This Standard replaces and cancels its previous revision.
Foreword
PETROBRAS Technical Standards are prepared by Working Groups - GTs
(consisting of specialists from PETROBRAS and its Subsidiaries), are commented by PETROBRAS
Units and PETROBRAS Subsidiaries, are approved by the Authoring Subcommittees - SCs
(consisting of specialists from the same specialty, representing the various PETROBRAS Units and
PETROBRAS Subsidiaries), and ratified by the Executive Nucleus (consisting of representatives of the
PETROBRAS Units and PETROBRAS Subsidiaries). A PETROBRAS Technical Standard is subject to
revision at any time by its Authoring Subcommittee and shall be reviewed every 5 years to be
revalidated, revised or cancelled. PETROBRAS Technical Standards are prepared in accordance with
standard PETROBRAS N-1. For complete information about PETROBRAS Technical Standards see
PETROBRAS Technical Standards Catalog.
FOREWORD
This Standard establishes the minimum conditions required for shaft sealing systems for
centrifugal and rotary pumps, to be supplied in accordance with API Standard 682,
1st edition, October 1994. This Standard is the Revalidation of standard PETROBRAS
N-2543 NOV/99, the contents thereof not altered.
1 SCOPE
1.1 The requirements of this Standard are additions to, or modifications of the
API Standard 682, 1st edition, which is an integral part of this Standard.
1.2 Sealing systems shall be in accordance with API Standard 682, 1st edition, plus the
following changes, as noted in parenthesis for each clause, according to the definitions
stated below. The information of each clause shall be read as follows, whenever starting
with:
1.3 Except for new clauses, item numbers used in this Standard are the same
API Standard 682, 1st edition, paragraph ones.
1.4 All deviations from the requirements in this Standard and/or API Standard 682,
1st edition, must be clearly identified in the proposal and submitted to PETROBRAS for
approval. Any requirement exception or deviation from any of the listed documents not
clearly mentioned in tender will be considered by PETROBRAS as full compliance with the
material requisition.
1.5 All deviations from the contracted design or scope of supply made by vendor during time
of drawings and documents review shall be clearly mentioned in the particular document to
be approved.
1.6 Vendor’s compliance with the requirements of these specifications does not exempt him
from the responsibility of supplying equipment and accessories suitable for the specified
service conditions.
2 COMPLEMENTARY DOCUMENTS
The documents listed below are mentioned in the text and contain valid requirements for the
present Standard.
2
N-2543 REV. A ENGLISH AUG / 2005
API Standard 682 - 1st edition - Shaft Sealing Systems for Centrifugal and
Rotary Pumps.
3 DEFINITIONS
1.1 Scope
1.1.1 (Substitution)
This Standard covers the minimum requirements for sealing systems for centrifugal and
rotary pumps with seal sizes from 30 mm to 120 mm (1.5 to 4.5 inches). Unless otherwise
specified, the applications outside the range of - 40 °C to 430 °C (- 40 °F to 800 °F) and 0 to
34.5 bar a (0 to 515 psi a) or which involve fluids not included in Appendix B of this Standard,
may require engineering and seal selection in addition to those provided in this Standard.
1.1.2 (Substitution)
This Standard is a “stand alone” seal standard which can be referenced by the current
edition of API Standard 610 (and PETROBRAS’ supplementary specifications, as well) or
API Standard 676 for new machines and can also be used to retrofit existing machines.
1.1.3 (Substitution)
This Standard is designed to default to the equipment types most commonly supplied to
PETROBRAS, and that have a high probability of meeting the objective of at least 3 years of
uninterrupted service while complying with emission regulations.
Where standard options exist, they are equivalent, acceptable and preferred: therefore, seals
and sealing systems will be specified in pump/seal data sheets, according to the Seal
Application Chart (SAC), if any, of the particular plant where the pump/seal is to be installed.
See Appendix L of this Standard.
The standard (according to the SAC) selection and the standard options provide a sealing
system that facilitates reliability, maintainability, and standardization, once seal type,
materials, and size will be standardized, aiming the maximum possible interchangeability of
parts (parts and materials not specified by PETROBRAS shall be per seal manufacturer
recommendations but shall also be selected considering spare parts inventories of the plant).
The standard selection and standard options also provide standard seal designs that have
been tested and qualified under equal or similar service conditions under which they are
intended to operate. On the other hand, this Standard also encourages evolving technology
through qualification testing, data sheet input, and particularly, for engineered seals.
3
N-2543 REV. A ENGLISH AUG / 2005
First of all, seal manufacturer shall quote sealing systems according to the Seal Application
Chart and pump/seal data sheets, which shall be filled in, signed and returned for technical
bid analysis (seal quotation summaries are not acceptable).
Nevertheless, the manufacturer may offer alternative designs with full-documented technical
justification (and eventually, is required to, mostly when a standardized selection might not
fully meet life, leakage rate and reliability requirements of data sheets and 1.1.3 of this
Standard. This Standard is not intended to impede technological advances in state-of-the art
sealing technology and therefore, pump and seal manufacturers are encouraged to
continually review new concepts and designs.
Concerning SI/English dimensions, see also in pump or seal data sheets the fields for size
standard about the required design system.
In case of conflict between the inquiry documents, the following priority shall govern:
a) data sheets;
b) supplementary job specifications (if any);
c) seal application chart (if any);
d) this PETROBRAS Standard and all other PETROBRAS standards specifically
referenced in the inquiry;
e) API Standards 682 and 610.
Concerning any conflict after placement of order, the following priority shall govern:
1.4.56 (New)
“Hazardous service”, when so marked on the data sheets, shall apply to all wetted parts of
pumps, seal system, piping, instruments and auxiliary equipment, and refers to the following
fluids and operational conditions:
4
N-2543 REV. A ENGLISH AUG / 2005
2.1.1 (Modification)
Unless otherwise specifically stated in the data sheets or in the applicable SAC, all standard
mechanical seals regardless of type or arrangement shall be of the cartridge design,
whenever feasible (exceptions shall be submitted for PETROBRAS’ specific approval).
2.3.3.1 (Modification)
2.3.9 (Substitution)
The pump manufacturer shall furnish curves or other characteristics allowing determination
of the seal chamber pressure over the entire range of the pump head capacity curve.
COMMENT: This information facilitates orifice sizing for cooling systems as well as
identification of flashing services.
The seal gland plate or seal chamber shall be furnished with a second flush connection to
permit measurement of seal chamber pressure directly.
2.3.11 (Addition)
Multiple ports shall be used for single seals and external dual seals.
2.3.14 (Addition)
Close clearances are not required for bushings installed at the inboard end of pressurized
dual seals.
2.3.16 (Substitution)
Gland plates and seal chambers shall have provisions for those connections required by the
seal flush plan but shall be designed and drilled, as a minimum, for flushing, drain and
quenching, even when not specified. In this case, connection points shall be plugged with
solid round or solid hex head plugs furnished in accordance with the dimensional
requirements of ANSI B 16.11. [TABLE 7 or 7a]. These plugs shall be of the same material
as the gland plate. An anaerobic lubricant/sealant shall be used on the threads to insure they
are vapor tight.
5
N-2543 REV. A ENGLISH AUG / 2005
2.3.20 (Modification)
For single seals and whenever feasible for dual seals, a non-sparking floating throttle
bushing shall be installed in the seal gland or chamber and positively retained against
pressure blowdown to minimize leakage if the seal fails.
2.5.1 (Addition)
Except for bellows seals, all inserts shall be submitted for PETROBRAS’ specific approval.
Ordinary inserts shall not be used.
Unless specifically stated in the data sheets, seals with multiple springs shall use
Hastelloy CTM as spring material. Seals with single springs shall use AISI type 316 stainless
steel as spring material. Should the possibility of 316 stainless steel stress corrosion cracking
occur, springs of Inconel or Hastelloy CTM shall be used for seals with single springs.
3.5.4 (New)
PTFE (TeflonTM) shall not be used unless it has been specifically approved by PETROBRAS
for that particular application.
3.9.1 (Addition)
Alloy 20TM, as a minimum, shall be used for services with chlorides concentrations above
10 ppm.
4.1.2 (New)
Piping accessories, instruments and openings shall be stamped or provided with metal tags
and arrows to identify flow direction, purpose and/or service. See also 6.4.4.
6
N-2543 REV. A ENGLISH AUG / 2005
4.1.14 (Substitution)
Unless otherwise specified, AISI 316L material shall be used when chlorides are present in a
concentration above 10 ppm.
Seal cooler data sheet shall be submitted to PETROBRAS for approval. Both actual and
design seal cooler heat loads shall be informed.
4.5.4.1.7 (Substitution)
Reservoir shall be equipped with a pressure switch and a pressure gauge sensing the vapor
space above the high liquid level (HLL). A low pressure alarm switch shall be used for
pressurized dual seal arrangements equipped with a barrier fluid reservoir and a high
pressure switch (with contacts for alert and danger) shall be used for unpressurized dual seal
arrangements with buffer fluid reservoir.
4.5.4.1.8 (Substitution)
The reservoir shall be equipped with a low level alarm (LLA) switch and, when specified, a
high level switch (with contacts for alert and danger), to actuate in the event of reservoir level
increase due to a failure of the primary seal of an unpressurized dual seal arrangement.
4.6.2.4 (Addition)
The seal chamber outlet connection shall be tangentially drilled in order to improve the
pumping effect of the ring (if ring is of the radial type), and shall be located as far as possible
from the seal faces, while the cold seal liquid inlet connection shall be located near the seal
faces.
7
N-2543 REV. A ENGLISH AUG / 2005
6.3 Testing
6.3.5.1.2 (Modification)
Unless formally requested by pump vendor and/or seal manufacturer (see 7.2.3 of this
Standard) and approved by PETROBRAS, the seal (or seals) shall not have any visible signs
of leakage during any phase of the pump performance test.
7.2 Proposals
7.2.3 (New)
Seal manufacturer is required to note on the proposal data sheets the expected or
guaranteed maximum leakage rates of the quoted seal, both at shop testing (with water) and
at job site, under rated operating conditions. See also 6.3.5.1.2 of this Standard.
Add the following plan (plan 14) same as API STD 610 / 8th edition:
8
N-2543 REV. A ENGLISH AUG / 2005
300 mm TO SUCTION
(12")
MÍN Q D/L
F1
FO
FROM DISCHARGE
TO PUMP SUCTION
FO
FI Q/D/L
NOTE: RECIRCULATION FROM PUMP DISCHARGE THROUGH A FLOW CONTROL ORIFICE (WHEN NECESSARY) TO THE
SEAL AND BACK TO THE SUCTION NOZZLE. THE ORIFICE IS TO BE SIZED IN ACCORDANCE WITH THE THROAT
BUSHING AND THE RETURN LINE. SIMILAR TO PLAN 11 BUT FLOW BACK TO SUCTION SIDE WILL EVACUATE
VAPORS THAT MAY COLLECT IN SEAL CHAMBER. RECOMMENDED IN LIGHT HYDROCARBON SERVICE.
L.1 The seal application chart (SAC) shall be considered as a general guidance regarding
mechanical seals selection and, therefore, should be consulted whenever a particular SAC
regarding the plant where the pump is to be installed is not available.
L.2 The chart 1 shall be considered for either new or existent pumps that are not in
accordance with API Standards 682 and 610 (7th and 8th editions) and their respective
PETROBRAS’ supplementary specifications.
L.3 The chart 2 shall be considered for either new or existent pumps that fully comply with
API Standards 682 and 610 (7th and/or 8th editions) and their respective PETROBRAS’
supplementary specifications.
9
N-2543 REV. A ENGLISH AUG / 2005
CHART 1
17.25 34.5
CHART 2
17.25 34.5
____________
10
N-2543 REV. A ENGLISH AUG / 2005
INDEX OF REVISIONS
REV. A
Affected Parts Description of Alteration
Revalidation
_____________
IR 1/1