You are on page 1of 10

SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018) Rev. 2018.03.

00 31-Mar-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Geotechnical Investigation SATIP-A-113-01 14-May-18 CIVIL


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD
CNTRCTR SAUDI ARAMCD

1.0 DOCUMENT REVIEW

SAIC-A-
1.1 Geotechnical Investigation Requirements SAIC-A-1007
1007 RH/ H RH/H

2.0 EXECUTION

SAIC-A-
2.1 Geotecnical Field Works Inspection SAIC-A-1008
1008 I W

SAIC-A-
2.2 Laboratory Testing Inspection SAIC-A-1009
1009 I W

ENGINEERING &
3.0
REPORTING

SAIC-A-
3.1 Geotechnical Investigation Reports SAIC-A-1010
1010 R/H R/H

4.0 PRE-COMMISSIONING

4.1 Not Applicable

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1 of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is
3 not present.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018) Rev. 2018.03.00 31-Mar-18

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Geotechnical Investigation SATIP-A-113-01 14-May-18 CIVIL


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.

5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H 100% Hold Point for QC Inspection or Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection/Test

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018)

Saudi Aramco: Company General Use


Rev. 2018.03.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


### ###

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018)

Saudi Aramco: Company General Use


Rev. 2018.03.00

###

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


### ###

Saudi Aramco: Company General Use

You might also like