Professional Documents
Culture Documents
a r t i c l e i n f o a b s t r a c t
Article history: The energization of long transmission lines can cause high overvoltage stresses not only along the trans-
Received 27 March 2008 mission line, but also in the rest of the network. The traditional method of limiting switching overvoltages
Received in revised form 1 June 2009 to acceptable levels is the use of circuit breakers equipped with pre-insertion resistors. The present
Accepted 21 August 2009
paper describes a study comparing this traditional method with two other alternatives for the limitation
Available online 1 October 2009
of switching overvoltages during line energization in an actual 500 kV transmission system: the use of
metal oxide surge arresters at both line closing of circuit breaker poles. Digital simulations were made
Keywords:
with PSCAD/EMTDC software and the degree of shunt compensation is considered as an independent
Synchronized switching
Metal oxide surge arrester
parameter.
Pre-insertion resistor © 2009 Elsevier B.V. All rights reserved.
PSCAD
0378-7796/$ – see front matter © 2009 Elsevier B.V. All rights reserved.
doi:10.1016/j.epsr.2009.08.011
116 P. Mestas, M.C. Tavares / Electric Power Systems Research 80 (2010) 115–120
Table 1 shown that the reliability of breakers with closing resistors tends to
Line parameters – 60 Hz.
be somewhat lower than that of standard breakers, because of their
Components Longitudinal (/km) Transversal (S/km) mechanical complexity. Moreover, the purchase and maintenance
Non-homopolar 0.0161 + j 0.2734 j 6.0458 of the pre-insertion resistor is expensive.
Homopolar 0.4352 + j 1.4423 j 3.5237
4. Simulation results
3. Methods analyzed • Class 5 – 420 kV rated arrester with a protection level of 830 kV
at 2 kA, normally specified for 500 kV Brazilian transmission lines
3.1. Surge arresters
[7].
• Class 5 – 396 kV rated arrester with a protection level of 783 kV
Surge arresters are used to protect the transmission line and
at 2 kA.
connected equipment against overvoltages caused by switching • Class 3 – 360 kV rated arrester with a protection level of 742 kV
and lightning. In this work, however, only switching overvoltage
at 2 kA.
protection was considered.
The switching overvoltages can be reduced by the provision of
The overvoltage profiles along the lines are given for all three
surge arresters with special characteristics at the end of the line.
kinds of arresters, for both 75% and 91% shunt compensation in the
Additional limitation of these overvoltages along the lines by surge
following situations:
arresters has been possible with the availability of surge arresters
with high discharge energy capability that permit easy installation
• Without any surge arrester;
without the need of extra substations, since they can be installed
• Surge arrester at line ends only;
directly in the towers at selected points to obtain the required
• Surge arresters at line ends and midpoint;
control of the overvoltage profile [2,4].
• Surge arresters at line ends and two intermediate points.
3.2. Controlled switching of circuit breakers
The circuit breaker poles were closed when the voltage of each
The controlled switching involves the individual closing of each phase was at its maximum, simulating the worst overvoltage con-
phase in the circuit breaker at the optimal point-of-wave to reduce dition possible. The results are presented below.
switching overvoltage. This can be achieved by using special con-
trol circuits that are based on the information of the system and 4.1.1. Class 5 – 420 kV rated arrester
the characteristics of the circuit breakers. Closing or opening com- The use of a 420 kV rated arrester on a line with 91% shunt com-
mands to the circuit breaker are delayed in such a way that making pensation during line energization did not reduce the overvoltages
or contact separation will occur at the optimum time instant related along the line, and at the remote terminal it decreased only 1.1%
to the phase angle [9,10]. (Fig. 2).
The line energization with 75% shunt compensation resulted in
3.3. Pre-insertion resistor a larger overvoltage, as expected. Using 420 kV rated arresters, the
reduction of the overvoltages along the line was more intense, and
The use of pre-insertion resistors in circuit breaker for the con- at the remote terminal, this reduction was up to 5% (Fig. 3).
trol of overvoltage has long been a common practice in extra high
voltage (EHV) systems during closing and re-closing operations. 4.1.2. Class 5 – 396 kV rated arrester
The practice is still common in Brazil, and all existing transmission The use of 396 kV rated arrester resulted in overvoltage values of
lines, even new ones specify this type of control mechanism. How- 1.68 p.u. and 1.72 p.u. which was a reduction at the remote termi-
ever, decades of operational experience around the world, have nal by 6.15% and 13.56%, for the transmission line of 91% and 75%
P. Mestas, M.C. Tavares / Electric Power Systems Research 80 (2010) 115–120 117
Fig. 2. Overvoltage profile along the line with 91% shunt compensation using a Class Fig. 5. Overvoltage profile along the line with 70% shunt compensation using a Class
5 – 420 kV arresters. 5 – 396 kV arresters.
Fig. 6. Overvoltage profile along the line with 91% shunt compensation using a Class
Fig. 3. Overvoltage profile along the line with 70% shunt compensation using a Class 3 – 360 kV arresters.
5 – 420 kV arresters.
Fig. 4. Overvoltage profile along the line with 91% shunt compensation using a Class Fig. 7. Overvoltage profile along the line with 70% shunt compensation using a Class
5 – 396 kV arresters. 3 – 360 kV arresters.
118 P. Mestas, M.C. Tavares / Electric Power Systems Research 80 (2010) 115–120
Fig. 8. Voltage waveform differences during synchronous closing of circuit breaker poles.
Table 2
Energy consumption of surge arrester.
Rated arrester (kV) Energy (MJ) 95% shunt compensation energy (MJ) 70% shunt compensation energy (MJ)
Fig. 11. Receiving end. Line energization with synchronized controlled switching.
The closing resistors are inserted in series with the load circuit,
acting as a voltage divider, normally being by-passed after 8–10 ms,
Fig. 13. Overvoltage profile along a line with 70% shunt compensation with con-
when the main contacts of the breaker are closed – thereby damp- trolled switching.
ing the switching transient overvoltages. In this study, an existing
Fig. 12. Overvoltage profile along a line with 91% shunt compensation with con- Fig. 14. Overvoltage profile along a line with 91% shunt compensation with the use
trolled switching. of a pre-insertion resistor.
120 P. Mestas, M.C. Tavares / Electric Power Systems Research 80 (2010) 115–120
Acknowledgements
References
[1] A.C. Legate, J.H. Brunke, J.J. Ray, E.J. Yasuda, Elimination of closing resistors on
EHV circuit breakers, IEEE Transactions on Power Apparatus and Systems 3
Fig. 15. Overvoltage profile along a line with 70% shunt compensation with use of
(1988) 223–231.
a pre-insertion resistor. [2] J.R. Ribeiro, M.E. McCallum, An application of metal oxide surge arresters in the
elimination of need for closing resistors in EHV breakers, IEEE Transactions on
Power Delivery 4 (1989) 282–291.
[3] J.K. Bladow, T.L. Weaver, Switching surge control for the 500 kV California –
400 resistor was simulated, with an insertion time of 8 ms. All Oregon Transmission Project, in: CIGRE, vol. 13, 1990, p. 304.
three switch breaker poles were closed at the same time, at the [4] L. Stenstrom, M. Mobedjina, Limitation of switching overvoltages by use of
transmission line surge arresters, in: CIGRE, vol. 33, 1998.
instant of maximum voltage value of the first phase, as this repre-
[5] A.C. Carvalho, M. Lacorte, O. Knudsen, Improved EHV line switching surge con-
sents the most critical situation. trol by application of MO-arrester and controlled switching, in: International
The use of a pre-insertion resistor was able to reduce overvolt- Conference on Energy Management and Power Delivery, 1995.
age at the remote terminal 25% and 15%, reaching values of 1.34 p.u. [6] K. Froehlich, A.C. Carvalho, B.L. Avent, C. Hoelzl, W. Hofbauer, D.F. Peelo, M.
Stanek, P. Hoegg, J.H. Sawada, Controlled Closing on Shunt Reactor compen-
and 1.69 p.u. for the line with shunt compensation of 91% and 75%, sated Transmission Lines. Part II, IEEE Transactions on Power Delivery 12 (1997)
respectively (Figs. 14 and 15). 741–746.
[7] P.C.V. Esmeraldo, J. Amon Filho, F.M.S. Carvalho, A.S.S. Carvalho, A.S. Morais,
Circuit-breaker requirements for alternative configurations of a 500 kV trans-
5. Conclusions mission system, IEEE Transactions on Power Delivery 14 (1999) 169–175.
[8] PSCAD® /EMTDCTM vs 4.2 User’Guide, Manitoba HVDC Research Centre, 2005.
Switching overvoltage can be limited during line energization [9] ABB, Controlled Switching Application Guide, 2004.
[10] CIGRE Working Group 13-07, Controlled switching of HVAC circuit breakers –
through the use of different methods, including the pre-insertion guide for application, Electra 183 (1999) 43–73.
resistor, line surge arresters and the controlled switching of circuit
Patricia Mestas was born in Peru; received degree in electrical engineering in 1998
breaker. Although the use of pre-insertion resistors in line circuit
from San Agustín de Arequipa University (UNSA) in Perú, and M.Sc. in 2007 from
breakers is an effective method it represents high costs for imple- the State University of Campinas (UNICAMP) in Brazil. She works in the planning,
mentation and maintenance. assembly and maintenance of transmission lines. At present she is working towards
The results obtained from the computer simulations of line ener- a Ph.D. degree from the School of Electrical and Computer Engineering of UNICAMP.
gization have shown that the use of metal oxide surge arresters Her areas of research include the study of electromagnetic transients, transmission
lines and digital simulations.
(396 kV MOSA) with low levels of protection, high reliability and
dissipation capability meets the needs of transmission lines switch- Maria C. Tavares received degree in electrical engineering in 1984 from the Fed-
ing. We also observed that the energy absorption capacity of the eral University of Rio de Janeiro (UFRJ) in Brazil, and M.Sc. (1991) from the same
university, and Ph.D. (1998) from UNICAMP. She has provided consultation for engi-
arresters was not exceeded in any simulation.
neering firms; works with power system analysis, HVDC, model development at
The use of controlled switching of circuit breakers and the use EMTP and electrical transmission planning. She is currently an Associated Profes-
of pre-insertion resistors are equally viable and effective to con- sor at UNICAMP where she works with power system analysis and long distance
trol switching transient overvoltages on long EHV lines with shunt transmission.