Professional Documents
Culture Documents
Purpose:
The purpose of this learning package is to help you understand the technical and
theoretical knowledge and associated skills of your selected trade area. This package
contains a number of learning and associated documents for this unit of competency.
Please read all parts of this package to ensure that you complete and manage the process
correctly. These assessment tools address the mandatory requirements of the unit of
competency including, evidence requirements, range statements and the required skills
and knowledge to achieve the learning outcomes indicated in the document. Performance
criteria are described below. The contents of this unit will contain some or all of the
following as required:
2. Manage remote power 2.1 Identify and avoid the risks posed by contact with remote power feeding
feed services when performing cabling activity
2.2 Make site safe by identifying remote power feeding services that operate at
above telecommunications network voltage (TNV) inside customer premises
3. Install cables and 3.1 Install cables according to manufacturer's application specifications,
protective earth wires including tension and bending stress requirements
3.2 Identify and avoid sources of possible damage to cable, including hot
pipes, sharp edges and cable burn
3.3 Allow sufficient excess at cable ends to facilitate termination
3.4 Place and secure cable to maintain safety and interference segregation
according to legislative and industry standards
3.5 Install cable ties with correct tension to prevent cable sheath damage or
transmission impairment and trimmed flush to prevent risk of personal damage
3.6 Install underground cables to minimum depth of cover and segregation
from hazardous electrical and other services according to AS/CA TS009:2013
3.7 Install underground cables excluding blown fibre tube systems to
incorporate a blocking agent within the cable to prevent the ingress of water
3.8 Install aerial cables to minimum clearance, segregation from hazardous
4. Terminate and test 4.1 Remove cable sheath to allow for correct termination length and without
cables and earth wires damage to underlying conductors and their insulation
4.2 Install NTD terminating modules according to manufacturer specifications
and with cable pairs neatly and sequentially fanned for termination
4.3 Terminate conductors according to recommended colour code sequence
using appropriate termination tools in the manufacturer's specified manner
4.4 Earth cable shield, if applicable, to manufacturer specifications, relevant
industry codes of practice and AS/CA TS009:2013
4.5 Conduct visual inspection to confirm termination colour code sequence has
been followed prior to end-to-end testing of wire and pair termination integrity
4.6 Terminate earth wires with connectors recommended by manufacturers
according to accepted industry codes of practice and AS/CA TS009:2013
4.7 Maintain earth wire continuity throughout and observe interface
requirements with electrical systems
4.8 Test earthing installation for continuity, insulation resistance and
conductive resistance according to accepted industry standards, including
AS/CA TS009:2013
4.9 Confirm compatibility of alterations with existing systems and test new work
both in isolation and when integrated with existing systems
5. Inspect cable route to 5.1 Inspect separations along the entirety of the cable route and rectify
ensure correct separations separations that do not comply with regulations
5.2 Install barriers to achieve separations where sufficient spatial separation
cannot be met
6. Create records 6.1 Provide the client with a job sign-off and telecommunications cabling
advice form, at the completion of each cabling task
6.2 Complete NTD record cards for the work undertaken
7. Monitor work activity 7.1 Supervise cablers not holding appropriate registration for the task to ensure
cabling activity is according to legislative requirements for safety and network
integrity, including AS/ACIF S008:2006 and AS/CA TS009:2013
ASSESSMENT
Theory Examination
During the period of this learning you will be required to complete a written theory
examination to establish the level of understanding of technical content.
Self Checks
Self-checks are to be completed on pages provided when requested by your trainer.
These exercises are used mainly as a learning tool; they may form part of your overall
assessment if deemed necessary by your Trainer.
Verbal Questions
Verbal questions may be used and recorded to establish your level of knowledge of the
competencies of this learning package.
Methodology
This unit may be provided as a separate learning instruction or provided with other units of
competency in a practical or theoretical learning experience.
Due care
Every care has been taken to ensure that the information in this learning guide is correct,
but trainers are advised to check the currency and the relevance of the content to their
own training package.
Copyright protects this publication. Except for purpose permitted by the Copyright Act
1968, reproduction, adaptation, electronic storage and communication to the public is
prohibited without prior written permission.
Pre-requisites
There are no Pre-requisites for this unit
Australian Standards
Standards are published documents setting out specifications and procedures designed to
ensure products, services and systems are safe, reliable and consistently perform the way
they were intended to. They establish a common language, which defines quality and
safety criteria.
Standards can be guidance documents including:
Australian Standards®;
AS/CA S009:2013
AS/CA S008:2010
AS/NZS 3000:2007
International Standards and Joint Standards;
Codes;
Specifications;
Handbooks; and
Guidelines
ACMA Competency Requirements
Telecommunications Cabling Provider Rules 2000
These documents are practical and don’t set impossible goals. They are based on sound
industrial, scientific and consumer experience and are constantly reviewed to ensure they
keep pace with new technologies.
Work Instructions
Before commencing any job, you will need to receive specific work instructions. These are
often presented to employees in the form of a Works Order. The instructions may vary
according to the size of the task or project and there may even be some circumstances
where no work instructions are given e.g. emergencies.
Obtain, confirm and apply work instructions for the allotted task. Work instructions may
include:
• Verbal or written and graphical instructions, signage, work, schedules/plans/specifications,
work bulletins, charts and hand drawings, memos, safety data sheets (SDS) and diagrams
or sketches
• Plans and specifications
• Quality requirements, including dimensions, tolerances, standards of work and material
standards
• Safe work procedures related to the operation of small plant and equipment on construction
sites
All safety requirements for the tasks you have been asked to do should be written down in
the Job Safety Analysis (JSA) or Safe Work Method Statement (SWMS) for the job. Read
this carefully and ask questions of your supervisor if these requirements are not clear to
you, so that you will correctly follow all safety requirements for the task. Furthermore
detail regarding any site safety requirements should be detailed in your organisation’s Site
Safety Management Plans.
Environment
The environmental impact from Installing telecommunications
equipment can be easily controlled.
Safe work practices that consider working in the vicinity of
chemicals or harmful substances can identify the correct use,
storage and disposal.
The most common risk is the chemicals used in the wet and dry
wipes for the cleaning of fibre optic connections and general
waste. Proper waste management controls this issue.
Site specific
Sites may have their own processes and procedures for working managing associated
hazards. Include in your development of SWMS (Safe work method statement) or JSA
(Job Safety Analysis) an authorised person who can inform you of any site-specific
considerations and ensure they comply with your company requirements
Convey any safety related information to the relevant people. This may include a site
supervisor, other work parties or the public as necessary. Communication can be through
relevant mediums e.g
• Email
• Direct conversation/phone call
• Toolbox talks
• Signage
• Barriers
Identified hazards
Inform appropriate personnel of identified hazards on worksite.
Identified hazards may include but limited to:
Access points that may contain:
• Remote power feeding services which operate at above telecommunications network
voltage (TNV).
• Earth potential rise.
• Hazardous light or non visible light laser.
• Hazardous conduit as according to AS 1345:1995 conduit colours associated with
hazardous service.
• Event at a site, such as an electrical distribution substation, may expose
telecommunications personnel, users or plant to hazardous voltages.
• Radio frequency equipment emitting radiation.
• Live power lines.
• Building debris.
• Manual handling.
• Mud and water.
• Natural gas and other gas build up.
• Slippery surfaces.
• Vermin.
Don’t just assume that a barrier will stop someone from entering the area. The public
especially are likely to walk straight through simple barriers such as witches hats, go under
tape and climb over bollards if you it prevents them from impeding their journey by even
seconds.
If the work area is accessible to the public or the associated risks pose a greater
consequence then more permanent barriers may be required.
These could include:
• Warning tape
• Temporary bollards
Crimpers
Keep hands and foreign objects clear of crimper jaws while crimping as large amounts of
pressure are applied at the jaws due to the mechanical advantage. Injuries may occur or
jaws may be damaged by applying excessive force.
NOTE: All tools and equipment should be cleaned and stored in the appropriate place after
use each day.
Cable Strippers
Cable strippers themselves are inherently relatively safe due to their design. Only use
them on the materials they are intended to strip and they will last a long time.
Cable strippers designed for use on coax can be used on structured cables with care.
Test equipment
Test equipment must be in correct operating order. To maintain insulation resistance
insulation must be clean and in very good condition. Ensure that any calibrated equipment
is in current test date.
Test equipment is generally more fragile than ordinary hand tools and more care must be
taken. Always return it to its protective case, keep clean and dry and do not use cleaning
chemicals as this may damage the plastic and seals, use a clean dry cloth.
Sound
All sound is created by mechanical vibrations that in turn disturbs the molecules of air
adjacent to the vibration source. The air becomes the medium for the transmission of
sound waves to the ear, which detects the sound. Hence, there are three requirements:
• A source of sound
• A medium for sound transmission
• An ear to receive and detect the sound
Loudness of sound
The intensity or loudness of a sound depends on the amount of energy that goes into
making that sound. The more energy used, the higher the level of the sound. It can be
measured, as pressure, in Pascal’s (term most commonly used in physics), which is
equivalent to 1 Newton per square metre. Loudness of sound is normally expressed as a
ratio compared to the lowest intensity level that a healthy human ear can perceive.
Type Title Standard Issue Version Ref Release date Page
LR ICTCBL2136B NVR Standard 15.5 2 1 ACMA Restricted Rule 06/08/2014 Page 16 of 225
Pitch of sound and frequency
The pitch of a sound wave depends on the number of vibrations per second made by a
sound-producing object. The number of vibrations per second is called the frequency of
the sound. The higher the frequency, the higher the pitch. The unit of frequency is the
Hertz (Hz).
X1 0
X2 3
X 10 10
X 50 17
X 100 20
X 1000 30
X 10000 40
X 100000 50
X 1000000 60
The zero reference level is chosen to be an intensity that corresponds to the threshold of
human hearing and is about the lowest sound pressure level (SPL) that the average ear
can perceive. This is equal to 0dB SPL.
NOTE: The decibel is only a ratio, however, dB SPL is an absolute level.
The image below shows the relationship between dB SPL for various sounds up to and
beyond the threshold of pain.
TRANSMISSION OF SOUND
Speed of sound
Sound travels fast, but is much slower than the speed of light. An example is the few
seconds’ delay of the clap of thunder from distant lightning. Also, echoes represent a delay
due to sound being reflected from distant walls.
The speed of sound varies with both the temperature of the transmitting medium and the
density of the medium. The velocity of sound through air is generally considered to be 332
metres per second at zero degrees Celsius. This is approximately 1200 kilometres per
hour.
It increases by about 0.6 metres per second for each degree increase in temperature.
Sound travels about four times faster through water and about 15 times faster through a
steel rod compared to air. In a vacuum, there is no sound transmitted.
Telephone Transmitter
The telephone transmitter or microphone is actually a transducer that converts acoustic
energy to electrical energy. A transmitter can be described as an input transducer. Not all
of the sound energy entering a transmitter is converted to electrical current, as no
transducer is 100 percent efficient.
Capacitor Transmitter
The capacitor or electric transmitter (also often called an electronic transmitter when used
in a telephone) is now the most popular transmitter used in telephones. It uses the sound
to vary the capacitance of an electronic circuit.
The diaphragm is mounted close to a second plate thus forming a capacitor whose value
depends on the area of the plate and their separation. The back plate is fixed and the front
plate serves as the diaphragm. When the diaphragm is moved by sound waves, the
distance between the plates varies and so does the capacitance. This causes a fixed
voltage across the plates to vary. The output voltage will be a representation of the sound
Waves. The DC voltage required for the capacitor is also used to power an amplifier within
the case.
Capacitor transmitters have an excellent frequency response, give a fairly high output at a
reasonable impedance level and have low distortion characteristics.
The principle of operation relies on the movement of a coil suspended between the poles
of a permanent magnet. The coil is connected to a movable diaphragm. When sound
waves cause the diaphragm to move. The coil that is located in the magnetic field also
moves. A current is induced into the coil that is proportional to the sound wave.
Telephone Receiver
The telephone receiver or earpiece is a transducer that converts electrical energy to
acoustic energy or sound waves. The action of the receiver is the exact opposite of the
transmitter or microphone.
The performance of the receiver has to be similar to the transmitter. That is:
• Have good sensitivity to reproduce adequate sound levels for a given electrical input
• Adequate frequency response for the telephony networks
• Be physically robust and
• Have minimal distortion
All telephone receivers in common usage nowadays use electromagnetic principles similar
to Bell's original telephone of over 100 years ago.
The Telegraph
The combination of the then new technologies resulted in the development of the
Telegraph system. It was first demonstrated in May 1844: when a signal was sent over
64km of wire from Washington to Baltimore in the US.
The telegraph system expanded rapidly. It used a series of repeater stations located about
200 km apart, connected together by a single conductor strung from a series of poles,
trees, buildings, or just about anything else that was convenient at that time.
The repeater stations were manned by operators (telegraphists) who would receive the
message and then relay it on to the next station down the line.
The message was transmitted by simply closing and opening an electrical circuit causing
current to flow in bursts. The period of time the circuit was closed and the number of tunes
it was opened and closed corresponded to a code of signals that were developed by
Samuel Morse.
The Telephone
The telegraph expanded and extended worldwide communications until some 32 years
later when, in March 1876 Alexander Graham Bell, demonstrated the first telephone.
The advantages of the telephone over the telegraph was quickly realised and people all
over the World began to install these instruments as their communication devices. In many
cases, the existing telegraph lines were used.
Australia’s first telephone link, was again in Melbourne, and was installed by Robeson
Bros. a firm of brass founders. The installation was made just 3 years after Bell's
successful demonstration.
Early services consisted of two telephone instruments permanently connected via
dedicated aerial lines. These lines remained connected between the instruments whether
the telephone instruments were actually being used or not.
This system was somewhat limited in that it only allowed communication with one fixed
location, so it was an obvious advance to have lines gong to other locations.
Initially, this is what happened - each telephone had lines going to many other telephones,
which meant many wires and there were practical limitations as to the number of phones
one could connect to.
Telephone Switch
The system or device that connects one telephone line to another telephone line is the
switch. It allows two or more people to carry on a conversation over their respective
telephones. It allows your computer modem to be connected to a remote modern which
turn allows connection to the Internet.
Nevertheless, it is more than that. Unlike a switch that allows a person to turn on and off a
bedroom light, a telephone switch or switching system is rather complex in that it has to do
more than just connect two wires together. It has to know when you pick up your
telephone's handset to make a call. It has to provide "supervision" of the call while the call
is in progress. It has to disconnect the connect path on completion of the call.
Manual switches
The first centralised switching location commenced operation in 1878, in the United
States. Initially, it was a simple arrangement where individual telephones were connected
on a grid of horizontal and vertical wired bars allowing the interconnection of any two of
the 21 telephones within the manual exchange grid. Australia’s first telephone exchange
opened in August 1880.
As the number of subscribers increased, exchanges became bigger and connected any
two telephones by a set of flexible cords. Thus switchboards were developed where upon
lifting your receiver, an operator was alerted and you would tell her (it was always a
female) whom you wished to speak to.
The operator would use a set of connecting (patch) cords to connect your socket with the
other person’s socket. When you completed the call, you would hang up your handset, the
operator would be alerted, and remove the plug from both sockets. A note of your call was
made which served as a billing docket.
As the popularity of the telephone grew, the number of operators grew. Large exchanges
had many tens of operators. Operators also offered value-added services such as social
information, call diversion and call waiting. Australia’s first manual telephone exchange
was installed in 1880. The last manual exchange in Australia was taken out of service in
1992. The same principal of operation applied to switchboards installed on private
premises.
Each item of equipment used to set up the call was also used for the duration of the call.
Step by Step exchanges ceased operating in the Australian Public Switched Telephone
Network (PSTN) in the 1980's
The remainder of the switching was still electro-mechanical, relay switching. This
equipment was retried in the early 1990's. Switches using all digital technology and no
moving parts then replaced it. This is the current method of operation in Australia, a fully
digital exchange system.
Manual Systems
Before the automaton of the private exchanges in customer premises, there were two
general types of manual switchboards, (a) cord type and (b) the cordless type.
A manual cord type Private Manual Branch exchange (PMBX) consisted of a frame
containing a jack field where all of the extension telephones and incoming exchange lines
terminated. A quantity of cords was then used to connect these jacks together by an
operator. The units were similar to the one shown below.
The cordless manual PMBX consisted of a cabinet with rows of keys. The operation of
corresponding keys connected extensions to exchange lines. The attendant, to answer
each and every call through the switchboard, used a standard telephone or an operator’s
headset.
Automatic Systems
Step-by-step automatic PABX's consisted of an assembly of by-motional, step-by-step
switches. All extensions were able to dial then own internal or external numbers. Incoming
calls were answered by the operator and then transferred to the required extension.
A crossbar PABX consisted of one or more crossbar switches and associated
electromechanical controlling circuits. All were mounted in cabinets and often contained
their own built in power supply.
NOTE: The development of the above types of systems has been the same as the
larger systems used by the public carriers. This development lead the way to the
current technology of equipment that has been reduced in size and enhanced with
an overwhelming amount of features.
ISDN PABX
Integrated Services Digital Network is a digital service that has a greater capacity and
speed for transmitting data, voice, video and images.
The services available are Basic Rate Access being a 2-channel service and the Primary
Rate Access offering 30 channels. These services are also known as Microlink and
Macrolink respectively. Most modem systems are able to connect to ISDN services with a
built in facility.
Physical make-up
Today's PABX's are modular in construction. Traditionally they have been constructed in a
cabinet, often based on a standard 19 inch rack mounted design.
With the constant miniaturisation of components, a PABX can now be the size of a
shoebox. Functional components of the system are usually provided on Printed Board
Assemblies that make up the whole system. A system may consist of just one cabinet or a
series of cabinets, the cabinet may be wall mounted or floor mounted, depending on the
size. This design philosophy often allows for simple expansion or upgrade if or when
required by the needs of the customer or owner.
Typical Constructions
Quite often, manufacturers will label a unit with the capacity of the unit. When a model
number 416 is seen, it can indicate that the unit can have a maximum access represents
of 4 external services and 16 internal services. The number 824 or 1236 has the same
format for external and internal connections. The current practice is to label a model with
the total number of ports (connections) of its designed capacity.
Port Microprocessor
The port microprocessor provides the necessary supervision and monitoring of the port
line card and its interfaces. It negotiates for CPU time when any activity occurs that
requires the use of the line card. The port microprocessor will also initiate alarms
associated with the ports under its control.
Memory
PABX memory is usually divided into two types, Read Only Memory (ROM), and Random
Access Memory (RAM).
The ROM is generally used to provide the basic operating system for both the CPU and for
the distributed processors.
The RAM is used to store the temporary information relating to the particular calls in
progress and to provide storage for the facilities and "Class Of Service" relating to a
particular extension. In the event of a power failure, a small back-up battery maintains this
memory; otherwise it would be lost, requiring re-programming.
Power Supply
The power supply for the system consists of circuitry that provides step-down of the 240V
AC that is rectified and filtered. The resultant regulated DC voltage is distributed to the
entire system. Typical voltages used are: +5v, -5v, +l2v, +24v, and +50v. These voltages
are constantly monitored at carious test points. Alarms are actuated if excessive changes
to these values are detected. Re-chargeable battened are used to provide DC power to
the entire system in the event of a power failure. The minimum supply's requirement and
duration is specified in the manufacturer manual. Back up batteries are an optional extra
and often neglected during installation.
Safety components are often included to protect PABX equipment from current or voltage
surges that are produced either from man-made equipment or from lightning strikes. These
surges could find their way into the system via the AC maims and/or the exchange lines
causing system failure.
Uninterruptible Power supplies (UPS) are currently being used in an increasing number of
installations. This ensures full service for a short period of time that is determined by the
size of the UPS as Well as the usage of the CAE.
Operators' console
An operator console/station/telephone can handle incoming calls from the public network,
transfer calls between stations of the PABX, provide access to the public network via the
available exchange lines and offer other services to the PABX users.
The operators console can also be described as the window to the PABX that allows the
operator to monitor the current state of the equipment as well as providing the status of the
exchange lines and extensions. Most PABX vendors will also equip the console with
indicators of any alarm and fault condition.
Standard handsets
This is a simple general purpose telephone that allows calls to be made and received with
other extensions within the customers premises, with external extensions, another PABX
or through the PSTN to other telephones. Depending on the PABX, the handsets may be
either analogue or digital.
Advanced handsets
These telephones come with additional features such as hands-free option, a Liquid
Crystal Display (LCD) screen to provide additional information such as clock, date, time
and many additional features needed by the user of the telephone.
Paging equipment
Provides for the announcement of an incoming call for someone either at one or all
stations, with or without the operators assistant.
Facsimile machine
Provides for the transmission of digital or analogue data corresponding to scanned
documents from the customer's premises to a similar machine across the PSTN and on to
other premises.
Answer Machines
Voice messages recorded by outside or internal callers are placed on this equipment for
persons at unattended stations. Current PABX's have this facility as an optional
feature in the form of voice mail.
Music-on-hold equipment
This provides for incoming callers, when placed on hold, to have the accompaniment of
music, either electronically generated by the system, or from an external source such as a
Compact Disc. The use of promotional recorded messages is also extensively used.
Station amplifier
With this device, incoming ring tones at a station are further amplified to allow them to be
heard within a defined area.
PABX FACILITIES
The fundamental role of the PABX is to
• Provide extensions with shared access to the Public Switched Telephone Network
• Provide interconnection of extensions without call charges.
Modem PABX's provide over 200 facilities. Unfortunately, as there are no standards
governing the way these facilities operate or the way each of them is described, each
manufacturer's facility can be the same but described differently.
Not all facilities are used or important to the operation or productivity of an organisation,
but are available as the standard facilities offered in the many systems available.
Some of these facilities are listed below and are briefly described.
Alternate routing
Allows the PABX to route a call via an alternative path if the "first choice" path is busy. This
facility performs a similar function to least cost routing but the routing decision is based on
call traffic costs.
Barring
This facility allows the PABX manager to control extension access to the public network
depending on the business needs of the extension user. The access level offered is often
referred to as the 'class of service '. Examples of classes of service are:
• No outside access (Internal calls only)
• Local area calls only
• STD access barred
• IDD access barred
• STD and IDD access barred
To make a call using a class of service not provided on a particular extension a caller
needs to contact the operator who would manually connect the call and record the details.
Call back
Allows a caller encountering an engaged extension, (busy on a call) to have the call
automatically connected when the busy extension becomes free.
Group Hunt
A call directed to a particular extension number will hunt through all extensions nominated
as part of that hunt group to fad the first "free" extension. Extensions within the group can
share a common extension number.
Group Pickup
An extension user can answer a call directed to another extension, within a predetermined
group of extensions, by dialing an access code.
Metering
The PABX can be equipped with facilities to monitor automatically any extension usage. A
typical example is a hotel where guests' telephone usage is monitored and they are
charged for any outside call made. This facility is also referred as 'call accounting’
Overflow
Similar to alternate routing, but allows a PABX to route a call via the PSTN If the "first
choice" tie lines are unavailable. The lines are direct and dedicated connections between
remote PABXS.
PABX Networking
PABX equipment can be interconnected via tie lines with a full signaling capability or via a
data link. This networking between the PABXS is transparent to users and provides a
simple numbering access. A common form of PABX interconnection today is a single high
speed (2Mbps) data link that provides for 30 simultaneous conversations.
Tennant service
Multiple tenants can share a telephone system. Each tenant can program to its own
operator, extensions and trunks for incoming and outgoing calls.
Speed dialing
Regularly called numbers, particularly long STD or International numbers can be stored in
a memory of the PABX. The required number is dialed by using a two or three digit code.
The stored list of numbers can be used by everyone.
System Programming
Modern CAE’s are programmed using web based programs. This intuitive software guides
the installer through the required programming steps. The system programming port
connects directly to the technician’s PC using USB or is directly connected to the network.
Remote off-site programming via a modem is inbuilt into larger systems and is optional on
the smaller systems.
(User Features)
Abbreviated Dialing Callback Busy Extension Intrusion
Agent Help Callback Busy Route Lock/Unlock Extension
Agent Log on/off Callback Busy Line Lookup Directory
Agent Wrap up time Camp On Numbers
Alert Conference Message Waiting
Answering Machine Conference Messaging
Emulation Unsupervised Mute
Authority Code Data Call No-Ring Transfer
(Travelling COS) Data Rate Selection Off Hook Voice
Auto Answer On/Off Default Settings Restore Announce
Automatic Conversation Directory Dialling Page Answer (Meet Me
Record Page)
Direct Station Select
Automatic Hold (DSS) Page Receive
Automatic Line Selection Distinctive Ringing Paging
Auto Message Do Not Disturb (DND) Pulse to DTMF
Notification DND Override Conversation
Automatic Transfer Extension Feature Check Automatic Busy Redial
Background Music (ABR)
Extinguish Lit Voice Mail
Call Forward Direct LED Last Number Redial
Call Forward Busy (LNR)
Feature Key
Call Forward Follow Me Programming Saved Number Redial
Key Systems are used to address the small end of the business market. While they
provided less facilities than a PABX, many are providing additional facilities that may be
required by a unique customer.
Often key systems are installed as extensions of large PABX’s. This provides the user all
the benefits of a PABX and Key System. Traditionally a Key System handset has been
referred as a station. This was to distinguish this handset from a handset connected to a
PABX.
Key System phone with DSS (Direct Station Select) and a DSS add on module
Some Key System phones have an additional module that allows the operator to have a
visual indication of the status of each station.
VoIP TELEPHONY
VoIP telephony (Voice over Internet Protocol telephony) is a general term for the
technologies that use the Internet Protocol’s packet-switched connections to exchange
voice, fax and other forms of information that have traditionally been carried over the
telephone networks of the PSTN or (Public Switched Telephone Network).
Typically VoIP is deployed in a converged network as a replacement for tie lines or inter
office trunks to “bypass” the PSTN and therefore reduce the cost or “toll” associated with
the PSTN use.
Type Title Standard Issue Version Ref Release date Page
LR ICTCBL2136B NVR Standard 15.5 2 1 ACMA Restricted Rule 06/08/2014 Page 45 of 225
Quick Overview
IP Telephony with it’s high scalabilities and low cost is finding its way into the enterprise at
a surprising rate. IP Telephony has already been integrated into many diverse businesses
as an alternative to the legacy PBX system. The latest in IP Solutions provides reliability,
improved application-integrations and business quality voice calls. As companies look to
reduce operating costs, IP Telephony becomes a solution.
In Today’s PBX environment vendors technicians support PBX systems, but while Network
Convergence takes place in the enterprise, IT professionals are becoming responsible for
“Dial Tone”. For most IT professionals “Dial Tone” is a new arena for them and as a
business critical application should not be taken lightly.
IP Telephony PRO’s
Price – Less expensive than the traditional PBX. There is no yearly maintenance or
service contracts required and can be simpler in administration
Easy Application integration – You can add many new applications to enhance your
product such as Unified Messaging and Call Accounting software or some open systems
allow you to develop your own.
IP Based – Can be easier and less expensive to manage and monitor
IP Telephony CON’s
Reliability – IP Telephony is NOT built to the Telecommunications standard that requires
99.999% up time or less than 30 minutes down time a year.
Implementation can be difficult to integrate or incorporate into an existing enterprise.
Not as robust as a PBX. PBX’s have hove 30 years of tested and developed features.
Most IP systems have the basics but some systems are still very limited. Some traditional
PBX’s can have over 300 specialised features.
With the constant development in technology, these shortfalls are being overcome.
Each manufacturer has its own method and style of programming their systems and
terminal. Modern practices are that on completing the installation of the hardware, the
installer uses a PC to program the configuration of the system so as to comply with the
customers’ requirements. With experience and practice, the programming can be
performed very quickly. It is also important that copies of the system’s settings and
customer data be kept on and off site.
Important Information
Installation of and service to CAE equipment should only be carried out by suitably trained
and qualified personnel. The cabling within a CAE environment and distribution frame may
be performed by non-registered personnel provided they are supervised by an open CPR
registered cabler. In this context ‘supervision’ is taken as meaning that the registered
supervisor is on site when the work is being done. The unregistered installer must be able
to locate the registered supervisor (cabler) when asked to do so by an ACMA inspector.
If the registered supervisor can not be found, the unregistered cabler will be regarded as
installing telecommunications cabling without a registration. The unregistered cabler will
receive an on the spot fine of $1320 or can be fined up to $13,200 in a court.
Types of earthing
Earthing equipment is required to be performed when the equipment is installed.
Depending on the type of equipment and its configuration, one of the following earthing
methods is mandatory. Manufacturers provide the type of earthing required for their
system.
Earthing Options
1. TRC and PE
The TRC and the PE must be connected to the equipment on separate terminals, in
accordance with the individual TRC and PE requirements listed above. The manufacturer
will indicate this in the installation manual.
2. None
Neither a PE nor a TRC is required to be connected to this equipment. The manufacturer
will indicate this in the installation manual.
3. TRC or PE
Either a PE or a TRC must be connected to this equipment. However in some uses of the
type of equipment, a TRC must be used. (E.g. a CAE mounted behind another CAE may
need earth recall to access the first CAE. A TRC is required for this functional use). If this
is the case, a note appears under the equipment listing in the installation guide. The
manufacturer will indicate this in the installation manual.
Building materials
There are several ways in which buildings can be classified. One way is by what the
building is used for or in other words by its specific occupancy such as:
• Single domestic – houses with one occupant
• Multiple domestic – flats, home units, hotels etc.
• Commercial – office blocks, schools, universities, shopping centres
• Industrial – factories, workshops etc.
All of which can be single or multi-story.
Of more interest to the cable installer is the type of structure. Therefore we get brick
buildings, brick veneer, timber-framed, steel framed, pre-stressed concrete and poured
concrete buildings, A structure as a whole can be made up of the following definable sub-
structures:
• Footings
• Support frame or structure
• External walls or cladding
• Internal walls or partitions
• Floor
• Roof
Material used for these sub-structures can be:
Foundations
Concrete, Concrete blocks, brick
Support frame or structure
Steel, steel reinforced concrete, brick, timber, and masonry blocks
Foundations
The foundations of a building or structure is the part of the structure which is in direct
contact with the ground and transmits the loads of the structure tot the ground.
Foundations must have an adequate factor of safety against bearing capacity failure of the
supporting soil or in other words be strong enough to cope with any local soil settlement
under a portion of the foundations.
The settlements (vertical movements) and the differential settlements between adjacent
parts of the foundation must be kept within acceptable limits for the structure.
Shallow foundations (or footings) are most frequently used to support relatively light loads
whereas deep foundation can be used to support much heavier loads or to provide support
in weak soils.
Strip footings
Strip footings are long shallow foundations that support a number of columns, piers or
stumps. For industrial and commercial structures the strip footing is used in soils of
medium to low compressibility or where some control of differential settlement is desired.
For residential dwellings concrete slab footings are now the most common footings used.
Support Structure
The supports structure or frame of a building is the part that holds the building up. And
provides the strength and rigidity to withstand internal and external forces. This support
structure can be simply the load bearing external walls of the building or a combination of
load bearing external and internal walls or a separate framework covered with lightweight
non load bearing cladding.
For buildings other than residential, the cost of timber in the sizes required is prohibitive.
Timber finds uses in non residential buildings where appearance is important and is
usually left exposed. Buildings such as theatres, churches and public halls are sometimes
framed in timber to take advantage of its natural beauty.
A popular and fast method of constructing factories, commercial premises and high-rise
buildings is to use prefabricated reinforced concrete panels. These are cast to suit the
design of the structure and may be cast on site or more likely in a factory and transported
to the building site. Doorways windows, holes for plumbing, electrical and other services
are cast into the wall panels. A decorative finish can be cast into the panels if required.
Conduits may be embedded into the panels at the casting stage and used fro electrical
and communication services.
A variety of steel sections are used which are normally cut and drilled off site. On site the
structural members are assembled, welded, bolted or riveted as necessary.
Walls
Roofs
Roofs basically come in two varieties, one that has accessible space between the roof
cladding and the ceiling and one that does not.
The pitch of a roof is variable however it should be noted that even on a “flat” roof has a
mandatory minimum slope of 3° to allow water run-off. The roofing material is usually steel
decking and fixed directly to the ceiling joists. Thermal insulation is normally placed in the
space between the decking and ceiling.
Industrial roofs are usually flat but often have an accessible gap (sometimes large enough
to walk upright in) to run services.
Pitched roofs more often have accessible space than flat roofs.
Concrete slabs
It is normal practice to run conduits carrying electrical services through concrete slabs, that
is, conduits are laid when the formwork for the slab is set up. The conduit is placed so as
to be as close as possible to halfway through the thickness of the slab to have the least
effect on the structural strength of the slab.
Cavity walls
Cavity walls can contain electrical services very often without any further mechanical
protection than sheathing. Cavity walls can also contain plumbing for both hot and cold
water services.
FASTENERS
Walls, floors, ceilings and other sub-structures in addition to forming the essential
components of a building are also used to support an assortment or equipment,
accessories, furnishings, decorations and services. In order to make this possible the
building materials have to be drilled, chiselled, cut and hammered.
Cable support systems i.e. conduits, trays, ducts, ladders and cable distribution require
fixing devices, otherwise known as fasteners or anchors to secure carious items
otherwise known as fixtures to walls, ceilings and other structural components.
The types of materials that are required to hold a fixing or support are:
• Lining and hollow materials
• Timber
• Masonry
• Metals
In selecting the appropriate fixing method the following points should be considered:
• Stress to be placed on the fixing under normal use and during installation
• The material that is to hold the fixing (timber, brick etc.)
• Number of fixings required
• Relative cost of each fixing
Gravity Toggle
The wall is drilled with the correct size hole. The machine thread screw is placed through
the object to be fixed then screwed into the nut of the toggle. The toggle is the inserted
into the hole and as it merges on the other side of the wall board the toggle is the inserted
into the hole and as it emerges on the other side of the wall the toggle swings down under
gravity and straddles the hole as the screw is tightened, this type of fixing is used for
lightweight to medium weight fixtures and a 5mm version can support a shear load of
175n. Because of its design the gravity toggle can be used only on vertical surfaces and
can only be used once as once the screw is removed the anchor section usually falls down
the wall. This particular type of fastener is available in two screw diameter sizes, 3mm and
5mm with length options of between 50mm and 100mm.
Wood Screws
Where fixing of a less permanent nature is required, wood screws are almost exclusively
used. Wood screws come in a range of lengths, gauges, metal and shapes.
Wood screws are designed with the thread forming a conical helix. They are designed this
way so that they will cut their own threads in the wood as they are driven. The heads are
slotted for a screwdriver and may be round, elliptical or countersunk. Wood screws are
threaded for approximately two thirds their length.
Fixing to metal
Fixing to metals involves either fixing to load bearing structural members or to non load
bearing metal. Load bearing structural members should not be drilled for purposes of
fixing. Any doubts as to whether a metal component can be drilled or not should be
resolved with a structural engineer. Some of the methods available for fixing to metal
(mainly steel) are as follows:
• Clamping
• Spring saddles
• Welding
• Explosive powered fixing
Where access is available to both front and back of a steel member and it is permitted to
drill that member, then a simple way of fixing is to use a nut and bolt.
If access is available to only one surface of a steel member then fixing can be achieved by
drilling and tapping. Where thin metal such as sheet metal or metal decking is involved
then self tapping screws may be used for fixing of light loads only.
For broadband cabling or other cables supporting high frequencies fix ties at irregular
intervals to avoid interference and harmonic reflection patterns.
Cabling can also be run in conduit. This provides support, some segregation and
mechnical protection. When running several cables in the same conduit consider the
intereference between cables. This can be partly compensated throught the use of the
correct category cable (with the relevant sheilding).
Low or high voltage cable cannot be run in the same conduit however the use of conduit
reduces the segregation distance required from these services. Refer to AS/NZS S009 for
more detailed information. Conduit containing telecommunications cable is to be
coloured white.
Saddles
Saddles are metallic or non-metallic clips used to support a single run of conduit. In the
metallic version saddles are also available as half saddles – that is they have only one
fixing hole. The half saddle is used for convenience (it is quicker to install) where the strain
on the fixing is not excessive or where a conduit needs to be run in a corner. A full saddle
is used for a more secure fixing. In timber or cladded timber saddles can be nailed or
screwed. Conduits where permitted can be saddled directly to the surface of a building.
Conduit clips
Conduit clips (Sledgy clips) are used for non invasive (no drilling is necessary) attachment
of conduit to structural steel members. The clips are made of spring steel and clamp the
conduit onto the steel member.
Sledgy.
Cable Trunking
Freestanding trunking
Freestanding trunking is used where:
• There are too many cables for easy installation in conduit
• Easy access is required for adding or moving cabling
• Conduit is too unsightly for the particular area
The metallic trunking can be installed with open face upward or on the side attached to
walls. The trunking can be fixed directly to a surface or a standoff arrangement can be
implemented using one or more of the arrangements for cable trays. Fixing is implemented
by drilling the back surface of the duct.
All the types of support systems used for cable trays can also be used for the metallic
freestanding duct with the due consideration to maximum support intervals as
recommended by the manufacturers and any ACMA and AS/NZS 3000:2007
requirements.
Plastic ducting because of its lack of rigidity cannot have excessive unsupported spans,
and is best fixed to a continuous flat surface. Smaller plastic ducting can be fixed to a
suitable surface using double sided adhesive tape and in fact some manufacturers supply
the ducting with adhesive tape already fixed to the underside.
Skirting trunking
Skirting duct is normally installed prior to the floor coverings being laid. The trunking is
secured to the walls by screws using appropriate anchors if required. After the cables have
been installed the cover strip is fitted into place.
Skirting duct can be linked to floor duct (Flushduct) at walls or holes can be provided at
rear for cable access.
Partition trunking
Partition trunking forms part of a modular partition system. The duct can be positioned at
any required height within the partition. Partition end posts secure the partition panels and
trunking into a single unit and also provide access into the trunking for installation of
cables.
Column trunking
Column trunking is used in some cases to provide the access channel between the main
cabling pathway and partition trunking and also infloor ducting as well as providing egress
points for the enclosed services. A column trunk has to be secured at the top to the main
suspension channel for the false ceiling or directly to the structural material of the ceiling.
At the bottom it must be secured to the floor.
Infloor ducting
Infloor ducting as is either conduit embedded in concrete floors or formed duct within the
floor. Conduits are laid onto the steel reinforcing before the concrete pour making sure that
any outlet pints are temporarily sealed against the ingress of concrete and that drawlines
are installed.
Domestic
Single domestic residences do not normally have any provisions designed into them for
cable pathways. Existing structural features are used for running cables that is wall
cavities, space between ceiling and roof and sub-floor areas.
CABLE CHARACTERISTICS
All cables that contain electrically conductive elements have the following properties
• Inductance (L)
• Resistance (R)
• Capacitance (C)
• Conductance (G)
The diagram shows a typical pair of conductors and their basic electrical characteristics.
On a perfect cable UTP, STP or coaxial cable, the properties shown below affect the
signal evenly along the entire length of the cable.
Inductance
When current flows through a conductor a magnetic field is created around the conductor.
When the current flow diminishes or increases the surrounding field weakens or
strengthens. If the magnetic field extends to, and cuts nearby conductors then changes in
field intensity will result in current flows in those nearby conductors. The circuits are then
magnetically coupled. In this way electrical energy is transferred from one circuit to
another. This causes attenuation to result.
Grouping wires in pairs and twisting them together and spiralling this twist out over the
length of the cable ensures that no two wires are in close contact over the entire cable
length.
For two conductors made of the same material and of the same diameter, one twice the
length of the other will have twice the resistance of the other.
Heating
Resistance in a cable means that heating will occur. Even the best quality copper wire has
some resistance that creates loss. The higher the resistance, the more heating occurs.
The heating itself is very minor.
Radiation
The signal emits into free air like a wave from a radio antenna. This happens due to the
fact that a signal in a cable is essentially a radio wave signal and an antenna is essentially
a conductor in free space. The amount of energy lost to radiation is usually fairly minor
Capacitance
A capacitor is a device that stores electrons. A capacitor is formed whenever there are two
electrical conductors separated by an insulator. The number of electrons stored is a
measure of the capacitors “Capacitance”. Unit of measure is the “Farad”
The capacitance of a cable is measured in picoFarad (pF) per metre.
Capacitance exists between the wires in a pair and between adjacent pairs. This
capacitance between adjacent pairs is called mutual capacitance.
The symbol for capacitance is show below
Cable capacitance
Capacitors act as electrical conductors to voice and data signals.
Capacitance in a cable is a problem for 3 reasons:
1. It takes energy to charge the capacitance as the signal moves down the line. This is related
to impedance
2. The signal passing down a cable pair is shunted between the paired wires and loses power
the further it travels. This is problem magnifies a frequency of the signal increases
3. The signal can be shunted to nearby conductors carrying other messages
Loss of Signal
As the signal passes along one cable pair, the mutual capacitance tends to couple the
signal into an adjacent pair. When this occurs on a telephone call one conversation would
be heard in the background of another. This effect is called ‘Crosstalk’.
Crosstalk
In the case of perfectly balanced link or channel there exists no electromagnetic coupling
from the pair to the environment. In practice there is, however, always more or less
electromagnetic coupling caused by imperfect balance. Unwanted electromagnetic
Frequency
The losses on communications cables are very dependent on frequency. As stated above,
the higher the frequency – the higher the loss. Frequency is measured in Hertz (Hz). 1
Hertz is the time it takes for one complete cycle to pass a given point in 1 second.
The above cable constants all affect the attenuation, propagation and quality of the signals
sent to line and this is proportional to the length of line.
Impedance Calculation
In technical descriptions of cables, the characteristic impedance is given the symbol Z.
Impedance is simply the ration of the voltages and currents on the line. In simple circuits
the equation –
!
!=
!
V = Voltage
I = Current
When circuits or currents become more complex other factors come into play.
Matching of Cables
It is extremely important to match the characteristic impedance of cables when installing a
data, telephone or video/TV network. If the cables are not matched then signal energy is
not transferred efficiently and will cause reflection. This reflection or return loss leads to
attenuation of the signal. In much the same way, it is important to use the correct
connectors on the ends of the cables and to ensure that they are fitted correctly.
Mismatching of cable properties results in interference, turbulence and reflections similar to that by mismatching water hose
sizes.
Information Capacity
The amount of information that cab be carried on a transmission system is directly related
to the maximum frequency signal that can be sent along a length of cable with a given
loss.
Shielding
Shielding is required to stop signals leaking from the cable and to prevent other signals
from nearby cables from interfering with the wanted signals.
Electric signals create electric and magnetic fields as they pass through the conductors.
Together they combine to form electromagnetic radiation or radio waves. The cable itself
acts as an antenna connected to the transmitter.
Water in cables
In any telecommunications cable that has metallic conductors, a change in the dielectric
can cause a reduction in the performance of the signal. If water enters the cable then
water changes the electrical properties of the cable. For the same transmitted power it
would not be as strong as it would normally be in dry air.
The dielectric constant of the insulation also determines just how fast signals can travel
down the cable. The dielectric constant affects only the electric field, not the magnetic
field.
CABLE TYPES
Transfer of data occurs at very high speeds therefore the correct selection of cable (and
matching components) is critical for the optimum operation of the network.
When communications are transmitted on cable one of four basic different types are used:
• Unshielded twisted pair
• Shielded twisted pair
• Coaxial
• Optical Fibres
Coax cable was originally used for Local Area Networks (LAN) or Ethernet (that has now
generally been replaced with Structured cable or wi fi).
It is still used on some CCTV and commonly on Radio Frequency and microwave
equipment and Pay TV communications.
Coaxial cable offers lower power loss to the signal than other types of cables.
Type Title Standard Issue Version Ref Release date Page
LR ICTCBL2136B NVR Standard 15.5 2 1 ACMA Restricted Rule 06/08/2014 Page 85 of 225
Optical Fibres
An optical fibre is composed of two concentric glass layers called the core and the
cladding that are made of an optical transparent material (e.g. silica glass). In addition to
these layers a surrounding layer of acrylate coating provides protection and flexibility.
The coating around the core/cladding may be coloured and consist of either UV cured
acrylate (250µm) or nylon (900µm). These coatings provide significant protection and
flexibility to the physical characteristics of the glass and do not have any adverse effects
upon the properties of light within the fibre.
External UTP
High pair quantity Underground UTP incorporates multiple bundles each separated by
whipping of differentiating colours that indicates ‘group’ number. External cable is
manufactured to the same basic specificaitons as internal cable howver there is a different
colour code and the insulation and sheath is of a type that will prevent penetration of
moisture that meets standards AS/CA S008:2010.
Extrenal cables are normally available in pair sizes 2-50, 70 and 100.
Aerial cables are available with integrated strain member called a messenger.
Common colour codes for various types of cable are provided in Tables B1
to B7. While it is not mandatory for cable manufacturers to follow these
colour codes, they usually do.
Where a cable colour code does not correspond to the colours in the tables
in this Appendix, the colour code provided by the manufacturer of the
cable should be followed as required by Clause 5.2 of this Standard.
Initial Preparation
The successful execution of any cable installation requires that the project be carefully
planned and contingencies be allowed for before the installation commences.
Site Survey
Before planning of the cable system begins, it will already be known what services the
cables are to carry and the locations that the cables will be required to be run between.
With this information in mind the first requirement is to carry out a comprehensive site
survey of the location the cables are to be installed. The site survey should focus on
determining the following:
• The most appropriate route for each cable. This may be in with existing cable runs or in
newly installed cable housings. It will generally be more cost effective to use existing
infrastructure but the decision depends on the amount of space in the existing housing and
on the condition of the housing. Also an existing cabling route may take a longer path and
the extra cabling costs associated with this may exceed the cost of installing a new route.
• The need to run the cables in cable trays, underground in roof tops or as aerial cables.
• The condition of the existing cable housings. Will costly maintenance be required before
new cables can be installed? Is there potential for damage to be caused to the cable
because of the poor condition of the housings? For example are the housings subject to
flooding?
• Is there any locations that need special attention. Are tradesmen with special skills
required?
• Are any cables in a chemically hazardous environment?
• Are there any locations where the cables will be subjected to extreme temperatures? If so
plan to use a different type of cable e.g. fibre or explosion proof cables.
• Will the cable route be near high voltage power cables? If so fibre optic cable that does not
contain any metal may be required.
• Will the cable route be near areas of high transient voltages (e.g. lightening?) If so ensure
the appropriate cable is used.
• Ensure that all the Electrical and Fire Codes of Practice that apply in the country in which
the installation is planned can be adhered to.
• Will there be sufficient room to use the cable pulling equipment? If not what equipment
needs to be moved to carry out the installation without hindrance.
Pulling Cable
Excessive tensional force can be very detrimental to the cable. Excess tension can cause
the twisting of the pairs to straighten out reducing the effectiveness of noise isolation
properties. The foil shielding can break having the same effect and even the copper wire
itself can break rendering the pair/cable useless.
Manufacturers will supply information regarding the torsional stress for the cable.
NOTE: Cable tension may also affect the Minimum bend radius – as the cable is more
likely to be damaged from tight bends when it is also being pulled – check to see if the
minimum bend radius needs to be increased during installation. As an indication the
minimum bend radius of a cable under haul is often double the normal minimum bend
radius.
Type Title Standard Issue Version Ref Release date Page
LR ICTCBL2136B NVR Standard 15.5 2 1 ACMA Restricted Rule 06/08/2014 Page 92 of 225
Never haul the cable through more than 3 x 90° bends even if the MBR is being observed.
Pull the cable part way along the run, lay it out in a figure 8 as you go. When pulled to the
required length flip the figure 8 pile over then pull the next section.
Cable Reels
• Cable’s should be given a number that is noted on the cabling diagram during installation.
Cable suppliers usually place a serial number on the side of the reel that can be used for
this purpose.
• Each cable reel should be tested for continuity before installation commences
• Cable manufacturers will normally leave the end of the cable that is on the inside or the reel
pointing out so that it cab ne used for testing. After each reel of cable is installed (if using
fibre) a second test should be carried out on each fibre to ensure that there has been no
significant damage incurred during installation. The results of these tests should be
recorded with the result of the pre installation tests.
• The cable en that is on the inside of the reel should be taped firmly to the side of the reel so
that it does not catch on the outgoing cable during runoff.
• In order to minimise damage and unnecessary handling of the cable during installation it is
advisable to runoff directly from the reel. This cab be achieved by holding the reel on a rod
and directly unreeling it as you walk along the cable tray or trench, or by placing the reel of
a payoff stand at the beginning of the cable run and directly runoff from there. This method
of a runoff also helps to prevent unwanted twisting and torsional tension of cables.
150!!!!!!!! ! !"#$!!"#$%&'(!")
!"#$%&'!!"#$%&# = !
1000
Where P is the number of pairs in the cable and d is the conductor diameter in mm.
For fibre optic cables the manufacturer supplies a list of hauling tensions and these must
be strictly followed at all times.
For copper conductors the hauling tension should never exceed 40kN. Hauling tension in
excess of 40kN can cause damage to conductors and/or cable sheath must be well
lubricated. Optical fibre is limited to 2kN
Hauling Speed
An even tension should always be applied and stopping and restarting should be avoided.
The tension required to start hauling the cable from rest is much larger than is required to
keep it moving. A hauling speed for approximately 30 meters per minute is desirable to
prevent surging and to reduce tension.
Registered cablers working with telephone lines carrying broadband services need to take
precautions to avoid electric shock. Carriage service provider (CSP) broadband equipment
within the customer’s premises requires increased voltage, which is called power feeding.
The risk of electric shock increases when working with these higher voltages. Network
cables carrying power feeding circuits may bypass the main distributor frame (MDF) to
extend through to the CSP’s equipment or they may be installed on the MDF. Usually the
power feeding network cable will be laid in areas accessed by cablers.
With broadband services, carriers and CSP’s may install terminal equipment that is
remotely fed using a current limited circuit. This has an open circuit voltage, which is
higher than normal telecommunications network voltage. (TNV) limit. (See below for a
definition of TNV).
Authorisation from the relevant carrier of CSP is required to work on these network cables
and should exercise caution when working near any accessible termination.
The increased voltage also has the capacity to damage test equipment.
The ACMA makes the following recommendation:
The ACMA wiring rules AS/CA S009:2013 prevent the use of customer cabling for any
service that exceeds TNV limits, such as remote feeding telecommunications current
(RFT-C) circuits. Consequently carriers and CSP’s using RFT-C should cable directly to
the terminal equipment bypassing the existing customer cabling infrastructure. The power-
fed terminal equipment must be network equipment between the carrier or CSP and the
customer.
The Communications Alliance Ltd. Has developed an industry code that specifies a
maximum voltage of 300Vdc and the current limitation parameters that carriers and CSP’s
should observe when power-feeding within their networks. CSP’s and carriers are required
to provide separation, barriers and warning labels to identify potential hazards.
Holding a cabling provider registration does not permit a cable to work on or interfere with
any carrier equipment or cables on the carrier side of the network boundary. RFT-C cables
and carrier terminations are all part of the carriers network.
Electric Shock
Electric shock is the worst outcome of working close to electrical plant. It can range from
an unpleasant sensation to fatal. Most aspects of the power safety training are concerned
with ways of avoiding electric shock or dealing with it if it happens.
Current Reaction
1 mA Faint tingle
One instructive example of the nature of voltage is the fact that a bird can sit on a high-
voltage wire without harm, since both of its feet are the same voltage. You can also see
that the bird is not “grounded” – you will not be shocked by touching a high voltage if there
is no path for the current to reach the Earth of a different voltage point.
Typically if you touch a 110 volt circuit with one hand, you can escape serious shock if you
have insulting shoes, which prevent a low resistance path to ground. This fact has led to
the common “hand-in-the-pocket” practiced by some electrical workers. If you keep one
hand in your pocket when touching a circuit that might provide a shock, you are less likely
to have a path to ground; which would result in serious shock.
Resistance)of)the)Body)
7000$
6000$
5000$
Resistance)in))
4000$
5%$of$Population$
3000$ 50%$of$Poplulation$
95%$of$Population$
2000$
1000,$1500$
1000$ 1000,$1050$
1000,$700$
0$
0$ 200$ 400$ 600$ 800$ 1000$ 1200$
Voltage)
TERMINATION TECHNIQUES
Extract from
http://www.acma.gov.au/Industry/Telco/Infrastructure/Cabling-rules/installing-a-
mode-3-socket
If you are a cabler who cannot provide a mode socket in the manner prescribed in the
diagram below (i.e. connected at or after the first socket), then you must arrange for
the carrier staff to provide the mode connection.
Cablers who have an Open registration may install mode sockets for security systems
that connect to the telecommunications network at industrial, commercial or
residential properties.
When there is no device connected to the 611 socket the terminals 1 and 2 are joined and
5 and 6 are joined hence the signal flows through the physical connection and
downstream outlets work normally.
When a mode 3 device is connected to the 611 socket the pins from the 604 plug separate
the terminals on the 611 socket. The phone line connects directly to the mode 3 device
and it can control whether to connect the phone line to the rest of the down stream devices
by sending the signal back into pins 2 and 6.
Mode 3 adapter’s are available that perform a similar function. They do not control any
existing downstream sockets permanently wired into the premises – only downstream
outlets that are connected into the adapter.
Procedure
Using the table below as a guide, strip the cable sheath to the correct dimension
After achieving the correct wire sequence insert the wires into the connector until they
bottom against the connector tip.
Ensure that the cable sheathing extends into the sheath clamp area.
Cable Records
For a technician or cabling installer involved in providing services in a building the
interpretation of plans and the practical application is very important.
The diagram below shows a simple floor plan with details of building layout, room function
and position of outlets.
This plan represents a small business requiring 8 telephone outlets. These outlets are to
be supplied from a 10 pair distribution frame.
Recording Systems
This section deals with the process of recording cable distribution details in a record book
and maintaining these records.
Record books and record keeping can vary from installation to installation. Generally a
record style similar to the sample record forms illustrated below is used. For larger
installations, customised records are usually kept and these will be printed out as required.
Some installations now use a PC based records management system, which is similar in
format to the written records system shown here.
MDF records
MDF records will generally be established and maintained by the carrier (e.g. Telstra).
Jumpers run here are called “Network Jumpers” and are also usually run by the carrier.
There are records for both sides of the Distribution Frame i.e. both sides of the cross
connection.
Cable Details Pair No Service Number Other particulars of Jumpered to vertical
Service pair
Termination records
Module 8
M8 1 2 3 4 5 6 7 8 9 10
Module 7
M7 1 2 3 4 5 6 7 8 9 10
Module 6
M8 1 2 3 4 5 6 7 8 9 10
Module 5
M8 1 2 3 4 5 6 7 8 9 10
Module 4
M8 1 2 3 4 5 6 7 8 9 10
Note that this frame may use 20 pair modules for the PABX tails.
| 0
| 9
| 8
| 7
| 5
| 5
| 4
| 3
| 2
| 1
| 0
| 9
| 8
| 7
| 5
| 5
| 4
| 3
| 2
| 1
Testing
Other devices
There are several instruments that can be used to identify low resistance faults such as
the Riser Bond, PET or C2300.
Multimeters
Two main types of multimeters are in common use, analogue or digital. Both types share
many common features and are equally good for general purpose testing. The digital
multimeter is a battery operated instrument that uses a digital display. The analogue type
is a simpler in design and has an analogue meter display.
All multimeters combine the operations of voltmeters, ammeters and ohmmeters and
usually offer the following:
• AC and DC voltage ranges from less than one to many hundreds of volts
• AC and DC current ranges from a few milliamps to several amps
• Resistance ranges from ohms to megohms
Combined instruments
Many manufacturers provide instruments that combine a number of functions. For
example one commonly available unit contains a test telephone, a cable identification
function and a multimeter. Other combinations of equipment are also available.
PICTURES OF COMBINED INSTRUMENTS
ACTIVITY – TESTING
For this activity you will need a typical test telephone, cable identification set, continuity
tester, megger and multimeter and their instruction booklets.
Method
Read the instruction booklet and then examine each unit in turn.
In the spaces below, write model identification details for each unit and list its features.
Perform a series of basic tests on cable or simulations to experience using each
instrument. Briefly summarise the tests completed and any observations made in the
spaces provided.
Test Telephone
Model Number ...........................................................................................................
Features ...........................................................................................................
...........................................................................................................
...........................................................................................................
Summary of activity
...........................................................................................................................................
...........................................................................................................................................
...........................................................................................................................................
Type Title Standard Issue Version Ref Release date Page
LR ICTCBL2136B NVR Standard 15.5 2 1 ACMA Restricted Rule 06/08/2014 Page 127 of 225
Cable Identification Test Set
Model Number ...........................................................................................................
Features ...........................................................................................................
...........................................................................................................
...........................................................................................................
Summary of activity
...........................................................................................................................................
...........................................................................................................................................
...........................................................................................................................................
Features ...........................................................................................................
...........................................................................................................
...........................................................................................................
Summary of activity
...........................................................................................................................................
...........................................................................................................................................
...........................................................................................................................................
Megger
Model Number ...........................................................................................................
Features ...........................................................................................................
...........................................................................................................
...........................................................................................................
Summary of activity
...........................................................................................................................................
...........................................................................................................................................
...........................................................................................................................................
Features ...........................................................................................................
...........................................................................................................
...........................................................................................................
Summary of activity
...........................................................................................................................................
...........................................................................................................................................
...........................................................................................................................................
Types of plans
In order to locate cables already installed in a customer premises, you must be able to
read and interpret plans including: building plans, floor plans, plumbing and electrical
plans, cable plans, street plans and site layout drawings.
Building plans
For a technician or cabling installer involved in providing services in a building, the
interpretation of plans and the practical application of the information obtained is most
important.
Most buildings have a standard layout of details on a plan. This means that people using
these plans need to know where to look and what to look for.
The term “Building plans” covers a range of plans, which are all parts of a complete
working plan. To understand plan layout it is necessary to recognise all parts of a working
plan. These are
• Floor plan
• Front elevation, rear elevation, side elevations
• Site or block plan
• Section
• Details
Underground Cabling
Underground cable will be enclosed inside an appropriate length of conduit buried to the
required depth and sealed to prevent the entry of water.
Table 3
Note:
The conduit sizes are rounded to the nearest integer and are based on the values listed in
AS/NZS 1477 for PN 9 and PN 12 PVC pressure pipes, which are the values used by
carriers for their conduit.
Exclusive trench Heavy duty orange conduit or a concrete barrier to Clause 100 mm
crossing under LV 3.11.4.3 or AS/NZS 3000 above the LV for 600 mm either side
of the crossing
Shared trench in In heavy duty orange conduit marked ‘ELECTRICAL’ Nil (Note 3)
insulating conduit
Shared trench Under a covering to Clause 3.11.4.3 of AS/NZS 3000 (Note 1) 100 mm
Exclusive trench Heavy duty orange conduit or a concrete barrier to Clause 300 mm
crossing under HV 3.11.4.3 or AS/NZS 3000 above the HV for 600 mm either side
of the crossing
HV
Exclusive trench In or under a covering to AS/NZS 3000 requirements (Note 1) 300 mm
parallel run
Note 1: Clause 3.11 of AS/NZS 3000 applies. This includes Category A systems where the
power cable is enclosed in a heavy duty cabling enclosure without further protection, such
as in orange (heavy duty) insulating conduit, and Category B systems where additional
mechanical protection is provided above the power cable in accordance with the
requirements of Clause 3.11.4.3 of AS/NZS 3000.
Note 4: For added cable protection, customer cabling may be enclosed in insulating conduit
that complies with AS/CA S008 requirements, but this does not reduce the minimum
separation distances required except for the case described in Note 3.
Aerial Cabling
Aerial cabling will be suspended on a catenary wire between the two premises being
cabled. It will meet the requirements for height or clearance and crossing power services
AS/CA S009:2013: 19.5.7.3 Separation from aerial power lines and fittings
Aerial customer cabling, including any joint or termination enclosure, that attaches to the
same pole or structure as an aerial power line or that crosses an aerial power line in span
shall be separated from the aerial LV and HV power lines and fittings in accordance with
Table 5 below.
APPLICATION
You are working on a customer site where there are two buildings. You note that an aerial
lead between the buildings is 2.7m above the ground. While you are watching several cars
go under the aerial wiring on that appears to be a driveway. What action should you take?
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
CABLING REGULATIONS
This section introduces the learner to the requirements detailed in Standards Australia,
Communications Cabling Manual (CCM) Package Volume 1 and 2.
The emphasis of this section of the resource is on the application of rules and regulations
governing the installation of customer cabling systems in customer premises. The main
focus is on regulations governing the installation and commissioning of customer cabling
systems.
While this resource examines the requirements of the Standards Australia Communications
Cabling Manual (CCM) package, it does not remove the learner’s responsibility to read this
document thoroughly.
Each subject within each section has been given a clause number and every number has a
heading. Clauses may contain paragraphs e.g. (a), (b), (c) etc, sub-paragraphs (i), (ii), (iii),
etc. These structural changes have been made to make it easier to find information.
ACTIVITY
1) Summarise the definition of Customer Access Equipment (CAE)?
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
Introduction
The purpose of this section is to develop knowledge of the classes of cabler registration
available and the obligations of registered cablers. We will describe the Australian
Communications and Media Authority’s (ACMA) role under the current Telecommunications
Act, detail the ACMA’s authority under the current Telecommunications Act and describe
the fundamental principles pertaining to the various classes of cabler registration.
International communications
The rapidly changing nature of communications and rapid growth of the industry worldwide
has led to increasing sensitivity being attached to international communication issues. The
ACMA has a primary role in representing Australia’s interests in discussions about such
issues.
Australia is taking a lead in Asia-Pacific forums convened to promote mutual recognition,
harmonise standards and enhance prospects for trade in equipment and services.
Introduction
This section examines the Telecommunications Cabling Provider Rules (CPR) 2000, which
came into effect 3rd October 2000 and is now know as the CPR Registration System. In this
section we will describe the rules that the ACMA makes under the Telecommunications Act
1997. These include:
• Cabling Provider Rules (CPR’s)
• Definition of terms
• Application of rules
• Types of cabling work
• Registration
• Performance of cabling work
• Relationship ACMA
ENDORESEMENTS
All five registrars offer Open, Restricted and Lift registrations, which provide a cabler with a nationally
recognised registration and endorsements/competencies
It is a requirement of the CPR that changes of registered cabler addresses are to be notified to the registrar
within 21 days.
Read the “Telecommunications Cabling Provider Rules 2000” prior to answering the following.
1) What are the three grades of registration the registrars offer?
_____________________________________________________________________________
2) How many registrars are there and how many are you required to register with?
Depending on the cabling work performed, cablers must meet the ACMA’s ____________________
for one of the areas of cabling work
Competency Standards
The ACMA requires that an applicant for registration as a cabler be required to have
sufficient competence, skills, knowledge and experience before being registered.
Competency consists of the specific knowledge, skill and application within an occupation or
industry, to the standard of performance required in employment.
Competency standards define those competencies for effective performance in
employment. This includes the specification of skills and knowledge. Competency standards
focus on what the workplace expects of an employee rather than on the learning process.
Read Section 4 of AS/CA S009:2013 prior to completing the following:
The objective of this standard is to protect ______________________ and
______________________ of any person who may (i) ______________________, (ii)
______________________, (iii) of any person who may (i) ______________________, (ii)
______________________ (iii) ________________________________ _____________
___________________________________________ or (iv) ______________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
A telecommunications network or a facility.
Registration number
Address
Name of registrar
POSTCODE
Contact details
WORK ( ) POSTCODE
MOBILE
Customer details
Name Contact details
WORK ( )
FAX ( )
Address
POSTCODE
Certification
I hereby certify that the cabling work described in this advice complies with the Wiring Rules (AS/CA S009 or its replacement).
This form is an optional addition to the TCA1 Telecommunications Cabling Advice form. It may be used by
registered cablers to alert the customer or building manager of any non-compliant cable installations that are
outside the contracted scope of work.
Pre works advice
Post works advice
Outstanding matters
While undertaking the contracted cabling work, the following issues have been identified with the pre-existing
cable installation, which may require your attention:
Compliance marks
The ACMA has three compliance marks. These marks
are:
Regulatory Compliance Mark (RCM)
The RCM has recently (1 March 2013) been confirmed as the single
compliance mark for all arrangements. Prior to this there were opportunities
for suppliers to use the RCM to indicate compliance with the EMC regulatory
arrangement where the RCM mark was used in conjunction with supplier
identification. There are transitional arrangements where suppliers were
previously labelling with the A-Tick, C-Tick or RCM under the previous
arrangements
A-Tick
C-Tick
The A-Tick and C-Tick marks can continue to be used by suppliers with a
Supplier code number issued by the ACMA until 01 March
2016. Downloadable A-Tick and C-Tick marks in 'Zip Format' are provided
below.
Further Information
Further information about all the labelling and compliance requirements can
be found on the ACMA website.
End of extract
Permit numbers may also be found incorporating the ‘C-tick’ in the format A96/0000. This
format no longer incorporates an equipment category number.
C-TICK and AUSTEL permit number – used on items approved from April 1996
to June 1997.
N####
The A-TICK and Supplier Identification have been used on items since July 1997.
N####
Equipment labelled with the above forms of identification is still approved to be connected
to the carriers network.
Electronic labelling
The Australian Communications and Media Authority’s (the ACMA) for device and
equipment labelling notices have been amended to allow suppliers the option of using
electronic labelling as an alternative to the traditional labelling of the surface of the device.
Suppliers can use electronic labelling for their device if the device has a built-in display.
Suppliers who choose to use electronic labelling are required to explain in the
documentation accompanying the device how the user can display the electronic label.
Suppliers must ensure that it is difficult to prevent the display of the electronic label when
the method specified in the documentation is used.
Compliance Tick
Customer Cables
Cables used for telecommunications cabling Shall be physically distinguishable from
products used fro mains power (refer to AS/CA S008:2010 5.1 & 5.6.1). All cabling
products shall be marked in English in accordance with the appropriate requirements
specified in the Labelling Notice (Refer to AS/CA S008:2010 5.2).
Basic construction
Two insulated copper conductors make the basis of the telephone service to the
customer’s premises. Twisting these insulated wires together forms a ‘twisted pair’. This
twisted pair forms the pathway for signals between the customer’s telephone and the
carriers exchange or for voice and data transmission within the customers premises.
Twisting the tow insulated wires into groups of two, forms a two pair cable. Twisting into
groups of four, forms quads of four pair cable. The number of twist varies so that no two
adjacent pairs or quads have the same rate of twist per meter. This reduces induction or
cross talk between pairs and between cables.
ACTIVITY
Obtain a cable manufacturers brochure for telecommunications cable, the cable
manufacturers websites (Belden, Pirelli, Olex, etc.) or a local supplier and find out the
typical conductor diameter for internal cables & external cables supplied by that
manufacturer.
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
Eight wire (4 pairs) jumpers are available for structured cabling sites and are referred as
patch cords. The colour code of the patch cords conductors is the same as the cable
colours.
2) What colour identifies non-metallic pipe as that of telecommunications, when used outdoors?
a) White as a full colour or stripe
b) Orange
c) Yellow
d) Grey as the full colour or a stripe
3) What would indicate that a customer equipment or customer cabling was compliant with the
relevant ACMA Technical Standards?
a) b)
c) d)
_____________________________________________________________________________
4) What material is suitable for the installation of underground customer cables?
a) PVC compounds
b) Any material that is suitable for telecommunications purposes
c) PVS, Polypropylene or other suitable material meeting the requirements of AS 1049
d) Polyethylene or other suitable material meeting the requirements of AS 1049
_____________________________________________________________________________
Important terminology
A glossary of definitions used in customer cabling is contained in section 4 of AS/CA
S008:2010 and section 3 of AS/CA S009:2013.
Use one of the above references as a guide to complete the following exercises.
1) Summarise the definition of Lead-in cabling
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
2) Summarise the definition of a Main Distribution Frame
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
3) Summarise the definition of a Network Termination Device
__________________________________________________________________________
__________________________________________________________________________
__________________________________________________________________________
4) Summarise the definition Cabling Product
__________________________________________________________________________
__________________________________________________________________________
__________________________________________________________________________
General
The Telecommunications Act 1997 provides the description of the network boundary. This
section looks at the physical point of the network boundary of a carrier or carriage service
providers network. This identifies the point of the telecommunications cabling from where
registered cables can work.
Read Clause 3.1.66 (including note) and Appendix J3 of AS/CA S009:2013.
Complete the following summary.
Prohibited Locations
Apart from the safety aspect, the remaining conditions relate to wet environments that
reinforce previous text relating to the fact that water in the enclosure of communications
terminations in a potential for corrosion and loss of signal.
Read AS/CA S009:2013 Clause 13.4. Complete the following
1) Note the three of the locations where a Network Boundary Distributor (MDF) shall not be
installed in
a) _____________________________________________________________________
b) _____________________________________________________________________
c) _____________________________________________________________________
A carrier will often leave jumpers for cancelled services in-situ within distributors to provide
the opportunity for the services to be taken up ‘in place’ by an incoming customer at a
lower cost. Nevertheless, not all cancelled services are taken up in place, and eventually
old jumpers for cancelled services (called ‘dead’ jumpers) may accumulate to a stage
where they clutter up the MDF and tie up spare pairs in the customer cabling connected to
the customer side of the MDF. It then becomes necessary to identify and remove dead
jumpers to free up pairs in the customer cabling.
A cabling provider must take all reasonable steps to ensure a working service is not
affected when removing dead jumpers.
Other Cabling Access Points
In premises where there is no distributor or a network termination device installed, the
carrier’s lead in cable may be terminated at any of the following:
• 610 sockets
• 611 sockets
• Modular socket
• Changeover switch
• Terminal strip of an obsolete wall phone (rotary dial type)
Clause 15.4.2 of AS/CA S009:2013 applies for these installations. Connection to the
carriers network is only allowed at these points and not at any other junction or terminal
box where the lead-in cable may be jointed by the carrier.
Clause 15.4.2 of AS/CA S009:2013 applies for these installations. Connection to the
carriers network is only allowed at these points and not any other junction or terminal box
where the lead-in cable may be jointed by the carrier.
Read Clause 15.4.2 of AS/CA S009:2013. Complete the following:
2) The cabling provider __________ __________ connect cable to lead-in cable connection
__________ or _____________ other than those described in clause 15.4.2.1, 2 and 3.
3) When can an open registered cabling provider, install cross-connections to the lead-in cable?
a) Under the direct supervision of the carriers technician
b) With written permission from the carrier
c) When licenced by the ACMA or under the direct supervision of a licensee
d) Under no circumstances can a licensee install cross-connects at the network boundary
_____
4) What is the maximum height specified in AS/CA S009:2013 for terminations of an outdoor
main distribution frame or NTD
a) 1.8 metres
b) 1500 mm
c) 1000 mm
d) 350 mm
_____
5) Who provides and terminates the lead in cable(s)
a) The customer
b) The building owner
c) The licenced cable installer
d) A cabler representing the carrier
_____
Important Terminology
Activity
Look up the definitions that are applicable to cabling installation need to be understood.
1) Summarise the definition of Customer cabling
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
2) Summarise the definition of Customer equipment
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
3) Summarise the definition of Low Frequency Induction
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
4) Summarise the definition of Catenary Support System
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
5) Summarise the definition of a Hazardous Service
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
6) Summarise the definition of Low Voltage
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
7) Summarise the definition of High Voltage
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
Cable Joints
Incorrect jointing devices and procedures are the cause of the majority of cabling faults.
Read Clause 5.8 of AS/CA S009:2013. Complete the following:
The cable joint __________ be suitable _____________, ____________ positioned and
supported to prevent the ingress of __________ or ________.
Explosive Atmospheres
Read Clause 7.1 of AS/CA S009:2013.
This clause provides industry standards to comply with when installing customer cabling in
hazardous areas. The use of equipment and its installation is to ensure safe use in areas
where flammable materials are generated, prepared, processed, handled, stored or
otherwise used and which are therefore potentially hazardous. A typical area may be a
flourmill, a chemical plant or an installation at a liquid fuel dispenser.
In practice (depending on the degree of danger), hazardous areas are defined in terms of
class and zones - for example a ‘Class 1 Zone 2’ hazardous area. Site owners should be
consulted to determine area classification prior to works commencing.
One or both of the outer chambers will ionise, providing a low resistance path to earth for
surge current on a line. The gas will return to the inert state when surge current
diminishes. The suppressor will handle many surges but will eventually need to be
replaced.
11) A registered cabler proposed to make an addition to an existing block cabling installation. To
comply with AS/CA S009:2013, the new installation
a) Must be installed to the previous installation standards used
b) Must be installed to the current ACMA standards
c) Must be installed using both old and new standards
d) Must pass inspection by the local electrical supply authority
_____
12) How is segregation between LV power terminations and conductors, and adjacent
telecommunications and conductors achieved in a shared enclosure?
a) By providing a shared enclosure, which meets double insulation requirements specified in
AS/NZS 3000:2007.
b) By the installation of a metallic screen connected to the Telecommunications Reference
conductor.
c) By maintaining the minimum specified clearance of 50mm between the terminations
d) By incorporating a permanently rigidly fixed barrier of durable insulating material, or metal
connected to the building protective earth.
_____
13) What protection shall be provided when a cable is used for power feeding
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
IP Rating
The IP (international Protection) rating defines the protection offered by a device against
the entry of solids and water. It consists of the letters IP followed by two numbers. The firt
number states the protection against the etry of dusts and solids while the second number
states the protection against the entry of moisture. The higher the number the better the
protection.
Protection against dust and solids has a value between 0 and 7 while protection against
moisture has a rating between 0 – 8.
The IP rating of AS 1939 details an X where no parameters’ are specified for that field.
The X field in this case deals with the intrusion of dust and probes such as fingers, wires
etc. These are covered by AS/NZS 3260.
Distributors
Section 12 of AS/CA S009:2013 applies to all distributors installed in customer premises
where cabling systems terminated. Additional requirements apply if the distributor is to be
used as a Main Distributor Frame. Section 13 of AS/CA S009:2013 details the additional
requirements for the main distribution frames.
Read clause 12 of AS/CA S009:2013. Complete the following.
Records
Where cross connections are made by means of jumpers, the registered cabling provider
shall supply sufficient information (records) relating to the cabling work performed to
enable ___________ and _____________________ to be correctly ______________ and
_________. Records shall be ___________ and updateable.
Dialling 1100 Before You Dig will help avoid damaging underground cables and pipes. As
more assets are being installed below ground, there is a greater need to exercise
increased care when digging.
DBYD provides FREE information preventing accidental damage to underground pipes
and cables.
1100 DBYD can be accessed through a variety of methods
Read clause 17.2 of AS/CA S009:2013, view Dial Before You Dig Video
and/or read DBYD brochures.
Log on to http://www.youtube.com/user/DialBeforeYouDig1100
Underground cabling
Read Clause 18 of AS/CA S009:2013. Complete the following:
This clause covers the specific installation requirements of underground customer cabling.
Pits & access holes Clause 18.1
1) Pits and access holes shall be ___________ and _______________ labelled on the cover to
_______________ them from other services
2) Shared pits for LV and HV power shall not be used except:
a. If the cable is traversing the pit, it shall be ____________ in a continuous run of __________
insulating conduit, which is suitably identified
b. The telecommunications cable does not contain ____________ conductive ________
Due to practicalities of placing pits over shared trench conduit runs, the sharing of pits with
power cables is allowed (but not encouraged), provided segregation of services is
maintained as provided for in AS/CA S009:2013. The segregation is to prevent mechanical
contact of the cable elements of each service. This could be a pit lid crushing cables if
dropped into the pit, the pit being crushed by a vehicle, or burning fuel or lightning fusing
the cores together. If a service is “sleeved” through a pit, this at least offers a barrier to
reduce the chances of conductor contact.
3) What are the requirements for installing pits or access holes in driveways?
_____________________________________________________________________________
_____________________________________________________________________________
4) Why is it recommended to seal entry holes of conduit/pipe into a building?
_____________________________________________________________________________
_____________________________________________________________________________
Pillars and cabinets Clause 18.2
5) What are the requirements for pillars and cabinets installed in a public place?
_____________________________________________________________________________
Conduit and marking tape Clause 18.3
6) Underground cable installed under a __________ ____________ or ___________ shall be
enclosed in ______________ ___________ or covered by a white ___________
__________ which identifies the service, installed a minimum of __________ above the
cable.
Cable type Clause 18.4
7) Cable installed underground shall meet the requirements for ______ __________ and
_________ _______________whether or not it is installed in a ___________
Underground Separations
NOTE: This diagram does not represent the physical layout of cabling in a trench, but is
provided as a learning aid to assist in understanding the basic principle of separation from
hazardous electrical services in an underground installation.
Refer to Table 2 of AS/CA S009:2013 for a full explanation and description of underground
separation.
For LV services
If both the customer cabling & power are enclosed in their respective coloured conduit in a
panel run, then no segregation is required. Otherwise:
• If only one LV power cable is protected then maintain a minimum of 100 mm separation
• If the LV power cable is unprotected then maintain a minimum 300 mm separation
Aerial cabling
Minimum installation heights
Read Clause 19.2 of AS/CA S009:2013. Write your answers for the following questions
1) What is the minimum height above ground for aerial cables in a non-trafficable area of a
customer premises?
_____
2) What is the minimum height above the ground for aerial cables in a non-trafficable area of
customer premises?
_____
3) What is the minimum height above the ground for aerial customer cables over a public
roadway or footpath?
_____
Bearer fastening
The termination of bearer wires must be such that, under adverse weather conditions, the
termination provides adequate support to the installation. It is preferable to install a
termination that tightens under increasing strain. Clause 19.4 (a) of AS/CA S009:2013
requires fastening to walls or other supporting structures to be capable of supporting the
load of the cable under the conditions of installation. When determining adequate support,
the following factors require consideration:
• Length of span
• Wind velocity
• Ambient temperature
• Sag
• Appropriate safety factors
Type Title Standard Issue Version Ref Release date Page
LR ICTCBL2136B NVR Standard 15.5 2 1 ACMA Restricted Rule 06/08/2014 Page 206 of 225
Crossings with power lines
Read Clause 19.5 of AS/CA S009:2013. Complete the following statements.
This clause details the requirements for the installation of aerial cabling when crossing with
power lines.
1) It is not possible for aerial customer cabling to cross aerial power lines, where the power
lines exceed ____ kV.
2) Electronically conductive aerial customer cables may attach to structures carrying high
voltage cables, provided that low voltage power lines are installed below the ______ power
cables.
3) The telecommunications cable at the crossing shall incorporate an _____________
____________ __________
4) Where telecommunications cables cross under 22kV HV lines in span, a minimum vertical
separation of _______ shall be maintained at the crossing between the telecommunications
cables and the HV lines.
5) Aerial customer cables are required to cross __________ aerial power lines except in
unusual circumstances, whereupon conditions apply.
6) If the aerial telephone cable must be uppermost then its height and span much be such tat in
the event of failure at either end it will clear the power cable by at least ____ m. The power
utility must also be in agreements.
Cabling across watercourses
Read Clause 19.7 of AS/CA S009:2013. Complete the following statement.
Aerial cabling over waterways shall comply with the ________________ of the relevant
_______________
Shared Poles
Read clause 19.5 of AS/CA S009:2013. Complete the following.
This clause and Table 3 in the standard details the requirements for the installation of
aerial customer cabling on shared poles.
1) What is the requirement for aerial customer cabling having an integral bearer wire?
_____________________________________________________________________________
_____________________________________________________________________________
2) Aerial customer cabling shall not be installed __________ power cables.
3) The cables of what other service can be present on a shared pole, where an engineered
solution has been devised when there are long parallel telecommunications cables that
contain electrically conductive elements? Answer Those of __________
4) What is the minimum separation specified for aerial customers cabling, when sharing a plie
with LV aerial services under the following conditions?
• The LV aerial service has insulated conductors and the separation is measured at a pole?
________ mm
• The separation is measured mid span between cables? ________ mm
• The LV aerial services are un-insulated and the separation is measured at a pole? ________
mm
Type Title Standard Issue Version Ref Release date Page
LR ICTCBL2136B NVR Standard 15.5 2 1 ACMA Restricted Rule 06/08/2014 Page 207 of 225
5) What is the minimum separation between customer cabling, joint terminations or enclosures
and uninsulated LV aerial lines at a pole?
mm
6) What is the minimum separation between aerial termination enclosures and conduits light
fitting and stays?
mm
7) What is the requirement for power earth cables on a shared pole?
_____________________________________________________________________________
_____________________________________________________________________________
_____________________________________________________________________________
Separation of cables of different services mid span on a cable route is a mechanical
separation to prevent cables tangling or chaffing when power cables sag due to heat or
are blown around by turbulent wind. Separation of service at poles and the requirement for
any earth conductors to be insulated if for the safety of cablers when required to work on
the poles.
Mark the minimum dimensions of W, X, Y & Z on the following diagram.
2) Where customer cabling is in a trench together with pipes supplying services for public
utilities such as gas and water, the customer cabling shall be:
a) Be uppermost in the trench
b) Be alongside, not above or below the other services
c) Be enclosed in conduit
d) Separate from the utility pipes in accordance with the utility requirements
_____
3) When can cable designed for indoor use, be used on the outside of a building?
a) Only if the insulation is of polyethylene or equivalent
b) When the cable is installed in a position that is not exposed to direct sunlight or it is
otherwise protected against exposure
c) When the cable is installed in a position that is not exposed to rainfall or it is otherwise
protected against moisture
d) Only when it is installed on the sheltered side of the building
_____
4) Where customer cabling is in a trench together with LV power cables and neither cables are
installed in conduit then separation must be such that:
a) The telecommunications cables are above the electrical cables
b) The cables are side by side
c) The telecommunications cables are below the electrical cables
d) Each service can be accessed without disturbing the other
_____
6) Where an outdoor customer cable in an exclusive trench crosses power cables, a concrete
barrier to AS/NZS 3000:2007 must be placed over the power cables:
a) Where the telecommunications cables are installed subsequent to the installation of the
power cables
b) For 600 mm either side of the crossing where the power cables will be uppermost and are
not enclosed in heavy duty UPVC orange conduit
c) For 300 mm either side of the crossing where the power cables are not enclosed in heavy
duty PVC conduit.
d) Where the power cables share a common trench with water or gas services
_____
7) Where a customer cabling is in a trench together with LV power cables and both systems are
in conduits, the minimum separation between the conduits is:
a) Nil, provided that heavy duty PVC conduit is used for both telecommunications and electrical
power cables
b) Nil provided that both conduits are identified by the colours, white for telecommunications
cables and orange for electrical power cables
c) 50 mm provided that the telecommunications cables are installed above the electrical power
cables
d) 100 mm
_____
8) The minimum height of aerial cables above the ground in a non-trafficable are on private
property is
a) 2.7 m
b) 3.5 m
c) 3.7 m
d) 4.9 m
_____
Type Title Standard Issue Version Ref Release date Page
LR ICTCBL2136B NVR Standard 15.5 2 1 ACMA Restricted Rule 06/08/2014 Page 210 of 225
9) The minimum height of aerial cables above ground over a residential driveway is:
a) 2.7 m
b) 3.5 m
c) 3.7 m
d) 4.9 m
_____
10) The minimum separation between aerial cables and uninsulated LV power main conductors
in span is:
a) 450 mm
b) 600 mm
c) 1.2 m
d) 1.8 m
_____
11) The minimum separation between aerial cables and an insulated service, lead or main power
conductor is:
a) 450 mm
b) 600 mm
c) 1.2 m
d) 1.8 m
_____
12) What separation is required between an aerial telecommunications cable and light fittings,
conduits and stays?
a) 50 mm
b) 100 mm
c) 300 mm
d) 600 mm
_____
13) Telecommunications cable installed as aerial cabling at a crossing of power lines, or on a
shared pole route, shall:
a) Have an earthed integral bearer (IB)
b) Be affixed to separate bearer cable
c) Have a polyethylene sheath
d) Have IB that is insulated from earth
_____
ACTIVITY
From Table 7 and figs 3, 4, 5 and 6 of AS/CA S009:2013 complete the following diagram
adding colours and references to minimum sizes of conductors used to:
• Equipotential bond to the designated distributor to the other distributors
• Run the TRC from the designated distributor to the other distributors
• Connect a CES to distributors (Shown as )
• Run a cable to a CET from an electrical distribution board to a distributor
• Run a cable to a metal barrier from the CET provided above
If you have the correct coloured marking devices then use those
• Using green for green yellow, and Blue if necessary for any violet insulated conductors
Planned Communication
When we are communicating it is always important to say exactly what we mean, and to
mean what we say. This means speaking clearly and making sure the other person
understands what we are saying. To do this you need to keep a few points in mind when
giving us feedback.
• Be sure of your facts. Know the cabling regulations well
• Know what information is required. Be sure which regulations are not being met
Australian Communications and Media Authority (ACMA) has statutory powers to impose
requirements on cabling providing concerning customer cabling.
The Telecommunications Cabling Provider Rules 2000 (Cabling Provider Rules) regulate
the cabling industry and establish an industry-managed registration scheme. The Cabling
Provider Rules ensure minimum cabling requirements are in place to promote safety and
maintain network integrity.
The principles behind CPRs are summarised in the 10 rules below:
CPRs promote safety and maintain network integrity with requirements including:
1. All customer cabling work in the telecommunications, fire, security and data industries must
be performed by a registered cabler.
2. Depending on the cabling work performed, cablers must obtain an Open, Restricted or Lift
registration that meets the ACMA's requirements.
3. Cabling work must comply with the Wiring Rules. The wiring rules detail the minimum
requirements for cabling installations to ensure that the network integrity and the health and
safety of end users, other cablers and carriers personnel protected.
4. A key requirement of the wiring rules is that telecommunications cabling is separated or
segregated from electrical cabling to avoid creating a dangerous situation.
5. Cablers are required to install only cabling product (including cable) and customer equipment
that complies with the requirements of the Labelling Notice.
6. Cablers must, at completion of each cabling task provide the client (i.e. the customer or
employer, whichever is appropriate) a job sign-off form, such as a Telecommunications
Cabling Advice 1 form (TCA1).
7. Registered cablers must directly supervise an unqualified cabler's cabling work. This is
known as Supervision Rule.
8. Under Supervision Rule a qualified cabler must accept full responsibility for the work done by
an unqualified cabler and ensure that it fully complies with the Wiring Rules including signing
TCA1 form.
9. Cablers provide all reasonable cooperation and assistance to ACMA inspectors and cabling
auditors. Cablers can be subject to fines if they do not abide by their registration conditions.
10. Cablers notify their registrar of any change of contact details within 21 days.
Self check questions are located as appropriate throughout the Learning Resource. They
are labelled as Learning Check 3 to Learning Check 9.
You are required to answer check questions as they occur throughout they Learning
Resource.
You must demonstrate competency in this unit by providing evidence of the ability to
complete a cabling installation and termination including:
• Three different types of telephone sockets.
• Australian modular socket.
• United States modular socket.
• Mode 3 alarm socket.
• One (1) network termination device (NTD).
• One (1) alarm panel including completion of a TCA compliance form and NTD records.
• One (1) Ethernet cable.
• Apply cable conductor identification codes.
• Conduct and interpret cable test results.
• Interpret and apply standards and regulations.
• Comply with all related OHS requirements and work practices.