Option-2: Re-design or Re-balance the existing line with more number of labors
Worker Worker1 Worker2 Worker3 Worker4 Worker5 Worker6 Worker7 Worker8 Worker9
Activities 2 1,5 4,7 3,8 12,11,6 16,9,15 13 10 14
Work Content 50 50 60 60 60 60 50 40 50
Choice Between Option-1 and Option-2? option-1 as it is cheaper . Assuming payment of OT for 1.167 Hours only.
Assume payment of OT for 2 Hours then which option is better?
Daily savings in Option-2 over Option-1 132 Rs/ day
Time required to recover training cost? 90.91 days
Recommendation? If new requirement would continue for more than 91 days then Option-2 Is better
else option-1 is better….
Option-3: Re-design or Re-balance the existing line with more number of labors, Using Paralel Workstations
Release
Unit time worker-1 worker-2
1st 0 120
2nd 60 180 60
3rd 120 240 60
4th 180 300 60