[i] ACTIVITY PROGRAMME


Design and printing information posters T-shirts and billboards to be placed to the public places both
on and
off side e.g. restaurants, bars guest houses
etc

Resources unit type unit type Unit cost Total cost


(TZs) (TZs)

Installation of billboard 6,300,000.


9 pc 1 each 700,000.00 00
Design and printing poster 2,900,000.
580 pc 1 each 5,000.00 00
Design and printing T-shirt 3,400,000.
200 pc 1 each 17,000.00 00
Transport hire for distribution 600,000.
400 pc 1 each 1,500.00 00
Sub total           13,200,000.
00

[ii] ACTIVITY PROGRAMME


Conducting training to peer heath educators (reference people) drawn from village along side the
project and
train them on HIV /AID and STI issues for discussion with colleague

Resources Unit type unit type Unit cost Total cost


(TZs) (TZs)
Facilitation allowance 2,952,000.
4 Person 9 days 82,000.00 00
Transport hire 600,000.
400 km 1 each 1,500.00 00
Printing of training manual 2,840,000.
568 pc 1 each 5,000.00 00
Tats stationeries 720,000.
120 Person 1 each 6,000.00 00
Sub total          
7,112,000.00

1
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION

[iii] ACTIVITY PROGRAMME


To explore the community alongside the project ,select and train non health works including people
living with
HIV for mobilization counseling and testing at community
level

Resources unit type unit type unit cost Total cost


(TZs) (TZs)
Facilitation ąllowance
4 Person 9 days 82,000.00 2,952,000.00
Printing of training manual
112 pc 1 each 500.00 56,000.00
Transport hire
400 km 1 each 15,000.00 6,000,000.00
Tots stationeries
150 Person 1 each 6,000.00 900,000.00
Procurements of gests kits of
bioline and determine 8 carton 5 days 50,000.00 2,000,000.00
Sub total          
11,908,000.00

[iv]ACTIVITY PROGRAMME
Empower girls and women alongside project area to negotiate safer sex through enhancing
knowledge about sexuality and imparting life skills which increase their effective control to
protect themselves against HIV/AIDS and conduct VTC services

Resources unit type unit type Unit cost Total cost


TZs) (TZs)
Facilitation allowance 4 Person 9 days 82,000.00 2,952,000.00

Facilitation aIIowat1ce 4 Person 9 each 82,000.00 2,952,000.00


medical staff
Transport hire 400 km 1 each 1,500.00 600,000.00
Picture 25 pc 9 each 2,000.00 450,000.00
Tots stationeries 45 Person 1 days 6,000.00 270,000.00
Sub total           7,224,000.0
0

[v]ACTIVITY PROGRAMME
2
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION

Conduct HIV/AID training for schools clubs and mobile cinema presentation in selected centres

Resources unit type unit type Unit Total cost


cost(TZs ) (TZs)
Hire mobile cinema truckers 700,0
and its facilities 1 group 2 days 00.00 1,400,000.00
Facilitation allowance 82,00
4 Person 6 days 0.00 1,968,000.00
Printing of training manual 5,0
297 pc 1 Each 00.00 1,485,000.00
Transport hire 1,
400 km 1 each 500.00 600,000.00
Sub total           5,453,000.
00

[vi] ACTIVITY PROGRAMME

To promote increase access to HIV preventive information,access friendly testing ,counseling


,STI Services for vulnerable people ,train volunteers on condom distribution networks/outlets
for condoms social marketing

Resources unit type unit type Unit Total cost


cost(TZs) (TZs)
             
Facilitation cost 2,952,000.
4 Person 9 days 82,000.00 00
Procurement of male condom 1,120,000.
56 cartons 1 each 20,000.00 00
Procurement of male condom 1,100,000.
50 cartons 1 each 22,000.00 00
Transport hire 600,000.
400 km 1 each 1,500.00 00
Procurement of gents kits 2,000,000.
bioline and determine 25 cartons 2 days 40,000.00 00
Sub total          
7,772,000.00

[vii] ACTIVITY PROGRAMME


Conduct training to non health workers on ARV and prevent mother to child transmission issues and its
applicability
3
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION

Resources unit type unit type Unit Total cost


coast(TZs (TZs)
)
Facilitation allowance
4 Person 9 days 82,000.00 2,952,000.00
Transport hire
400 km 1 each 1,500.00 600,000.00
Printing of training manual
102 pc 1 each 5,000.00 510,000.00
Tots stationeries
150 Person 1 each 5,000.00 750,000.00
Subtotal          
4,812,000.00

[viii] ACTIVITY PROGRAMME


Conduct training spiritual leaders to perticipate in monthly and semi annual support group
meeting

Resources unit type unit type Uñit Total


cost(TZs) cost(TZs)
Facilitation allowance 2,952,000.
4 Person 9 days 82,000.00 00
Transport hire 600,000.
400 km 1 each 1,500.00 00
Printing of training manual 310,000.
62 pc 1 each 5,000.00 00
Tots stationeries 250,000.
50 Person 1 each 5,000.00 00
Sub total           4,112,000.
00

[ix] ACTIVITY PROGRAMME


To promote events eg footbal matches to encorage openness and discussion of HIV/AIDS
issues
4
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION

Resources unit type unit type Unit Total cost


cost(TZs (TZs}
Facilitation cost
4 Person 9 days 82,000.00 2,952,000.00
Purchasing of sports gears 106,0
10 balls 1 each 00.00 1,060,000.00
Transport hire 1,5
400 km 1 each 00.00 600,000.00
Sub total          
4,612,000.00

[x] ACTIVITY PROGRAMME


Monitoring evaluating learning and documentation organize information sharing meeting with
key stakeholders on quarterly basis to monitor the performance of this programme

Resources unit type unit type unit Total


Cost(TZs) cost(TZs)
             
Facilitation allowance medical
staff 2 Person 9 day 82,000.00 1,476,000.00
Facilitation allowance
organization staff 4 Person 4 day 82,000.00 1,312,000.00
Transport hire
400 km 1 day 1,375.00 550,000.00
Film editing and CD printing
35 pc 1 each 43,000.00 1,505,000.00
Facilitation allowance medic
people 4 Person 9 each 82,000.00 2,952,000.00
Sub Total          
7,795,000.00

Grand Total Activity Budget           74,000,000.00


             
Total Project value for HIV Training
and awareness for 24 months as per
contract         74,000,000.00

5
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION

GENERAL REÇUIREMENTS
1. HIV/AIDS awareness campaign
2. HIV / AIDS preventative campaign
3. HIV/ AIDS Training

OBJECTIVES
The Objectives is to reduce risk of exposure to and spread of the HIV Virus in
the area of road constructions. The target group will be local labors and their
supervisors employed by the works contractor and the associated community will
benefit through their normal day to day interaction with the target groups.

SCOPE ACTIVITIES
Activities for HIV / AIDS awareness prevention and training will be broad based
targeting, both individual and groups

OUTPUT 1: Expansion of work place interventions with special attention for


construction workers and other mobile population along Road construction project
LOT:1. RUANGWA – NANGANGA ROAD SECTION 52 KM

Strategy 1: Capacity building on safer sexual behavior among general population,


company workers, through peer education, community mobilization and culturally
sensitive information education and communication sports.

Strategy 2: Improve person protection by Promotion events such as Condom


and supply to the outlets, provision of IEC materials, billboard, T-shirts, caps and
fliers with HIV/ AIDS messages.

6
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION

Activity Budgets
S/N MONTH , YEAR PLACE ACTIVITIES TARGET AMOUNT

1: MAY, SEP. 2021 KITANDI To design & printing 2000 community members
NOV LIKUNJA, information posters, T- alongside road construction project
NKOWE shirt and billboards to be in the in targeted communities will
JAN, MAR, 2022 placed to the public acquire knowledge on safer sex
NAMAHEMA,
MAY, SEP,
NANDAGALA, places both on and off practices and life skills to protect
OCT site (eating houses, bars themselves against HIV/AIDS
CHIMBILA B,
MICHENGA, AND guest houses vehicles infection
JAN AND 202 NANGUMBU etc) 13,200,000
APRIL
2. JULY, 2021 KITANDI
NOVEMBE LIKUNJA, Conduct training to Direct training to peer health
R, NKOWE peer health educator educators drawn from company
DEC NAMAHEMA, (reference people) stay and communities alongside
MARCH, 2022 NANDANGALA, drawn from 8 village road construction project 7,112,000
JULY, CHIMBILA B, alongside the project
NOVEMBE MICHENGA, AND and train them on
R, NANGUMBU HIV/AIDS and STI issue
for discussion with
colleagues.

7
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION
3. AUGUST, 2021 KITANDI To explore the Direct training to 150 non health
OCTOBER, LIKUNJA, community alongside workers ’ for mobilization and
NKOWE the project select train counseling and testing to 192
JANUARY, 2022 NAMAHEMA, 150 non health workers people 92 project stay and 100
APRIL, NANDAGALA, including people with communities shall attend VCT.
SEPTEMBE CHIMBILA B, living HIV for 11,908,000
R AND MICHENGA, AND mobilization ,counseling
NOVEMBE NANGUMBU and testing at
R community and family
level appropriates

8
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION

Activity Budgets
4. JUNE, 2021 KITANDI Empower women and The girls and women will educated
OCTOBER, LIKUNJA, girls alongside the on HIV/AIDS infection and
NKOWE project sites to negotiate negotiate safer sex of condom use
FEBRUAR, 2022
NAMAHEMA, safer sex through
APRIL' 7,224,000
NANGANGALA, enhancing knowledge
JUNE,
CHIMBALA B, about sexuality and
OCTOBER,
MICHENGA, AND imparting life skills which
NOVEMBE
NANGUMBU increase their effective
R,
control to protect
themselves against
HIV/AIDS and conduct
VCT services.

5. MAY,JULY 2021 KITANDI, LIKU Conduct HIV/AIDS To conduct HIV education through
SEPT,DEC NJA,NIKOWE, education to school sports gears promotion and
NAMAHEMA, children clubs and posters
MAY, AUG 2022 NANDAGALA, mobile cinema
NOV, CHIMBALA A, representation 5,453,000
CHIMBALA B,
MICHENGA ,
NA NGUMBU
6. JULY,AUG 2021 KITANDI To promote increased 600 project workers and
NOVEMBE LIKUNJA, access to HIV/AIDS communities will benefit for
R, NKOWE preventative information voluntary counseling and testing
FENRUARY 2022 NAMAHEMA, and services IES for HIV/AIDS and 105 car tons of
NANGANGA , condom access peer condoms will be distributed.
MARCH, CHIMBALA B, education, friendly 7,772,000
JUNE,JULY

9
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION
OCTOBER 2022 MICHENGA, AND testing and counseling
NANGUMBU and STI services for
vulnerable population
train volunteers and
condom distribution safe
sexual practice and
establish condom
7. JUNE,AUG 2021 KITANDI To conduct training to 25 non health staff shall be trained
UST LIKUNJA, 150 non health workers on ARV and prevention mother to
FEBRUARY 2022 NKOWE on ARV and prevention child transmission
NAMAHEMA, mother to children 4,812,000
APRIL, NANDAGALA, transmission issue and
AUGUST, CHIMBILA B, its applicability
NOVEMBE MICHENGA, AND
R NANGUMBU

8. MAY,OCTO 2021 KITANDI Conduct training to 50 50 spiritual leaders shall be trained


BER LIKUNJA, spiritual leaders to on HIV/AIDS issue and shall be all
NOVEMBER NKOWE participate in monthly to participate on community
NAMAHEMA, and semiannual support awareness 4,112,000
JUNE,SEPT 2022 NANDAGALA, groups meeting
EM CHIMBILA B,
BER,OCTO MICHENGA, AND
BER NANGUMBU

9. JUNE,SEPT 2021 KITANDI, LIKU To promote events such 10 balls will promoted to
NJA,NKOWE as footballs matches community youth together with
JANUARY, 2022 NAMAHEMA, and to encourages some school children to 4,612,000
MAY NANDAGALA, openness and encourage openness and
JULY,NOV. CHIMBILA. A, discussion of HIV/AIDS discussion
CHIMBILA. B, issue
MICHENGA
NANGUMBU

10
中铁十五局集团有限公司
CHINA RAILWAY 15 BUREAU GROUP CORPORATION
10. MAY. 2021 NJA,NIKOWE Monitoring valuating Documentary pictures shall be
TO NAMAHEMA, learning and produced to show the project
APRIL. 2022 NANDAGALA, documentation organise performance
CHIMBILA, A, information sharing
CHIMBILA.: B, meeting with key stake 7,795,000
MICHENGA NA holder on quarterly basis
NGUMBU to monitor the
performance of this
objectives

11