Design of Beams:

Beams: B1-B23-B3-B4-B5-B6- 300 x 400


D= 400 d= 367 b= 300 mm

35 35 35 35 35 35
4.55 4.55 4.55 4.55 4.55 4.55
A B C D E F G

Fixed End Momemts - M FAB = M FBA = ± W * l 2 /12


= 60.38 KN m
M FBC = M FCB =M FCD = M FDC =M FDE = M FED =M FEF = M FFE =M FFG = M FGF == ±60.38 Kn m

Free B.M. = M AB = M BC = M CD = M DE = M EF = W * l 2 /8
= 90.57 Knm

Distribution Factors :

K AB = 203698.6 K BC = CD = DE = EF = 271598.1

D BA = 0.43 D BC = 0.57
D CB = D DC = D ED = D FE = 0.5
D CD = D DE = D EF = D FG = 0.5

AB BA BC CB CD DC DE ED EF FE
0.43 0.57 0.5 0.5 0.5 0.5 0.5 0.5 0.57
-60.38 60.38 -60.38 60.38 -60.38 60.38 -60.38 60.38 -60.38 60.38
60.38 30.19
0 90.57 -60.38 60.4 -60.4 60.38 -60.38 60.38 -60.38 60.38
-12.98 -17.21 0.0 0.0 0.00 0.00 0.00 0.00 17.21
77.59 -77.59 60.4 -60.4 60.38 -60.38 60.38 -60.38 77.59

90.57 90.6 90.57 90.57 90.57


77.59 77.59
60.4 60.4 60.4
`

A B C D E F
Net B.M. #NAME? M AB = 51.78 Kn m
M BC= EF = 21.59 Knm
M CD = DE 30.19

Moment of Rersistance: Mrmax. = 2.76 * b d 2 = 111.52 Kn m

at bottom
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *60 x 106 / (20*300*467
2)]*300*467
= 0.024 0.16 110100
= 425.0 mm2

Provide 3 - 16 mm ɸ + 1 -12 φ 603 mm 2

at top
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *90 x 106 / (20*300*467 2)]*300*467
= 0.024 0.25 110100
= 670.593 mm2

Provide 3 - 16 mm ɸ + 1 -12 φ 716 mm 2

Shear Force:

AB BA BC CB CD DC DE ED EF FE
79.63 79.63 79.63 79.63 79.63 79.63 0.00 79.63 79.63 79.63
-17.05 19.49 -3.78 0.00 0.00 0.00 0.00 0.00 0.00 3.78
62.57 99.12 75.84 79.63 79.63 79.63 0.00 79.63 79.63 83.41
3 -16 φ 603 0.43 % 0.452

shear resistance of concrete - Vuc = ζuc *bd


= 0.452*300*467 = 49.77 KN

shear resistance of minimum strps - Vusmin = 0.348bd 38.54


shear rsistance of section with min. strps = Vurmin = Vuc+Vurmi 88.30

provide strps 8 mm φ @ 150 mm c/c

Beams: B7-B8-B9-B10-B11-B12- 300 x 400


D= 500 d= 467 b= 300 mm

44 44 44 44 44 44
4.55 4.55 4.55 4.55 4.55 4.55
A B C D E F G

Fixed End Momemts - M FAB = M FBA = ± W * l 2 /12


= 75.91 KN m
M FBC = M FCB =M FCD = M FDC =M FDE = M FED =M FEF = M FFE =M FFG = M FGF == ± 69.01 Kn m

Free B.M. = M AB = M BC = M CD = M DE = M EF = W * l 2 /8
= 113.86 Knm

Distribution Factors :

K AB = 419701.5 K BC = CD = DE = EF = 559602

D BA = 0.43 D BC = 0.57
D CB = D DC = D ED = D FE = 0.5
D CD = D DE = D EF = D FG = 0.5

AB BA BC CB CD DC DE ED EF FE
0.43 0.57 0.5 0.5 0.5 0.5 0.5 0.5 0.57
-75.91 75.91 -75.91 75.91 -75.91 75.91 -75.91 75.91 75.91 75.91
75.91 37.96 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0 113.87 -75.91 75.9 -75.9 75.91 -75.91 75.91 75.91 75.91
-16.32 -21.63 0.0 0.0 0.00 0.00 0.00 0.00 21.63
97.54 -97.54 75.9 -75.9 75.91 -75.91 75.91 75.91 97.54

113.86 113.9 113.86 113.86 113.86


97.54 97.54
75.9 75.9 75.9
`

A B C D E F

Net B.M. + ve M AB = 65.09 Kn m


M BC = EF 27.14 Knm
M CD = DE 37.95 Knm

Moment of Rersistance: Mrmax. = 2.76 * b d 2 = 180.58 Kn m

at bottom
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *65 x 106 / (20*300*467
2)]*300*467
= 0.024 0.12 140100
= 411.3 mm2

Provide 4 - 16 mm ɸ 804 mm 2

at top
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *98 x 106 / (20*300*467 2)]*300*467
= 0.024 0.19 140100
= 639.35 mm2

Provide4 - 16 mm ɸ + 12 -12 φ 917 mm 2

Shear Force:

AB BA BC CB CD DC DE ED EF FE
100.10 100.10 100.10 100.10 100.10 100.10 0.00 100.10 100.10 100.10
-21.44 21.44 -4.75 0.00 0.00 0.00 0.00 0.00 0.00 -4.75
78.66 121.54 95.35 100.10 100.10 100.10 0.00 100.10 100.10 -95.35
4 -16 φ 804 0.57 % 0.501

shear resistance of concrete - Vuc = ζuc *bd


= 0.452*300*467 = 70.19 KN

shear resistance of minimum strps - Vusmin = 0.348bd 49.04


shear rsistance of section with min. strps = Vurmin = Vuc+Vurmi 119.23

provide strps 8 mm φ @ 150 mm c/c

Beams: B13-B14-B15-B16-B17-B18- 300 x 400


D= 500 d= 467 b= 300 mm

44 83 83 71 64 44
4.55 4.55 4.55 4.55 4.55 4.55
A B C D E F G

Fixed End Momemts -

M FAB = M FBA = M FFG = M FGF = ± W * l 2 /12


= 75.91 KN m
M FBC = M FCB =M FCD = M FDC = W * l 2 /12
143.19 KN m

M FDE = M FED = W * l 2 /12


122.49 KN m
M FEF = M FFE = W * l 2 /12
110.41 KN m

Free B.M. : M AB = M FG = W * l 2 /8
= 113.86 Knm
M BC = W * l 2 /8
214.79 Knm
M CD = W * l 2 /8
214.79 Knm
M DE = W * l 2 /8
183.73 Knm
M EF = W * l 2 /8
165.62 Knm
Distribution Factors :

K AB = 419701.5 K BC = CD = DE = EF = 559602

D BA = 0.43 D BC = 0.57
D CB = D DC = D ED = D FE = 0.5
D CD = D DE = D EF = D FG = 0.5

AB BA BC CB CD DC DE ED EF FE
0.43 0.57 0.5 0.5 0.5 0.5 0.5 0.5 0.57
-75.91 75.91 -143.19 143.19 -143.19 143.19 -122.49 122.49 -110.41 110.41
75.91 37.96 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0 113.87 -143.1923 143.2 -143.2 143.19 -122.4898 122.49 -110.4133 110.413
12.61 16.72 0.0 0.0 -10.35 -10.35 -6.04 -6.04 1.97
0.00 8.4 -5.18 0.00 -3.02 -5.18 0.98 -3.02
0.00 0.00 -1.6 -1.6 1.51 1.51 2.10 2.10 1.72
126.48 -126.48 150.0 -150.0 134.35 -134.35 113.37 -113.37 111.08

214.8 214.79
183.73
150.0 165.62
134.4
126.48 113.37 111.08
113.86 `

A B C D E F

Net B.M: B 13 = 50.63 Kn m


B 14 = 76.57 Kn m
B 15 = 72.63 Kn m
B 16 = 59.87 Kn m
B 17= 53.39 Kn m
B 18 = 58.32 Kn m

Moment of Resistance M. rmax. 2.76*b*d 2


= 180.58 Kn m

at bottom
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *76 x 106 / (20*300*467
2)]*300*467
= 0.024 0.15 140100
= 489.9 mm2

Provide 4 - 16 mm ɸ 804 mm 2

at top
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *150 x 106 / (20*300*467 2)]*300*467
= 0.024 0.31 140100
= 1054.53 mm2

Provide 5 - 16 mm ɸ 1005 mm 2

Shear Force:

AB BA BC CB CD DC DE ED EF FE
100.10 100.10 188.83 188.83 188.83 188.83 161.53 161.53 145.60 145.60
-27.80 27.80 -60.75 60.75 -60.75 60.75 -54.44 -54.44 -49.33 -49.33
72.30 127.90 128.07 249.58 128.07 249.58 107.08 107.08 96.27 96.27
4 -16 φ 804 0.57 % 0.501

shear resistance of concrete - Vuc = ζuc *bd


= 0.501*300*467 = 70.19 KN

shear resistance of minimum strps - Vusmin = 0.348bd 49.04


shear rsistance of section with min. strps = Vurmin = Vuc+Vurmi 119.23 Kn
provide strps 8 mm φ @ 150 mm c/c for BEAM B 13, 16, 17,18
Design shear at critical section = VUD = Vumax - Wu*(b/2+d) 198.37 Kn
Shear to be resisted by shear reinforcement = Vus = V UD - V UC = 198.37 -70.19
= 128.18 Kn
spacing of 8 mm strps = S = 0.87*415*100.52*467/128.18*1000
= 132.23 mm
say 125 mm c/c

Beam B19-B20-B21-B22
D= 500 d= 467 b= 300 mm

44 44 57 71
4.55 4.55 4.55 4.55
A B C D E

Fixed End Momemts -

M FAB = M FBA = M FBc = M FCB = ± W * l 2 /12


= 75.91 KN m
M FCD = M FDC = W * l 2 /12
98.34 KN m

M FDE = M FED = W * l 2 /12


122.49 KN m

Free B.M. : M AB = W * l 2 /8
= 113.86 Knm
M BC = W * l 2 /8
113.86 Knm
M CD = W * l 2 /8
147.51 Knm
M DE = W * l 2 /8
183.73 Knm

Distribution Factors :

K AB = DE = 419701.5 K BC = CD = 559602
D BA = 0.43 D BC = 0.57
D CB = D DC = D ED = 0.5
D CD = D DE = 0.5

AB BA BC CB CD DC DE ED
0.43 0.57 0.5 0.5 0.57 0.43 0.57
-75.91 75.91 -75.91 75.91 -98.34 98.34 -122.49 122.49
75.91 37.96 0.0 0.0 0.0 0.0 -61.2 -122.5
0 113.87 -75.90917 75.9 -98.3 98.34 -183.7347 0.00
-16.32 -21.63 11.2 11.2 48.68 36.72
5.61 -10.8 24.34 5.61 0.00
-2.41 -3.20 -6.8 -6.8 -3.20 -2.41
95.13 -95.13 69.5 -69.5 149.42 -149.42

113.9 147.51
183.73
69.5
149.4
113.86 95.13
`

A B C D E

Net B.M: B 19= 66.30 Kn m


B 20 = 31.52 Kn m
B 21 = 38.02 Kn m
B 22 = 109.02 Kn m

Moment of Resistance M. rmax. 2.76*b*d 2


= 180.58 Kn m

at bottom : B19,B20,B21
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *66 x 106 / (20*300*467
2)]*300*467
= 0.024 0.12 140100
= 419.5 mm2

Provide 3- 16 mm ɸ 603 mm 2
Beam B22
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *109 x 106 / (20*300*467
2)]*300*467
= 0.024 0.21 140100
= 724.7 mm2

Provide 4- 16 mm ɸ 1 -12 φ 917 mm 2

at top
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *150 x 106 / (20*300*467 2)]*300*467
= 0.024 0.31 140100
= 1049.92 mm2

Provide 5 - 16 mm ɸ 1005 mm 2

Shear Force:

AB BA BC CB CD DC DE ED
100.10 100.10 100.10 100.10 129.68 129.68 161.53 161.53
-20.91 20.91 -36.19 36.19 48.13 -48.13 -32.84 -32.84
79.19 121.01 63.91 136.29 177.80 81.55 128.68 128.68
3-16 φ 603 0.43 % 0.452

shear resistance of concrete - Vuc = ζuc *bd


= 0.501*300*467 = 63.33 KN

shear resistance of minimum strps - Vusmin = 0.348bd 49.04


shear rsistance of section with min. strps = Vurmin = Vuc+Vurmi 112.36 Kn
provide strps 8 mm φ @ 150 mm c/c

Design shear at critical section = VUD = Vumax - Wu*(b/2+d) 142.63 Kn


Shear to be resisted by shear reinforcement = Vus = V UD - V UC = 142.63 -63.33
= 79.31 Kn
spacing of 8 mm strps = S = 0.87*415*100.52*467/128.18*1000
= 213.71 mm
say 150 mm c/c

Beam B 23 - B24 : 300 x 500

D= 500 d = 467 b= 300 mm

64 50
4.55 4.55
A B C
Fixed End Momemts -

M FAB = M FBA = ± W * l 2 /12


= 110.41 KN m
M FBc = M FCB = W * l 2 /12
86.26 KN m

Free B.M. :
M AB = W * l 2 /8
= 165.62 Knm
M BC = W * l 2 /8
129.39 Knm

Distribution Factors :

K AB = 559602.0 K BC = 559602

D BA = 0.50 D BC = 0.50

AB BA BC CB
0.5 0.5
-110.41 110.41 -86.26 86.26
110.41 55.21 -43.13 -86.26
0.00 165.62 -129.39 0.00
-18.1 -18.1
147.51 -147.5

165.62

147.51
129.39

Net B.M. B 23 = 91.87 KN m


B24 = 55.64 KN m

Moment of Resistance = M rmax. = 2.76 * b * d 2


= 180.58 Kn m

at bottom :
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *92 x 106 / (20*300*467
2)]*300*467
= 0.024 0.18 140100
= 598.1 mm2

Provide 3- 16 mm ɸ 603 mm 2
at top
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *147 x 106 / (20*300*467
2)]*300*467
= 0.024 0.31 140100
= 1033.4 mm2

Provide 5- 16 mm ɸ 1005 mm 2
FG GF
0.43
-60.38 60.38
-30.19 -60.38
-90.57 0
12.98
-77.59

90.57

G
FG GF
79.63 91.00
-19.49 19.49
60.14 110.49
FG GF
0.43
-75.91 75.91
-37.96 -75.91
-113.87 0
16.32
-97.54

113.86

G
FG GF
100.10 100.10
-21.44 21.44
78.66 121.54
FG GF
0.43
-75.91 75.91
-37.96 -75.91
-113.87 0
1.48

1.30
-111.08

113.86
G

FG GF
100.10 100.10
-55.54 -55.54
44.56 44.56
Name of Work: Supplying raw water to the Proposed 25 MLD water treatment plant at Tuem
and to Irrigate 165.0 Ha of Command in Pernem, Tuem, Korgao and Palyem Villages and to
supply 1.73 MLD of water to the Leading Hotels at Tiracol by pumping water from Ch.22.00
Km of R.B.M.C. of T.I.P. at Dhargal.

R.C.C. Design of Pump house at Dhargal:


Design Data:
i) Grade of Concrete : M20, (1:1 1/2 :3 )
ii) Grade of Reinforcement: Fe 415 - for main Reinforcement( HYSD Bars),
Fe 250 -for secondry reinforcement (Mild steel bars )
LOADING:
i) Live Load on slab = 4.0*1.5 4.5 Kn
wt. of slab Wslab = 0.15*25*1.5 = 5.625 Kn
Dead load on slab= 2.5*1.5 3.75 Kn
Floor Finish 1.5*1.5 2.25 kn
16.13 Kn

ii) Staircase
Live Load on slab = 4*1.5 6 Kn
wt. of slab Wslab = 0.17*25*1.5 7.215375 Kn
Dead load on slab= 2.5*1.5 3.75 Kn
Floor Finish 1.5*1.5 2.25
19.22 Kn

iii) Bath/wc
Live Load on slab= 2*1.5 3 kn
Wt. of slab wslab= 0.15*25*1.5 5.63 kn
Dead load on slab= 2.5*1.5 3.75 kn
Floor Finish 1.5*1.5 2.25 kn
14.63 kn

iv) chajja 5.0 Kn

v) Wt.of Beam:Ws= 0.30*0.50*25*1.5 = 5.625 Kn


say 5.6 Kn

vi) Wt.of wall W w = 0.3*2.5*20*1.5 = 22.5


say 22.5 Kn

Wt.of wall W w = 0.15*2.5*20*1.5 = 11.25 Kn


(W*Lx*/2)*(1-(1/(3β 2)
24.45625
Beam Loads
B1-B6 B17 B24/B36
Ws 5.625 Ws 5.63 Ws 5.625
Ww= 28.8 Ww= 28.8 Ww= 28.8
Wsl 5 Wsl 24.5 Wsl 5
WsR 0 WsR 5 WsR 10
39.425 Kn 63.93 49.425

B7 to B12,B13,B18,B19,B20 B14 & B15 B16


Ws 5.625 Ws 5.625 Ws 5.625
Ww= 28.8 Ww= 28.8 Ww= 28.8
Wsl 5 Wsl 24 Wsl 24
WsR 0 WsR 24 WsR 12.10
39.43 Kn 82.43 kn 70.52 kn
Pt.Ld 125

B21 B22 B23/B35


Ws 5.625 Ws 5.625 Ws 5.625
Ww= 28.8 Ww= 28.8 Ww= 28.8
Wsl 18.41 Wsl 25 Wsl 5
WsR 5 WsR 5 WsR 24.5
57.84 64.43 63.925
Pt. Ld 57

B25 B26/B27/B28/B30/B32/B34 B29


Ws 5.625 Ws 5.625 Ws 5.625
Ww= 28.8 Ww= 0 Ww= 0
Wsl 5 Wsl 24.5 Wsl 24.5
WsR 24.5 WsR 24.5 WsR 15.48
63.93 54.63 45.6098

B31 B33 B37


Ws 5.625 Ws 5.625 Ws 5.625
Ww= 11.3 Ww= 28.8 Ww= 11.3
Wsl 18.41 Wsl 29.1 Wsl 12.10
WsR 29.1 WsR 5 WsR 18.41
64.44 kn 68.53 47.43
Pt.Ld B37 55 kn
Column Loads

Column
Mark Load on Column (KN)

Total Bracket
(2+3+4+5) Girder Crane load - Loadd -
1 2 3 4 KN Load - KN KN KN
1 2 3 4 5 6 7 8 9
C1 0.00 91.00 91.00 0.00 182.00 50.00 100.00 2.25
C2 0.00 91.00 0.00 91.00 182.00 50.00 100.00 2.25
C3 0.00 91.00 0.00 91.00 182.00 50.00 100.00 2.25
C4 0.00 91.00 0.00 91.00 182.00 50.00 100.00 2.25
C5 0.00 91.00 0.00 91.00 182.00 50.00 100.00 2.25
C6 0.00 91.00 0.00 91.00 182.00 50.00 100.00 2.25
C7 0.00 91.00 0.00 91.00 182.00 50.00 100.00 2.25
C8 91.00 145.00 145.00 0.00 381.00 50.00 100.00 2.25
C9 0.00 145.00 125.00 145.00 415.00 50.00 100.00 2.25
C10 0.00 145.00 125.00 145.00 415.00 50.00 100.00 2.25
C11 0.00 145.00 125.00 145.00 415.00 50.00 100.00 2.25
C12 0.00 145.00 125.00 145.00 415.00 50.00 100.00 2.25
C13 0.00 145.00 125.00 145.00 415.00 50.00 100.00 2.25
C14 91.00 0.00 145.00 145.00 381.00 50.00 100.00 2.25
C15 145.00 145.00 0.00 0.00 290.00 --- --- ---
C16 125.00 190.00 145.00 145.00 605.00 --- --- ---
C17 125.00 187.52 125.00 190.00 627.52 --- --- ---
C18 125.00 236.95 103.76 187.52 653.23 --- --- ---
C19 125.00 145.44 181.64 208.93 661.01 --- --- ---
C20 125.00 89.69 155.89 145.44 516.03 --- --- ---
C21 145.00 0.00 0.00 89.69 234.69 --- --- ---
C22 145.00 89.69 0.00 0.00 234.69 --- --- ---
C23 125.00 89.69 0.00 89.69 304.38 --- --- ---
C24 103.76 198.29 0.00 89.69 391.75 --- --- ---
C25 166.53 182.00 0.00 167.59 516.13 --- --- ---
C26 155.89 0.00 0.00 182.00 337.89 --- --- ---
Group of Columns

Column Column load -Kn

GF-Ftg. FF-GF RF-GF


1 2 4 6

C1
Type I C15,C21,C22,C26 =
- C7, 760.00 591.32 253.42

C8 - C14, C23,C24, C25


Type II = 1161.00 903.00 387.00

Type III C16 - C20 = 1490.00 1160.00 500.00

Typical Column Design:

GF-Ftg.

Type I : C1 - C7, C15,C21,C22,C26


Max. Factored Load on Gr.Gl. Column , C26 = P W = 760 Kn
Effective length of column = Leff = 2.5 m
Assumed section D= 450 mm 0.45 m
b= 300 mm 0.3 m
Slenderness ratio = Leff / B= 2.5 / 0 .30 8.3 < 12 column is short
Area of reinforcement = Asc = 0.80% = 0.8 *300*450 = 1080 mm2
Provide ,16 Ø - 6 no 1206 mm 2

Load carried by Column = Pw = ( Puc + Pus ) = Puc = 0.4fck*b*D


= 0.4*20*300*450
= 1080000 N
Pus = (0.67*fy-0.4fck)*As
= 325680.3 N
P= Puc+Pus = 1405.68 Kn > P W OK
Provide lateral Ties 8Ф @ 100 mm C/C
Type
GF - Ftg I II III

Load - Kn 760 1160 1490


B x D - mm 450 x 300 450 x 300 500 x 300
% of steel 0.8 0.8 1
Ast. Reqd 1080 1080 1500
Ast. X 1206 1206 1608

Load acrrying
capacity - Kn 1405 1405 2057
Main steel 6 -16 Ø 6 -16 Ø 8 - 16 Ø
laterral ties 8 @100 c/c 8@100 c/c8@100 c/c

FF- GF
Load - Kn 590 903 1160
B x D - mm 450 x 300 450 x 300 500 x 300
% of steel 0.8 0.8 1
Ast. Reqd 1080 1080 1500
Ast. X 1206 1206 1608
Load acrrying capacity 1405 1405 1634
Main steel 6- 16 Ø 6 -16 Ø 8 - 16 Ø
laterral ties 8 @100 c/c 8@100 c/c8@100 c/c

Rf - FF
Load - Kn 291 387 500
B x D - mm 300 x 300 300 x 300 300 x 300
% of steel 0.8 0.8 0.8
Ast. Reqd 720 720 720
Ast. X 1030 1030 1030
Load acrrying capacity 937 937 937
Main steel 4- 16 Ø 4 -16 Ø 4- 160 Ø
laterral ties 8 @100 c/c 8@100 c/c8@100 c/c
Footing Design:

i) Type I : C1 - C7, C15,C21,C22,C26


Bearing Capacity for soil Type ; Rock : Qu 300 Kn/m2
Design Load due to column C26 : Pu 760 Kn
Column section : D 450 mm , 0.45 mm
B 300 mm , 0.3 mm
concrete grade : M20
Reinforcement grade : Fe415
Moment of Resistance : Rumax 2.76 N/mm2
-0.15
Size of Footing ;
Working Load, Pw = Pu / 1.5 = 760/1.5 = 506.66667 Kn/m2
Assumed self wt. of footing = 10% x Pu = 7.6 Kn
required bearing area of footing = Af = 1.8577778 m2

Required Length of Footing = Lf = (D-B) / 2 + ( sqrt(sq(D-B))/4 +Af )


0.075 1.3650651
1.440065119 m, say 1.5 m 1500 mm

required breadth = Bf1.238518519 m say 1.3 m 1300 mm


Area of footing provided = Afp =Lf 1.5*1.3 = 1.95 m2

upward factored reaction causing bending in footing = Wu = Pu / Afp


760.0 /1.95 389.74359 Kn/m2

projection of footing for bending @ X - axis ┴ tX1 = ( Lf - D ) / 2


0.525 m 525 mm

projection of footing for bending @Y - axis ┴ tY1 = ( Bf -B ) / 2


0.5 m 500 mm

depth of Footing for Two way bending ;

B.M. @ column face ║el to X -


axis= Mux = Wu * Bf * X12 / 2 = 389.74* 1.3* 0.525 2 / 2
= 69.825 Kn.m
B.M. @ column face ║el to X -
axis = Muy = Wu * Lf *Y12 / 2 = 389.74 * 1.50* 0.50 2 / 2
= 73.07692 Kn.m

B'f = B+ 50*2 = 400 mm


L'f = D+ 50*2 = 550 mm

required effective depth of footing √ Mux / ( Rumax *


=dx= b'f ) = √ (69.83 x10 6 / 2.76 * 400 )
= 63247.2826
= 251.49 mm

required effective depth of footing √ Muy / ( Rumax *L'f )


= dy = √ (73.08 x10 6 / 2.76 *550 )
= 48140.2655
= 219.41 mm

Assumed bar dia. = Ф = X1 / 57 = 525/ 57 = 9.21 mm 12 mm


effective cover = dx = 50+12/2 = 56 mm Area of bar = ╥ / 4 *10 2

50+12+12/2
effective cover = dy = = 68 mm = 113.08

provide Total depth = Df = 400 mm


effective depth = dx = 344 mm 0.344 m
effective depth = dy = 332 mm 0.332 m
Dfmin = 150 mm
dxmin = 150-50-12/2 = 94 mm
dymin = 150-50-12-12/2 = 82 mm
d'x =50+12/2 = 56 mm
d'y =50+12+12/2 = 68 mm
Area of steel :

Required area of steel = Astx = ( 0.5 *20 / 415 ) * [1 - √ 1 - 4.6 *69.83 x 10 6 / (20*550*344 2 )]*550*344

= 0.024 0.13 189200


= 602.25 mm2
( 0.205*550*344 ) /100
required Astxmin = Pt.min * L'f * dx / 100 = = 387.86 mm2

Required area of steel = Asty = ( 0.5 * 20/ 415 ) * [1 - √ 1 - 4.6 *73.08 x 10 6/(20*400*332 2)
400*332
= 0.024 0.21 132800
= 682.79 mm2

required Astymin = Pt.min *B'f * dy / 100= ( 0.205*400*332 ) / 100= 272.24 mm2


required Ld = 57 * Ф 684 , Available = X1 or Y1 whichever is less = 525

Modifided Astx = ( reqd.Ld/Avail. Ld ) * Astx = ( 684/525) * 602.25 = 784.65 mm2

Modifided Asty = ( reqd.Ld/Avail. Ld ) * Asty =( 684/525 ) *682.79= 889.58 mm2


reqd. no of bars ║el to length of footing for bending @ X axis = reqd.Asty /ast = 784.65 /113.08
12 mm ɸ 6.94 no
say 11 no
reqd. no of bars ║el to width of footing for bending @ Y axis = reqd.Astx /ast = 889.58/ 113.08
12mm ɸ 7.87 no
say 11 nos

Check for One way shear :

width at top of footing at critical section = Ly1 =D + 2*dy


= 450+2*332
= 1114 mm
Effective depth of footing at critical section = dy1 = ( Df - (Df - Dfmin )*( dy - 50) )/(Y1-50)) -d'y
= (400 - (400 - 150 ) * ( 332 - 50 )/(525-50)) - 68
= 175.33 mm
area of footing at critical section = Ay1 = Lf * dymin + (dy1 - dymin ) (Lf + Ly1 ) /2
= 1500 * 82 + (175.33 - 82) ( 1500+1114) /2
= 244986.7 mm2
Pty = 100 Asty/Ay1= 100*11*113.08/244986.7= 0.51 %
shear strength of concrete in one way shear = Tucy1 = 0.483
shear resistance of concrete in one way shear = Vucy1 = Tucy1 * Ay1 = 0.483*244986.70
= 118.33 KN
Design shear = Vudy1 = Wu * Lf * (Y1 - dy ) = 389.74*1.50*(0.525-0.332)
= 98.22 Kn Vudy1 < Vucy1 hence safe
Design of Slabs:
S1
Two Way Slab:
End condition :Three Edges Discontinuous
spans : a) short span = Lx = 4.55 m 4550 Ly / Lx = 1
b) Long span = Ly = 4.55 m 4550
for Fe 415
Assumed Pt % = 0.3% ά1 = 1.4
basic allowable L/d ratio , rb = for continuos slab = 26
allowable L/d ratio ra = 36.4
Reqd.,d = Lx / ra = 4550/36.4 = 125 mm bar dia.= Ø =(mm) 8
effective cover = d'x =Ø / 2 + 15 = 19 mm d'y =d'x+8 = 27
area of bar = ast = ╥/4*Ø2 = 50.27 mm2
Reqd.,D = d+d' = 144 mm say , D= 150 mm
b= 1000

Design Load on Slab = Wu = 16.13 Kn/m


Design Moments : Mux = Wu * Lx 2 * ά = mu=Wu * Lx 333.93 Kn.m
span position B.M. coeff mu Mux
short support 0.057 333.93 19.03 Knm
mid span 0.043 333.93 14.36 Knm
long support 0.043 333.93 14.36 Knm
mid span 0.043 333.93 14.36 Knm
check for concrete depth : Mur.max = 2.76*b*d 2 = 47.36 Kn m
d = Mux / 2.76 * 100048.78969955 mm dx = D-d'x = 131 mm
dy = D-d'y = 123 mm
reqd.. Area of Steel = Astx =( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *6.67x 10 6 / (20*1000*131 2 )]
1000*131
at support = 0.024 0.14 131000
= 432.23 mm2 116.29
provide 8mm Ф @ 90 mm c/c
reqd.. Area of Steel = Astx =( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *5.01 x 10 6 / (20*1000*101 2 )]
*1000*101
at mid span 0.024 0.10 131000
= 319.96 mm2 157.10
provide 8mm Ф @ 100 mm c/c

Design of Beams:
typical design
Beams: B1-B23-B3-B4-B5-B6- 300 x 500
D= 500 d= 467 b= 300 mm

40 40 40 40 40 40
4.55 4.55 4.55 4.55 4.55 4.55
A B C D E F G

Fixed End Momemts - M FAB = M FBA = ± W * l 2 /12


= 69.01 KN m
M FBC = M FCB =M FCD = M FDC =M FDE = M FED =M FEF = M FFE =M FFG = M FG= ± 69.01 Kn m

Free B.M. = M AB = M BC = M CD = M DE = M EF = W * l 2 /8
= 103.51 Knm

Distribution Factors :

K AB = 419701.5 K BC = CD = DE = EF = 559602

D BA = 0.43 D BC = 0.57
D CB = D DC = D ED = D FE = 0.5
D CD = D DE = D EF = D FG = 0.5

AB BA BC CB CD DC DE ED EF
0.43 0.57 0.5 0.5 0.5 0.5 0.5 0.5
-69.01 69.01 -69.01 69.01 -69.01 69.01 -69.01 69.01 -69.01
69.01 34.51
0.00 103.52 -69.01 69.01 -69.01 69.01 -69.01 69.01 -69.01
-14.84 -19.67 0.00 0.00 0.00 0.00 0.00 0.00
88.68 -88.68 69.01 -69.01 69.01 -69.01 69.01 -69.01

103.5125 103.5125 103.5125 103.5125


88.67785
69.01 69.01 69.01
`

A B C D E

Net B.M. +ve M AB = 59.17 Kn m


M BC= EF = 24.67 Knm
M CD = DE 34.50

Moment of Rersistance: Mrmax. = 2.76 * b d 2 = 180.58 Kn m

at bottom
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *60 x 10 6 / (20*300*467 2)]*300*467
= 0.02 0.11 140100
= 371.57 mm2

Provide 3 - 16 mm ɸ 603 mm 2

at top
Required area of steel = Astx = ( 0.5 * 20 / 415 ) * [1 - √ 1 - 4.6 *90 x 10 6 / (20*300*467 2)]*300*467
= 0.02 0.17 140100
= 575.20 mm2

Provide 3 - 16 mm ɸ + 12 -12 φ 716 mm 2

Shear Force:

AB BA BC CB CD DC DE ED EF
91.00 91.00 91.00 91.00 91.00 91.00 0.00 91.00 91.00
-19.49 19.49 -4.32 0.00 0.00 0.00 0.00 0.00 0.00
71.51 110.49 86.68 91.00 91.00 91.00 0.00 91.00 91.00
3 -16 φ 603 0.430407 % 0.452

shear resistance of concrete - Vuc = ζuc *bd


= 0.452*300*467 = 63.33 KN

shear resistance of minimum strps - Vusmin = 0.348bd 49.04


shear rsistance of section with min. strps = Vurmin = Vuc+Vurmin. 112.36
provide strps 8 mm φ @ 150 mm c/c
Floor Beam details:

Max. Mmt
of
Beam Resistance Shear
mark section Max. B.M. -Mrmax Main steel force strp

mm mm Kn m Kn m mm 2 Kn mm

B1 300 500 59.97 110.49

B2 300 500 24.67 90.1

B3 300 500 34.5 90.1


180.58 3 - 16φ 8 φ @ 150
B4 300 500 34.5 90.1

B5 300 500 24.67 90.1

B6 300 500 59.97 110.49


--- --- --- ---
support B1/2 88.68
--- --- --- ---
support B2/3 69
4 -16 φ+
--- --- --- ---
support B3/4 69 1-12φ
--- --- --- ---
support B4/5 69
--- --- --- ---
support B5/6 88.68

B7 300 500 65.9 121.54

B8 300 500 27.14 100.1

B9 300 500 37.95 100.1


180.58 4 -16 φ 8 φ @ 150
B10 300 500 37.95 100.1

B11 300 500 27.14 95.35

B12 300 500 65.9 78.66


--- --- --- ---
support B7/8 97.54
--- --- --- ---
support B8/9 75.9
4 -16 φ+
--- --- --- ---
support B9/10 75.9 1-12φ
--- --- --- ---
support B10/11 75.9
--- --- --- ---
support B11/12 97.54
8 φ @ 150
B13 300 500 50.63 127.9

180.58 4 -16 φ
B14 300 500 76.57 249.58
8 φ @ 125
B15 300 500 72.63 249.58
180.58 4 -16 φ
B16 300 500 59.87 107.8
8 φ @ 150
B17 300 500 53.39 96.27

B18 300 500 58.32 44.56


--- --- --- ---
support B13/14 126.48
--- --- 5 -16 φ --- ---
support B14/15 150.00
--- --- --- ---
support B15/16 134.40
--- --- --- ---
support B16/17 113.37
3 -16 φ
--- --- --- ---
support B17/18 111.08

B19 300 500 66.297 121.01


3 -16 φ
B20 300 500 31.525 136.29
180.58 8 φ @ 150
B21 300 500 38.020 81.55
4 -16 φ+
B22 300 500 109.022 1-12φ 128.68
--- --- ---
support B19/20 95.13
4 -16 φ
--- 180.58 --- ---
support B20/21 69.5
--- 5 -16 φ --- ---
support B21/22 149.1

B23 300 500 91.87 178.3


180.58 3 -16 φ 8 φ @ 110
B24 300 500 55.64 81.33
--- 5 -16 φ --- ---
support B23/24 147.00

B25 300 500

B26 300 500

B27 300 500

B28 300 500


Floor level

Rf-FF = FF-GF GF-Ftg =


0.75*6 (6+7+8+9 (11+0.50*
KN +10) KN 6) KN
10 11 12
136.50 470.75 561.75
136.50 470.75 561.75
136.50 470.75 561.75
136.50 470.75 561.75
136.50 470.75 561.75
136.50 470.75 561.75
136.50 470.75 561.75
285.75 819.00 1009.50
311.25 878.50 1086.00
311.25 878.50 1086.00
311.25 878.50 1086.00
311.25 878.50 1086.00
311.25 878.50 1086.00
285.75 819.00 1009.50
217.50 507.50 652.50
453.75 1058.75 1361.25
470.64 1098.15 1411.91
489.92 1143.15 1469.77
495.76 1156.77 1487.28
387.02 903.05 1161.06
176.02 410.71 528.06
176.02 410.71 528.06
228.29 532.67 684.86
293.81 685.56 881.43
387.09 903.22 1161.28
253.42 591.32 760.26
FE FG GF
0.57 0.43
69.01 -69.01 69.01
-34.51 -69.01
69.01 -103.52 0.00
19.67 14.84
88.68 -88.68

103.5125 103.5125
88.67785

F G

FE FG GF
91.00 91.00 91.00
4.32 -19.49 19.49
95.32 71.51 110.49