Professional Documents
Culture Documents
PART 1 - GENERAL
1.1 DESCRIPTION:
A. The work under this Section consists of furnishing and installation of chilled water
piping system as indicated on the drawings and as specified herein.
1.2 REFERENCES:
ASTM A 234 Piping Fittings of Wrought Carbon Steel and Alloy Steel for
Moderate and Elevated Temperatures.
ANSI B16.1 Cast Iron Flanges and Flanged Fittings, Classes 25, 125,
250 and 800.
ANSI B16.5 Pipe Flanges and Flanged Fittings, Steel Nickel Alloy and
Other Special Alloys.
BS 143 Malleable Cast Iron and Cast Copper Alloy threaded Pipe
Fittings.
BS 5154 Copper alloy Globe, Globe Stop, and Check, Check and
Gate valves
F. HI - Hydraulic Institute:
1.3 SUBMITTALS:
B. Shop Drawings: Submit scaled layout drawings of chilled water piping and fittings
including, but not necessarily limited to, pipe sizes, location, elevations and slopes
of horizontal runs, wall and floor penetrations, and connections. Show interface
and spatial relationship between piping and proximate equipment.
D. Maintenance Data: Submit maintenance data and parts lists for chilled water piping
materials and products. Include this data, product data, shop drawings, and record
drawings in maintenance manual.
1.4 WARRANTY:
A. Submit written guarantee signed by the contractor and manufacturer for the period
of 1 year from the date of substantial completion. The guarantee shall cover the
repair and replacement of defective materials and workmanship as directed by the
Engineer. If manufacturer warranties any equipment for more than one year as a
standard practice such warranties shall also be submitted.
A. Pipes
1. Pipes for above ground installation shall be seamless Black steel, Schedule
40, conforming to ASTM A 53, with beveled ends.
B. Fittings:
1. Install above ground black steel pipes with threaded joints and fittings for 50
mm and smaller, and with VICTAULIC or approved equal fittings for 65 mm or
larger pipes. Fittings for all preinsulated piping shall be by Victaulic. Type of
Victaulic fittings shall be as recommended by Victaulic manufacturer and
approved by the Engineer.
2. Dielectric Union: Threaded or soldered end connections for the pipe material
in which installed; constructed to isolate dissimilar materials, prevent galvanic
action, and prevent corrosion.
3. Flexible Connectors: Stainless steel bellows with woven flexible bronze wire
reinforcing protective jacket; minimum 1035 kPa working pressure, maximum
120oC operating temperature. Connectors shall have flanged or threaded end
connections to match equipment connected; and shall be capable of 19 mm
misalignment.
5. Welding Materials (Where required): Comply with Section II, Part C ASME
Boiler and Pressure Vessel Code for welding materials appropriate for wall
thickness and chemical analysis of pipe material being used.
2. Circuit Setters: A calibrated balance valve equipped with readout valves and
provided with differential pressure meter.
3. Self Contained Flow Control Valves: Class 150, cast iron housing, stainless
steel operating parts; threaded connections for 50 mm and smaller, flanged
connection for 65 mm and larger. Factory set to automatically control flow
rates within plus or minus 5 percent design, while compensating for system
operating pressure differential. Provide quick disconnect valves for flow
measuring equipment. Provide a metal identification tag with chain for each
valve, factory marked with the zone identification, valve model number, and
rate flow in m3/min.
E. Piping Specialties:
1. Manual Air Vent: Bronze body and non-ferrous internal parts; 1035 kPa
working pressure, 110 oC operating temperature; manually operated with
screw-driver or thumb-screws; and having 3 mm discharge connection and 13
mm inlet connection.
3. Pressure and Temperature Taps: Install pressure and temperature taps at all
coil connections across two port valves, pumps, chiller evaporator, or
otherwise as indicated:
b. Furnish No. 500 pressure gauge adapters with 3-8 mm probe and No.
701, 125 mm stem pocket thermometers with - 5 o to 50o range for chilled
water.
A. Size and number as indicated; construct of welded carbon steel for 850 kPa
working pressure, 190 0C maximum operating temperature. Separate air charge
from system water to maintain design expansion capacity, by means of a flexible
diaphragm securely sealed into tank. Provide taps for pressure gauge and air
charging fitting, and drain fitting. Support vertical tanks with legs or base; support
horizontal tanks with steel saddles. Tank, with taps and supports, shall be
constructed, tested, and labeled in accordance with ASME Pressure Vessel Code,
Section VIII, Division 1.
A. Provide pressure relief valve and automatic cold sweet water fill assembly complete
with pressure reducing valve, after meter arrester, sight glass, backflow preventer
with test cocks, water filter, vacuum breaker and valved by-pass.
A. Type: The air release tank shall be of the in-the-pipe-line type with tangential
openings for water in and out. The inside shall be specifically designed to create a
low velocity vortex for the separation of free air from the water stream.
B. Size: The size of the air release tank shall be based on the line size of the pipe
shown on the drawings.
C. Shell: The shell shall be constructed of welded carbon steel; ASME constructed
and labeled for 8.78 kg/cm 2 (850 kPa) water working pressure and 190 0C operating
temperature.
D. Strainer: The tank shall be equipped with an internal steel strainer with perforations
sized for water flow. The strainer shall be installed in a location of assist in the
separation of air. The strainer shall be removable from the bottom by unbolting the
steel bolt heads.
E. Drain: The tank shall be equipped with a bottom drain and this drain shall be piped
to the nearest open site drain. The drain line shall be equipped with a gate valve
and a union to facilitate the removal of the strainer.
A. General:
2. The selection of pump type and pump drive shall be based on each specific
3. Pump Q-TDH curve shall be such that it provides stable operation for the
pump when operating at any point on the curve. Shut-off head shall be
approximately 25 to 35 percent above the rated head.
5. For pumps with variable speed drive, the control system shall include as a
minimum, the programmable logic pump controller, adjustable frequency
drive(s) and remote sensor/transmitter as required. All additional items
required to properly execute the sequence of operation shall be provided.
C. Chilled water pump being the integrated component of pipe work shall be split
couple vertical inline or horizontal split-case type as shown on drawings and
equipped with mechanical seals. Specific pump ratings and types shall be as
indicated on plans. Pump shall be split coupled type with rigid spacer type coupling.
D. Pump and motor shall be mounted on a high grade, heat-treated cast-iron common
baseplate and shall be installed with suction guides. Pump motor shall be TEFC
Class ‘F’.
E. Casing: Cast iron, split volume, double suction, rated for greater than 10.54 kg/cm o
(150 psi) actual working discharge pressure, with renewable bronze wearing rings,
flanged suction and discharge connections and shall be drilled and tapped for seal
flange and gauge connections..
F. Impeller: Bronze enclosed double suction type, keyed to shaft with a slightly press
and suitable lock-nut arrangement.
H. Drive: Split coupling with space between the shafts sufficient to replace mechanical
seal without disturbing pump or motor coupling guard.
J. Mechanical seal shall be stainless steel multi-spring balance type with secondary
seal suitable for specific application and shall be accessible and easily replaceable
type.
L. The manufacturer shall submit certificate, including test data to show that pump
meets performance specifications.
B. The Contractor shall supply and/or install the water treatment facilities and
chemicals as listed below. Chemicals shall be specially formulated to prevent
accumulation of scale and corrosion in piping system and connected equipment,
developed based on a water analysis of make-up water.
1. Chemical pot feeder complete with sampling point and valving as indicated.
2. Corrosion scale and electrolytic action inhibiter dosing in the chilled water
system.
3. Test Kit.
4. Carry out tests on local water necessary to finalize details of the water
treatment.
C. Treatment:
1. Thoroughly clean and system of oil grease and swarf deposits using an
approved soluble solvent in accordance with the manufacturer's instructions.
2. Circulate the solution for at least one hour, drain and then flush system
thorough with fresh water.
3. Does system with corrosion and electrolytic action and scale inhibitor.
D. Handover:
1. The Contractor shall supply a test kit and instruct the user in its use.
3. Prior to handover, the Contractor shall carry out his own tests and ensure the
system is correctly dosed.
2.7 INSULATION:
3.1 INSTALLATION:
A. Refer to Section BASIC PIPING MATERIALS AND METHODS for basic piping
installation instructions. Refer to the drawings for further details. The entire chilled
water system installation shall conform to the requirements of ASME B 31.9
Building Services Piping, IAPMO Uniform Mechanical Code, ARI Standard 260, and
ANSI B 9.1, or equivalent.
B. Install above ground black steel pipes with threaded joints and fittings for 50 mm
and smaller, and with Victaulic fittings for 65 mm or larger.
For underground pre-insulated pipe use Victaulic fittings. Provide concrete support
at the interval of maximum 4000 mm, at both sides of coupling and at change of
direction. Provide concrete thrust blocks at each change of direction. Details of
concrete support and thrust block shall be as approved by the Engineer.
C. Proper foundations for mounting of piping system shall be provided, including
supports, vibration isolators, guides, anchors, clamps and brackets.
E. If oil grease lubricated bearings are supplied with the pumps, the oiler shall be filled
with the specified lubricating oil, or bearings shall be pre-lubricated with specified
grease prior to start-up.
F. Field testing of the pumps shall be performed at the time of overall system start-up
and testing. Installed pumps shall meet the performance specifications.
H. Air Vents: Provide at all changes in elevation downward in direction of flow. Except
where shown, provide automatic air vents. Also provide air vents at system high
points.
I. The air separator shall be installed dead level in both directions and shall be
supported from the structure so that all pipes can be removed without moving the
air separator. The separator shall be installed so that the strainer can be removed
without moving the tank.
J. The chilled water piping, valves, fittings, separator and expansion tank shall be
insulated as per Section MECHANICAL INSULATION.
1. Water for the chiller system shall be chemically analyzed and shall be treated
to insure its suitability as the permanent system charge. Additional water
treatment shall be provided whenever required after final analysis at no
additional cost to Owner.
A. Preparation for testing: Prepare chilled water piping in accordance with ASME B
31.9 and as follows:
1. Leave joints uninsulated and exposed for examination during the test.
2. Provide temporary restraints for expansion joints which cannot sustain the
reactions due to test pressure.
4. Isolate equipment that is not to be subjected to the test pressure from the
piping.
5. Install relief valve set at a pressure no more than 1/3 higher than the test
pressure, to protect against damage by expansion of liquid or other source
of over pressure during the test.
2. Use vents installed at high points in the system to release trapped air while
filling the system. Use drains installed at low points for complete removal of
the that liquid.
4. After the hydrostatic test pressure has been applied for at least 10 minutes,
examine piping, joints, and connections for leakage. Eliminate leaks by
tightening, repairing, or replacing components as appropriate, and repeat
hydrostatic test until there are no leaks.
A. Clean and flush chilled water piping system. Remove, clean, and replace strainer
B. Mark calibrated name plates of pump discharge valve after chilled water system
balancing has been completed, to permanently indicate final balanced position.
D. Check expansion tanks to determine that they are not air bound and that the
system is completely full of water.