Document Details:
Document No. Document Title Author Domain Owner
SNOC CHM ZTE BSS -
VIL/SNOC/MOP/2019/ZTE_ 2G_BTS_VLAN Change
Vipin Vinod Sumit Nangia
2G_BTS_VLAN Change
Reviewers:
Reviewed
Name Version Approved Position
Date
Approvers:
Version
Name Position Approval Date
Approved
Distribution List:
Name/Position / Available at Published Date
NextReview*:
Next Review Date Domain Owner
Sumit Nangia
*Document should be reviewed every year or whenever there is a major change, whichever is earlier” For
Feedback/Suggestions please drop a mailto: sumit.nangia@vodafoneidea.com
Contents
1. Purpose of Document.....................................................................................................................3
2. Objective.........................................................................................................................................3
3. Scope...............................................................................................................................................3
4. Resources........................................................................................................................................3
5.1 Pre-requisites..................................................................................................................................3
1. Purpose of Document
This technical document covers the activity of ZTE_2G BTS VLAN CHANGE in the BSC’s for
Circles. The purpose of this document is to describe the actions needed for addition of 2G BTS VLAN
change in ZTE BSC’s.
2. Objective
The objective of this MOP is to provide the user as to how to perform ZTE_2G BTS VLAN CHANGE
in BSCs.
3. Scope
The scope of this process document is to present the process ZTE_2G BTS VLAN CHANGE in BSCs,
which is to be observed by SNOC, for ZTE based circles and Corporate Team.
This process is for Vodafone Managed Circles Only.
4. Resources
5.1 Pre-requisites
2G_VLAN
CHANGE.xlsx
Check for any incorrect or missing parameter in the license file given by circle.
(Validation Step through NETNUMEN).
Check if BSC name specified matches with BSC NUM specified.
Take Pre Logs: Take all the required pre-logs of Planned BSC’s – SNOC responsibility
Query SCTP Link Status via Dynamic Management of OMMB >> Query SCTP
Check VLAN Mapping via Configuration Management >> IP Layer Config List
Befote going to change the VLAN ID for BTS need to check the SCTP LINK and CELL status.
Step 1:Before start the VLAN Change activity DEACTIVATE the BTS at OMMB & BSC Level.
Before modifying the VLAN we need to deactivate the BTS to avoid unwanted alarms
Put Maintenance status of GSM in “Fault Testing” from Managed Network Element in OMMB
We Have to put Cell in FM Testing in BSC from Cell Maintain Status Management
Step 2: Check VLAN Mapping via Configuration Management >> IP Layer Config List
Step 3: ADD Required VLAN in Ethernet Link Layer List in Configuration Management.
Node: Before change the BTS VLAN kindly check the gateway IP is for BTS or not.
Step 4: Then Select Your Required VLAN & Modify VLAN in 2G IP Layer Configuration.
Sr
Execution Outage Time Duartion for Activity in
No Activity Process
Time Inv mins
.
Checking CR if all required data
1 Day No 20
provided
2 Validate the plan Day No 10
S.
Points need to be checked Status Remarks
No.
1 Verification of VLAN at planning sheet
2 Cross check all cell services
3 Ensure after activity no alarm in network