Armtec Mini-Span structures are patented products developed in response to our NOTE
customers’ need for an economical and rapid solution for crossings of • On-site technical support
environmentally sensitive streams. The features that differentiate Mini-Span from available from Armtec
conventional culvert structures are: • Factory-installed headwalls are
available on all Mini-Spans
Versatile Durable
Ideal for use in applications such as Mini-Spans I and II are manufactured
logging roads, secondary highways, using Hot Dip Galvanized components.
municipal creek crossings, utility Additional paint finish is available on
crossings, hiking trails and access roads. Mini-Spans III.
Rugged Reusable
Originally developed for the logging The rugged design of Mini-Spans III
industry, Mini-Span structures are means that the structures may be
designed to meet the most demanding recovered and reused many times.
handling and in-use requirements.
QUiCK FACTs
Mini-spans are available in 3 models for optimum suitability
Standard
Lengths Material
68 x 13mm Corrugated
Mini-Span I Up to 20m
Galvanized Sheet
800 400 0.25 2.8 0.3 7.4 0.3 7.4 0.4 7.4 0.4 7.3
1,000 500 0.39 2.8 0.3 5.9 0.3 5.9 0.4 5.8 0.5 5.7
NAL LENGTH OF STRUCTURE (MULTIPLE OF 609.6mm)
1,200 600 0.57 3.5 0.4 4.8 0.4 4.8 0.4 4.8 0.6 4.6
1,800 900 1.27 3.5 0.5 3.0 0.5 3.0 0.6 2.9 0.9 2.6
FASTEN ARMTEC MINI-SPAN
ARCH AT CIRCUMFERENTIAL
LAPS WITH 3/8” DIA X 1” LG
BOLTS c/w NUT & WASHER
(TYP)
CROSS STRUT
CROSS STRUT
610 COVERAGE
FLANGED CSP SHELL
(TYP)
305 COVERAGE
FLANGED CSP SHELL
(TYP BOTH ENDS)
3658
(TYP) FASTEN ARMTEC MINI-SPAN
GALVANIZED FOOTING PLATE ARCH AT FOOTING PLATES
A 1219 (TYP)
GUSSET PLATE
(TYP) WITH 3/8” DIA X 1 1/2” LG
BOLTS c/w NUT & WASHER
(TYP)
CROSS STRUT
CROSS STRUT
CROSS STRUT
610 COVERAGE
FLANGED CSP SHELL
(TYP)
305 COVERAGE
FLANGED CSP SHELL
(TYP BOTH ENDS)
A
GALVANIZED ALL HOLES IN FLANGED
FOOTING PLATE GALVANIZED GUSSET PLATE CSP TO BE SLOTTED
(TYP) CROSS STRUT (TYP)
DOWNSTREAM END (TYP) UPSTREAM END
Minimum
Inside Inside End Steel CS-600 L-75 L-100 L-165
Span Rise Area Thickness Cover Cover Cover Cover
Min. Max. Min. Max. Min. Max. Min. Max.
mm mm m2 mm m m m m m m m m
2,130 1,120 1.86 3.0 0.4 4.8 0.4 5.1 0.5 4.7 0.6 4.5
2,440 1,270 2.42 3.0 0.4 4.1 0.5 4.4 0.5 4.0 0.7 3.8
2,740 1,440 3.07 3.0 0.6 3.6 0.6 3.9 0.6 3.5 0.7 3.3
3,050 1,600 3.81 2362 3.0 0.6 3.2 0.6 3.4 0.6 3.1 0.8 2.8 ¾" DIA X 2" LG
127 X 76 X 13 @ 406 LG
LIFTING LUG ANGLE
76 MULTI-PLATE BOLT c/w NUT
GUSSET GUSSET AND MULTI-PLATE WASHER
3,350 1,750 4.65 3.0 0.6 2.9 0.6 3.0 0.7 2.8 0.9 2.4
3,660 1,910 5.48 3.0 0.6 2.6 0.6 2.7 0.7 2.5 0.9 2.0
NOTE
• Minimum soil bearing capacity = 250kPa
• Footing Plate = 400mm x 12.7mm
(plate to A36 minimum)
ARIES
SECTION A-A
UPSTREAM END
2362 2362
76
FOOTING PLATE GUSSET GUSSET
O/O FOOTING PLATES, SEE CHART
DIMENSION VARIES
SPAN, SEE CHART
FOOTING PLATE
DOWNSTREAM END UPSTREAM END
Mini-Span II & III – PLAN VIEW
mini-span bridges
2,130 1120 1.86 7.0 0.4 4.8 0.4 4.8 0.4 4.7 0.5 4.5
2,740 1440 3.07 7.0 0.4 3.6 0.4 3.6 0.6 3.5 0.7 3.3
3,660 1910 5.48 7.0 0.6 2.6 0.6 2.6 0.7 2.5 0.9 2.0
_
NOTE
• Obtaining permits for diversion
work(s) and installation of the
mini-span are the responsibility
of the owner
• For design of foundation/footing call
Armtec for un-factored footing loads
• Foundation should be investigated by
qualified local geotechnical engineer
INSTALLATION
1. Foundation Preparation
A properly prepared foundation, to support the footing plates, is essential for
a successful Mini-Span installation. The elevation, grade and alignment of the
footing plates are dependant on the foundation.
2. Footing Design
Mini-Span structures are typically designed so that the footing plates bear
directly on the foundation or bedding. If required, a concrete footing should be
designed by a local qualified structural engineer, using available soils data,
un-factored footing loads provided by Armtec, and appropriate design methods.
It’s the responsibility of the owner to determine the scour line of the creek, and
position the footings and detail rock armour accordingly.
If concrete footings are required, the Mini-Span is lowered onto the cast-in-
place or precast footings after they are installed to the correct grade and
alignment. Holes shall be drilled into the top surface of the footings, matching
the holes pre-drilled in the footing plate. The footing plate is then bolted to the
footing using 12.5mmø x 100lg anchor bolts.
STIFFENING RIB
mini-span bridges
BACKFILLING PERPENDICULAR
TO LENGTH OF STRUCTURE
_
INSTALLATION (CONTINUED) NOTE
All dimensions are in millimetres
5. Backfilling & Compacting
LIVE LOAD AS PROVIDED BY ENGINEER
unless otherwise noted
Areas close to the sides of the structure shall be compacted using vibrating or
tamping equipment running parallel with the length of structure at all times.
Granular fill material shall be at optimum moisture content during compaction.
PARALLEL TO LENGTH
¾ RISE BACKFILLING
Each fill layer shall be compacted to at least 95% standard proctor density.
OF STRUCTURE
PLACE AND COMPACT GRANULAR BACKFILL
IN 200MM LIFTS TO 95% STANDARD PROCTOR
When
DENSITY (MIN) the backfill reaches 3/4 of the rise, spreading and compaction over the
top arc must
STREAM BED be made in a direction perpendicular to the length of the
300 LOOSE CUSHION ARCH Backfill and compaction parallel
structure (parallel to corrugations) until the finished height of the critical
to arch up to 3/4 rise above top
300 MIN
RIP RAP
STIFFENING RIB
backfill zone is reached.
of footing
BACKFILLING PERPENDICULAR
A minimum of 300mm of backfill must exist at all times between the spreading
TO LENGTH OF STRUCTURE
equipment and the structure. This layer of backfill must be built up evenly from
both sides. The equipment used shall not be heavier than a D-4 Caterpillar
dozer (7,250kg) for spreading material and not heavier than a Buffalo-Bomag
BW-755 for compaction.
TO SUIT COMPACTION ARMTEC 200
OOTING If the backfill is not to be placed immediately to the
EQUIPMENT BUT NOT finished elevation, a
NON-WOVEN
LESS THAN 600 (TYP) GEOTEXTILE
wearing and traveling surface is to be built over the critical backfill zone in
order to maintain a minimum allowable cover. Backfill and compaction perpendicular
INSIDE SPAN ½ SPAN MIN
to arch from 3/4 rise above top of
footing to finished grade
PARALLEL TO LENGTH
¾ RISE BACKFILLING
OF STRUCTURE
2 X INSIDE SPAN
STIFFENING RIB
TO SUIT COMPACTION
BACKFILLING PERPENDICULAR
ARMTEC 200
TO LENGTH OF STRUCTURE
OTING EQUIPMENT BUT NOT NON-WOVEN
LESS THAN 600 (TYP) GEOTEXTILE
300
2 X INSIDE SPAN
INSIDE RISE
PARALLEL TO LENGTH
¾ RISE BACKFILLING
OF STRUCTURE
STREAM BED
300 MIN
RIP RAP
ANCHOR BOLTS
(12.5mmø x 100mm LONG) TO SUIT COMPACTION ARMTEC 200
AT 1m O/C EQUIPMENT BUT NOT
CONCRETE FOOTING NON-WOVEN
LESS THAN 600 (TYP) GEOTEXTILE
(BY OTHERS)
2 X INSIDE SPAN
Drawings and product details are for information
and/or illustrative purposes only and may vary. Please con-
tact your Armtec representative for the most
current product information.
Armtec is a leading Canadian infrastructure and construction materials company combining creative
engineered solutions, relevant advice, dedicated people, proven products and a national presence with
a local focus on exceptional customer service.
1-877-5-ARMTEC | ARMTEC.COM
PROD-C01-G07-P02_TG-2013-06-E
Armtec / Bridge Materials / Structural Plate / Mini-Span Bridges / Technical Guide | 2013–06