Professional Documents
Culture Documents
Deterministic Scheduling
Muhammad Saqib
NED University of Engineering & Technology Karachi 1
Project Planning & Scheduling - Fundamentals and CPM
Muhammad Saqib
NED University of Engineering & Technology Karachi 2
Project Planning & Scheduling - Fundamentals and CPM
A SS 2 B SS 3 C
10 FF 6 11 10
SS 4
FF 5
FF 7
D SS 6 E SS 3 F
10 FF 0 10 FF 4 8
0 10 9 20 8 18
5 16
SS 4
FF 5
FF 7
15 25 27 35
12 22 21 31 24 32
D SS 6 E SS 3 F
10 FF 0 10 FF 4 8
21 31 21 31 27 35
15 25
Now assume there is a constraint to
What is the free float for different activities? finish project by day 30 – Activity F
should FNLT day 30
Muhammad Saqib
NED University of Engineering & Technology Karachi 3
Project Planning & Scheduling - Fundamentals and CPM
5 16
0 10 2 13 8 18
A SS 2 B SS 3 C
10 FF 6 11 10
-5 5 4 15 3 13
0 11
SS 4
FF 5
FF 7
15 25 27 35
12 22 21 31 24 32
D SS 6 E SS 3 F Constraint
10 FF 0 10 FF 4 8
16 26 16 26 22 30
10 20
What is the float on critical path now?
5 16
0 10 2 13 8 18
A SS 2 B SS 3 C
10 FF 6 11 10
0 10 9 20 8 18
5 16
SS 4
FF 5
FF 7
15 25 27 35
12 22 21 31 24 32
D SS 6 E SS 3 F
10 FF 0 10 FF 4 8
21 31 21 31 27 35
15 25
Now assume there are following two constraints:
Constraint 1: to finish activity D no later than day 18
Constraint 2: to finish project no later than day 30
Muhammad Saqib
NED University of Engineering & Technology Karachi 4
Project Planning & Scheduling - Fundamentals and CPM
5 16
0 10 2 13 8 18
A SS 2 B SS 3 C
10 FF 6 11 10
-7 3 2 13 1 11
-2 9
SS 4
FF 5
FF 7
15 25 27 35
12 22 21 31 24 32
D SS 6 E SS 3 F Constraint 2
10 FF 0 10 FF 4 8
26 16 26 22 30
8 18
What is the float on critical path now?
Constraint 1
What is the effect on free float?
TIME-CONSTRAINED SCHEDULING
WITH CPM
Muhammad Saqib
NED University of Engineering & Technology Karachi 5
Project Planning & Scheduling - Fundamentals and CPM
Time Constraints
A Time Constraint refers to a restriction set on the start or finish time/
date of a deliverable.
Using Constraints
Start No Earlier Than (SNET)
Suppose, An Activity has following characteristics:
Early Start = 1st Jan 2021 Early Finish = 18th Feb 2021
th
Late Start = 10 Jan 2021 Late Finish = 28th Feb 2021
No Effect!
Muhammad Saqib
NED University of Engineering & Technology Karachi 6
Project Planning & Scheduling - Fundamentals and CPM
Using Constraints
Finish No Earlier Than (FNET)
Suppose, An Activity has following characteristics
Early Start = 1st Jan 2021 Early Finish = 18th Feb 2021
th
Late Start = 10 Jan 2021 Late Finish = 28th Feb 2021
No Effect!
Using Constraints
Start No Later Than (SNLT)
Suppose, An Activity has following characteristics
Early Start = 1st Jan 2021 Early Finish = 18th Feb 2021
th
Late Start = 10 Jan 2021 Late Finish = 28th Feb 2021
No Effect!
Muhammad Saqib
NED University of Engineering & Technology Karachi 7
Project Planning & Scheduling - Fundamentals and CPM
Using Constraints
Finish No Later Than (FNLT)
Suppose, An Activity has following characteristics
Early Start = 1st Jan 2021 Early Finish = 18th Feb 2021
th
Late Start = 10 Jan 2021 Late Finish = 28th Feb 2021
No Effect!
0 10 9 20 8 18
5 16
SS 4
FF 5
FF 7
15 25 27 35
12 22 21 31 24 32
D SS 6 E SS 3 F
10 FF 0 10 FF 4 8
21 31 21 31 27 35
15 25
Now assume there is a constraint to
What is the free float for different activities? finish project by day 30 – Activity F
should FNLT day 30
Muhammad Saqib
NED University of Engineering & Technology Karachi 8
Project Planning & Scheduling - Fundamentals and CPM
5 16
0 10 2 13 8 18
A SS 2 B SS 3 C
10 FF 6 11 10
-5 5 4 15 3 13
0 11
SS 4
FF 5
FF 7
15 25 27 35
12 22 21 31 24 32
D SS 6 E SS 3 F Constraint
10 FF 0 10 FF 4 8
16 26 16 26 22 30
10 20
What is the float on critical path now?
5 16
0 10 2 13 8 18
A SS 2 B SS 3 C
10 FF 6 11 10
0 10 9 20 8 18
5 16
SS 4
FF 5
FF 7
15 25 27 35
12 22 21 31 24 32
D SS 6 E SS 3 F
10 FF 0 10 FF 4 8
21 31 21 31 27 35
15 25
Now assume there are following two constraints:
Constraint 1: to finish activity D no later than day 18
Constraint 2: to finish project no later than day 30
Muhammad Saqib
NED University of Engineering & Technology Karachi 9
Project Planning & Scheduling - Fundamentals and CPM
5 16
0 10 2 13 8 18
A SS 2 B SS 3 C
10 FF 6 11 10
-7 3 2 13 1 11
-2 9
SS 4
FF 5
FF 7
15 25 27 35
12 22 21 31 24 32
D SS 6 E SS 3 F Constraint 2
10 FF 0 10 FF 4 8
26 16 26 22 3s0S
8 18
What is the float on critical path now?
Constraint 1
What is the effect on free float?
Questions/Queries?
Muhammad Saqib
NED University of Engineering & Technology Karachi 10