Professional Documents
Culture Documents
Submitted to:
Dr. Neha Gulati
Assistant Professor
Computer Science &
Applications
University Business School
Panjab University
2
CONTENTS
Basic concept
Brief History
The process
The Goal
Goldratt’s Rules
Capacity
Example
Synchronous Manufacturing System
Drum Buffer Rope Approach
3
4
CONSTRAINTS
• Element, factor, or subsystem that works as a bottleneck.
• It restricts an entity, project, or system (such as
a manufacturing or decision making process) from
achieving its potential (or higher level of output) with
reference to its goal.
INTERNAL EXTERNAL
CONSTRAINTS CONSTRAINTS
• Badly deployed production • Demand for the product.
methods. • Shortage of power supply.
• Lack of competent • Shortage of raw materials.
employees.
• Poorly organized business
policies.
6
7
Increased profits.
Faster improvement.
Improved capacity.
Reduced inventory.
9
Identify the
system’s
constraints
Exploit the
Repeat the
system’s
process
constraints
THE
PROCESS Elevate the
Subordinate &
system’s
synchronise
constraints
12
GOLDRATT’S GOAL OF
THE FIRM
TO MAKE A
PROFIT
13
14
PERFORMANCE
MEASURES
FINANCIAL OPERATIONAL
PRODUCTIVITY
The transfer batch does not have to equal the process batch.
CAPACITY
• BOTTLENECK • NON-BOTTLENECK
RESOURCE : One whose RESOURCE : One whose
capacity is equal to or less capacity is greater than the
than the demand placed on demand placed on it.
it.
X Y
A Capacity Constraint resource (CCR) is a resource, if
not properly scheduled and managed, is likely to prevent the
product flow to deviate from the planned flow.
21
CAPACITY EXAMPLE SITUATION
1
• There is some idle production in this set up. How
much?
X MARKE
CASE A Y
T
X Y
Y MARKE
CASE B X
T
X Y
3
• Is there going to be a build up in unnecessary
production in Y?
X
ASSEMBL
MARKET
Y CASE C
Y
X Y
26
ASSUMPTIONS ….
27
OBJECTIVES OF SMS…
• To balance the flow through the system
• To determine the level of utilization of a non
bottleneck and other related constraint.
• To monitor the utilization and activation of a
resource.
• To evaluate the time lost at a bottleneck because
the time lost at it is the time lost for the entire system.
• To sum up the time saved at a non bottleneck
• To identify the bottlenecks governing both
throughput and inventory,
28
30
DBR APPROACH
• As in an example of boy scouts hiking, those who are
bottlenecks are positioned at the beginning and a rope
is used for subordinating (synchronizing) the speed of
followers with that of the bottleneck persons. This
enables preventing the march (work-in-process
inventory) from expanding. In other words, to
eliminate work-in-process inventory is to reduce costs.
Also, in preventing the front ones of the bottleneck
group who determine the marching speed of the entire
team from slowing down, a rope plays an important
role as a buffer to absorb the changes in the marching
speed of the front ones of the bottleneck group. A
31
drum plays a role of conveying the information about
the speed of the slowest bottleneck persons to
DBR APPROACH
• When the rope is stretched out to the limit, it is
necessary to impose a constraint on those who tied to
the rope so that they will not be able to raise the
speed any further. In some cases, work needs to
suspend when the buffer reaches the limit. Similarly,
the team may sometimes need to stop. If the drum is
beaten at the speed of the first person of the team, an
interval with the following persons will get wider and
wider. In that case, the inventory level will increase
and throughput will decrease. If the drum is beaten at
the speed of the last person of the team, i.e. the team
marches at the speed of the inventory, the inventory
32
level will decrease and throughput will increase as the
speed of demand increases. The pull-type system
33
DBR APPROACH….
34
35
36
37
THANK
THANK YOU
YOU
38