Professional Documents
Culture Documents
System Restoration
Revision: 28
Effective Date: June 22, 2020
Prepared by
System Operations Division
PJM © 2020
PJM Manual 36: System Restoration
Table of Contents
Table of Contents
Table of Exhibits.........................................................................................5
Approval.......................................................................................................6
Current Revision.........................................................................................7
Introduction................................................................................................. 8
About PJM Manuals............................................................................................................ 8
About This Manual.............................................................................................................. 8
Using This Manual...............................................................................................................9
Section 1: Overview................................................................................. 10
1.1 Policy Statements........................................................................................................10
1.2 PJM System Restoration Plan Objectives.................................................................. 12
Section 4: Communications.................................................................... 35
4.1 Communications.......................................................................................................... 35
4.1.1 Voice Communication and Logging Protocols................................................35
Section 6: Generation.............................................................................. 45
6.1 Generating Stations.....................................................................................................45
6.1.1 Generating Stations........................................................................................45
6.1.2 Plant Shutdown.............................................................................................. 46
6.1.3 Generating Plant Communications.................................................................46
6.1.4 Cranking Power Availability............................................................................46
6.1.5 Plant Starting Procedure................................................................................ 46
6.1.6 Notify Plants................................................................................................... 46
6.1.7 Blocking Governors........................................................................................ 46
6.1.8 Plant Frequency Control................................................................................ 46
6.2 Cranking Power...........................................................................................................46
6.2.1 Units Requiring Cranking Power.................................................................... 47
6.2.2 Cranking Power Demand............................................................................... 47
6.2.3 Cranking Power Source and Black Start Paths............................................. 47
6.2.4 Energize Start-up Loads................................................................................ 48
Section 7: Transmission.......................................................................... 49
7.1 Voltage Regulation and Control.................................................................................. 49
7.1.1 Reactive Regulation....................................................................................... 49
7.1.2 Minimum Source Guidelines.......................................................................... 50
7.2 Synchronization........................................................................................................... 52
7.2.1 Synchronizing Process Phases......................................................................53
Revision History....................................................................................... 98
Table of Exhibits
Exhibit 1: Underfrequency Relay Automatic Load Dump - PJM Mid-Atlantic Control
Zone............................................................................................................................16
Exhibit 2: Underfrequency Relay Automatic Load Dump - PJM West Control Zone.....16
Exhibit 3: Underfrequency Relay Automatic Load Dump - PJM ComEd Control Zone...16
Exhibit 4: Underfrequency Relay Automatic Load Dump - PJM South Control Zone.... 17
Approval
Approval Date: 05/29/2020
Effective Date: 06/22/2020
Rich Brown, Manager
System Operator Training
Current Revision
Revision 28 (06/22/2020):
• Periodic review updated as follows:
o Attachment B: Added web links to the restoration forms.
o Attachment G: Updated Table 1 Annual Restoration Plan Review Deadlines to
include new TOs and a revision to SMECO.
o Attachment H: Updated Under Frequency Load Shed table with new data.
Introduction
Welcome to the PJM Manual for System Restoration (M36). In this Introduction, you will find
the following information:
• What you can expect from the PJM Manuals in general (see “About PJM Manuals”).
• What you can expect from this PJM Manual (see “About This Manual”).
• How to use this manual (see “Using This Manual”).
For a complete list of all PJM manuals, go to the Library section on PJM.com.
Intended Audiences
The intended audiences for the PJM Manual for System Restoration (M36) are:
• PJM System Operator — Personnel who work in conjunction with the transmission
owners to respond to outages and blackouts to restore the transmission system to
service.
• Transmission Owner operators — Personnel who respond to emergency procedures
issued by PJM System Operator.
• Generator Operators – Personnel who interact with PJM System Operators and TO
operators to facilitate operation of generation during system restoration.
References
The references to other documents that provide background or additional detail directly related
to the PJM Manual for System Restoration (M36) are:
• PJM Manual for Control Center and Data Exchange Requirements (M-1)
• PJM Manual for Transmission Operations (M-3)
• PJM Manual for Balancing Operations (M-12)
• PJM Manual for Emergency Operations (M-13)
• PJM Manual for Generator Operational Requirements (M-14D)
• PJM Manual for Operating Agreement Accounting (M-28)
• Restoration Plans of PJM neighboring Reliability Coordinators, Transmission Operators,
and Balancing Authorities
• PJM TO/TOP Matrix
Section 1: Overview
Welcome to the Overview section of the PJM Manual for System Restoration (M36). In this
section, you will find the following information:
• A description of PJM policy statements for system disturbances (see “Policy
Statements”).
When a disturbance or blackout occurs, the PJM Members are responsible for performing the
following activities:
• Taking other actions, as directed by PJM, to manage, alleviate, or end the disturbance or
blackout.
• Using the company restoration plan to restore the system and coordinate with PJM if any
deviations from the published plan are required.
• Cooperating with each other and PJM to implement requests and instructions received
from PJM for the purpose of managing, alleviating, or ending a disturbance or blackout.
• Providing notification and other information to governmental agencies as appropriate.
• Collecting, storing, and providing data and other information to PJM, as necessary, to
facilitate preparation of reports required by governmental or industry agencies as a result
of a disturbance or blackout.
• Cooperating and coordinating with PJM and other PJM Members in the restoration of all
or parts of the bulk power system in the PJM RTO with a priority of restoring the integrity
of the Interconnection.
A PJM Generator Operator controlling the output of a generating resource must take or arrange
for any or all of the following actions as directed by PJM in order to manage alleviate, or end an
Emergency, or such actions as PJM may deem appropriate for these purposes:
• Reporting the operating status and fuel situation.
• Starting, including black start, and loading such generation, as directed.
Note:
PJM Emergency Authority: Section 10.4 of the PJM Operating Agreement (OA) provides that
PJM has the responsibility to “direct the operations of the Members as necessary to manage,
alleviate, or end an Emergency”. Likewise, Section 11.3.1 of the OA states that PJM Members
must comply with “all directives of the Office of the Interconnection to take any action for the
purpose of managing, alleviating or ending an Emergency.”
2.1 Overview
When a system disturbance occurs, it is important to maintain a parallel operation throughout
the PJM RTO and the adjacent interconnected Balancing Authorities. Providing maximum
assistance to the other Balancing Authorities that are experiencing a system disturbance may
prevent cascading to other parts of the interconnected system and assist in restoration of
normal operation. If sufficient assistance cannot be obtained, the deficient system may need
to provide load relief measures or ultimately face the loss of assistance being provided by its
neighbors when separation occurs. The PJM RTO provides all possible assistance, including a
5% voltage reduction, provided the adjacent power system requesting assistance has already
implemented a 5% Voltage Reduction.
Depending on the level of the disturbance and available resources post-disturbance, PJM
may implement a “Top-down”, “Bottom-up”, or both a “Top-down” and “Bottom-up” restoration
strategy simultaneously to restore the system as quickly as possible. The exact restoration
strategy will be communicated at a PJM System Operations Subcommittee conference call once
a system status is ascertained consistent with Section 3 of this manual.
Note:
Details of procedures for these situations can be found in PJM Manual M-13, Emergency
Operations.
60 – 59.5 Hz Unlimited
PJM ComEd Control Zone (Based on the former MAIN region requirements)
In those cases where generators must be tripped for their own protection outside the
specifications of the table below, additional load shedding must be installed within the
immediately adjacent load entity, to compensate for the generators that trip outside the
specifications.
59.3 Hz 10%
58.9 Hz 10%
58.5 Hz 10%
Exhibit 1: Underfrequency Relay Automatic Load Dump - PJM Mid-Atlantic Control Zone
59.5 Hz 5%
59.3 Hz 5%
59.1 Hz 5%
58.9 Hz 5%
58.7 Hz 5%
Exhibit 2: Underfrequency Relay Automatic Load Dump - PJM West Control Zone
59.3 Hz 10%
59.0 Hz 10%
58.7 Hz 10%
Exhibit 3: Underfrequency Relay Automatic Load Dump - PJM ComEd Control Zone
59.3 Hz 10%
59.0 Hz 10%
58.5 Hz 10%
Exhibit 4: Underfrequency Relay Automatic Load Dump - PJM South Control Zone
PJM Actions:
When a power shortage causes a separation of all or parts of the PJM RTO with the probability
of overloaded transmission lines and/or abnormal frequency, PJM System Operator orders a
sufficient amount of load to be dumped to:
• return the frequency to 59.75 Hz or higher
• relieve the actual transmission overloads
• return inter-area ties to schedule
PJM System Operator immediately establishes communications with the effected Transmission
Owners and adjacent Balancing Authorities experiencing the disturbance to determine the
extent and severity of the separation. If direct communication channels are not functioning,
communications are established via whatever means are available (i.e., routing calls through
alternate channels, outside phone lines, cellular phones, radio communications, and/or PJM
Satellite Phone System).
Specific communication and task assignment between Transmission Owner operators,
Generator Operators, and plant operators will be detailed with the individual TO restoration plan
if they differ from what is described in this Manual.
Exhibit 5 presents the general steps that are performed to restore the PJM RTO following
separation.
• PJM System Operator determines the extent and cause of the service interruption
and informs the appropriate personnel as soon as possible of existing generation and
transmission capabilities, equipment damage, and other pertinent information.
• PJM System Operator collects specific information from each Transmission Owner/
Generator Operator and adjacent areas to ascertain current system conditions.
• PJM System Operator reports, via the ALL-CALL system, the extent and cause, if
known, of the outage.
• Offsite safe shutdown power should be restored as soon as possible to nuclear units,
both units that had been operating and those that were already offline prior to the
system disturbance, without regard to using these units for restoring customer load.
Transmission Owners and Nuclear Power Plants must effectively communicate to keep
Nuclear Power Plant apprised of the anticipated restoration time for offsite power.
• Generating units that are able to maintain on-line status have priority of load
assignments to provide loading above minimum levels to achieve stable unit operation.
• Transmission Owner operators will continue to collect the required status information
from the Generator Operators or plant operators within their zone for the Company
Hourly Restoration Reports and submit to PJM. The Transmission Owner operators will
continue to complete and submit the Company Transmission Restoration Report.
• Each Transmission Owner/Generator Operator that is isolated may elect to adhere
to all or none of the guidelines for system control, as described in the PJM Manual
for Balancing Operations (M12), depending on system conditions. Each affected
Transmission Owner shall resynchronize islanded area(s) with neighboring area(s) only
when coordinated by PJM and in accordance with the established procedures in this
manual.
Frequency Control
The control objective of the frequency regulating unit(s) in the frequency controlling area (or
subsystems) is to keep the frequency on schedule. All units not assigned to regulate frequency
are re-dispatched to keep each frequency regulating unit's energy at the middle of its regulating
range.
The best regulating unit(s) in the area (or subsystems) are used to regulate frequency during
restoration. The best regulating unit is determined based on the amount and quality of
regulation provided, as well as energy considerations. If the frequency burden becomes too
large for one unit, the frequency burden is shared by two or more units, preferably in the same
plant control room for better coordination.
The frequency is regulated between 59.75 Hz and 61.0 Hz. If the frequency decays to 59.50
Hz, or below, Synchronous Reserve and/or manual load shedding is initiated to restore the
frequency to between 59.75 Hz and 61.00 Hz. Shed approximately six percent (6%) of load to
increase frequency 1.0 Hz (General rule for small island).
Frequency is adjusted to slightly above 60.00 Hz before load is picked up. The TOs pick up load
in small increments. The regulation requirement to maintain frequency during system restoration
is calculated as 2% of the area load.
Voltage Control
During the restoration process, the bulk power system is operated so that reasonable voltage
profiles can be maintained (generally 90% to 105% of nominal). Distributed reactive regulation
is also established to limit voltage drop for any single contingency.
Transmission shunt capacitor banks are removed from service until sufficient load
(approximately 40% of system load) has been re-energized to prevent high voltage. Shunt
reactors are placed in service when initially restoring the system to help reduce system
voltages. Static VAR Compensators under automatic control are placed in service as soon as
practical. Generator automatic voltage regulators are placed in service as soon as practical
while continuing to aim low on voltage when energizing circuits to reduce charging currents.
Reserves
There are only two categories of reserves that are essential and therefore need to be tracked
during system restoration. These are Dynamic Reserve and Synchronous Reserve. These are
described later in more detail in Section 5.
• Dynamic Reserve — The amount of Dynamic Reserve in an area (or subsystem) must
be sufficient to allow the system to survive a frequency deviation due to the loss of
the largest energy contingency (generation or load). Dynamic Reserve may consist
of reserves on generators via automatic governor action, as well as system load with
underfrequency relay protection enabled.
No more than 50% of the total Dynamic Reserve in an area (or subsystems) can consist of load
with underfrequency relay protection enabled.
• Synchronous Reserve — Synchronous Reserve is required in order to enable an area or
subsystem to return to a pre-contingency state (both tie lines and frequency) as soon as
possible after a contingency.
During system restoration each area or subsystem carries enough Synchronous Reserve to
cover its largest energy contingency. Synchronous Reserve may be either on-line generation
that can be loaded within 10 minutes, or load (including customer load and "pumping load") that
can be shed manually within 10 minutes.
Unit Dispatch
No generator should be loaded above a level at which there is not enough Dynamic Reserve on
remaining units to survive the resultant frequency decay if that unit trips. Generator Operator/
Transmission Owner maintains sufficient load on each unit to stabilize its operation. Generating
units are loaded as soon as possible to load levels above their normal minimum point to
achieve reliable and stable unit operation unless the area (or subsystems) cannot survive the
contingency loss of the unit at minimum load.
Synchronization of Areas (Subsystems) Within a Transmission Owner Zone
Prior to synchronizing two areas (or subsystems), the Transmission Owner will communicate
with PJM. The transmission owner adjusts the frequency of the smaller area (or subsystem) to
match the frequency of the larger area (or subsystem). In addition, the voltages of the two areas
(or subsystems) are as close as possible prior to synchronization.
Upon synchronization, the regulation requirement for frequency control must be recalculated
and reassigned. After synchronization, the Transmission Owner calculates reserve requirements
for the combined system, and adjust unit dispatch accordingly.
Area (or subsystem) frequency is maintained above 59.75 Hz and below 61.0 Hz. Achieving
and maintaining these frequency levels require close coordination between plant operators and
Transmission Owners.
and control frequency, tie line, voltage schedules, share reserves, and coordinate emergency
procedures (per EOP-005-3 R1.3, EOP-005-3 R1.7, and EOP-006-3 R1.2). This step is
performed after the Transmission Owners have established stable island(s) and desire to
interconnect and share reserves or Transmission Owners have coordinated plans to restart
while interconnected.
PJM Actions:
• PJM System Operator acts as coordinator and disseminator of information relative to
generation and transmission availability.
• PJM System Operator keeps the Transmission Owners/Generator Operators apprised
of developing system conditions to assist in the formation and on-going adjustments of
a cohesive System Restoration Plan. System Restoration Plans may be adjusted to take
advantage of this additional information.
• PJM System Operator provides the Transmission Owners/Generator Operators with
updated run-of-river hydro capability.
• PJM will coordinate with neighboring RCs and TOPs to establish external
interconnections and establish tie schedules with neighbors
PJM Member Actions (in those areas being controlled by PJM as the Balancing
Authority):
• The Transmission Owner operators continue to return generating units to on-line status
and restore native load in small increments to maintain generation and load balance.
• As units return to service, the Transmission Owner operators and Generator Operators
report their status to PJM System Operator.
• The Transmission Owner operators maintain scheduled Transmission Owner-to-
Transmission Owner tie line flows until the PJM RTO returns to free-flowing tie
conditions.
• The Transmission Owner operators assure that adequate underlying transmission
capability is electrically connected at the interconnection point of the 500 kV and above
bulk transmission system to provide adequate fault current (relay protection) and VAR
absorption capability when the line is energized (overvoltage).
• The Transmission Owner operators and Generator Operators respond to emergency
procedures when initiated by PJM System Operator.
• The Transmission Owner operators request PJM System Operator’s approval prior to
the closure of any reportable transmission line (see the PJM Manual for Transmission
Operations (M-3)) or a line that establishes an interconnection, either Transmission
Owner-to-Transmission Owner or to an external system.
• Transmission Owner operators will continue to collect the required status information
from the Generator Operators or plant operators within their zone for the Company
Hourly Restoration Reports and submit to PJM. The Transmission Owner operators will
continue to complete and submit the Company Transmission Restoration Report.
System Control
PJM system control may progress through three stages depending on existing system
conditions:
• Manual Control — Manual control is initiated when sufficient data is not available for any
type of automatic control. When this mode of control is initiated, PJM is replacing the
frequency controlling Transmission Owner.
PJM System Operator notifies Transmission Owners and Generator Operators of their
share of the regulation requirement by percentage. Regulation energy assignments are
dispatched manually using whole numbers, with each Transmission Owner responding with
their percentage. These assignments are made via the ALL-CALL system. Frequency is
maintained between 59.75 Hz and 61.0 Hz. If the frequency decays below 59.50 Hz, PJM
System Operator initiates emergency procedures, which may include load shedding, to maintain
stable operations. If load shedding is required, it is assigned on a proportional basis.
The amount of generation adjustments to control frequency may be based on one percent (1%)
of system load to adjust frequency by 0.1 Hz. Actual system response may differ based on the
changing system characteristic. Real-time adjustments may be required.
PJM System Operator directs generation and load adjustments, as required, to maintain reliable
operations. TO zone native generation normally is assigned to native load, except in instances
where Transmission Owner-to-Transmission Owner tie line schedules are arranged. PJM
System Operator notifies all Transmission Owners on the interconnected area of schedules that
are in effect, or pending.
Transmission Owners are responsible for communicating to PJM System Operator any potential
transmission problems i.e. contingency or actual overloads, voltage problems, etc. PJM System
Operator coordinates corrective action. PJM monitoring system has limited capability for
contingency evaluation and on-going monitoring until a majority of the bulk transmission system
is intact.
• Flat Frequency Control — Flat frequency control is initiated when the capability exists
for an ACE signal to be developed by using a frequency value in the interconnected
area. If PJM is not electrically connected to the area being controlled (i.e., frequency is
different), the frequency of the area being controlled may be utilized in the AGC control
program. If PJM is electrically connected to the area being controlled, and not on diesel
stand-by power, the in-house frequency may be used. The Frequency Bias setting is
one percent (1%) of the interconnected areas' load. The bias setting is readjusted as the
interconnected area load changes.
The PJM AGC control program is capable of developing an ACE based on scheduled frequency
versus actual frequency. Regulating signals may also be developed via the automatic regulation
program. Regulation is two percent (2%) of the interconnected area load.
PJM System Operator continues to direct generation and load assignments as required to
maintain reliable operation. PJM System Operator regulates area frequency between 59.75 Hz.
and 61.0 Hz. When the regulating energy has been loaded to restore frequency to 60.0 Hz.,
efforts are made to return the units to their mid-point.
The Transmission Owners are notified via the ALL-CALL system to closely monitor transmission
parameters, since the PJM monitoring program may not have sufficient data at this point except
for actual overloads.
Energy available from external sources is assigned to the Transmission Owners/Generator
Operators based on need and transmission capabilities and/or limitations.
• Tie Line Bias Control — Tie Line Bias Control is used to develop an ACE signal when
Balancing Authority tie lines are in service. When ties to external systems are placed in
service, PJM returns to the Tie Line Bias control mode. This mode (normal control mode)
develops an ACE by comparing scheduled frequency versus actual frequency and
scheduled tie line flow versus actual tie line flow to facilitate interconnected operation.
All control functions are normal including ACE and the regulation control program. The
regulation continues to be two percent of the area's load.
The frequency bias setting is one percent of the interconnected area's load and is readjusted
as the load changes. Generation and load assignments continue to be manually dispatched
until the system can respond automatically via the AGC system. PJM may now be capable of
monitoring the transmission parameters, but Transmission Owners continue to closely monitor
their systems.
Allocations of Load Shedding
Load shedding, if required for frequency or ACE control, is allocated based on connected load
on a proportional basis. Exhibit 6 presents an example.
No re-allocation of load already shed is made as other sub-areas are added to the
interconnected island. However, new allocation factors are calculated if additional load shedding
is required.
Load shedding for transmission overloads will be based on the most effective location to
alleviate the overload.
EHV Restoration
Due to the heavy reactive charging current generated by the 500 kV / 765 kV bulk power
transmission system (approximately 1.70 MVAR per mile), sufficient load and generation
must be restored to the affected areas. Transmission Owner operators assure that adequate
underlying transmission capability is electrically connected at the interconnection point of the
500 kV / 765 kV bulk transmission system to provide adequate fault current (relay protection)
and VAR absorption capability when the 500 kV / 765 kV line is energized (overvoltage). See
Minimum Source Guidelines in Section 7.1.2.
Allocation of Joint Owned Generation
PJM System Operator directs the increase of the generation/transactions when it is beneficial
to the overall system restoration process. Allocations of energy are not based on ownership
or joint-owned generation allocations, but on the capabilities and needs of the interconnected
area. Allocations, if possible, are on a proportional basis. As additional Transmission Owners/
areas interconnect, no attempt is made to re-allocate generation that is already carrying load.
However, revised allocation factors are calculated.
3.1.9 PJM Reliability Coordinator Responsibilities during the Restoration Process and
Coordination of Information
• PJM maintains the current coordinated version of the restoration plan of each
Transmission Operator in its Reliability Coordinator Area. There are three TOPs in PJM's
Reliability Coordinator Area: PJM, ITCI, and AEP. PJM serves as both RC and TOP for
the PJM area. American Electric Power (AEP) operates the 138 kV transmission, though
PJM serves as TOP for its other transmission assets. Additionally ITCI is a TOP in PJM
for a 345 kV generating station, Covert and the Covert-Segreto (AEP) 345 kV line in
Michigan.
• PJM monitors restoration progress and coordinates any needed assistance in the RC
area. PJM actions during a system restoration include:
o PJM will coordinate all interchange schedules with external Balancing Authorities
o PJM will coordinate and direct all restoration of the 500 kV and above transmission
systems
o PJM will develop and calculate ACE as required when appropriate data is available
to perform this calculation
o PJM will coordinate and direct all transmission tie connections to external Balancing
Authorities
o PJM will identify opportunities for interconnection between PJM internal
Transmission Owners and/or neighboring Reliability Coordinator, Balancing Authority,
and Transmission Operator systems
o PJM will collect system status information and provide status updates to members on
system restoration status
o PJM, in its role as Reliability Coordinator, is the primary contact for disseminating
information regarding restoration to neighboring Reliability Coordinators and to
Transmission Operators and Balancing Authorities within its Reliability Coordinator
area.
o PJM will conduct periodic System Operations Subcommittee (SOS) conference calls,
as appropriate
o In the event the restoration plan cannot be completed as expected, PJM will develop
and coordinate alternate steps to restore the system
o PJM System Operator establishes communications between the Transmission
Owners that are experiencing the disturbance and between adjacent Transmission
Owners or TOP/ BA areas
o PJM System Operator determines the extent and cause of the service interruption
and informs the appropriate personnel as soon as possible of existing generation and
transmission capabilities, equipment damage, and other pertinent information
o PJM System Operator collects specific information from each Transmission Owner/
Generator Operator and adjacent areas to ascertain the present system conditions
o PJM System Operator reports via the ALL-CALL system, the extent and cause, if
known, of the outage
o PJM’s Reliability Coordinator Area restoration plan provides coordination between
individual Transmission Operator restoration plans and ensures reliability is
maintained during system restoration events.
o PJM's Reliability Coordinator Area Restoration Plan is contained in PJM Manual
for System Restoration (M36). As stated in section 1.1 of Manual 36, "Policy
Statements,” This manual (M36, the PJM Restoration Plan and other data sources as
noted) include the following:
− A reliable black-start capability plan including:
• Fuel resources for black start power for generating units (Black start
database)
• Available cranking and transmission paths (Black start database)
• Communication adequacy and protocol and power supplies (Black start
database)
• Accounting for the possibility that restoration cannot be completed as
expected.
• Operating instructions and procedures for synchronizing areas of the system
that have become separated
• Procedures for simulating and, where practical, actually testing and verifying
the plan resources and procedures
− Documentation in the personnel training records that operating personnel have
been trained annually in the implementation of the plan and have participated in
restoration exercises (training database)
− The functions to be coordinated with and among Reliability Coordinators and
neighboring Transmission Operators (including references to coordination of
actions among neighboring Transmission Operators and Reliability Coordinators
when the plans are implemented).
− Section 3.1.5 ("Implement Restoration Procedure") and 3.1.6 ("Member
Interconnection") of Manual 36 describes broadly the implementation of PJM's
RC Area Restoration Plan so as to maintain reliability during system restoration
events. Additional procedures for maintaining reliability during system restoration
are included in Section 6, "Generation," and Section 7, "Transmission."
• PJM is the primary contact for disseminating information regarding restoration to
neighboring Reliability Coordinators and Transmission Operators or Balancing
Authorities not immediately involved in restoration (per EOP-006-3 R1.5). As stated
in Section 3.1.3 (Determine Restoration Process), the criteria for sharing information
regarding restoration with neighboring Reliability Coordinators and with Transmission
Operators and Balancing Authorities within its Reliability Coordinator area (in
accordance with EOP-006-3, R1.4) is listed below:
o PJM's RC Area can be restored from complete system failure without outside
assistance, and as such will not cause a burden on any neighboring areas. Section
1.1, "Policy Statements," of this manual states: "The policy of PJM is to maintain,
at all times, the integrity of the PJM RTO transmission systems, the Eastern
Interconnection, and to prevent any unplanned separation of the Transmission
Owners' systems. The purpose of this plan is to establish procedures with a priority
of restoring the integrity of the Interconnection.
o Based on system restoration lessons learned in 2003, the PJM restoration plan
should stand alone with no dependencies on neighboring systems to help prevent
separation of additional systems."
o Section 8.1.9 of this manual, "Guidelines for Area Interconnection and Use of
External Power during System Restoration" provides guidelines for reconnecting to
the Eastern Interconnection and assisting neighbors by actions such as providing
excess power to deficient areas, taking power from areas with excess, sharing
reserves, and providing cranking power to neighboring areas, so as to provide a
service rather than a burden to neighbors and assist in the overall restoration of the
Eastern Interconnection as needed.
• PJM will take steps to restore normal operations once an operating emergency has
been mitigated in accordance with its restoration plan. As stated in Section 3.1.8 (PJM
Returns to Normal Operation): "Re-establish PJM single control center coordination.
This occurs when an ACE can be calculated for the area to be controlled (entire PJM
area or portion) and a return to central coordinated operation is desired by PJM and
the Transmission Owners. When conditions permit, PJM System Operator notifies all
Transmission Owners/Generator Operators that the PJM RTO is returning to normal
operation, i.e., free flowing Transmission Owner-to-Transmission Owner ties, Balancing
Authority to Balancing Authority ties, generation under AGC control, and return to
published regulation and reserve requirements."
Section 4: Communications
Welcome to the Communications section of the PJM Manual for System Restoration (M36). In
this section you will find the following:
• A description of the communications guidelines for use during a restoration.
4.1 Communications
All modes of communication used in power system operations, including voice, print, SCADA,
and data exchange, are of great importance to the prompt restoration of the PJM RTO after a
major event that results in shutdown or separation. Of the several forms of exchange, voice
communication is most critical.
Communications by operators involving voice (and printed data) can include exchange with
plant operators and field personnel operators within neighboring Reliability Coordinators,
Transmission Operators, and Balancing Authorities, Transmission Owner/Generator Operator
management, identified federal, state, and local authorities and agencies. Operators also
interact with corporate public relations departments or other designated groups that, in turn,
issue communiqués to the media that advise the general public of system status and appeals
for actions that customers may be asked to take.
The system restoration procedures identified earlier in this section assume normal
telecommunications systems are available and functioning properly. These include telephone,
internet, microwave, and radio. However, the possibility exists that this assumption may not be
supported due to the effects of the event leading to shut-down or separation, or the system's
response to the event. The possibility that one or more modes of communication may not be
readily available requires that system operators and others be familiar with the organization
of their telecommunications network including primary, secondary, and alternate pathways to
important locations. This possibility is raised due to the critical role that communications play
in the restoration process and that problems may arise despite all efforts taken to assure the
reliability of the communications systems prior to the event. In addition, these communication
systems should be tested by Transmission owners at a minimum annually or during the
restoration drills.
Primary and back-up sites must contain sufficient communications and power supplies
consistent with PJM Manual for Control Center and Data Exchange Requirements (M-1).
Specific communication and task assignment between Transmission Owner operators,
Generator Operators and plant operators will be detailed with the individual TO restoration plan
if they differ from what is described in this Manual.
• PJM will communicate with Transmission Owner operators and Generator Operators/
MOC dispatchers utilizing the same contacts that they use in normal operations.
• Prior to PJM resuming its Balancing Authority role, Transmission Owner operators may
communicate to the Generator Operator or directly to the generating plant operators
for generation related communications (i.e., starting units, changing unit output, etc.).
However, if the Transmission Owner operator is communicating directly with the plant
operators, either the Transmission Owner operator or the plant operator must also keep
the Generator Operator informed of the operating status of their generators.
• Once PJM resumes the Balancing Authority role (see section 3.1.7), PJM must also
be made aware of any changes in unit dispatch or operating status. Changes to unit
dispatch may be directed by PJM at this point through their normal Generator Operator
contacts. Transmission Owner will continue to provide hourly reports until directed by
PJM to discontinue these reports.
• Support Staff participating in conference calls must adhere to M36, Attachment C:
Conference Call Protocol.
• Voice messages have three parts:
o Introduction — to get the attention of the receiver and allow them to focus
o Body — the substance of the message
o Summary — repeat main points of message
• Receivers must critically assess the content of the message and must get clarification
if needed before carrying out any action. Logging is of critical importance to operators
during restoration of the system and to others after the system has been restored.
Therefore, all log entries must be complete, accurate, and readable. To the extent
possible, logs include relevant data to support strategic decisions as well as specific
actions taken. Data regarding the PJM RTO status is important to note since actions are
referenced to conditions as they were known at that time. All entries include the time and
identification of the dispatcher making the entry.
• Since logs are likely examined by various groups after-the-fact, all entries are in
accordance with Transmission Owner/Generator Operator protocols using correct terms.
determine whether there is an adequate power source to the communication equipment in order
to handle the duration of the blackout conditions.
• Ability to Receive and Evaluate Customer Calls — In the early stages of system
restoration, Transmission Owners and Distribution Providers are bombarded with phone
calls from employees and customers. From their perspective, continual calls inquiring
into status of service provide no useful purpose. In fact, continual customer calls may be
a detriment by degrading the public telephone system to a point that it is not functional.
Some of the ways of mitigating problems are:
o automatic dialing system to notify employees on the status
o immediate notification of customer service representative
o public appeal to limit phone system use
o priority call system for utility dispatcher's phone system
o notifications of restoration status posted on company websites
• Employee Call-ins — System restoration requires an enormous number of tasks for
Transmission Owner/Generator Operator personnel to complete. It is essential for
Transmission Owner/Generator Operator to promptly get their off-duty personnel notified
to report to duty. Automatic notification systems can provide system and plant operators
with necessary relief of this burden. For effective use of extra personnel, utilities should
consider defining responsibilities in advance of the event. Consideration must also
be given for rotating personnel in order that system and plant operators maintain
effectiveness.
Owners should include periodic monitoring of RTU and other communication equipment
to verify independence from standard AC powered equipment feeds as part of their
routine inspections.
Calculation of other reserve categories (i.e., Operating Reserve, etc.), while important, are not
required during a system restoration.
The amount of Dynamic Reserve needed can be determined by analysis of generator "load
pick-up factors" for units paralleled to the system. These "load pick-up factors" are the maximum
load a generator can pick up as a percentage of generator rating without incurring a decline in
frequency below safe operating levels. "Rule of Thumb" load pickup factors are:
A generator that trips offline may be considered to have the same effect on a system as picking
up load equal to the tripped generator's output on the remaining generators. Therefore, the
maximum level of dispatch for a generator in a system should not be allowed to exceed an
amount over which the remaining generators in a system could maintain acceptable frequency
given a loss of the generator. To determine the maximum level of dispatch for a unit, or in other
words, the largest acceptable energy contingency, generator load pick-up factors must be used.
• Load with Underfrequency Relaying — System load with underfrequency trip levels
above the frequency at which generators will normally separate from the system during a
frequency disturbance (i.e. 57.5 Hz).
Generator governor response takes place in seconds and is smooth. Technically, both load
with underfrequency relaying enabled and generator governor response act similarly and are
automatic and can both be considered as Dynamic Reserve.
Most underfrequency load shedding relays can trip feeders within a matter of cycles; therefore,
it is very valuable because it increases the safe levels of dispatch in a system. In fact, every
megawatt of load with underfrequency load shedding enabled acts to improve the ability of
a system to withstand a sudden increase of load or loss of a generator similar to "generator
governor response", except that the effect takes place in cycles and is not as smooth.
During the early stages of restoration, it is not advisable to restore load that has underfrequency
relaying enabled. With a small generating base, even small amounts of load pick-up can
cause large deviations in system frequency. It is advisable to resist picking up load that has
underfrequency relaying enabled until normal load pick-up has been demonstrated to not cause
frequency decay below the applicable underfrequency trip level.
Load restored with underfrequency relays enabled too early in the restoration process can result
in frequent automatic load shedding. If too much load is shed, there is a risk of running the
frequency too high which may result in an overspeed condition.
As the generation base grows, and normal load pick-up does not cause frequency to decay
below the underfrequency trip levels, it is advisable to start adding load with underfrequency
relays set at the lowest trigger frequency. As the generation base continues to grow, load should
be added with increasing underfrequency relays settings.
It is advisable to limit the amount of Dynamic Reserve that consists of load with underfrequency
enabled. This is desirable because frequent tripping of load with underfrequency enabled
occurs unless we also rely on "generator governor response" to restore frequency after a
frequency decay. If too much load has been restored with underfrequency relays enabled and
an incident occurs that results in all underfrequency relays operating, there is a risk of having
high frequency which may cause an overspeed condition. As a guide, no more than 50% of
Dynamic Reserve in a system consists of load with underfrequency enabled.
The ultimate goal is to rely totally on generator governor response to restore frequency should
any credible contingency which causes frequency decay occur. This occurs naturally as system
restoration proceeds since many generators are paralleled to the system. Eventually, system
restoration reaches a point where all systems agree to suspend calculation of Dynamic Reserve
since more than enough Dynamic Reserve exists to enable the system to survive any credible
contingency. Before this point is reached, however, Dynamic Reserve must be calculated.
Calculation of Dynamic Reserve for an area connected to the Eastern Interconnection is not
required.
• Example #2 — Same data as Example #1, except 150 MW of load with underfrequency
load shedding enabled has been restored.
No more than 50% of Dynamic Reserve can consist of load with underfrequency load
shedding enabled. Therefore, the maximum contribution from this source of Dynamic
Reserve is 130 MW.
No governor response will be available from the steam units which have blocked
governors or from the hydroelectric units at full output.
Note:
The calculation of Dynamic Reserve indicates that the total contribution of underfrequency
load shedding should only approximate fifty percent (50%) of the Dynamic Reserve in the
interconnected area(s). [However, if a contingency occurs that reduces the area(s) frequency
to a level of the underfrequency relay settings, all of the relays would operate and may
cause over-frequency problems.] During the restoration process, it is advisable to restore
load with underfrequency trip enabled by alternating the restored load among the three or
five underfrequency steps. Consideration may be given to adjusting the calculated Dynamic
Reserve for the governor response that is provided by the largest energy contingency.
Section 6: Generation
Welcome to the Generation section of the PJM Manual for System Restoration (M36). In this
section, you will find the following information:
• How the generating stations in the PJM RTO respond during restoration (see
“Generating Stations”).
• A description of cranking power during restoration (see “Cranking Power”).
transmission and distribution lines and buses must be established. Each Transmission Owner’s
system restoration plan (SRP) must provide for cranking power to non-black start units including
any necessary arrangements with other Transmission Owners or systems as may be necessary
to provide start-up assistance not readily available within the company's area.
The following types of paths are defined:
• Cranking Path – transmission path from a Black Start unit to another generator with the
intent to facilitate startup of that generator to aid in the restoration process.
• Critical Restoration Path (Nuclear) – transmission path from a Black Start unit (or other
source) that provides offsite power to a nuclear plant’s auxiliary equipment to allow the
nuclear plant to maintain safe shutdown
• Critical Restoration Path (Load) – transmission path from a Black Start unit (or other
source) to restore load that is identified as critical load in Attachment A
• Non-Critical Restoration Path – transmission path from a Black Start unit (or other
source) to restore non-critical loads or facilities as identified in the System Restoration
plan
Transmission or distribution corridors for supplying start-up power are selected, taking extra
care to isolate and avoid damaged facilities, while restoring critical AC power to key substation
facilities along the black start path. The integrity of air and gas operated circuit breakers and
pressurized oil filled cables, as well as relay, control, and communications systems at these key
substations depends on the timely restoration of their stations service facilities.
Where possible, field personnel are used to verify the condition of equipment along the black
start path and to verify breaker positions.
Transmission Owners must include available cranking power and transmission paths in their
individual restoration manuals.
When start-up power or Black Start generation is required from another Transmission Owner
or Balancing Authority, arrangements include a determination of whether or not the unit
receiving start-up assistance becomes synchronized to the supplying company or system.
Implications could include isolation of the receiving unit from its own system or creation of an
unintended interconnection between the two areas. Cranking paths between TO zones must be
documented within each TO system restoration plan.
See Section 9 for more information on Cross Zonal Coordination.
Section 7: Transmission
Welcome to the Transmission section of the PJM Manual for System Restoration (M36). In
this section, you will find the following information:
• How PJM provides voltage regulation and control during the restoration process (see
“Voltage Regulation and Control”).
• A description of the synchronizing process phases (see “Synchronizing”).
69 kV Line 0.025
Energization Guidelines
• Lines —500 kV / 765 kV lines and transformers are energized separately, not in
combination. Ideally, both sending and receiving end 500/230 kV transformers are
energized from the low side; the 500 kV / 765 kV line is energized from the strongest
source; and a parallel made with a 500 kV / 765 kV breaker.
Load the newly energized path appropriately before energizing additional 500 kV / 765 kV lines.
There should be a minimum of 20 MW of connected load per mile of 500 kV / 765 kV line that is
energized.
Energize only transmission lines that carry significant load. Energizing extra lines generates
unwanted VARS.
• Line and Transformer — When energizing a 500 kV / 765 kV bus section with a 500/230
kV transformer, if not already open, open all 500 kV / 765 kV line breakers (clear bus
section). Close the source end transformer's 230 kV breaker. Before energizing a line,
reduce the 500 kV / 765 kV voltage by adjusting the tap on the sending end 500 kV / 765
kV TCUL transformer. This minimizes VARS generated by line charging, reducing VAR
absorption requirements on the underlying system and helps control the voltage to less
than 500 kV / 765 kV at the receiving end.
• Transformer Voltages — Adjust the sending end line voltage to 475 kV or below. The 230
kV voltage should not exceed 230 kV, preferably as low as reasonable.
Adjust the receiving end line voltage to around 500 kV / 765 kV and 230 kV (+/- 5%).
The receiving end transformer tap matches or exceeds the receiving end voltage. This may
be difficult if there is no AC station service power at the receiving end substation. TCUL
transformers require AC power for operation which could be supplied by an emergency
generator, or since the transformer is de-energized, the TCUL could be operated manually. To
minimize overheating due to excitation, before energizing, the high side transformer tap position
must be above neutral (receiving end line voltage is typically higher than 500 kV / 765 kV due to
charging).
Energize the receiving end transformer only after all the above conditions are met. A circuit
switcher or air switch is a good device for energizing a transformer because it energizes at a
favorable point of wave (voltage crest).
conservative and can be used in the absence of more detailed study results. Specific situations
may dictate energizing EHV without all of these guidelines being met.
The 500 kV / 765 kV pre-engineering guidelines are:
• Primary and backup relays in service
• Shunt capacitors out-of-service
• Generation
• 600 MW of electrically close generation (energy) connected 230 kV or higher
• Electrically close is defined as less than 50 230 kV miles
• Provides adequate short circuit current for fault clearing
• Minimum of 30 MW of generation (capacity) per mile of energized 500 kV / 765 kV line
• Load
• Minimum of 20 MW of load per mile of energized 500 kV / 765 kV line
• Energized Line = Already Energized + The Line Being Energized
The rules of thumb for voltage control are based on available analysis:
• Detailed analyses unavailable
• Generation electrically close to energizing point
• Minimum generating capacity, 30 MW/mile of 500 kV / 765 kV to be connected
• Load electrically close to energizing point
• Minimum load, 20 MW/mile of 500 kV / 765 kV to be connected
• Provides approximately 1.8 MVAR load to prevent machines from excessive loading
operation
• When detailed information about the system is lacking, the following guidelines provide
a 2:1 safety factor. Generation must be electrically close to the point where the EHV
system is to be energized.
• If available, real-time analysis tools or off-line studies should be utilized to confirm
aforementioned “rules of thumb”.
Description Reason
Description Reason
VAR Absorption — A minimum of 3.0 MVAR This will control line voltage less than 500 kV / 765
of electrically close VAR absorption per mile kV.
of 500 kV / 765 kV line connected must
be available. May be generator reactive
(leading), reactive load, shunt reactors,
etc. Static VAR compensator may assist in
accomplishing this if available.
At least 3 MW of load per mile control of 500 To provide damping to dynamic over- voltage when
kV / 765 kV line to be energized must be energizing transformers.
established on the underlying system.
7.2 Synchronization
Restoration of an interconnected system involves re-establishing electrical ties between
generators in two or more areas (or subsystems) within a single Transmission Owner, or
between two or more Transmission Owners or systems, by synchronizing the two areas
to a common speed or frequency. This section describes the process to be followed for
interconnecting two or more areas or subsystems within a single TO area, or between two or
more TOs or systems, and PJM’s operating processes to reestablish connections within its
TOP system for areas that have been restored and ready for reconnection (as required by
EOP-005-3 R1.3, EOP-005-3 R1.7, and EOP-006-3 R1.2). The increased inertia of the resultant
enlarged area tends to dampen fluctuations in frequency and increases the capability of the
area to pick up larger blocks of load and establishes or maintains Dynamic and Synchronous
Reserves. These increased capabilities promote more stable operation, thus facilitating further
restoration efforts. However, the benefits of tying two or more areas together must be balanced
with the risk of the synchronizing process and the ability to control the enlarged area to maintain
generation-load balance within acceptable frequency and voltage bandwidths.
Synchronization is only required when connecting two areas or islands that have running
generation sources. Simply using generation in one zone to pick up load in an adjacent zone
does not require synchronization.
On a related note, implications of synchronization need to be evaluated in cases where cranking
power for unit restart is provided by another Transmission Owner or system.
Preparation plans must also consider additional lines to close once joined, to strengthen ties
to protect against contingencies. Also, the additional line(s) may be needed as alternates if
synchronization is not successful on the identified line for tie in.
• Evaluate the capabilities of two areas to be joined and exchange data between
Transmission Owners when not within a single Balancing Authority.
• Each of the two areas to be joined must demonstrate sufficient capability of maintaining
frequency and voltage control in order to permit synchronization. Additionally, each one
must be strong enough to withstand the "tie-in" and have the capability to share in the
control of the enlarged system.
Interconnection Checklists (Exhibit 16) are completed by Transmission Owners of the two
systems to be tied.
Synchronization
Prior to synchronization, the Transmission Owner must communicate with PJM (PJM will
coordinate with neighbors as required) and get approval for synchronization if connecting 2
Transmission Owners (internal or external). Before synchronizing, the frequency of the two
areas must be matched. Adjustments are made by the area most able to do so (preferably the
smaller area). The aim of the other area is to maintain its frequency at a stable point. Voltages of
the two areas are as close as possible. Ideally, the smaller area adjusts frequency and voltage
to that of the larger area. When using a synchroscope, frequencies are such that the scope
is moving slowly in the fast direction, or with three lights, all lights are out. Failure to match
frequency and voltage between the two areas can result in significant equipment damage and
possible shut-down of one or both areas. A synchro-check relay can also be used to connect
two areas, provided that the indication of the phase angle difference is visible to the operator at
the control device initiating the circuit breaker closure.
Post-tie Follow-up
• Coordinated operation, as agreed to, is carried out within the enlarged area (subsystem)
maintaining frequency control and tie line schedule(s). Dynamic and Synchronous
Reserve requirement are recalculated and re-allocated.
• Communications are maintained on a regular basis between interconnected areas or
systems.
• Additional ties are established according to plan to strengthen and stabilize the
interconnection between the two areas when appropriate.
During system restoration, it is critical that AC power be restored to key substations as soon
as possible to maintain the integrity of air and gas operated circuit breakers. Assure that
communication equipment be independent of local AC power supply during abnormal operation.
The local generating plant operator should have sufficient control over frequency and terminal
voltage so that he or she can parallel any generating unit with an external source at any time it
becomes available. Enough equipment and staff are available at generating stations to assure
safe shutdown and to be capable of being restarted as soon as cranking power becomes
available.
• It is desirable that restoration plans have redundancy built into them such as, when
developing each subsystem, at least two sources of cranking power and black start are
included.
• When a Transmission Owner can provide a demonstrable plan to restore adequate
service from an offsite source to an energy control center, a substation, or a generating
station within less time than required in the following guidelines, that plan is then to be
considered in compliance with PJM black start standards. PJM black start standards are:
o Energy control centers are provided with adequate on-site facilities to provide a
minimum of 24 hour stand-alone capability.
o Substations on the bulk power system are provided with adequate back-up power
supplies to provide a minimum of eight (8) hour stand-alone capability.
o Generating stations are provided with a minimum of two hour stand-alone capability.
Base case conditions exist which include both a system configuration following a disturbance
and the operational status of equipment on the system. It is recognized that some equipment
failures can and will occur during a system shutdown and subsequent restoration. These
failures are addressed on an individual basis as they are found and adjustments are made to
system restoration procedures, where necessary. For these guidelines, the assumptions are as
follows:
• Black start unit is a unit that is capable from going to a shutdown condition to an
operating condition and start delivering power without assistance from the system.
• All steam generators on-line at the time of the disturbance trip offline, without damage.
Emergency diesels/batteries, where available, can be used to rotate turbines on turning
gear. Emergency start-up power is accomplished without incident.
• Steam units are available to synchronize or energize the bus and subsequently load at
times as found in the PJM Markets database.
• All voice and data communication systems required for system operations are functional.
• Emergency energy supply systems are operational.
• Fuel inventories at all peaking units and emergency generators are adequate.
• Transmission Owner restoration plans are coordinated with the adequacy of the
substation battery capability.
• All circuit breakers remain operational without station service being available.
• Staffing requirements for system restoration can be met by available personnel. Any
additional staffing is assumed available through existing procurement procedures.
• Transmission Owners do not establish bilateral transactions.
To ensure consistency in TO Restoration Plans, PJM requires that each Transmission Owner
include the following list of generation (Exhibit 10) within their zone into their Restoration Plan
as an appendix. This document will identify Black Start units, Critical Load generation (< 4 hour
start up time), Nuclear Units and any other generation referenced in the TO Restoration Plans
(as determined by the TO). Exhibit 10 will be utilized to generate the Spring System Restoration
Drill invitations.
Unit Unit ICAP Emergency Prim.Fuel Sec. Hot Start Cold Ramp Rate
Name Type Minimum Fuel Time Start (MWs/Minute)
(Unit Min (Hours) Time
Stable Load) (Hours)
Unit Unit ICAP Emergency Prim.Fuel Sec. Hot Start Cold Ramp Rate
Name Type Minimum Fuel Time Start (MWs/Minute)
(Unit Min (Hours) Time
Stable Load) (Hours)
Nuclear Units
Unit Unit ICAP Emergency Prim.Fuel Sec. Hot Start Cold Ramp Rate
Name Type Minimum Fuel Time Start (MWs/Minute)
(Unit Min (Hours) Time
Stable Load) (Hours)
Unit Unit ICAP Emergency Prim.Fuel Sec. Hot Start Cold Ramp Rate
Name Type Minimum Fuel Time Start (MWs/Minute)
(Unit Min (Hours) Time
Stable Load) (Hours)
does not inhibit detection of problems and are capable of continued operation during system
disturbances/blackouts.
Energy control centers have adequate back-up power to provide a minimum of 24 hour stand-
alone capability. However, plans should include provisions to ensure longer stand-alone
capability. Future hardware is designed and powered by redundant sources where possible.
Telecommunications systems used in conjunction with RTUs, operating computer systems,
telemetry, voice, etc. must be powered by battery, UPS, or emergency generators and be
capable of operating during a complete system blackout.
• Field reports from personnel in substations can be used to enhance information
obtained from SCADA systems regarding the status of the electric power system. These
personnel can provide meter readings, breaker status, alarms, etc.
• PJM reports via the ALL-CALL system provide information regarding the extent of the
outage known at the time.
• Generation plant reports are used to determine unit availability. The Generator Operators
notify each power plant about the extent of the outage and system status known at the
time.
• Equipment status is tabulated by Generator Operators through communications with
power plants.
• Cranking Power Availability — Sufficient resources for black start units are available to
ensure safe shutdown and be capable of restart as soon as cranking power is available.
• Cranking power is available to restart necessary generating units at plants or through
portions of the internal transmission system.
• Confirm status of plant starting procedures — Each steam plant prepares to implement
start-up procedures immediately following plant shutdown. Estimated time of return (on-
line time) — Plant Operators provide estimates to Transmission Owner operators and
Generator Operators of unit return times.
• Where applicable at steam power plants, station services are restored as soon as
possible taking into consideration battery limitations and loss of water/steam in boilers.
• Units that were able to maintain on-line status have priority for additional load to achieve
stable operation.
• Organize steps and/or sequential order of System Restoration Plan (SRP) — Once an
overall restoration strategy is identified, all or portions of the SRP are selected as being
appropriate for use based on the current system status. In addition, the order of the
restoration steps to be used may require changes due to the prevailing conditions.
• Assign sections/steps of the SRP to individuals and begin implementation — Once the
steps to be used have been identified, they are assigned to operators or appropriate
personnel who begin implementation of the restoration process.
• Power system disturbances are most likely to occur as the result of the loss of
generating equipment, transmission facilities, or as the result of unexpected load
changes. These disturbances may be of, or develop into, a magnitude sufficient to affect
the reliable operation of the PJM RTO. The associated conditions under severe system
disturbances generally result in critically loaded transmission facilities, critical frequency
deviations or high or low voltage conditions. Such disturbances can result in equipment
damage and a system blackout. Due to the unknown impact of the system blackout on
generator and transmission equipment, both PJM and the Transmission Owner must be
able to adjust restoration strategies based on actual system conditions.
A person in each Transmission Owner and PJM are assigned to act as an information
coordinator. He or she relays disturbance information to PJM as soon as it becomes available.
PJM is informed of the restoration of bulk power transmission lines within an Island or between
neighboring PJM companies so that PJM can keep abreast of Transmission Owner restoration
progress. PJM is also informed of generation lost at each station, generation still operating, load
lost and location, and critical voltages throughout the system.
• Substations that have the capability of synchronizing two systems that are isolated from
each other are identified and included in SRPs. Normally, a synchroscope, a synchro-
check relay or synchronizing lamps are used to synchronize two subsystems that are
isolated from each other.
Based on pre-studied examination of steady state voltages and selected switching surge
studies:
• Loadflow solutions are used to examine steady state voltage levels that may exist during
the restoration process, including those of open-end lines. If necessary, switching surge
studies are used to identify transient problems for questionable switching conditions
8.1.9 Guidelines for Area Interconnection and Use of External Power during System
Restoration
• Any opportunity to connect to the Eastern Interconnection should be explored as soon as
possible.
• Any available energy from neighboring companies or Balancing Authorities should be
utilized by a deficient company regardless of the “firmness” of the energy.
• Cranking power to neighboring companies is to be supplied as a priority to restoring
internal customer load.
• A company connected to the Eastern Interconnection should supply any available
excess energy for load restoration to a deficient company. Stability is normally not a
concern in this situation.
• There is no need to employ or monitor Dynamic Reserves for companies connected to
the Eastern Interconnection.
• Two or more isolated islands under different Transmission Owners that are
interconnecting must adhere to the guidelines set up in the Interconnection Checklist
found in Attachment B, Exhibit 16.
• Two isolated islands within the same Transmission Owner that are interconnecting are
also encouraged to consider the guidelines in the Interconnection Checklist found in
Attachment B, Exhibit 16.
• Certain informational items, contained in the Interconnection Checklist in Attachment B,
Exhibit 16, are not required for an island tying to the Eastern Interconnection or tying to a
PJM company already connected to the Eastern Interconnection. These items deal with
dynamic reserve and frequency stability.
• When tying to the Eastern Interconnection, only items 1-5 and 15-25 of the
Interconnection Checklist in Attachment B, Exhibit 16 are required.
• If only supplying load to an adjacent TO (i.e. no synchronization required), only items 1-5
and 15-25 of the Interconnection Checklist in Attachment B, Exhibit 16 are required.
• PJM will set up and coordinate any interchange schedules with external Balancing
Authorities.
• When a company connects to the Eastern Interconnection, it must have adequate
Synchronous reserve by way of available unloaded capability on synchronized
generation and/or load shedding to cover their largest energy contingency. It may be
possible to make agreements with the external area to share in covering of some of
these reserves.
The following considerations will be evaluated when analyzing cross-zonal coordination options:
• Technical feasibility requirements including:
o Maintaining voltages within limits
o Maintaining MW flows within thermal limits
o Maintaining dynamic stability of generation
o Timing requirements of serving critical load
o Test history and performance history of Black Start resource
• Complexity considerations
o Amount of switching to establish cranking path(s)
− Characteristics of cranking path (length, geography, travel time, number of
substations, voltage level, etc.)
These cross zonal opportunities will be evaluated during the 5 year Black Start selection
process (as outlined in Manual M-14D) or upon changes to Black Start capability or critical load
amounts. TOs may also request PJM to evaluate opportunities.
Should there be a disagreement about the location, amount or number of Black Start
resources, or disagreement between the supplying TO, receiving TO or PJM about cross zonal
coordination, the following process will be followed:
• The parties involved would bring the issue to the SOS-T for consultation
• If the parties continue to disagree, the issue would be referred to the Dispute Resolution
Process as detailed in Section 5 of the PJM Operating Agreement
• General notification of initiation and result of Dispute Resolution process will be given to
the Operating Committee
There are three possible levels of Cross Zonal Coordination as defined in the following
subsections.
A.1.1 Goal
PJM and its stakeholders have developed requirements for the amount and redundancy of
Black Start generation based on critical load requirements. Specific black start data to include
fuel resources for black start power for generating units, available cranking and transmission
paths, and communication adequacy and protocol and power supplies are contained in the PJM
Black start database.
Note:
For generating stations with multiple units (0-4 hour start), consider the impact on restoration
time if only enough critical load was carried to start one of the units at the station. This
unit could then supply the other units at the station with auxiliary power. If doing this would
increase restoration time significantly, critical load will be identified for all units at the
station. Consideration will also be given to whether plant personnel can start all units at the
plant in parallel given physical plant or resource constraints.
Note:
PJM will utilize the above definitions for critical load in the 5 Year Black Start Selection Process
scheduled for 2018 for implementation in 2020. Following the selection of Black Start units that
would best meet these critical load requirements, cranking paths will be updated in TO system
restoration plans and the PJM Black Start database.
Off-site power should be restored as soon as possible to nuclear units, both units that had been
operating and those that were already off-line prior to system disturbance, without regard to
using these units for restoring customer load. Nuclear units that are taken off-line on a controlled
shutdown can normally be restored to service between 24 and 48 hours following the controlled
shutdown.
A list of critical substations that serve Gas Infrastructure critical load will be documented in the
Transmission Owner’s Restoration Manual.
Required Black Start = 110% (Critical Load requirement) on a locational basis
This will account for an average forced outage rate (5%) plus an allowance for additional,
unexpected Critical Load (5%). It is recognized that while this requirement is generally specified
on a TO zonal basis, that zones may be aggregated, as described in Section 9 (cross zonal
coordination) , such that the Black Start resources may physically lie in adjacent zones.
In addition, PJM recognizes the need for some redundancy in Black Start generation.
Redundancy allows for system restoration even if some Black Start resources are unavailable,
potential system damage precludes use of certain Black Start resources and also allows for
variance between Critical Load calculations and actual needs.
To achieve this redundancy:
• PJM will ensure a minimum of two Black Start resources are “allocated” to each
transmission zone with a Critical Load requirement. Note that the Black Start resources
are not required to be physically located within the zone to which they are allocated.
However, each zone must be able to identify within their system restoration plan
the two resources allocated to them during a system restoration. Exceptions to this
“two resource rule” will be allowed with PJM and System Operation Subcommittee-
Transmission (SOS-T) endorsement.
Black Start Resource Operators must maintain fuel to allow for 16 hours of run time or as
defined by the Transmission Owner restoration plan, whichever is less. Generator Operators
must notify PJM and Transmission Owners if a Black Start resource fuel level falls below these
values.
Also, per NERC Standard EOP-005-3, R13, each Generator Operator with a Blackstart
Resource shall notify its Transmission Operator of any known changes to the capabilities of that
Blackstart Resource affecting the ability to meet the Transmission Operator’s restoration plan
within 24 hours following such change.
Additionally, off-site power should be provided to Nuclear Generation consistent with the
timelines identified in the Transmission Owner’s Restoration Plan or NPIR agreements.
PJM, in collaboration with the TOs, will select Black Start units to meet Critical Load
requirements during the 5 year Black Start Selection process described in PJM Manual M-14D,
Generator Operational Requirements. PJM will utilize the Black Start Replacement Process,
as described in PJM Manual M-14D for changes to Black Start availability or Critical Load
requirements that occur within the 5 year period.
PJM, in its role as Transmission Operator (TOP), is responsible for selecting the Black Start
resources for a system restoration plan. PJM would work closely with the TOs to identify these
units based on:
• Critical Load requirements
• Available Black Start resources
• Minimum number of Black Start resources allocated to a zone
• Possible cross zonal coordination opportunities
PJM will utilize the start time parameters and test data to evaluate the Black Start resources
and whether these resources will meet the requirements of the restoration plans. PJM may
require some Black Start resources to adhere to less than a 3 hour start time given critical load
restoration timing requirements. These units will be notified of this timing requirement and tested
to it during annual Black Start testing. PJM recognizes that Black Start resources with three hour
start times may not appropriate to meet nuclear power off-site safe-shutdown load restoration
requirements. The target restoration time for off-site power to nuclear stations is 4 hours.
The TO will adjust its system restoration plan based on the Black Start units allocated to it from
this selection process. The TO has the option of procuring additional Black Start resources (if
not already procured by PJM), but the costs of these resources will be recovered, if necessary,
outside of the PJM Open Access Transmission Tariff (OATT).
Should there be a disagreement about the location, amount or number of Black Start
resources, or disagreement between the supplying TO, receiving TO or PJM about cross zonal
coordination, the following process will be followed:
• The parties involved would bring the issue to the SOS-T for consultation.
• If the parties continue to disagree, the issue would be referred to the Dispute Resolution
Process as detailed in Schedule 5 of the PJM Operating Agreement.
o General notification of initiation and result of Dispute Resolution process will be given
to the Operating Committee.
A.1.3 Background
A. Restoration Targets / Assumptions:
A system assessment following a blackout is a critical first step in identifying an overall system
restoration time. While PJM and its Members work to restore the integrity to the interconnection
as quickly and safely as possible, there are a wide variety of factors that can influence a system
restoration. Following a system assessment, estimates of restoration times of the Bulk Electric
System (BES) transmission and customer load restoration estimates can more accurately be
made.
The following assumptions are applied to planning for a System Restoration:
Black Start generation will not be specifically procured to meet these loads. Sufficient generation
should be available in the early stages of system restoration to restore these loads.
The Transmission Owner’s Restoration Plan will identify the importance of restoring these loads,
although the Transmission Owner may choose not to explicitly quantify; ensuring these loads
are restored as the restoration process progresses.
B. Selection of Critical Black Start Replacement
Minimum Critical Black Start Criterion—The minimum critical black start criterion is measured
against a transmission owner’s definition of critical load. If a transmission zone level of critical
black start falls below that transmission zones definition of critical load, additional existing black
start generation would need to be declared/compensated as critical black start or replacement
black start generation would need to be procured if there is insufficient pre-existing black start
capability (refer to the PJM Manual for Generator Operational Requirements (M-14D),
Section 10: Black Start Generation Procurement).
Variables for Critical Black Start Replacement—Determining the amount of critical black start
generation by transmission zone depends upon the physical characteristics of the units,
transmission system, and proximity of the critical black start generation to the critical load, as
well as the installed capacity and reactive capability of the critical black start generator.
The following variables should be considered when selecting the size and location of critical
black start replacement:
• Critical black start generation should be electrically dispersed within the Transmission
zone. The placement of critical black start units should:
o Provide sufficient redundancy within an electrical area to protect against equipment
failures, allowing the execution of the documented restoration plan.
o Ensure multiple transmission outlets, protecting against equipment damage.
o Ensure a minimum of 2 critical black start generators per Transmission Zone.
Note:
Replacement black start outside the boundaries of the Transmission Zone should be
considered.
• The following factors should be considered in ranking the benefits of replacement Black
Start Generation.
o Located at Plant – It is more beneficial to co-locate Black Start generation at a station
with multiple generators. Electrically close to Critical Load. Some consideration may
be given to location based on fuel diversity of critical steam.
o Start time of the Black Start unit.
o Sized appropriately (MW and MVAR lead/lag) – Black Start Generation must be
sized appropriately to provide sufficient MW to restore critical load and sufficient
MVAR capability for voltage control.
o Transmission outlet(s) / sufficient load for voltage control – Units that are not co-
located at a station should ensure multiple transmission outlets so that the Black
Start generation is not bottled in the event of equipment damage. Additionally, Black
Start generation size requirements may increase depending upon the electrical
closeness to critical steam in order to restore sufficient load to maintain voltage
control.
o Fuel Diversity – Restoration Plans should not rely too heavily on potential fuel limited
resources and should consider fuel diversity. Priority will be given to Black Start
generation that has dual fuel capability.
*May be required more often. Information to be compiled by TO operators for units within their
zone and submitted to PJM.
Web link to this form: http://www.pjm.com/~/media/documents/manuals/m36-reference-
materials/company-hourly-generation-restoration-report.ashx
Transmission Owner restoration plans are tested on at least a semi-annual basis, consistent
with the PJM Restoration Drill schedule. As part of the drill post-assessment, PJM and
Transmission Owners verify the plan resources and procedures. Additional Transmission Owner
simulations or tabletop exercises are conducted to ensure Transmission Owner personnel are
familiar with PJM and Transmission Owner restoration plans.
Transmission Owner Training Staff retain personnel training records that demonstrate PJM
Certified operating personnel have been trained annually in the implementation of restoration
concepts and the PJM and Transmission Owner restoration plans (EOP-005-3 R8). Training
records are provided to PJM on an annual basis or as requested.
PJM and Transmission Owners verify the restoration procedure during the semi-annual PJM
System Restoration Drill and internal drills. Transmission Owners review and update their
restoration plans at least annually and whenever it makes changes in the power system
network, and shall correct deficiencies found during the simulated restoration exercises.
Drill Objectives
A set of objectives for each restoration drill is set for that specific drill. These objectives are
proposed by the System Restoration Coordinator Subcommittee (SRCS), and approved by the
SOS. The following are the typical drill objectives:
• Foster a greater understanding between the company and PJM System Operators as to
the responsibilities and functions of each group during a restoration.
• Utilize both the top-down and bottom-up approach during the drill, understanding that
initial actions will have to be bottom-up for companies that are blacked-out and isolated
(all of PJM).
• PJM will take a proactive approach in identifying opportunities to assist TO in the
restoration process. PJM will coordinate restoration opportunities at the Shift Supervisor
level.
• Direct the restoration of all available 765 kV and 500 kV transmission facilities.
• Target restoration of at least one offsite source for safe shutdown to all nuclear units
within 4 hours.
• PJM to facilitate all interactions and schedules with outside pools.
• Coordinate the restoration process with fuel-limited or unavailable generation and
possibly damaged transmission equipment.
• To facilitate training and familiarization of transmission owner restoration plans for PJM
System Operators.
caused stability problems at several generating stations. Several major units were lost over the
next two minutes.
0700 hours—Due to low frequency, the PJM island collapses. The status of PJM’s neighbors is
unclear.
Generation / Transmission / Details
The drill will utilize the generation and transmission outages that exist on the day of the drill. Any
facilities unavailable on that date will also be unavailable for the drill.
Interchange Details
In the Spring scenario, initially, no outside assistance will be available. This will require all
companies to begin the drill utilizing a bottom-up approach only. Should outside assistance
become available as the drill progresses, those opportunities will be presented to the affected
companies on a case by case basis.
In a fall scenario, the drilling transmission zone would have separated from the RTO. The
disturbance will extend into neighboring zones to varying degrees, based upon specific drill
objectives.
Drill Summary / Synopsis
The PJM Drill Coordinator or designee will document drill results for the System-wide drill and
provide a debrief at the following committees:
• System Restoration Coordinators Subcommittee
• Dispatcher Training Subcommittee
• System Operations Subcommittee
• Nuclear Generation Owner/Operator Users Group
To avoid confusion associated with PJM directly contacting a neighboring entity, PJM will
predominately use the RCIS to communicate these details to its neighboring RC’s with the
expectation that unless direct coordination is required with a neighboring TOP, our neighboring
RC’s will disseminate this information.
In addition, PJM will incorporate the restoration plans of internal Transmission Operators (AEP
and ITCI) and monitor and coordinate their plans with other PJM internal and external areas.
Purpose: PJM updates and coordinates its restoration plan with the Generator Operators
(GOP) and Distribution Providers within its footprint and as well with its neighboring Reliability
Coordinators (RC), and Transmission Operators (TOP) as required by NERC EOP-006 R2.
This process ensures PJM’s effective coordination of its Restoration Plan both internally and
externally to its neighboring entities. This process has three key elements:
1. Restoration Plan Coordination Checklist (Section G-2) - This coordination checklist
will facilitate an active discussion and PJM approval on the pertinent EOP-005-3
Requirement 1 elements with the respective parties.
2. Annual Coordination Timeline (Section G-3) – this timeline will generate the required
updates and coordination at a minimum on an annual basis.
3. Dynamic Study and Emergent Restoration Plan Updates (Section G-4) – this
process describes required updates to restoration plans based on planned or unplanned
system changes
Point of Contact:
Phone Number:
e-Mail:
Effective Date of
Restoration Plan
Registered Entity
Date for the Annual
Update)
PJM approval indicates that the plan has been reviewed and
accepted and is compatible with the RC restoration plan and other TO
Restoration Plans as per EOP-006, R5.1. Any required changes are
communicated to plan owner. The PJM approval will be provided via
the eDART tool.
Comments:
3 Relationships and Responsibilities: Were there any significant changes to the plan’s
identified responsibilities and relationships, since the last update?
□ No
□ Yes
Comments:
4 Restoration Plan Components: Verify that the Restoration Plan includes the following
components (per R1 of EOP-005-3) and list the page number where it can be found or an
explanation as to why the component was not included. This item is only required for the
Annual Review.
□ Included
□ Included
□ Not Included
□ Included
□ Not Included
□ Included
□ Not Included
□ Included
□ Not Included
□ Included
□ Not Included
□ Included
□ Not Included
□ Included
□ Not Included
□ Included
□ Not Included
□ Yes
□ No
Comments:
6 R5 – Restoration Plan availability: Are copies of this plan available within your primary
and backup control rooms prior to the effective date of this plan?
□ Yes
□ No
Comments:
Annual updates of Restoration Plans will be submitted through eDART based on the schedule in
Table 1 to allow PJM adequate time to review and approve the plan.
Procedure:
1. Changes to PJM’s emergency operations plans (including but not limited to Manuals
13 and 36) shall be sent electronically to all neighboring RCs and TOPs (and BAs as
appropriate) with an electronic receipt request within 30 calendar days of revision per
EOP-006-3 R2.
2. The transmittal will include PJM contact information for any questions by our neighbors
and for any corresponding changes that may result to our neighbors’ emergency
operations or restoration plans.
3. The receipts will also be used to track acknowledgement for follow-up of contact
information for neighboring systems.
Additionally, PJM will work with the neighboring RC to resolve any conflicts within 30 calendar
days of receipt of written notification (per EOP-006-3 R4.1).
G-4 Dynamic Study and Emergent Restoration Plan Updates
In addition to the annual update process described in Attachment G-3, other system events will
require updates to System Restoration plans in accordance with EOP-005-3, R4 and dynamics
studies in accordance with EOP-005-3, R6.
Table 2 below summarizes these situations and provides guidance on which events require
update to System Restoration plans and dynamic studies as well as expected timeframes for
when these activities should take place.
PJM Black Start Study and Restoration Plan Update Guidelines
1 New Black Start Unit- Yes - develop cranking paths Yes - prior to Black Start unit
Incremental RFP- 5 and complete studies (prior to or cross zonal solution going
Year RTO wide RFP- Black Start unit or cross zonal into service
Interim Cross zonal solution going into service)
solution
3 Black Start Unit Only if there is no other studied Yes - prior to unit retirement
Retirement or path to critical load (prior to or terminated
Termination retirement or termination)
4 New Critical Load Unit Yes - include in Restoration Yes - during Annual Update
Plan Annual Update - develop (1 month prior)
cranking paths with TOs and
complete studies
5 Critical Load Unit Only if critical load unit is used Yes - prior to unit retirement
Retirement to feed other critical load a.k.a.
"daisychaining" (prior to unit
retirement)
8 Unplanned/ No No
Planned Temporary
Change(i.e.
maintenance outage)
Table 2 – PJM Black Start Study and Restoration Plan Update Guidelines
For Event 6 and 7, System Restoration Plan changes are required when there are changes to
the implementation of the restoration plan based on unplanned permanent System modifications
(within 90 calendar days) or prior to implementing a planned BES modification.
Process for Planned BES changes that impact Restoration Plan
• The “BlackStart” section of eDART is used to manage the Restoration Plan Update process.
• PJM will flag all “cut-in” eDART tickets for review by the TO to determine if the change requires
update to the TO restoration plan.
• If the cut-in impacts the implementation of the restoration plan, the TO will upload a
revised restoration plan and checklist (in G-2) through eDART for PJM approval prior to
the implementation of the BES modification. If possible, updated restoration plans should
be submitted 14 days prior to cut-in equipment energization to allow PJM sufficient time
to review and approve updated plan.
• If the cut-in does not impact the implementation of the restoration plan, the TO will select
“No Update Required” in eDART.
• eDART “Cut-In” tickets should be reviewed by the TO well prior to their expected energization
date to allow for sufficient time for the TO review of the cut-in impacts to the implementation of
the restoration plan, allow sufficient time to update the restoration plan if required, and allow
sufficient time (14 days) for PJM to review and approve the updated restoration plan.
• “Cut-In” tickets can be viewed in the queue in the “Pending Restoration Plans” screen of
eDART to allow users to review “Cut-In” tickets ahead of time.
• “Cut-In” tickets will not be energized upon completion of the outage if there has not been
action taken to review the restoration plan and update if required.
• If a “Cut-In” ticket is included in a restoration plan update more than 15 days in the
future, PJM recommends that the “Cut-In” be included in a separate update OR note
in the plan that the update is scheduled for the future and include the expected date of
energization.
Revision History
Revision 27 (12/03/2019):
• Update for FERC Order 814 Electric Storage Resource Participation Model
• Attachment A: A.1.2 Minimum Critical Black Start Requirements
o Updated exception to critical cranking power to include non-hydro energy storage
resources
Revision 26 (06/27/2019):
• Cover to cover annual review. Changed terminologies and corrected grammar
throughout.
• Throughout: Updated NERC standard references from EOP-005-2 and EOP-006-2 to
EOP-005-3 and EOP-006-3.
• References Section: Removed TO/EOP-005 mapping link and replaced with TO/TOP
Matrix site.
• 3.1.7 and 7.2: Added section description and purpose statements.
• Attachment F: Changed title from Transmission Owner and Black Start Supporting
Documentation References to Transmission Owner Special Procedures. Removed
language in reference to training record, black start database, and Transmission Owner
plan reference to EOP-005-2.
• Attachment G: Added coordination review with neighbors in case of conflicts with a
particular restoration plan. Modified distribution list for M-36. Added DOE PORTS to
Table 1.
• Attachment H: Updated attachment with new UFLS data.
• Attachment I: Deleted attachment which had specified M-36 Sections corresponding to
EOP-005 and EOP-006 Requirements.
Revision 25 (06/08/2018):
• Cover to Cover Annual Periodic Review
• Updated Manual Owner to Rich Brown
• Section 6.1.7 – Added clarifying language for “equivalent frequency control systems”
• Section 7.2.1 Synchronizing Process Phases – added clarification around use of
synchro-check relay as recommended by the PJM Relay Subcommittee
• Section 8.1 – System Restoration Plan Guidelines
o Updated Exhibit 10 Generation Information Template
Revision 24 (06/09/2017):
• Cover to Cover Period Review
• Change “Generation Owner/MOC dispatcher” to “Generator Operator” throughout
manual to match NERC terminology
• Updated “About PJM Manuals” section in the Introduction to reflect revisions on
pjm.com. Added Generator Operator to Intended Audience section of Introduction.
• Section 1.1 – Removed references to EOP-009 and EOP-007-RFC-01 as these
standards have been retired
• Section 7.1.2 – Clarifications to Minimum Source Guidelines. Removal of Exhibit 10,
Locations of Synchronization Devices due to this information being in the TO restoration
plans
• Section 8.1 – Restoration Plan Guidelines. Added template for Generation Information
(Exhibit 10) for inclusion in TO System Restoration Plans
• Attachment A: Minimum Critical Black Start Requirement – Removed references to
System Restoration Strategy Sr. Task Force
• Attachment B: Restoration Forms – Exhibit 14 and 15 – Updated email address to mail
forms. Added OVEC
Revision 23 (06/10/2016):
• Annual Review per EOP-005-2, R3 and EOP-006-2, R3
• Minor formatting changes throughout
• Consistency in title “Transmission Owner operator” and “Generation Owner/MOC
dispatcher” throughout manual
• Section 3.1.2 Clarification of responsibilities for report submittals and communications
• Section 3.1.7 Clarification on load shedding during system restoration
• Section 4.1.1 Additional detail on communication protocols during system restoration
• Section 6.2.1 Clarification on responsibility for tabulation of unit status
• Section 7.2.1 Update Exhibit 10. Added clarifying requirement on establishment of tie
schedule between interconnected areas
• Section 8 Minor clarifications and updated references
• Attachment A Noted that critical nuclear safe shutdown power is defined in NPIRs.
Updated dates for Black Start RTO wide RFP. Removed transitional process verbiage.
Added EOP-005-2, R-15 requirement on notification of change to Black Start unit ability
to meet TO restoration plan within 24 hours.
• Attachment B Added SMECO to Exhibits 11 and 13.
• Attachment D Change from System Restoration Coordinators Task Force to
Subcommittee.
• Attachment F Updated Figure 1 – TO restoration document references
• Attachment G Clarification of eDART Restoration Plan coordination process. Clarification
on completion of Attachment G-2. Added SMECO and ITCI to annual update timeline.
Changed EKPC annual update timeline.
• Added new subsection G-4 Dynamic Study and Restoration Plan Updates
• Attachment H – Updated Under Frequency Load Shed Table
Revision 22 (06/15/2015):
• Annual Review per EOP-005-2, R3 and EOP-006-2, R3
• Formatting and clarifying changes to Sections 2.3, 3.1.5, 3.1.6, 6.1.4, 7.1.2 and 7.2
• Sections 3.1.7 and 3.1.8 – Added more detail to when PJM Assumes Control and when
PJM Returns to Normal Operation in response to feedback from Spring Restoration Drill
• Section 7 – Annual Update of Exhibit 10 “PJM Table of Major Synchronization Devices”
• Section 8.1.9 – Added guidance on completion of Interconnection Checklist
• Section 8.1.11 – Deleted section on System Control Progress
• Attachment B – Minor updates to Restoration Forms
• Attachment F – Figure 1 “TO Restoration Document References” updated based on
latest TO restoration plans
• Attachment H – Under Frequency Load Shed (UFLS) Table updated based on updated
load values
Revision 21 (12/05/2014):
• Removed Section A.1.3 Reliability Backstop Options from Attachment A
Revision 20 (06/16/2014):
• Annual Review per EOP-005-2, R3 and EOP-006-2, R3
• Changed Control Area to Balancing Authority throughout document
• Section 7.1.2 – Renaming of Minimum Source Requirements to Minimum Source
Guidelines and clarification on their use
• Section 7 – Annual Update of Exhibit 10 “PJM Table of Major Synchronization Devices”
• Attachment A – Documented exceptions to the calculation of critical load as approved by
System Restoration Strategy Task Force
• Attachment D – Added expectations of Generation Owners and Transmission Owners for
participation in PJM sponsored Restoration Drills
• Attachment F – Figure 1 “TO Restoration Document References” updated based on
latest TO restoration plans
• Attachment G – Table 1 updated to reflect adjustments to First Energy Restoration Plan
annual update and addition of Rock Springs
• Attachment H – Under Frequency Load Shed (UFLS) Table updated based on updated
load values
Revision 19 (06/20/2013):
• Annual Review
• Minor grammatical adjustments throughout manual
• Rewrite of Attachment G to conform with EOP-005-2
• Update to Exhibits 16 (Interconnection Checklist) to make consistent across Eastern
Interconnection
Revision 18 (04/01/2013):
Incorporated changes related to system restoration strategy revisions developed by the System
Restoration Strategy Senior Task Force. These include:
• Minor updates to section 6.2, cranking power
• Minor updates to section 8.1.1 Ascertaining System Status
• Created new section 9 on Cross Zonal Coordination
• Major edits to Attachment A to reflect changes in critical load definition, Black Start
requirements and the reliability backstop process.
• Minor changes to Attachment D – Drill Guide
Revision 17 (12/20/2012):
• Updated to reflect EKPC integration:
• Section 7, Exhibit 10: Locations of Synchronization Devices
• Exhibits 11 and 13
• Figure 1 in Attachment F
• Table 1 in Attachment G
• Appendix 4 in Attachment G
• Attachment H: Under Frequency Load Shed Tables
• Removal of references to System Restoration target times in Section 3.1 and Attachment
A
Revision 16 (08/14/2012):
• Annual Review of Manual
• Replaced Local Control Center with Transmission Owner
• Removed references to Load Serving Entities
• Updated Figure 1 in Attachment F
• Updated Attachment H: Under Frequency Load Shed Tables
• Removed references to OVEC as PJM is no longer the Reliability Coordinator for OVEC
• Added UGI to Exhibits 11 and 13
• Expanded on definitions of Cranking Paths in Section 6.2
• Minor grammatical and formatting changes throughout
Revision 15 (08/17/2011):
• Annual Review of entire Manual
Revision 14 (04/27/2011):
• Updated Attachment B – Initial and Hourly Restoration Reports
• Updated Attachment F – Figure 1 TO Restoration Document References
• Updated Attachment G – TO Coordination Checklist (Table 1)
• Updated Attachment H – UFLS Table
• Updated Table 1 – PJM Table of Major Synchronization Devices
Revision 13 (11/01/2010):
• Add Reliability Coordinator language to section 3.1.9
• Added Attachment H – UFLS Table
• Updated Attachment F
• Updated Table 1- PJM Table of Major Synchronization Devices
Revision 12 (01/01/2010):
• Section 6.1.4 - added - Black Start unit operators should not permit their fuel inventory
for Critical Black start CTs to fall below 10 hours - if it falls below this level, unit operators
shall notify PJM and place the unit in Max Emergency.
• Clarified language in Sections 3.1.5 and 7.2.1 that PJM must both approve and
coordinate synchronization
Revision 11 (10/05/2009):
• Additional language on annual communications system testing
• Additional language on coordination with Internal TOPs
• Additional clarifying language on TO/TOP responsibilities
Revision 7 (1/11/2008):
• Updated language to align existing restoration procedures with NERC EOP language.
• Added language to reference confidential portions (non-posted) of PJM Restoration Plan
• Added EOP checklist as an attachment
Revision 6 (5/25/2007)
• Clarifying statements added with respect to PJM and Member Company Actions based
on NERC EOP-005.
Revision 5 (05/16/2007)
• PJM will provide RFC on an annual basis a copy of the Blackstart Capability Plan
and associated list of units designated as blackstart capable for Inclusion in the RFC
Blackstart Database per NERC standard EOP-009-0 and RFC standard EOP-004-0,
“System Restoration Plans.”
• Control area to control area replaced with Balancing Authority
• Spinning replaced with synchronous
• Section 2 Disturbance Conditions
• Internal with Separation
• PJM procedures require that each Generation owner may take independent actions to
protect its generating plant equipment and preserve as much load as possible during
separations with the following guidelines for the different control zones
• List of zones
Revision 4 (02/27/2007)
• Section 8: System Restoration Plan Guidelines—Revised to clarify existing PJM system
restoration procedures for better alignment with RFC standards.
• Attachment D: Restoration Drill Guide—Minor revision to clarify existing PJM restoration
drill procedures for better alignment with RFC standards.
Revision 3 (5/17/2006)
• Incorporated concept of “Minimum Critical Black Start Criteria” as Attachment A.
Removed former Attachment A and Attachment B (located in PJM Emergency
Procedures Manual (M-13) and relettered all subsequent attachments.
Revision 2 (11/01/05)
• Reorganized document by subject matter, creating new sections. Included Restoration
Drill Document as attachment. Revised Restoration Forms. Deleted forms contained in
Manual 13.
Revision 1 (5/01/05)
• Miscellaneous editorial corrections and removal of Appendix 7 and Attachment E, which
are already contained in Manual M-13.
Revision 0 (10/01/04)
• Initial version of the manual, composed of Sections 6 and 8 of Manual M-13, Rev 18.