ENERGY & RESOURCES

SUPPLY MANAGEMENT EXPERTISE


IN DYNAMIC MARKETS

INNOVATING SUPPLY MANAGEMENT


The supply chain process to remote
PROCESS TO ENHANCE OPTIMIZATION sites is very complex. It involves many
From dealing with extreme climatic conditions, to a complex supply stakeholders making it challenging
chain, one of the biggest challenges operating in the remote far- to get the right product at the right
eastern region of Russia is not only getting all supplies transported place, right time and at the right cost.
during the short delivery window but ensuring the quality of the At Sodexo, we do not settle for status
products upon arrival meet Sodexo’s high standards to best serve the quo. Our teams continue to further
residents onsite. develop our procurement capabilities
and enhance our supply chains to
Since 2010, Sodexo has been providing foodservices, cleaning, exceed our clients’ expectations and
technical maintenance and accommodations services for Kinross’s
drive added-value.
remote mining sites located in the Chukotka region of Russia as
well as their regional headquarters in Magadan. Our dedicated team
understands the importance Kinross places on operational excellence OUR CAPABILITIES
and takes an active role in the supply management process to ensure • Develop and manage supply chains
process and cost optimization. remotely

Working side by side with Kinross, our procurement and logistics • Continuous Supply Chain improvement
experts in Russia established an innovative approach to the supply focused on identifying opportunities to
chain design that has significantly increased savings, improved improve efficiency and reduce cost
efficiency and enhanced consumer satisfaction.
• Procurement expertise in dynamic and
unpredictable markets

INNOVATIVE APPROACH TO DRIVE VALUE

Strategic sourcing Agile procurement model Optimization of delivery Rigor in quality and HSE
partnering with strategic allowing to ensure cost lead time to reduce costs standards throughout the
suppliers to produce unique optimization in volatile and meet variable departure entire supply chain process
tailored-made goods to markets with unknown price dates from sea ports from the production of
meet long lead time and availability of goods goods to pre-shipment
inspections to ensuring
quality control during
transport
STRATEGIC SOURCING ENSURING EXCELLENCE OPTIMIZING DELIVERY ROUTE
TO IMPROVE PRODUCT QUALITY ALONG THE 11,500 KM JOURNEY TO DRIVE SAVINGS

The total delivery time for goods is over Another key challenge in operating As Kinross was incurring significant
7 months spanning over 11,500 km, on the remote locations is ensuring logistics costs in shipping empty
which raises the shelf-life requirements consistent product quality along the containers to our distribution centers, we
for goods to 24 months. The local long delivery route under extreme worked closely with Kinross to optimize
challenge is most product categories are climatic conditions. The only option to the logistics network to increase savings
restricted to 6-12-month span under replace defective products once onsite for both Kinross and Sodexo.
Russian regulations. So, we innovated is by air shipment at an exorbitant
our sourcing approach and partnered price. Our solution evaded this costly First off, we reorganized the distribution
directly with suppliers to tailor make risk by implementing a new product process to directly deliver some goods
goods with a 24-month shelf life, in testing process to ensure quality to the seaport to avoid the empty
particular for protein foods as it is a key before being shipped. Then taking a container shipment costs– a $100K cost
category in our procurement needs. step further, we installed sensors in savings. We also optimized the cost
the refrigerator containers with real- of goods delivered by buying directly
Not only did we focus on a longer shelf time monitors to prevent cargo losses from the manufacturers at a negotiated
life – but also insisted on improved and in parallel retain product quality volume discount and transporting them
quality and excellent Health, Safety as well as shelf life. by heavy vehicle at a lower price. This
& Environmental (HSE) compliance in reduced the cost of goods delivered by
operations. In selectively building our 6.5% per ton.
supplier network, we were Over 11,500 Km / 7 months
able to provide better
quality goods with a Pevec Port
significant reduction in Kinross remote sites
risk for potential foodborne
April 2019 - © Kinross Media Library - Adobe Stock

diseases. Moreover, we Magadan


were able to source 65% Arkhangelsk Port
of the goods locally
St Petersburg
Moscow
compared to the
Suppliers
previous average Suppliers
Suppliers Vladivostok
of only 35%.
Suppliers

Suppliers