PACKAGE 1 : 150 KV GAS INSULATED SUBSTATION (GIS) AND UNDERGROUND CABLE (UGC) FOR JAKARTA AND WEST
JAVA
SCHEDUL.E NO.4: INSTALLATION SERVICES
1.1 3 phase busbar conductor 2000 A, 40 kA, 1 sec - double busbar 2 sets 137,742,246.91 275,484,493.82
(refer to single line diagram).
1.3 3 phase busbar discomector 1600 A, 40 kA, 1 sec. With 4 sets Included
3 phase drilling mechanism.
1.10 Cable and box suitable to tenninate 3 single core 1x1ooo sqmm Cu 2 sets 18,873,036.17 37,746,072.35
150 kV XLPE cables
1.11 Local Cont/'ol Panel at GIS room, each comprising : 2 sets Included
1 - Mimic diagram
1 - Local I remote switch
7 - Discrepancy switch
1 - Gas Monitoring equipment
1 - Cable Marshalling board
1.12 f>rotection & Control Cubicle for UGC Comprising : 2 sets 19,277,188.39 38,554,376.78
- lEO Main Une Protection (Current differeroal, synchrocheck, etc.)
- lEO Backup Protection (OC, DEF, Break fall, FalAt Locator, etc)
- lEO Bay CortroI, metering, etc.
- Ethernet Switchfor Inter-bay system-l
- Ethernet Switch for Inter-bay system-2
Induding miscellaneous equipment, local mimic and material, rack
cabinet, cables, clamps, connectors, compression teonlnal, connection
to Individual items of equipment, test terminal, auxiliary relay, Interior
lamp, heater ... etc, to complete the scope of work.
1.13 LV power and control cable. power cable and necessary equipment to 2 sets 22,679,045.16 45,358,090.33
complete the specified scope of work .
rJ
\
SIGNATURE OF BIDD:R:
\}
1 0406
PACKAGE 1 : 150 KV GAS INSULATED SUBSTATION (GIS) AND UNDERGROUND CABLE (UGC) FOR JAKARTA AND WEST
JAVA
SCHEDULE NO.4: INSTALLATION SERVICES
2.1 3 phase busbar condldor 2000 A, 40 kA, 1 sec - double busbar 3 sets 93,954.567.39 281,863,702.17
(refer to single line diagram).
2.3 3 phase busbar disconnector 1250 A, 40 kA, 1 sec. With 6 sets Included
3 phase driving mechanism.
2.8 Cable and box suitable for terminating 3 single core 400 sqmm 3 sets 15,382,983.11 46.148,949.34
Cu 150 kV XLPE cable
2.9 Local Control Panel al GIS room, each comprising : 3 sets Included
1 - Mimic diagram
) 1 - Local 1remote switch
5 - Discrepancy switch
1 - Gas Monitoring equipment
1 - Cable Marshalling board
2.10 Protection & Control Cubicle for 150120kV Transformer Comprising : 3 sets 19,2n.188.39 57,831,565.17
- lED Main Transformer Protection (Differential. REF HVILV side, DFR, etc.)
- lED Backup Protection (OC, EF, SEF, OV, UV, AVR, FR, etc.)
- lED Bay Control AVR, metering, etc.
- Ethernet Switch for Inter-bay system-1
- Ethernet Switch for Inter-bay system-2
Including miscellaneous equipment. local mimic and material, rack
cabinet, cables, clamps. connectors, compression terminal, connection
to individual items of equipment. test terminal. auxiliary relay, interior
lamp, heater ...etc, to complete the scope of woct.
2.11 LV power and control cable. power cable and necessary equipment to 3 sets 22,679,045.16 68,037.135.49
complete the specified scope of work .
SIGNATURE OF BIDDER:
1 0407
PACKAGE 1 : 150 KV GAS INSULATED SUBSTATION (GIS) AND UNDERGROUND CABLE (UGC) FOR JAKARTA AND WEST
JAVA
SCHEDULE NO.4: INSTAlLATION SERVICES
3.1 3 phase busbar conductor 2000 A, 40 kA, 1 sec - double busbar 1 set 93,953,275.14 93,953,275.14
(refer to single line diagram).
3.3 3 phase busbar disconnector 2000 A, 40 kA, 1 sec. With 2 sets Included
3 phase driving mechanism.
3.8 Local Control Panel at GIS room. each comprising : 1 set Included
1 - Mimic diagram
1 - Local I remote switch
7 - Discrepancy switch
1 - Gas Monitoring equipment
1 - Cable Marshalling board
3.9 Protection & Control Cubicle for Bus Coupler Comprising : 1 set 19,277,188.39 19,277,188.39
lED Main Bus Protection
lED Backup Protection
lED Bay Control
Ethernet Switch for Inter·bay system-1
Ethernet SWitch for Inter-bay system-2
Including miscellaneous equipment, local mimic and material, rack
cabinet. cables, clamps. connectors, compression terminal, connection
to Individual items of equipment. test tennlnal, auxiliary relay, interior
lamp, heater ... etc. to complete the scope of worIL
Marshalling kiosk for 150 kV bus coupler bay.
3.10 LV power and control cable, power cable and necessary equipment to 1 set 19,277.188.39 19,277,188.39
complete the specified scope of work .
4. Energy meter panel consist of 4 set meters for 150 kV UGC feeder 2 1 set 19,277,188.39 19,277,188.39 ./
sets and for20 kV incoming 2 sets (complete with 4 set metering per-
panel as required)
Including ethemet swi1ch for comection to WAN and miscellaneous
equipment & material, rack cabinet. clamps, connectors, compression
terminal, comection to individual items of equipment. test terminal,
auxiliary relay, Interior lamp, heater ... etc.
TOTAl PRICE ITEM 4 19.2771IU9
SIGNATURE OF BIDDER:
1 0408
PACKAGE 1 : 150 KV GAS INSULATED SUBSTATION (GIS) AND UNDERGROUND CABLE (UGC) FOR JAKARTA AND WEST
JAVA
SCHEDULE NO.4: INSTALLATION SERVICES
UNIT PRICE
TOTAL PRICE
ITEM DESCRIPTION QUANTITY INSTALLATION
SERVICES
lC Rupiah _ilC Rupiah I
i1} (2) (31 (4) (5) '" 3lxl41
7. AC SUPPLY EQUIPMENT
7.1 Inverter 1 set 4,535,809.03 4,535,809.03
7.2 AC Distribution Board 1 set 4,535,809.03 4,535,809.03
/
8.1 150120kV, 60 MYA Power Transformer with necessary accessories 2 sets 294,827,587.13 589,655,174.26
and facilities for IIlOLW'iing150 kV and 20 kV NCT.
8.2 Auxilialy transformer 200 kVA complete with necessary accessories. 2 sets 11,339,522.58 22,679,045.16
8.3 20 kV single core XLPE cable 630 sqmm AI conductor for 3-ph 2 set 22,679,045.16 45,358,090.33
comection between power transformer and 20 kV incomming 6OOm)
cubicle, 4 cables perphase.
The total cable lOIte length is approximately 50 meters.
The supply shall Include cable ends, cable supports and necessary
accessories etc. to complete the soope of wof1I at both side.
8.4
- 20 kV single core XLPE cable 50 sqmm AI conductor for 3-ph 2 sets 4,535,809.03 9,071,618.07
connection between 20 kV cubicle and Auxiliary transfonner (150 m)
The cable length Is approximately 50 meters.
The supply shall Include cable ends, cable supports and necessary
accessories etc....., to complete the soope of wof1I at both side.
8.5 150 kV single phase netbal CT class X 300-150/1A for 2 sets 4,535,809.03 9,071,618.07
restricted elf proteclioo, suitable for IIlOLW'iingoutdoor on
transformer tank or on separate steel structure supporL
8.6 20 kV Stainless steel Neutral Earthing Resistor 12 ohm, 10 sec. 2 sets 11,339,522.58 22,679,045.16
SIGNATURE OF BIDDER:
1 0409
PACKAGE 1 : 150 KV GAS INSULATED SUBSTATION (GIS) AND UNDERGROUND CABLE (UGC) FOR JAKARTA AND WEST
JAVA
SCHEDULE NO.4: INSTAlLATION SERVICES
!I
8.7 20 kV single phase neutral CT Class X ratio 2000-1000 / SA 2 sets 4,535,809.03 9,071,618.07
for restricted elf protection suitable for mountJngoutdoor on
transformer tank or on separate steel structure supporL
8.8 20 kV single phase neutral CT Class 10P20 ratio 1000 /SA, 2 sets 4,535,809.03 9,071,618.07
30 VA for standby earth fault protection s\.itabte for mOll:1tingOItdoor
on transformer tank or on separate steel structure supporL
8.9 Transformer blast and fire prewntJon equipment 2 sets 4,309,018.58 8,618,037.16
9.1 Air compressor for circuit breaker, discomector and earth switch 1 set NlA
operation complete with plpe work to GIS for minimum
7 bays, if required
11. SUBSTATION EARTHING FOR EARTHING ALL EQUIPMENT TO 1 lot 15,274,433.84 15,274,433.84
EARTHING GRID INCLUDING DESIGN, SUPPLY OF ALL
MATERIALS AND INSTALLATION
12.1 110 V DC Battery minimum 240 AH, 8 hours rate 2 sets 22,679,045.16 45,358,090.33
12.2 110 V DC Battery minimum 240 AH. 8 hours rate (for cubicle 20kVJ 1 set 22,679,045.16 22,679,045.16
12.3 110 V DC Battery Charger for item 12.1 (duplicate system) 2 sets 11,339,522.58 22,679,045.16
12.4 110 V DC Battery Charger for item 12.2 (for cubicle 20 kVJ 1 set 11,339,522.58 11,339,522.58
12.5 110 V Battery Control and Distribution Board 3 sets 11,339,522.58 34,018,567.75
12.6 48 V DC Battery minimum 120 AH, 8 hours rate 1 set 11,339,522.58 11,339,522.58
12.9 48 V DC Battery minimum 120 AH, 8 hours rate for remote substation NA set
12.11 48 V Battery Control and Distribution Board for remote substation NA set
13. LVAC distribution board for minimtm 9 bays Including 20% spare 1 lot 11,339,522.58 11,339,522.58
for each type of MCB(S), fuses, 3 Ammeter, 1 Voltmeter with
selector switch, 1 single rate 3 phase kWH meter, 4 wire, 3 phase
CT sUtabIe for the load, wiring, clamp, connector and all necessary
material to complete the scope of work.
SIGNATURE OF BIDDER:
1 0410
PACKAGE 1 : 150 KV GAS INSULATED SUBSTATION (GIS) AND UNDERGROUND CABLE (UGC) FOR JAKARTA AND WEST
JAVA
SCHEDULE NO... : INSTALLATION SERVICES
UNIT PRICE
TOTAL PRICE
ITEM DESCRIPTION QUANTITY INSTALLAT10N
SERVICES
(LC Rupiah) ILCRuplah)
11) (2) 13) 4) (5) .. (3)x(4)
14.1 Preparation of diagram and core schedule for compete substation 1 lot Included
including cables in item 14.2.
14.2 Supply and Installation of LV auxiliary power and control cables for: 1 lot 219,591,308.58 219.591,308.58
14.3 Clamps, comectors and other necessary materials for item 14.2 1 lot 2,267,904.52 2.267,904.52
15.1 150 kV single core XlPE cable 400 sqmm AI conductor for 2 sets 31,758,416.75 63.516,833.50
3 phase connection between GIS cable end box and transfonner
cable end box, 1 core perphase.
The cable length Is approxJmately 150 m
15.2 Cable end box/Cable sealing end, cable support, clamps. connectors 2 sets 30,765,966.23 61,531,932.45
and accessories for item 15.1 at the GIS for proper connection
between GIS and 150 kV XlPE cables, 3 phase set
15.3 Cable tenninatlonlcable end box. cable support, clamps, connectors 2 sets 30,765,966.23 61,531.932.45
and accessories for item 15.1 at the power transformer for proper /
connection between power transfonner and 150 kV XlPE cables,
3 phase set.
SIGNATURE OF BIDDER:
1 0411
PACKAGE 1 : 150 KV GAS INSULATED SUBSTATION (GIS) AND UNDERGROUND CABLE (UGC) FOR JAKARTA AND WEST
JAVA
SCHEDULE NO.4: INSTALLATION SERVICES
19. Training program applied for 1 (one) packag. contract 1 lot NlA
19.1 Substation Automation Eogineer (2 trainee. 15 duration) 30 MD
19.2 Substation Aliomation Operation and Maintenance (2 Trainee, 15 duration) 30 MD
19.3 Optical Telecommunication I NMS Eogineer (2 trainee, 15 duration) 30 MD
19.4 Substation Telecommunication Operation and Maintenance Staff 30 MD
(2 Trainee, 15 Duration)
) 20. Spar. Parts I Suku Cadang applied for 1 (one) packag. contract
20.1 Node SOH-ADM 1 set 1,814.323.61 1.814,323.61
20.2 STM-4 line Interface 1 Port
20.3 2 MB Interface 1 Port
20.4 2 MB Digital Branchiog 1 set
20.5 DIU Data Interfaciog Unit 64 Kbps 1 Port
20.6 VF 214 Wire ElM Interface 1 Port
20.7 VF/subsc Interface 1 Port
20.8 Ethernet interface 1 Port
2O.9 Digital Teleprotection 1 sets
20.10 Miscellaneous equipment and materiallncludlog cables, path cord, pig 1 lot
tail, telephone cable, connectors, compression terminal, connectlon to
individual items of equipment ..• etc. to complete the scope of works.
21. MISCEL.LAHEOUS
21.1 CCTV System complete as specified in the technical specification. 1 lot 27,214,854.20 27,214,854.20
21.2 Miscellaneous equipment and material required for completion the 1 lot 11,339.522.58 11,339,522.58
scope of work.