Professional Documents
Culture Documents
TAMPING TECHNOLOGY
- Schö, Okt. 01 -
AA – 17a I
CONTENTS
1. INTRODUCTION.......................................................................................................1
2. BASIC PRINCIPLES FOR TRACK TAMPING ..........................................................2
2.1 WHY IS TAMPING CARRIED OUT? ........................................................................2
FUNCTIONAL PARAMETERS OF THE TAMPING UNIT .........................................4
THE PLASSER & THEURER TAMPING PRINCIPLE ...............................................5
ASYNCHRONIC UNIFORM PRESSURE TAMPING.................................................5
THE COMPACTION PROCESS................................................................................7
AFFECT OF LIFT ON THE TAMPING PROCESS ....................................................9
PRACTICAL HINTS AND REGULATIONS FOR TAMPING....................................15
PRELIMINARY CONDITIONS AND PRELIMINARY WORK ...................................15
LEVELLING AND LIFTING ......................................................................................24
MACHINE SETTINGS .............................................................................................28
REASONS FOR QUALITY DECREASE:.................................................................33
IMPROVEMENT OF TRACK QUALITY.................................................................. 36
AA – 17a 1
1. INTRODUCTION
For the construction or repair of deteriorated track systems with the aid of
levelling, lifting, lining and tamping machinery, certain preliminary conditions and
the adherence to relevant regulations are essential to ensure successful
completion of work.
Due to the different track designs and site conditions it is not possible to list
every applicable detail for each application. We have therefore listed only the
important basic rules and guidelines for the tamping of plain track and switches,
which apply for cases of properly constructed track and work procedure.
It is taken for granted that all necessary safety precautions, preparatory work,
and work in progress, will only be carried out by properly instructed, qualified
and authorised personnel, under consideration of and strict adherence to,
guidelines for track work and instructions for the proper operation of utilised
machinery.
We would ask you to pay special attention to the following hints and advice on
working practice and to ensure that all personnel affected by the them take due
note and adhere to the same.
Disregard, i.e. contravention, will lead not only to unsatisfactory quality and poor
durability of work, but also to premature wear or damage to utilised machinery,
and will therefore affect the economical viability and operational status.
2 AA – 17a
SCHEMATIC REPRESENTATION
BALLAST BED
TRACK FORMATION
- Schö, Okt. 01 -
AA – 17a 3
picture 1
picture 2
4 AA – 17a
Vibration frequency
Tine amplitude
Way of squeezing
Tamping pressure
Squeezing time
Tamping depth
Track lifting
- Schö, Okt. 01 -
AA – 17a 5
squeezing squeezing
force force
directed vibration
6 AA – 17a
For tamping a sleeper the tamping tools penetrate the ballast and perform a closing,
“squeezing”, movement. On this squeezing movement a sinusoidal vibration is
superimposed. The Plasser & Theurer tamping tools work according to the
asynchronous tamping principle under equal pressure, with directed, rectilinear
vibration and a tamping frequency of 35 Hz.
- Schö, Okt. 01 -
AA – 17a 7
SETTLEMENT
The diagram shows that a frequency in SLEEPER
tine
ampliude
Suitable power and timing is required for the re-layering and reforming of the ballast
bed structure. The compaction energy during the tamping process is applied during the
short phase of the support movement of the tine and is carried over with a short power
blast of the positive sinus half-shaft (see diagram top).
Tamping depth, squeeze time and squeeze pressure are all influential working
parameters, which are particularly important to match the tamping process to the
individual track conditions.
- Schö, Okt. 01 -
AA – 17a 9
A further and very important requirement for the even compaction process is the lift,
which precedes the tamping. The lift creates voids under the sleepers, which enables
the ballast bed to form a new structure.
LIFT
SLEEPER
SETTLEMENT
SLEEPER „liquefaction“
of ballast
picture 8
10 AA – 17a
Too large a lift cannot (even after Lifting and lining unit
repeated tamping manoeuvres)
produce an evenly compressed, load
bearing ballast structure, due to the
limited working area of the tamping
instruments. (see picture on the next
page)
picture 20
picture 21
- Schö, Okt. 01 -
AA – 17a 11
In such cases, several lift and tamping procedures and additional ballast will be
required to build up the required height of ballast in several layers.
Lifting value
before tamping after tamping
sleeper
cavity
consolidated sleeper
bed
12 AA – 17a
Tamping Pressure
Squeeze Time
- Schö, Okt. 01 -
AA – 17a 13
Tamping Depth
Track Lift
The lift does not only influence the track position, but also the production of an evenly
compacted sleeper support surface.
The following therefore applies: Without lift, no track positioning improvement, and
following that, no improvement of track stability only through tamping.
PLASSER & THEURER tamping machines are equipped with proportional levelling
and lifting controls, to enable all required positioning detail work to be carried out.
- Schö, Okt. 01 -
AA – 17a 15
Faults in the track material are to be removed before the machine commences work,
for example:
- Schö, Okt. 01 -
AA – 17a 17
Cleaning of trenches.
18 AA – 17a
Removal of further faults on ballast ballast
bed part of a standard cross
bed and sub surface. formation
protective section
layer
geotextile
drain
railway
pole with
fundament
deep drainage
with pit
- Schö, Okt. 01 -
AA – 17a 19
Preliminary Measurement
To determine the top and lift, suitable e. g.: fixed points measuring device
preliminary measurements should be
carried out.
20 AA – 17a
Ballast Requirement
The requirement of additional ballast is to be calculated whilst taking any apparent lifts
into consideration. Additional ballast is to be added, or ploughing to be carried out
accordingly.
- Schö, Okt. 01 -
AA – 17a 21
Removal of Obstacles
Wheel sensors.
Indusi-magnets.
Overheating sensors.
Obstacles which can not be removed should be marked clearly to avoid accidental
damage.
22 AA – 17a
Machine Readiness:
The technically immaculate condition of the utilised machine should be assured. The
following is particularly important:
- Schö, Okt. 01 -
AA – 17a 23
As previously described, the lift has an important influence on the correct positioning,
tamping quality and stability.
Satisfactory work results will only be achieved when the following ground rules are
adhered to:
When setting the levelling element it is important to remember that sufficient lift should
be achieved even for the highest point in any measured range, to achieve a good
overall top position. Faults in the relevant top measurements, especially when
determining the highest points, should be taken into consideration.
If a rail lying opposite to the measured rail lies too high, this additional height should
be added to the calculation of the total lift requirement and also any lifts in between
such points.
- Schö, Okt. 01 -
AA – 17a 25
It must be ascertained that sufficient voids will be constructed under the middle of the
sleeper with each lift in order to eliminate “centre bound sleepers”, and to avoid any
tendency of sleepers to ride up in the future.
It should further be considered, that the tamped rail will be lowered under subsequent
loads, i.e. that the should be lowered under controlled conditions with the aid of a
dynamic track stabiliser (DGS), to raise the lateral stability.
Unbalance gearbox
Horizontal vibration
Press-down roller
Horizontal vibration
26 AA – 17a
Basic Lift
From experience, we know that only this measurement principle will result in
good top positioning with durable tamping quality.
- Schö, Okt. 01 -
AA – 17a 27
Ramps
For the connection between existing and newly constructed top position, or the other
way around, a crossing as flat as possible (at least 1:1000) is to be constructed.
Run-in ramp
The lift adjustment should commence from zero and run across the whole length of
the ramp according to its level. The construction of a decline interchange at the end of
the ramp (by setting of an appropriate extension of the ramp decline) is not usually
necessary. With the continuing adjustment of actual lift values the ramp end will be
automatically rounded out. Exceptions to this guideline are ramp end points which are
to be retained as fixed points.
Run-out ramp
Tamping Depth
Tamping Pressure
To achieve the correct tamping pressure values for an individual surface condition,
proceed as follows:
Observe the support motion of the tamping tools and the resulting tamping process.
- Schö, Okt. 01 -
AA – 17a 29
Squeeze Time
For tamping of ballast the squeeze time should normally be set at 1,2 seconds per
application. For new applications (with loose layering) shorter times will suffice,
however, you should not be below 0,8 seconds.
EXECUTION OF WORK
Working Speed
Individual processes in the work cycle are to be adjusted to the relevant conditions on site.
The following is to be taken into consideration:
Speeding up and slowing down of the machine will depend on the contact friction
between wheel and rail, and this in turn depends on the surface type of the rail. Wet,
rusty or oily rails tend to cause the wheels to turn excessively (slip), and cause the
blocking of wheels when braking. Accelerating away and braking are carried out
hydrostatically, and can be affected.
The adjustment of acceleration can be set with the help of the throttle, so that no
wheel-spin will occur, as otherwise high wear will affect the wheels and skid marks will
be caused on the rails.
The brake pressure is to be adjusted to avoid the blocking of wheels, also the creation
of flat points and skid marks.
- Schö, Okt. 01 -
AA – 17a 31
Disregard of this regulation will lead to negative consequences for track and machine
(for example dislocation or damage of sleepers, insufficient tamping, broken tines,
damage to tamping unit and associated materials, etc.).
32 AA – 17a
Tamping of Switches
- Schö, Okt. 01 -
AA – 17a 33
Increasing deterioration of track geometry has several reasons, which may occur
individually or in interaction with others.
picture 7
picutre 8
34 AA – 17a
Insufficient ballasting.
Defective rail and fastening material (rail form defects, corrugations, skid marks,
incorrect height of joints, bent rails, loose joints and fastenings etc.)
picture 11 picture 9
picture 10
- Schö, Okt. 01 -
AA – 17a 35
picture 13
Minor ballast quality (soft rocks, inadequate size of grain, loose ballast, mixed ballast
etc.)
A levelling, lifting, lining and tamping machine (see figures below) may effectively remedy
only the consequences of the reasons mentioned above, provided further requirements
are met.
All other defects have to be repaired by adequate measures to be taken before operation
of the tamping machine, otherwise no satisfactory tamping quality and, consequently, no
long service life, may be expected.
- Schö, Okt. 01 -