You are on page 1of 1

! " Textbook Solutions Expert Q&A Practice NEW!

Find solutions for your homework Search

home / study / engineering / civil engineering / building materials and theory of constructions / building materials and
theory of constructions solutions manuals / principles of geotechnical engineering / 9th edition / chapter 6 / problem 11p

Principles of Geotechnical Engineering (9th Edition)


See this solution in the app

Chapter 6, Problem 11P 8 Bookmarks Show all steps: ON


Post a question
Answers from our experts for your tough
homework questions
Problem
Enter question

A proposed embankment fill requires 7500 m3 of compacted


Next
soil. The void ratio of the compacted fill is specified as 0.7. Continue to post
Soil can be transported from one of the four borrow pits, as 20 questions remaining

described in the following table. The void ratio, specific


gravity of soil solids, and the cost per cubic meter for moving
Snap a photo from your
the soil to the proposed construction site are provided in the phone to post a question
We'll send you a one-time
table. download link

a. Determine the volume of each borrow pit soil required to 888-888-8888 Text me
meet the specification of the embankment site.
By providing your phone number, you agree to receive
a one-time automated text message with a link to get
the app. Standard messaging rates may apply.

b. Make the necessary calculations to select the borrow pit


which would be most cost-effective. My Textbook Solutions

Principles of... Mechanics of Mechanics of


Materials Materials
9th Edition 8th Edition 7th Edition

View all solutions

Step-by-step solution

Chegg tutors who can help


Step 1 of 8
right now

a) Pavel
Southern Methodis… 1248

Calculate the volume of borrow pit -I using the formula.


Maria
MSU-IIT 2414

Reza
Here, is the compacted fill, is the volume of borrow pit, University of Sherb… 3623

is the void ratio of compacted fill, is the void ratio of


Find me a tutor
borrow pit.
Substitute 7500 for , 0.7 for , 0.85 for :

Therefore, the volume of borrow pit is .


Calculate the cost for transportation.

Therefore, the cost for transportation is .

Comments (1)

Step 2 of 8

Calculate the volume of borrow pit -II using the formula.

Substitute 7500 for , 0.7 for , 0.92 for :

Therefore, the volume of borrow pit is .

Comment

Step 3 of 8

Calculate the cost for transportation.

Therefore, the cost for transportation is

Comment

Step 4 of 8

Calculate the volume of borrow pit -III using the formula.

Substitute 7500 for , 0.7 for , 1.21 for :

Therefore, the volume of borrow pit is .

Comment

Step 5 of 8

Calculate the cost for transportation.

Therefore, the cost for transportation is

Comment

Step 6 of 8

Calculate the volume of borrow pit -IV using the formula.

Substitute 7500 for , 0.7 for , 0.89 for :

Therefore, the volume of borrow pit is .

Comment

Step 7 of 8

Calculate the cost for transportation.

Therefore, the cost for transportation is

Comment

Step 8 of 8

b)
The cost of the borrow pit II is less compared to the other
borrow pits.
Therefore, Borrow pit II is considered as most cost-effective.

Comment

Was this solution helpful? 9 0

Recommended solutions for you in Chapter 6


Chapter 6, Problem 8P Chapter 6, Problem 7P

A standard Proctor test Results of a standard


was conducted on a silty Proctor compaction test
clay soil collected from a on a silty sand are shown
proposed construction in Figure 6.40.Figure
site. The results are 6.40a. Find the maximum
shown... dry unit...

See solution See solution

See more problems in subjects you study

ABOUT CHEGG LEGAL & POLICIES CHEGG PRODUCTS AND SERVICES CHEGG NETWORK CUSTOMER SERVICE
Become a Tutor Advertising Choices Cheap Textbooks Online Tutoring EasyBib Customer Service
Chegg For Good Cookie Notice Chegg Coupon Sell Textbooks Internships.com Give Us Feedback
College Marketing General Policies Chegg Play Solutions Manual Studyblue Help with Chegg Tutors
Corporate Development Intellectual Property Chegg Study Help Study 101 Thinkful Help with eTextbooks
Investor Relations Rights College Textbooks Test Prep Help to use EasyBib Plus
Jobs Terms of Use eTextbooks Textbook Rental Manage Chegg Study
Join Our Affiliate Program Chegg Tutors Terms of Chegg Math Solver Used Textbooks Subscription
Service Return Your Books
Media Center Mobile Apps Digital Access Codes
Global Privacy Policy Textbook Return Policy
Site Map
DO NOT SELL MY INFO
Honor Code

© 2003-2020 Chegg Inc. All rights reserved.

You might also like