Professional Documents
Culture Documents
(Part 1)
6. Bottlenecks govern both throughput and inventory. 5. Resources must be utilized, not simply activated.
7. The transfer batch does not have to equal the process batch. 6. The transfer batch need not, and many times should not,
equal the process batch.
8. A process batch should be variable.
9. Priorities can be set only by examining the system’s constraints.
7. A process batch may be variable both along its route and
over time.
Dependent events & variability
1.Dependent events
An event, or a series of events, must takes place
before another can begin. The subsequent event
depends on the ones prior to it.
2.Statistical fluctuations
Some information can not be determined precisely.
example.
Process Time (A) Process Time (B) Process Time (C)
Actual:
1 pm 2 pm 3 pm 4 pm 5 pm Total
X (units) 19 21 28 32 100
Y (units) 19 21 25 25 90
• Bottleneck Resource : Any resource whose capacity is equal to or less than the demand placed
upon it.
• Non-bottleneck Resource : Any resource whose capacity is greater than the demand placed
upon it.
The five basic resource interactions
1. From non-bottleneck to bottleneck : → Y → X →
• If Y produces 400 units/week →An inventory build up of 160 units/week. Blocking.
• If Y produces 240 units/week → No inventory, utilized only for 24 hrs/week. Utilization = 24/40
❖ Y must be synchronized with X to balance the flow. (Goldratt’s rule # 1 )
❖ The level of utilization of a non-bottleneck is determined by some other constraint. (Goldratt’s rule # 2)
❖ Utilization and activation of a resource are not the same. (Goldratt’s rule # 3)
• Y processes faster than X. Inventory build up in front of Bottleneck.
❖ Bottlenecks govern both throughput and inventory. (Goldratt’s rule # 6)
What happen if X down for an hour? Throughput decreases to 234 units → Bottleneck dictates throughput.
❖ An hour lost at a bottleneck is an hour lost for the entire system. (Goldratt’s rule # 4)
What happen if Y down for 1 hr? If process time in Y decreased? It will not effect the throughput.
❖ An hour saved at a nonbottleneck is a mirage. (Goldratt’s rule # 5)
The five basic resource interactions (2)
2. From bottleneck to non-bottleneck : → X → Y →
Is it possible for Y to produce 400 units/week? Y is Starving.
Manufacturing Lead Time depends on transfer batch.
❖ The transfer batch does not have to equal the process batch. (Goldratt’s rule # 7)
If Process batch 240 units : a) What happen if Transfer batch 240? b) What if 10?
0 40 hours
X
Y
64 hours
Drum-Buffer-Rope
Goldratt used the concept of a troop of boy scouts on a hike through a forest to
illustrate the idea of synchronization.
To prevent spreading, tie the weakest soldier to the front row. To protect overall pace, provide
some slack in the rope.
Drummer sets the pace of the slowest hiker.→ All hikers will be forced to march at the same pace.
drum-buffer-rope system
Bottleneck (Drum)
A B C D E F Market
Inventory buffer
Communication (time buffer)
(rope)
▪ What is the throughput rate for the process? 240 units/ week
Assume that one unit of RM1 is used to produce one unit of X and that one unit of
RM1 and one unit of RM2 are required to produce one unit of Y.
Available capacity per week for each resource = 2400 minutes.
Create a production schedule that maximizes profit.
(Narasimhan et al., 1995, p.573)
X
conventional accounting:
Net profit : X = $(100 – 40) = $60 → Set X as priority.
Y = $(110 – 20 – 40) = $50
Capacity required :
WC A for X = 90 units x (15 min + 10 min) = 2250 min
Number of Y produced in WC A = (2400 – 2250) / 15 = 10 units
An hour lost on the bottleneck is an hour lost for the entire system.
Y (Goldratt’s rule # 4)
The throughput is dependent on the bottleneck (system’s constraint)
Priorities can be set only by examining the system’s constraints
(Goldratt’s rule # 9) to improve profits.
profits/ time on bottleneck
→ Prioritize product Y!
X
STEP 4: Elevate the system’s constraint Resource A only uses 2350 min of 2400 min
available.
There are 2400 minutes of capacity available at each work center per
week, setup times are zero, and operating expense are $6000 per week.
Resource D Resource D
15 min/unit 5 min/unit
RM = $5
W is priority:
W = 100 units, X = (2400 – 1500) / 30 = 30 units.
3. What is the net profit ?
Net profit = throughput – operating expense
= 100($45) + 30($60) - $6000
= $300
4. What is the capacity utilization for each work center ? If the transfer batch equal to the
process batch, Is it possible to finish 100 W and 30 X in 2400 minutes?