formula
The excisable status of (b) was mandatory and invalidated all
important because if the CWB non–compliant tenders. This
Tunnel component went ahead, claim relied on a submission that
it would form a large part of the word ‘may’ where used in
the project. To avoid price SCT–2 should be read as ‘must’.
manipulation of the various The Government argued that the
components by the tenderers, word ‘may’ gave the Government
the Government included a a discretion not to invalidate non–
provision, SCT–2, in the tender, compliant tenders and that the
which set out a formula for price word ‘may’ meant that a tenderer
calculation so that the price who chose not to comply with the
for (b) had to represent at least formula ran a risk of having its
33.7 percent of the overall price. tender disqualified.

38 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #118 JANUARY/FEBRUARY 2008


THE DECISION THE APPEAL for success. If a bidder is
Justice Burrell found that there China Harbour appealed, claiming in doubt about the effect of
was a process contract arising that: particular tender requirements,
from the Request for Tenders. He clarification should be sought
• it was a term of the process
rejected China Harbour’s claim at the earliest opportunity.
contract that only conforming
and found that if the word ‘may’ tenders would be assessed;
was read as ‘must’, the final
sentence of SCT–2 would serve • it made the only conforming REFERENCE
no purpose. Rather, ‘the message tender; and 1. China Harbour Engineering
to tenderers is— do your sums • the underlying rationale of the Company (Group) v The Secretary
according to this equation, if you approved marking scheme was for Justice of the Hong Kong
do not you run the risk of being to compare like with like and as Special Administrative Region
disqualified however good the there was only one conforming HCCT 44/2004 and China
rest of your bid is.’ Justice Burrell tender, the Government acted in Harbour Engineering Company
found that SCT–2 had a clear and breach of contract by comparing Limited (formerly known as
unambiguous meaning that was it to the non–conforming tenders China Harbour Engineering
interpreted by every tenderer and awarding the contract to a Company (Group)) v The
but China Harbour in the same non–conforming tenderer. Secretary for Justice of the Hong
way, and that if China Harbour Kong Special Administrative
had been confused it could have The Court of Appeal dismissed Region CACV 138/2006
sought confirmation that bids that the appeal. It agreed with Justice
did not comply with the formula Burrell that if the word ‘may’ in Stuart Cosgriff and Katherine
would not be invalidated. the final sentence of SCT–2 was Mallik’s article was previously
read as ‘must’, that sentence published in Clayton Utz’s
Justice Burrell also found that would be useless. If the word
there were many other examples Project Insights—December
‘may’ was read as ‘may’, the 2007. Reprinted with permission.
in the process contract of the effect would be to confer on
tenderers being directed that the Government a discretion to
they ‘shall’ do something and invalidate any tender that did not
that if they fail to do so, their bid comply with the pricing formula.
‘may’ be disqualified. He said that Unless and until a tender that
it was desirable that the word otherwise complied with all of the
‘may’ should consistently mean requirements was invalidated by
the same thing in the process an exercise of the Government’s
contract and that it would be discretion, it would remain a valid
confusing for one occurrence of and conforming tender.
‘may’ to mean ‘must’. Justice
Burrell also pointed out that IMPLICATIONS OF THE
there were many examples DECISION
in the tender documents of Although this decision may not
mandatory provisions where be binding in Australia, there are
non–compliance would have two key messages arising from
inevitable consequences so that if this case which have universal
compliance with the formula was application:
to be mandatory, SCT–2 would • for owners/governments,
have been drafted accordingly. careful drafting of tender
Justice Burrell also took into requirements is essential to
consideration that all the ensure that any desired flexibility
tenderers were big players in in decision–making is retained;
the Hong Kong construction and
industry, and that they were highly • for bidders, careful
experienced and regular bidders analysis of what constitutes a
for Government contracts. China ‘conforming tender’ in the tender
Harbour’s decision to take a documentation is essential to
conservative approach to the ensure that tenders submitted
bidding process did not mean have the maximum prospects
there was an unlevel playing field.
AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #118 JANUARY/FEBRUARY 2008 39

You might also like