You are on page 1of 1

CONTRACTS

LIMITS TO THE SCOPE the result that the house was Plainly, Hargrave J considered it
OF THE WARRANTY not reasonably fit for its intended was the owner, not the contractor,
purpose. From the Tribunal’s who assumed the risk of the
OF FITNESS FOR finding the contractor appealed to actual conditions encountered
PURPOSE—ACTUAL OR the Supreme Court of Victoria. being different and inferior to the
ANTICIPATED? The Tribunal member had conditions reasonably anticipated
at the time of contract. Seen in
John Sharkey, Partner found that there was severe salt
that way, the decision contains
efflorescence and spalling of
Deacons, Melbourne brickwork on specified sections within it a clear message to those
charged with drafting warranties
of the brick walls beneath the
in design and construct contracts.
damp proof course, that the
source of the salt which had If a principal wishes the common
entered the bricks was salty law warranty of fitness for
groundwater present at the land, purpose to extend to that which is
Barton v Stiff [2006] VSC 307 that the bricks were ‘unsuitable actually encountered (as distinct
concerned the construction of a in an environment where there is from that which could reasonably
house at Wodonga in 2000. Under salty groundwater’ and that the have been expected or likely to be
the contract, the contractor presence of salty groundwater at encountered) then the contract
agreed to construct the house the land was ‘highly unusual’. will have to provide expressly for
in accordance with plans and that result, thereby transferring
Upon appeal, the contractor did
specifications it had prepared and the risk to the contractor.
not dispute the presence of a
supplied and in accordance with
warranty of fitness for purpose Contractors will doubtless not
engineering designs prepared on
in relation to the materials. be pleased to see such contracts
its behalf. The only soil test report
What it maintained was that the drafted in that manner but at
was one prepared in 1992, eight
intended purpose for which the least no–one will be in doubt as to
years before the construction of
house was constructed was to which of the parties, as between
the house, and which was given
meet the groundwater conditions the principal and the contractor,
by the owners to the contractor.
actually prevailing at the time of has agreed to bear that risk.
The contract contained express construction or which were likely
warranties that, inter alia, all to be encountered at the land John Sharkey’s note was
materials to be supplied would during the expected design life previously published in Deacons’
be ‘good and suitable for the of the house. As those conditions Critical Path—October 2007.
purpose for which they are used’. were not such as to give rise to Reprinted with permission.
The contractor further warranted the expectation that the bricks
‘that the work and any material would be subject to attack by
used in carrying out the work will salts in the groundwater, the
be reasonably fit for that purpose contractor maintained, the bricks
or will be of such a nature were reasonably fit for their
and quality that they might be intended purpose.
reasonably be expected to achieve
Hargrave J expressed his
that result’.
conclusion in the following
Shortly after the owners took manner:
possession, disputes arose
I hold that the warranties of
between the parties as to the
fitness for purpose in this
quality of the works. The owners
case required the builders
commenced proceedings in the
to provide materials, and a
Victorian Civil and Administrative
completed house, which would
Tribunal against the contractor.
be proof against any groundwater
One of the items in respect of
conditions likely to be
which they were successful in
encountered at the land. As the
the proceedings was a claim that
presence of salty groundwater
the bricks used by the contractor
at the land was ‘highly unusual’,
below the damp proof course
the failure of the bricks for this
were not suitable for the purpose
reason does not constitute a
for which they were used with
breach of those warranties.

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #117 NOVEMBER/DECEMBER 2007 13

You might also like