You are on page 1of 1

Project: Maintenance Work for International School of Creative Science, Muwaileh , Sharjha , UAE

Client : Beam Group Shr

MAINTENANCE COMPLETION SCHEDULE


Plan
Sl Activity Description Unit Action Plan Scope of Work Manpower Days % Plan % Done Remarks
Start Date Work Period Finish Date

Phase 3 G floor External building wall Repairing of the lower part of the wall (the base) around
damaged at floor level Repairing of the wall around the External building Wall damaged at floor level
1 LS the building. Commencemnt Date 15 Days - 8 100% 0%
building Quantity: approx 27 panels and 5 columns
Phase 1 Ground floor External building
2 wall damaged at G level LS Need to repaired Need to repaired Commencemnt Date 10 Days - 4 100% 0% External building Wall damaged at G level

Phase 3 & 5 Ground floor Play area wall


and bridge Wall damaged at various
3 location LS Need to repair/ install new cladding Need to repair/ install new cladding Commencemnt Date 10 Days - 2 100% 0% Wall damaged at various location

Phase 6 Ground Floor Hot Oven Side


Boundary wall mis aligned and moved Need to fix the Slabs with required Demolition of 3 panels and re construct reinforced Boundary wall mis aligned and moved from it original
4 LS Commencemnt Date 20 Days - 4 100% 0%
from it original position modification works concrete wallwith the same of existing finish position

Need to build a ramp as per the Provide ramp with proper slope including the side wall, Provide ramp with proper slope including the side wall,
Phase 2 Ground floor Reception ,New
5 ramp LS opposite side ; requested by Principal required backfilling, concrete screed finish with granite on Commencemnt Date 5 Days - 4 100% 0% required backfilling, concrete screed finish with granite
to enhance pick up & drop of kids top on top

You might also like