Professional Documents
Culture Documents
IN SURFACE EXCAVATIONS
CODE OF PRACTICE
1989
CODE OF PRACTICE
1989
Although every effort has been mad� to e�sure tha(the information and data present
ed in this Code of Practice are correct, neither the Geotechnical Division nor the South
African Institution of Civil Engineers are responsible for any errors and omissions, nor
for any consequences resulting from these errors, omissions, etc. The views expreSSed
in this Handbook are not necessarily those of the Geotechnical Division nor the South
African Institution d Civil Engineers.
CM McMILLAN
SAICE President, 1988 March 1989
MEMBERS OF THE
COMMITTEE
ACKNOWLEDGEMENTS
During 1966, a group of individual engineers held discussions with the City Engineer
of Johannesburg with a view to clarifying problems related to the safety of excavations
tor deep basements.
Arising from these discussions, a symposium on deep basements, organised by
the Johannesburg Branch of the South African Institution of Civil Engineers in
association with the Structural Division, was held in August 1967. The symposium
aroused national interest and the proceedings were published.1
At the conclusion of the symposium it was suggested that a Committee be
established to draft a code of practice for lateral support which would be applicable
to the whole of the Republic.
2
The Committee consisted of members of the interested Technical Divisions of
the Institution, and was assisted by a practising barrister and by insurance brokers
and underwriters.
When it became apparent that the Committee could not hope to complete the
task in a reasonable period, a co-ordinating editor was appointed. 3 It is due to his
persistence that the code has seen the light of day.
It is not intended that this code be the final word on lateral support; rather that
it will be used, amended and updated by all engineers engaged in the design,
construction and monitoring of lateral support works. The Institution hopes it will
serve the purpose for which it was prepard, namely to provide safe and consistent
guidelines to engineers.
To the best of the Council's knowledge no similar specific code of practice relating
to lateral support exists anywhere in the world.
1.1 SCOPE · · · · ···· ··· · ······ ··· · ········ · ······· · ···· ·· ······ · · · · · ····· 1
2.1
-
INTRODUCTION ...... :........................................
• • •: • •
7
SYSTEM OF LATERAL
CHAPTER 3: SELECTION OF A ................. 15
SUPPORT................................................
4.1 INTRODUCTION............................................... 31
4.4.1 . General.................................................. 35
4.4.2 Movements required to develop active
and passive earth pressures.................. 36
4.12.1 General.................................................. 48
4.12.2 Failure mechanisms and methods of
analysis ................................................. 49
5.1 INTRODUCTION............................................. 53
5.1.1 General................................................ 53
5.1.2 Design objectives................................. 53
S.1.3 Deformations ....................... •............. .. 54
s.1.4 Factors of safety.................................. 54
.
5 . 2 1 General................................................ 56
s.2.2 cantilever wall systems....................... 58
5.2.3 Anchored wall sys tems........................ 58
5.2.4 Soil nailing........................................... 60
5.2.5 Strutted wall systems........................... 64
5.2.6 Underpinning ........... •• .... • .......... ••......... 65
5.5.1 General................................................ 73
5.5:2 ·. An�hors ............ ·:... :.·.�::.-........................ 74
5.5.3 �truts and rake rs................................. 75
·5. 5.4 Soldiers . . . .. ......... . . .......... . .. . ................. 76
5.5.5 Walers........... . . . . .............. .. ......... ......... 77
5.5.6 Lagging .... :........................................... 77
5 .5.7 Factors of_ safety................. :··.............. 79
5.6 MOVEMENTS................................................. 81
.5 .6.1 General................................................ 81
5.6.2 Effect of movement on adjacent
structures............................................. 81
5 .6.3 Effect of movement on buried services 83
5.6.4 Limiting deformations........................... 84
7. 1 INTRODUCTION............................................. 107
APPENDICES
APPENDIX A. STEP-BY-STEP GUIDELINES FOR
INVESTIGATION AND ACTION FOR LATERAL
SUPPORT OF A BUILDING BASEMENT.............. 123
TABLES
TABLE 1.1 Engineering an excavation .................................... 6
2.1 -investigation planning ....•....................................... 8
2.2 Factors to be investigated · during desk study and
preliminary field work .. : ............. ,:; ........................ . 9
4.1 Appropriate shear strength parameters for various
soil types..................... :......................................... 32
4.2 Wall movement {rotation about base of wall) required
to develop active and passive earth pressures...... 38
4.3 Coefficient of earth pressure at-rest (KJ................ 39
4.4 Equivalent fluid "densities" to be used in the
computation of minimum active thrust................... 43
4.5 Analysis methods for various failure modes........... 51
5.1 Th ickness of lagging........................................ ..... 79
5.2 Minimum safety factors recommended for design of
. ..
individual anchors ....................................... .... . ... 80
. 82
5.3 Permitted relative vertical movement.. ..................
6.1 Corrosion protection guide.................................... 93
Typical relaxation of stress in tendons.................. 94
6.2
.......... . 128
B.1 Laboratory tests on soils............................
·••············ 132
8.2 Field tests....................... •·•••••·••••·••·····•···
............. 134
8.3 Laboratory tests on rocks .........................
............... 136
C.1 Consistency of granular soils..................
c.2 Consistency of cohesiv e soils....... ............ ............. 137
· ··
g: �=�!:i�:?; ;��?��-_-;.:.;d ;;;i��-;i;����-�;;;;;i��:
;:
C.S Grain si ze class1fIcatIon........................... .............. 140
C.6 Hardness........................................ ....................... 14
1
F.1 Movements of anchored walls (Peck).................... 167
F.2 Movements of anchored walls - South African case
histories ............ ••••••••••······················· ••·••••............. 170
H.1 . Maximum particle velocities (vibration).................. 184
H.2 Maximum charge levels......................................... 18S
FIGURES
FIGURE . 3.1 Construction within an open _unsupported
excavation............................... ....... ....... ........ 18
3.2 Temporary support strutteq against central
dumpling....................................................... 18
3.3 Temporary support by fully braced trench..... 19
3.4 Fully braced temporary support ..................... : 19
3.5 Permanent wall constructed prior to excavation
(Diaphragm or contiguous augered pile) and
braced for central permanent construction.... 20
3.6 Ground anchors............................·.................. 21
3.7 Soil nailing..................................... : .... :......... 22
3.8 Rock bolts...............=...................................... 22
3.9 Cantilever walls............................................. 24
3.10 Caissons ............................................. �......... 25
3.11 Concurrent upward and downward construction 26
3.12 Unconventional methods of support.............. 29
3
which may exist and which may in any
or anyother restrictions ns on the property are
way influence the proposed operatio
accounted for.
be made available to the
c ies of these records should
ed by the owner/developer in
insu��r. if required, and retain
perpetuity. .
careful note should be taken of any requireme nts or
reg ulations laid down by local authorities and applicable to the
area where excavation is to be exec uted. The consent of any
owner whose property will be encroached upon by ground
anchors or underpin ning must be obtained.
Where blasting may be required, Appendix H should be
referred to.
1.3.3 Notifications
Notification of intention to excavate, accompanied by details
of the proposed system for lateral support and for any
underpinning required, should be submitted as e�rly as possible
to:
(a) Adjoining property owners .
(b) The local authority or township board engineer
(c) Insurance companies covering the works
(d) The Government Mining Engineer, where relevant.
1.3.4 Insurances
Prior to the commencement of- any open excavation it 'is strongly
recommended that provision be made for insurance against
possible damage and liability. The following points are listed
for guidance:
a) A provisional sum should be allowed for in any Bill of
Quantities to adequatelycover all insurance relating to the
removal of lateral support risk, to remain in force up to the
end of the construction contract, including the maintenance
period. The attention of the owner/developer should also
be drawn to his risk exposure thereafter in order that he
mayconsider the need to arrange the appropriate insurance
cover after completion of the contract.
b) Instructions to effect such insurance should be given in clear
and precise terms and the responsibility of the respective
parties should be clearly defined. (See Appendix E.)
Consideration should be given to the suggestion that the
owner arrange this insurance.
4
c) A phot?graphic record of exis
ting defects of adjoining
propert ies should be prepared and if possible, signed by
_
all partie s. (See Section 2.4.)
d) The terms, conditions and requirements (e.g. deductibles,
crack surveys, etc.) of the insurance should be agreed to
and understood by all interested parties, e.g. the owner,
con�ractors (including subcontractors), the geotechnical
engineer, professional team, etc., before the works are
commenced;
e) It may be necessary to provide insurers with full details of
the proposed method of lateral support, including, in the
case of major or complex basements, detailed drawings
showing adjacent properties or other relevant
features/photographs, etc.
5
AN EXCAVATION
TABLE 1.1 ENGINEERING
Activity Considerations/Comment;-
Step
No.
Structure, size, depth
-
1 Select dimensions of requirements, depth to good
excavation
soil, depth to float structure
stability requirements
--
construction and alter support for monitoring survey
as needed
(Based on Lambe (1970))
6
CHAPTER 2
SITE INVESTIGATION
2.1 INTRODUCTION ·
Site in�estigations for projects requiring late
ral support differ from
others m that they are concerned largely with cond
itions beyond the
�ite b?un?aries and above the proposed founding level. The site
mvest1gat1on should strive to identify those features which will have
a marked effect on the design of the lateral support system including
the shear strength of the supported ground, geological discontinuities,
adverse jointing and the presence of perched and permanent water
tables. Some of the approaches described are applicable to major
projects and may be inappropriate for smaller works.
While the techniques used for the investigation are similar to those
used for foundation investigations, the emphasis is different. Since
the consequences of overlooking important features can be disastrous,
it is essential that the investigation be well planned and executed and
that allocation of funds for this work should be commensurate wi�h
the risks involved. Adequate reporting on the results of the investigation
is essential.
(d) Groundwater:
P·revious pumping/recharge of groundwater
- Evidence of shallo�/perched wate� table eg. marsh vegetation,
water seepage, t3t�.
INVESTIGATION
2.4 DETAILED FIELD AND LABORATORY
2.4.1 Extent and Intensity
extends well
In most cases the influence of the excavation izontally. It
and hor
beyond the excavation itself both vertically
igation _to cove� not
is therefore necessary to extend the invest unding retained
surro
only the site of the works, but also the
9
. m te rial below the base of the excavation
material and the a ility of encountering unstable mat
. the possib erial�
Where. there IS particular attention
.
s h ou Id b .
e given to the
,·
on adJacent s tes ' · tes Wh ere gro un d anchors
. est1. gat·10 n on such adja cent si .
mv · ··
avio ur of the anc h or 1s sens1t 1ve to al
are emp I oyed , the beh • e strata deta1·1ed ·inve · g lot con
, sti a
ground cond·1 t,·ons and in vanabl o e ue account sh u d ibe
. or D o l
,s requir. ed 1- 0 the fixed anch z n 1.tin ·
taken °f ground disturbance
resu · g from mstaIIat,· on of
ta 1
b·1·t1 y o f the excavatio ·
se rvice s etc . on the ove rall s n or
behaviour of the anchors. . . rs .
. available . .
on a site for which little prevr ous data , a lr mtted
number of key boreholes or trial holes s � ould be su nk to
_
determine the stratigraphic sequence, the orientation of strata
and discontinuities and to identify those· strata of particular
significance either for anchor design or for overall stability.
These holes* may be located at th� site extremities and
conditions can initially be interpolated between holes. This
preliminary work can be followed by a more detailed phase of
the investigation which could include further holes and/or in situ
tests to confirm the predicted sequence and to obtain
representative information on strength and deformation
characteristics.
The investigation should ideally extend laterally a distance
equal to twice the d�pth of the excavation beyond the .
excavation perimeter and vertically either: • ! ..
(a) to a stable geological formation, or
(b) to a depth below which no underlying strata will affect the
design. (This may be as deep as one excavation width below
the base of the excavation.. )
Where rock is encountereq, it is· advisable to continue
investigation 3m or more into the rock to assess the ·degree of
weathering or jointing and to distinguish between boulders and
bedrock.
The number of holes depends on the variability of the strata,
!he area of t�e site and nature of the proposed works. Except
m the case of minor excavations in known conditions a
m1m . . mum of ,
three holes is recommended even on the smallest
?f sites In the absence of reliable previously record d
information : e
, a minimum of five holes is recommended for a
uniform site of 1 000m 2 and nine hole
recommendations are given for g ids for a 4 ooom2 site. These
bor�holes should be left to the disu ance and the spacing of
engineer or engineering geolo cretion of the geotechnical
gist.
• The term 'hole' is used In a
investigation and includes general :nse t o cover all type
test pits, uger h oles, and s of holes intended for subSurtace.
rotary core holes.
10
Particular
_ sets care should be exercised where steeply dipping
.Joint
or bedding planes are present in the rock mass. In
Johann�sburg, for example, it is usually the northern faces of
excavations which_
_ prove the greatest risk due to the generally
southward dip of the strata. In Pretoria, the strata dip north and
the south face is at risk. (Rohde 1983)
2.4.4 Sampling
In soils, the sample size and type will depend on the laboratory
tests envisaged, the type of material and method of
investigation. Various sampling techniques are described in
Giddings and Kantey (1979) and in BS 5930 (1981). As a guide,
where a continuous core is not recovered or the soil profile is
11
. the maximum vertical sp acing be twe
not inspected in situ ' . . en
istu rbe d samp les should b e . 1, 5m with intermediat
und e
. turbed samples at 0,75m. In variable ground
d1s . conditio n s .
, 1n
uous core recovery 1s recom me n de
situ profiling or contin d.
2.4.9 Monitoring
The horizontal and vertical movements and water levels within
and around the excavation should be monitored during
construction as described in Chapter 8. It is essential that
accurate initial readings be taken for the monitoring programme
before any constru ction work begins. Any activities on or near
the site which may influence the lateral support system must
also be monitored as described in Chapter 8.
2.6 REPORTS
2.6.1 Site investigation report
All investigations should be fully documented and all test results
should be reported so that the complete information on the tests
is available. Copies of these reports and data should be made
available to the engineer, tenderers. owner and architect. Where
relevant, the reports should be forwarded to the local data bank
and to any research organisation engaged in collection of data
or mapping of the area.
In the contract documents the engineer should not make
disclaimers about the validity of the geotechnical information
supplied.
13
2.6.2· Completion report
At the end of the main contract, a completion report on the
lateral support should be prepared including actual geological
conditions encountered, results of any additional inves tigations
carried out, any changes to the latera l support system, typical
anchor records, results of monitoring surveys etc. This report
should be forwarded to the own�r, - local authority an<;t loca l data
bank.
14
CHAPTER 3
SELECTION OF A SYSTEM
OF LATERAL· SUPPORT
3.1 INTRODUCTION
The selection of a lateral support system requires careful consideration
of all aspects of the proposed development, the site conditions and
adjacent structures. In most cases, these factors cannot be considered
in isolation and, together with economic considerations, interact to
yield an optimal solution to the satisfaction of the full professional team.
It is important that essential details of the proposed development
be established at a fairly early stage in the project. Such details include
geometry, depth of excavation relative to rockhead* and to the water
table, proximity to site boundaries and adjacent structures, intended
use of excavation, floor loading and permanence of lateral support,
amongst others. The acceptability of encroachment of temporary
structures or anchors beyond the site boundary must be considered
and permission obtained from adjacent land owners or the local
authority concerned. Changes to these essential details at a later stage
can significantly affect the suitability of the support system selected.
The systems of lateral support described below represent some of
the options available to the designer. Clearly, the nature of the
excavation will influence the extent and complexity of the support
measures required. For example, an excavation which is only 1,Sm
deep will hardly justify the use of some of the methods described below
or the detailed consideration given in this Code. Equally, the various
systems described in the remainder of this chapter and the
recommendations of this Code may be inadequate for very deep or
complex basements.
• 'Rockhead' In this context is taken to mean the upper surface of competent rpck.
15
influence the support require ments, cost of
excavati..on d 8pth will · ·
nst1cs of the· excavat·10n fl oor. Special
excavatio n and founding characte . .
.. prox1m1ty• of mme work"mgs.
cond1t1ons m ay exist in the cons,·derat,· on. The presence
The depth of the water table is a maJor _
may affe ct the. supp ort requirem ents, cost of the
of groundwater
proJe. c,t stability of the excav· ation floor, wor k"mg cond"t· I ions during
any permanent structures.
construction and the design of
If groundwater lowering is carried out, great care should be taken
to ensure that adjacent structures are not adversely affected. In certain
cases, it may be necessary to install a system of rec�arge wells near
the adjacent structures to avoid damag�_. Further details on dewatering
are given in Chapter 7.
In the case of basement construction, the founding characteristics
of the underlying material will influence the minimum required depth
of excavation. Where there is no distinct founding stratum, it may be
possible to 'float' the proposed structure by excavating to the depth
where the mass of material removed exceeds the mass of the structure.
Where saturated sands or soft clays are to be supported, continuous
support is often required in the form of diaphragm walls, contiguous
or secant piles, sheet piles or caissons. Most other support systems
require the material to stand unsupported over limited areas for short
periods while lagging or shotcrete is applied to the face.
If ground anchors are considered, it may be advisable as part of
the site investigation, to carry out proving tests on anchors installed
as described in Section 6.7.2. The results obtained from these tests
should be made available to interested tenderers.
-I___-
I
FIGURE 3.1 CONSTRUCTION WITHIN AN OPEN UNSUPPORTED EXCAVATION
II
II Reinforced concrete or gravity wall
---- II
II
UMPLING
FIGURE 3;2 TEMPORARY SUPPORT STRUTTED AGAINST CENTRAL D
18
3.�.3 Temporary support by fully braced trench (Figure 3.3)
This is suitable for excavations relatively large in area rather
than depth. Again the groundwater problem can be avoided if
sheet piling provides an effective seat in an underlying stratum.
This method is also slow and the wall has to be self supporting
when the base area is excavated. The wall also has to be boxed
out to allow for the bracing.
- .
FIGURE 3.3 TEMPORARY SUPPORT BY FULLY BRACED TRENCH
Permanent
retaining
---•
Temporary struts enable berm
wall to be removed before structural
frame is completed
·.
I
I
Shotcrete- �. Mesh
..·.·=·· �
J
:► •. ,; :· •
tl·-r>::
Grout or mechanical
anchorage
3.5.1 o Caissons
(Figure 3.10)
A caisson provides an u
e �a ation, but the sy nobstructed working face within the
stem is more suited to circular structures
�� ic � do not normally take the full adva
sit e. Extremely cautious ntage of the available
24 construction is required to achieve
verticality of positioning and because boulders can retard
construction, a thorough site investigation is required.
A large basem,:nt structure, usually circular in plan, may
be constructed, U!)'ing the caisson technique of concreting at
ground level and allowing the structure to sink during
excavation within its confines. The sinking of such a mammoth
caisson may be controlled in the early stages by hydraulic
jacking and may be facilitated by lubricating the contact
surface with the earth by suitable means, such as a bentonite
slurry. In addition, it may be feasible, depending on the size
of the structure, to construct floors at ground level
monolithically with the peripheral wall. Support to floors could
be provided by introducing temporary trussed girders at
suitable stages. Where floors are incorporated, it may be
possible to depart from the circular form.
Ground level
Bentonite skin to
reduce friction
Cutting edge
Simultaneous basement excavation
Superstructure in progress"""T,'"'\. :
.. _ . ...lLl.JL---�JL-�-�-JL 11
___ ...JL ... �- G
Concurrently. -,r :- - --,r-----,r----,r-
-3
-4
1
of the site, joined by four small radius arches near the
corners of the city block, referred to as abutment arches.
Suitable voic s were created behind the abutment arches
to enable cem\1nt grout to fill the zone behind them and
suitable grout stops were built- in to confine the grout to
these zones. The voids behind these abutment arches were
filled with cement grout and pressurised to induce an
inward deflection of these abutment arches and thus induce
an outward thrust in the flat arches that was greater than
the disturbing forces.
The site was excavated in successive stages of 6m and
each stage pressured as indicated above until the full depth
of approximately 30m was completed..
This method requires specialised knowledge and
techniques.by both designers and contractors, as well as
very careful monitoring.
28
Abutme nt arch formed by
gunite backing to soil and
voidage for grout entry -�
created before concreting
I
I
I
I
I
I
L---
__ .J c.:;;,---
_____)
Chemical or cement grouts _
injected Into ground to form
__,,__-r--
monolithic gravity type wall
Pressure grouting behind to act both as underpinning to
abutment arches induced existing structure and also form
inward thrust thus causing
stable material to excavation face
outward thrust on flat arches
(a) UNBRACED PERIPHERAL WALLS CONSTRUCTED FROM (b) CHEMICAL AND CEMENT GROUTS USED TO
THE TOP DOWNWARDS (& STABILISED BY GROUT JACKING) PROVIDE LATERAL SUPPORT
Water table
Freezing lance
Dry sand (cohesionless). Total stress; angle of friction. Shear box test. Test performed dry with sand
compacted to field density.
Moist or saturated sand Effective stress; angle of friction. Drained shear box test. Test performed saturated with sand
(cohesionless). compacted to field density. The
time to failure should exceed 10
min. to allow drainage.
Long term stability; Effective stress; Consolidated undrained triaxial test Test performed on saturated
failure taken as 10% strain in the with pore water pre�sure undisturbed samples with no
absence of a clearly defined peak measurements or consolidated drainage. Rate of testing sufficiently
shear stress. drained triaxial test. Soaked drained slow to allow 95% p.w.p. *
shear box test. equalisation during test 1
Fissured clay and over-consolidated Short term stability; Total stress; Quick unconsolidated undrained Test performed on saturated
materials. cohesion and friction angle at peak triaxial test. undisturbed samples with no
and residual strength. drainage.
Long term stability; Effective stress; Consolidated drained triaxial test, Test performed on undisturbed
cohesion and friction angle at peak drained shear box test or sample. Test at slow rate to allow
and residual strength. consolidated undrained triaxial test 95% dissipation of induced p.w.p. *
with p.w.p. * measurements.
Soaked drained shear box test with Residual strengtl] generally gives a
residual strength measurements. lower bound to the strength of
Ring shear apparatus. fissured or slickensided materials.
Partially saturated clays. Effective stress; cohesion and angle Consolidated undrained triaxial test Test performed on saturated
of friction. with p.w.p. * measurements. undisturbed samples. Test at slow
rate to allow 950/o dissipation of
induced p.w.p. *
Soaked drained shear box test. This will yield conservative results.
,� T
I
I \
\ I
I \
/
I I
I \
I
I
I PASSIVE ACTIVE w�
I
I
I
Kp
I
I
I
I
I
I
I
I �a
I
0
�p �a
No wall movements
Active
H
Ka "I H
I At-rest
H I
I Active
I
At-rest
H Active
39
Surcharge q
p ah = 0z + q) Kah . 2c Kah J
2
p h=
a
{122 + qz) Kah· 2c �Kahz
z
<2
2
Pph = ,r + qz) Kph + 2c JKphZ
• I • 2c )Kph I• 1zKph
Pph :\
(b) PASSIVE EARTH PRESSURE
FIGURE 4.3 ACTIVE AND PASSIVE EARTH PRESSURES FOR VERTICAL RETAINING WALLS
WITH HORIZONTAL BACKFILL ASSUMING NO WALL FRICTION (o = 0)
40
SIGN CONVENTION
ACTIVE CASE
PASSIVE CASE
z2
Pah = -1Ka h
2
1
p ah
cos ( ex -o ) p -P _1__
p - ph cos ( ex • 0 )
cos2 (0 + oc)
2
sin (0 + ,5 ) • sin (0 . /3 )
]
cos ( oc • ,5 ) . cos ( oc + /3 )
cos2 (0 -oc )
sin (0 + ,5 ) • sin (0 + f3 ) j2
cos ( oc + ,5 ) . cos ( (X + /3 �
TAKING ACCOUNT OF
FIGURE4
4 SSIV TH RUSTS FO R GRANULAR BACKFILL
TIVE AND PA
WALL' FR�TIO E ING BACKFILL
N, WALL INCLINATION AND SLOP 41
4.6.1 Active pressures - general guidance
The followin g guidelines may be applied to the calculation of
active pressure:
EQUIVALENT
DESIGN SITUATION . FLUID UNIT
WEIGHT (kN/m3)
(a) Where adequate measures are taken to
ensure no water pressures can act on the
structure or on the soil within the zone
affecting the structure, and provision is made
for immediate detection of any water pressure
build up . . ._ . 4,8
0,65 Ka1H
� ...1
Ka = tan2 (45 ° - !)
CLAY �, H
STABILITY NUMBER N =
Cu
(a) N>6 (b) N<4
Supports
�, 25H
DO. SH
H
0,?5H
V0, 2 1 H to
0.25H
I- 0,41H
--1
Further guidance may be obtained from Duncan and Seed {1986) and
Ingold {1979).
49
N
Great circle
representing·
slope face
N
Crest of slope
Great circle
representing
slope face
Direction of
sliding
Great circle representing
planes corresponding to
. -. ,� centre of pole concentration --=::.._�-.:::--4�
Great circle
representing
slope face
(d) TOPPLING FAILURE IN HARD ROCK WHICH CAN FORM COLUMNAR STRUCTURE
SEPARATED BY STEEPLY DIPPING DISCONTINUITIES
· 5.1.3 Deformations .
In the design of retaining structures, it may be important to
predict the deformations, wall deflections and ground
movements.
In general, deformations depend on a variety of parameters
such as the soil properties and conditions, construction method,
system of the structural support, its components and installation
· sequence, environmental . influences and = the time period
involved.
There are a number of numerical methods available to
calculate the deformations. ·. . -. •. : ·
Deformations can be predicted by applying finite element
methods with a minimum of simplifying assumptions. However,'
these are subject: to limitations arising from the inability to
quantify accurately the constitutive behaviour of the retained
material.' Numerous solutions . to practical · problems are
documented and may be referred to; i.e. Simpson et al (1979),
Clough (1975), etc: Subgrade reaction methods may be applied
for prediction of deformations taking account of the flexibility
of the structure and soil stiffness.· No information on surface
movements behind or in front of the structure can be provided
by this method. The Coulomb and Rankin·e theory, being a limit
_
analysis approach, cannot ·predict deformations.
Recommendations on allowable deformations and effects on
adjacent structures can be based on .case histories. (See
Section 5.6 and Appendix· F.) .. - . ,
d) Appropriate values
In deciding on an appropriate factor of safety, the foll owing
considerations should be taken into account:
- the method by which the factor of safety is incorporated
into the design calculation,
- the degree of confidence in the input parameters,
- the permanence of the structure,
- the consequences of failure.
No single design method is recommended in this Code as
it is always advisable that the result of any method employed
be checked against that of other methods.
It may be necessary to provide more lateral support than is
required to ensure an adequate factor of safety in order to meet
serviceability requirements such as the control of ground
movements.
Guidance is given in Sections 5.3.2 and 5.5.7 as to the
minimum factors of safety recommended for various design
situations. These guidelines make no allowance for exceptional
conditions resulting from excessive shocks, explosions,
seismicity, etc. which the designer should take into acc ount in
his design.
It may be necessary to reassess the factor of safety during
the construction period as further information on site conditions
becomes available.
5.2 DESIGN CONSIDERATIONS
5.2.1 General
Conventional design methods are usually based on the
evaluation of forces exerted by the supported material on the
structure. Generally, earth pressure theories and/or slop
e
Nut----...._
Face plate
PVC-sheath
Nut---...._
Face plate
Reinforcement mesh
F
actor of safety sf = ,=-
FNact
Nreq
�2. 0
IL smuCTURE (c = 0)
FIGURE 5.3 STABILITY ANALYSIS OF NAILED SO
63
carried out by a contractor experienced in soil nai
ling 1s a
fundamental requirement.
1
regular checks should be made and the required add
itional
supp�rt measures provided. This is most important for the
material above the uppermost level of struts.
5.2.6 Underpinning
Underpinning may be required in the following situations
associated with open excavations:
I I I J I I I Where:
Known
P is the surcharge;
W is the weight of sliding wedge = !, 1H 2 cotB;
T 1 is the density of wedge;
H is the depth of excavation;
A� S is the shear resistance of retained material
along plane of rupture (S = (c'H /sinB) + N tan a)');
A is the angle of inclination of anchor;
H 0· is the angle of shearing resistance of ground; ·
. c' is the cohesion of retained material.
Unknown
B is the angle of inclination of potential plane
Potential plane of rupture (B should be varied and plotted
against values of T);
of rupture
T is ttie anchor force.
T=
(P + 1 H/2) H cosB (Sf - cotB tan af) - c' H /sin� � ·.
sin (A+ B) tan(l)' + Sf cos (A+ B) ·, ·.: '. ·
' .
'
. \.... ' � :
. J
c'H/sinB + [(P + 1H/2) H cosB cotB +·r sin (A+ B)) tan 0·
I '
=
sf
(P + 1H/2) H cosB -T_cos (A+ 8)···
where
· =·
0 • - 25 • I . ·-=·= =·:=::: : ..:. •.
'Q· 4m
✓•
·
_-1-I-(I �r
7 ... --.....-.. ... �-
/ f �
/J"I .
I . Full resistance •.•
p
p
Equally spaced
j FIGURE 5. 7 SLIDING BLOCK METHOD OF ANALYSIS. [OSTERMAYER (1977)] (after BS 8081 (1989)]
or l, pp y g the
walls should be checked for each an�h leve a l in be
t he design procedure may
same procedure. Detailsdof ster
ob tained from Ranke an O mayer (1968) and Bureau
Securit as (1977).
Particul ar considerations �p�ly to �ed ge failures in rock,
th y ge. he
especially if a discont inuity 1s filled wi claye gou T f
strength of the rock mass is controlled by the strength o
the filling material. See Hoek and Bra� �1977), Hobst (1965)
and Hobst and Zajic (1982) for stabil ity analyses of rock
wedges.
N = ,.. .H
Cu
w here 'Y.H is the terr ace load and c
strength of the soil be Io ' u the quick undrained shear
w the excavation floor as measured under the
tota I overburden press
ure of:
Po = 1,25 'Y.H
If N < 3 0 no Si
'f•cant deformations are expecte
If N > 6 ,'0' 1 arge gnr
mo vements will occur and d. re
exists. ' the probab ility of failu
72
A wide and long exc�vatio
n is more susceptible
than a narr�w and relatively short one. to a floor failure
For excavations which ha
a bottom width between faces greater th ve
an H/2 and length of fac
greater than H , N should not exceed 5,0 e
. The value of N ma be
increased to 6,0 in special cases i.e., wher Y
e:
a) exce ptional care is exercised in the explor
ation and in the testing;
b) rebound of the excavation floor and d eforma
tions of the supporting
system components are carefully me
asured , provid ed the
requirements of Section 8.3.3 are fully com
plied with,
c) provision is made for suitable augmentation
of th e supporting
system where the field observations ind icate this
requirement.
The strengthening of the supporting system in this case
should
include heavy strutting and/or the use of anchors near the
bottom of
the face so as to arrest lateral movement of the supported material
towards the excavation. Replacem ent of material to form a berm
against the supporting structure may also be required . ·
For excavations having a bottom wid th between faces of less than
H/2 and/or length of face less than H , th e above requirements may
b e relaxed slightly but due·caution must still be observed.
In cohesionless soils, especially in fine grained materials subject
to a high water head, instability of the floor of the excavation ta��s
the form of piping or heave associated with ground water flow. �tab1hty
against piping should therefore be consid ered . (See also Section 7.3.)
5.5.2 Anchors
In the design of anchors, the.cross-sectional area of the tendo
and the fixed anchor length for _tt1e applied load have to b�
provided with an adequate margin �f safety. The total anchor
length should be in accordance_ with the block and overall
stab ility requirements. (See Section 5.3.)
Details on anchor construction, installation and testing are
provided in Chapter 6.
The positioning of the anchor heads at the. face of a wall is
often a function of constraints, imposed by the geometry of the
permanent structure.
Where the angle of inclination to the horizontal of an anchor
exceeds 20 degrees it will normally be necessary to consider
the need for vertical support at the excavation face; where this
angle of inclination exceeds 30 degrees, it will seldom be
feasible to dispense with such.vertical support. (Compare step
(c) in Section 5.2.1.) .
In the upper level of excavations; the maximum force in any
support or group of supports should not exc�ed the safe passive
resistance of the retained material. Account should be taken
of the t�mporary increase of force used for testing of anchors
·:.
(Section 6.7).
Load capacity and movement of each anchor within a group
arrangement depend on the location and spacing of the fixed
anchor zones.
Some general design recommendations on anchors are given
below. In rock, these measures may be relaxed depending on
the quality_ of the rock mass.
,,,------------:-1
·
.
-- Extent of zone of influence
_
Tie
.
(a) CORNER USING CROSS-OVER ANCHORS
.
Alternate fixed anchors in
differing horizontal zones
if spacing restricted
5.5.4 Soldiers
In the design of soldier piles, the maximum axial and bending
stresses should be considered. Generally, self-weight of the
member and the timber lagging may be ignored, but the axial
force induced by the earth pressure on the wall should be
included.
A n important design aspect is a check of shear stresses at
the location of the supports. In particular situations,considerable
shear forces are induced which require specific design
considerations.
Any reduction of the cross-sectional area of the pile such as
76
holes for anchors, fixing bolts or even corrosion in the case of
regained soldiers has to be taken into account.
A�count should be taken of stresses induced during handling,
particularly where long pile members are concerned.
Where site welding is used, the designer's expectations of
the quality of such welding must be reasonable and compatible
with the conditions under which such welding will be executed.
Structural continuity of the piles cannot normally be achieved
with site welding as opposed to shop welding.
Piles consisting of two structural steel sections such as
channels with their webs back to back must be connected at
both flanges with a sufficient number of tie plates spaced not
more than 1,5m apart.
Stresses and moments are usually calculated on the basis
of the theory of elasticity. In certain instances, soldiers need only
act as bearing members transferring the anchor load to the
supported face.
Care should be taken not to exceed the bearing capacity of
the supported soil.
Plastic design methods may -be used, provided the
assumptions made in the analysis of stability are fulfilled.
In the assessment of bending moments to be resisted by
soldier and sheet pile walls , considerable saving can be
achieved by taking account of the relative stiffness of the soil
and the wall members and its effect on the stress distribution
in the retained material behind the wall. Rowe's reduction
method (1952) which takes account of the flex!bility of the wall
for single anchored walls may be applied.
5.5.5 Walers
The waler; typically a channel section or double I section, should
be considered as a continuous beam subjected to point loads
in the case of a soldier pile system and to a uniformly distributed
load in the case of a sheet type wall structure. Walers may be
subjected to axial loading which should be included in the
design.
It is recommended that the waler length be selected such that
the mid-span moment is equal to the moment at the supports.
5.5.6 Lagging
Lagging is installed by hand after a depth of up to 1,25m has
been excavated. The boards are placed horizontally (see Figure
5.9) and normally wedged tightly behind the face flange of each
soldier pile against the soil. The depth of excavation before a
77
section of lagging is installed depends on the soil characteristics.
In cohesionless soils it should not be more than 1,0m and in
loose materials and fill, it may have to be limited to the. width
of a plank. Under certain conditions, other techniques can be
applied (vertical lagging, shotcrete, etc.). When the excavation
exceeds 3m in depth, the top metre should always be lagged.
The voids behind the lagging should be backfilled with granular
material to assist free drainage of the soil; a suitable packing
should be placed behind the lowest plank to avoid a loss of
ground into the lower excavation. In some extreme cases, grout,
mortar or concrete packing may be necessary.
�oil
_ �
(ii) Struts, rakers, soldiers, walers
Steel �nd timber structural members should be designed
_
to resist the design force at working load level without
exceeding the permissible stresses in the case of a
permanent lateral support system and 1,25 times these
stresses in the case of a temporary system. Reinforced
concrete members should be designed for the ultimate limit
state. Due allowance should be made in the case of
temporary systems by using the appropriate load factors:
(iii) Lagging
In most practical cases, the timber sizes recommended in
Se�tion 5.5.6 should be used for installation.
The effect of arching in terms of a reduced moment acting
along the lagging _may be considered, except where the
material around the soldier is disturbed.
The design stress should not exceed the permissible
stresses of . the appropriate lagg[ng material (timber,
shotcrete, concrete or steel).
5.6 MOVEMENTS
5.6.1 General
The prediction of movement caused by excavation and
dewatering is difficult, but the essential point is that no
excavation, however well supported, can be ·made without
causing some ground movement. An !3Cceptable degree of
movement should therefore be aimed at in all design.· (See
Append��)
Limit values ·of force on support systems (active or· passive
pressures) should only be assumed to apply where sufficient
movements of the material will occur. (See Table 4.2.)
5.6.2 Effect of movement on adjacent structures
The effects of movement on all structures and services in the
vicinity of the excavation should be investigated. In every case,
the deformations which may be produced by the movements
should not exceed those which can be tolerated by that particular
structure or service without adverse effects. The movements
of supported material may therefore require to be limited. Where
the permissible movements are less than would be required to
ensure that fully active pressures only are imposed on the
supporting system, the increased loading associated with such
restricted movements should be provided for.
. 81
Where granular materials are to be supported, it may generally
be assumed that no movement will take place beyond a distance
equal to twice the excavation depth measured horizontally from
the face of the excavation. However, in the assessment of
horizontal ground strains near excavation faces, a li near
reduction of ground strain from a maximum at the face to zero
. at a distance of twice the excavation depth from the face should
not be assumed. The distance of twice the excavation depth
may be conservative and could lead to underestimates of
horizontal ground strain near excavation faces.
Where clays are supported, movements may well occur at
distances greater than twice the excavation ·depth from the face
of the excavation.
Effects of movements on a building should be considered with
respect to the performance of the com·plete structure, the
structural framework, if any, walls· and other structural elements
and all finishes.
The tolerance of buildings and building elements to
deformations is a highly complex matter; empirical guides may
have to be accepted in practice. ·
In the absence of special investigations, Table 5.3 may be used
to assess the maximum relative vertical movement, which is
permissible in typical building frames or walls, of two· footings
or points on the same footing, a distance L apart.
Additional guidance on the effect of movements on buildings
and structures has been provided by Burland et al (1977),
. Burland et al (1979) and Wahls (1981).
TABLE 5.3 PERMITTED RELATIVE VERTICAL MOVEMENT
(a) Services which are unlikely to suffer damage and which will
not endanger the excavation if damaged, e.g. electric cables,
telephone cables. Normally, no special precautions are
required for these services.
(b) Services which niay ·suffer damage but. will ·not endanger
the excavation if damage�. e.g. · gas· pipes; gas-filled
telepryone cables. Wherever the possibility of damage to
such services exists and more particularly when. there could
be consequential damage to life, limb or property,
precautions should be taken in good time to detect and avoid
such damage. Limitation of movements of supported
material or other precautions such as rerouting in order to
prevent damage to such services · may be warranted on
economic grounds. :· · ·
. (c) Services which may suffer damage arid will endanger the
excavation if damaged, e.g.· water mairis, stormwater drains,
sewers. Such services may permit leakage of water prior
to commencement of excavatio·n and require special
attention. Possible courses of action to minimise the
possibility of leakage in the vicinity of the excavation include
rerouting or replacement by a more flexible conduit.
Examples of relatively flexible conduits include pipes with
rubber ring joints, small diameter steel pipes and PVC pipes.
Determination of the maximum curvature of a pipe as a result
of earth movement should be based on the probable plan
shape of the distorted face of the excavation, combined with
reasonable allowances for associated vertical movement.
For a pipe with rigid joints, the investigation should cover
the possibility of failure of the joints or of the pipe itself. In
brittle materials, e.g. plain concrete, earthenware, asbestos
cement, the maximum permissible tensile st�ess should not
exceed one-third of the tensile strength of the material. In
ductile materials, e.g. steel, reinforced concrete, the stresses
due to distortion combined with stresses due to all other
causes should not exceed the values usually specified for
the material considered.
83
For a pipe with flexible joints such as rubber ring joints
t angular rotation at any joint produced by earth movement
he
together with the deviation from the straight which m ay have
been allowed at the time of laying of the pipe should not
exceed the angular deviation from the straight recommend8Cf
by the manufacturer. Note that certain rubber ring joints
become hardened with age and may not retain their original
flexibility. For further guidance see Attewell et al (1976).
84
CHAPTER 6
DESIGN AND CONSTRUCTION
OF -GROUND ANCHORS
6.1 INTRODUCTION
This Chapter gives guidelines on the design and practical applications
of ground anchors for lateral support. The word 'ground anchor' is
a generic term covering all types of ground anchors which are generally
sub-divided into rock anchors, and soft ground (soil) anchors.
Anchors may be used as a method of support for vertical or near
vertical faces of surface excavations and can be used as permanent
or as temporary support. (For definitions of permanent and temporary
anchors and other related terms, see Appendix J.)
Anchors are formed by drilling holes from the excavation, generally
at an angle approaching normal to the face. Suitable tendons are then
installed and a fixed anchorage is formed at the.far (distal) end, beyond
any potential failure surface. The near (proximal) end of the anchor
at the excavated face is provided with a suitable anchor head to enable
the anchor force to be applied to the face of the supported material.
(See Figure 6.1 for basic nomenclature.)
Anchor head
Empty hole
Secondary grout
Distal end
�. .I
STRAIGHT SHAFTED UNDERREAMED
I
Gravity
I
Low pressure
I
High pressure · Gravity
grouted grouted grouted grouted
{b) The tendon can pass through the grout body in sheathing
and be attached to a plate at the distal end, which bears
on the grout transferring the load to the grout in
compression. This latter system is seldom used.
�
I
.l �
Horizontal spaci�g �
Fixed anchor length
�
Vertical spacing
c;.6 CONSTRUCTION
Reference is made throughout this Code to permanent anchors and
temporary anchors both in respect of the testing necessary to enable
the performance of the anchors to be relied upon during their life, and
in respect of corrosion protection to ensure that the anchors do not
fail during their life because of corrosion.
Table 6.1 attempts to classify anchors into categories based on the
ground conditions and the service conditions to enable some idea of
the necessary corrosion protection requirement to be given.
No two sets of anchors are installed under identical conditions or
for exactly the same purpose. Thus, it has been necessary to group
together a wide variety of ground anchors and service conditions to
limit the number of categories in table 6.1. Other factors not mentioned
in this table, such as stray currents, should also receive attention.
In practice, all the relevant conditions should be noted and taken
92
I CONDITIONS PERTAINING \
I SERVICE UFE CONSEQUENCE OF
FAILURE
CORROSION
ENVIRONMENT
a
MATERIAL AROUND FREE
LENGTH
LATER ACCESS
\
TEMPORARY RATING RATING RATING RATING RATING
Not serious 0 Non-corrosive 0 Rock A Needed/Restressable
m Up to six months 0
anchor X
r-
m
.....
Six months to two Not needed/non-
0) years 1 Serious 1 Corrosive 1 Sand B restressable anchor y
PERMANENT
Over two years. 2 Catastrophic 2 Very corrosive ·2 Clay C
0
::D
::D TOTAL THE SCORES IN THE COLUMNS-AND REFER TO THE PROTECTION ALTERNATIVE TYPE CODE BELOW
0
�
0
z
PROTECTION ALTERNATIVES
-0 FIXED ANCHOR LENGTH FREE LENGTH HEAD AND UPPER PART OF TENDON
::D
Type Code Treatment Type Code · Treatment Type Code Treatment
0-1, ABC,XY Tendon grouted bare o;AXY Bare tendon empty hole 0-1, ABC, XV Bare head
0-6,AY
0
z
2-3, ABC, XY Tendon epoxy coated 1-6, AY " Bare tendon grouted in hole 2,ABC,XY Painted head
-
C) 4-5, ABC, XV Tendon grouted into 0, BC, XV. Sheathed tendon in empty
C: corrugated sheath while 1,A, XY hole 3-4,ABC,X Epoxy coated head
grouting anchor
C
m 1, BC, XV Sheathed tendon in' grouted 2-6,ABC,X Head covered with cap filled
hole '· with grease
5-6, ABC, XV Tendon pregrouted in
corrugated sheath before 2,ABC,XV Greased and sheathed tendon 5-6,ABC, V Head concreted or grouted Into
homing . in empty hole boxout
3-6,ABC,XV Greased and sheathed tendon
In grouted hole
5-6,ABC,XV Greased and sheathed tendon
in common sheath in grouted
hole (double corrosion
<O protection)
ti)
FOR EXAMPLE: Temporary anchors are required for up to 4 months in very corrosive conditions to support a face where failure could have serious consequences in sand,
and which must be tested at one. month intervals. Score O + 1 + 2 • 3BX
SUGGESTED CORROSION PROTECTION : FIXED ANCHOR LENGTH : Tendon epoxy coated before grouting into holes
FREE LENGTH : Tendon greased and sheathed before grouting into hole
HEAD ANO UPPER TENDONS : Head epoxy coated
to ?c co un t, Ta bl 6 1 being used only as a guide to assist.decision
in tection and not rigidly adhered to
making on corros?,on. pro
6.6.1 Materials
uf t�red from high carbon or
Steel tendons are normally man ac
ds sU1table for prestressing.
alloy steel bars, wires or stran h c rbon or alloy steel
Bars are generally cold worked hig a
te and as a minimum
suitable for post-tensioned concre ,
r ents of BS 4486
standard, should comply with the requi em
(1980).
Wires or multiple wire strands are manufactured to various
o
stress and relaxation criteria in line with the requirements f
BS 5896 (1980) and ASTM A416 (1987), A421 (1980) and Ang
(1980). These criteria can be obtained from the specialist
manufacturers.
Permissible stress should be in accordance with the
manufacturer's recommendations. However, the permissible
stress of the tendon when locked off should normally not exceed
700/o of characteristic strength for strand or bars. For short
periods d'-:'ring testing, the stresses should not exceed 80
percent of characteristic strength with due regard to safety and
the stress/strain characteristics of the steel used. For long term
permanent anchors, the permissible stresses are sometimes
reduced.
Note that strand manufacturers supply load/elongation curves
with each batch of strand delivered.
· Both normal relaxation and low relaxation wire and strand
are available. Typical relaxation of stress (as percentage of initial
stress) from an initial stress of 70 percent of specified
characteristic strength at a temperature of 20 ° C appears in
Table 6.2.
TABLE 6.2 TYPICAL RELAXATION OF STRESS IN TENDONS (AT
INITIAL STRESS OF APPROXIMATELy 70% OF
CHARACTERl�TIC STRENGTH AT 20 ° C)
Seit-
straightening Normal 0,0-0,1 0,fHl,8 1,5-2,2 2,3-4,3 4,0-6,5 4,5-7,5
wire and 7 wire
strand Low 0,0-0,1 1,1•2,2
0,2-0,3 0,5-0,7 0,7-1,0 1,0-1,5
94
Protection against corrosion may be achieved by cement or
other grouts or by sheathing, generally with grease in the
annulus between the sheathing, and the steel. One of the
approved techniques for corrosion protection of the fixed
anchorage length for permanent cables, using the above
materials, is referred to as encapsulation. (See Appendix J.)
Stainless steel
At present there is no prestressing steel specification or code
covering stainless steel wire, bar and stainless clad bar. The
preferred composition of the stainless steel is Type 316S16 in
line with BS 1501: Part 3 (1973).
Sheathing
. Care_ shouid be exercised to ensure that the proximal end of
the grouted fixed anchor length canno� encroach within the
theoretical slip surface and, to achieve this it is recommended
that �he free length of the anchorage be sheathed. Where
permanent anchors are sheathed, the annulus between the
· tendon and the sheathing. should be completely filled with a
grease, resin or cementitious material.
High density polyethylene or polypropylene sheath� with a
minimum wall thickness
-- .
of 1 mm are recommended and should
be applied under factory conditions. Heat shrink tubing·may
also be used. ·.
Grease
- -
. Rust inhibiting grease is a compound with the consistency of
gre�se and should contain_ no sulphides, nitrates or chlorides.
Guidance to selection of suitable greases is given in Section
K3 of BS 8081 (1989) (Grease).
(Note: 'grease' as supplied by a motor dealer or oil company
is normally unsuitable for this purpose and details of any grease
proposed should be checked with the supplier against the
above reference and only used if suitable).
Corrugated sheathing
Where double corrosion protection is recommended for the fixed
anchorage length, the corrugated tubing should be high density
polyethylene, polypropylene or similar non-corrosive material
with a minimum wall thickness of 1 mm. (The amplitude, pitch
and profile of corrugations have been specified in BS 8081
(1989) but different profiles, amplitudes and pitches have been
95
a and field trials should be usect
used successfully in South Afric
in cases of doubt.)
Anchor heads
t gri� the tendon,
The upper anchorage consists of a device �
e which Is _capable of
bearing against a suitable bearing plat
e atio f ce v a
distributing the load from the tendon to the xcav n a v id
p
steel soldiers, piles, thrust blocks, walings or other ap ro e
methods. (See Chapter 5 and Figures 6.4, 6.5 and 6.6.)
Anchor heads for strand, or locking nuts f or bar tendo ns with
their bearing plates, must be of an approved design capable
of sustaining twice the working load with an angular deviation
of not more than 5 degrees from the tendon axis and without
excessive distortion. For permanent anchors, an adequate
corrosion protection system must be provided encapsulating
the entire anchor head down to the sheathed strand behi nd the
head, including the junction between the bared steel of the
tendon and the gripper- mechanism. Where anchors are not
required to be retensioned, this encapsulation is frequently
made from cement grout, but for restressable anchors the filling
material is usually a grease or pl�stic resin. (See Table 6.1)
6.6.2 Drilling
Drilling methods may be rotary, percussive, rotary- percussive
or vibratory and should be chosen to give the minimum
disturbance to the surrounding ground. The drilling fluid should
have no deleterious effect on the ground, the tendon or the
grout.. Hole stability �� critical and special care is required to
ensure that the drilling or flushing method does not give rise
to excessive loss of ground. Holes for ground ancho rages
should generally be drilled to within the following tolerances:
sealing nut
Corrugated plastic tube
Sealing cap
over whole tendon
Grease
Locknut
Anchorhead---
Palnted steel thrust
plate _____,,,,.
6.6.3 Manufacture
Permanent anchors should be fabricated in a workshop or under
cover on site by experienced personnel under adequate
supervision. However, temporary anchors are frequently
manufactured in the open. During manufacture, handling and
storage, the anchors should be kept dry, clean and free from
excessive rust. (Loose, easily removable surface rust is
acceptable, but pitting is not p'ermitted).
Anchors composed of plastic sheathed greased strand should
have the exposed strand in -the fixed anchorage zone thoroughly
cleaned and degreased, using steam or solvents, after unlaying
of the strand.
Centralisers and cover spacers which should preferably be
of plastic or non-metal manufacture must be firmly attached to
the tendon at a maximum spacing of 1,Sm to ensure central
location in the borehole, with a minimum cover of 10mm.
- -
6.6.4 Homing
Tendon installation and grouting should be carried out as soon
as practicable after the drilling of the fixed anchor length and
preferably within 2 to 4 days. Homing should be carried out at
a steady controlled rate, where the anchor is homed into a grout
filled hole.
6.6.5 Grouting
Grouting is required to bond the anchor to the ground o d
,b n
the te�don to the capsule and to pro
tect the tendon again5t
corrosion.
Cement grout
Cement �rou� sho�ld be thoroughly mi�ed (a colloidal hi�h
speed mixer IS suitable) usi
_ ng portfand cement (OPC/rapid
hardenmg/sulphate resisting) and p a l
ot b e water with a
98
water/cement ra�i? ranging fron:, 0
,35 to 0,5, depending upon
the ground con d1t1ons. Unless there is esta
blished information
of rate of strength gain of grouts made from
the particular
cement bein g used, tield tests should be done to
establish this
i�f�rmation, and it is recommended that anchors not
be stressed
until the grout has attained a crushing strength of at least 25
MPa. ·
Admixtures should only be used if it can be established that
they have no Ufldesirabl� effects on corrosion, setting times and
�ren�h. .
Resin grout
Resin grouts. may be used under the reco�mendation gi�en
in BS 8081 (1989).' - ·
Injection of grout
The grout should be injected at the bottom of the h�!e, through
a tremie tube. This may be dol"!e either prior to homing.of the
anchor or after homing, but in the latter case, the tremie tube
should be built into the anchor in the course of manufacture.
Where a tendon is decoupled in the free length, it is important
that the column of injected grout does not extend to the structure
being anchored prior to stressing.
'
1
LoadT Load T
s s = additional extension
Tp ==
1,5Tw
Tp =
1,25Tw
I -I � -I � lock-off
- -f./ I- X Y
d
,...lo_a__
Lock-off
--r__________
Anchor test
1,1Tw -1, 1Tw o
I 1--p_ _in_t-+-----------.1
X Routine acceptance - temporary
Routine acceptance - permanent
l:::..TS y
0,25Tw Site suitability temporary and
and }
Proving test
permanent
0
Total elastic Tp Lt
«)
?.:- extension d = ET"
«)
I
C:
E 0...
a. (/)
E
«)
---
(/)
Ti
I lnitialload T1 ::;: 0, 1Tw to 0,25Tw
-,- � d--t Extension
------
Anchor
(1) Dial gauge on tripod
FR M A AXED DATUM
ENDO DISPLACEMENT O
M RING T N
FIGURE 6.8 TYPICAL METHODS OF EASU 101
The liftoff tests should then be repeated at 24 hours, 3 da
and 10 days as previously described, after relocking the anchYs
at 1100/o Tw. If, after such re-tensioning to 110% Tw, the anchor
fails to comply with the maximum permissible losses in tensii
r
6. 7 .4 Working Anchors
-(a) General
. _to routine
The working an� hors hould all be subjected
pared with the
acceptance test1_ng w��1ch -�.1II then be com
h ors before bein g
results of the site suitabiht test anc
� nchor should al so be
accepted. The free length 0 the a
checked. (See � 0t? 2 � l�W -�c
I n some app l1cat1ons it is
n essary for the anchors to
ore being fu l ly
be left on parti�I �tress fo�=� me timedbef h proo test
ib·le to o t e f
stressed and it is not P
103
immediately. In such cases, the partial working load should
be assumed to be Tl (See _Figure 6. 7), for the �urpos8 f
O
the routine acceptance testing when the anchor 1s stressec1
to full load.
When assessing working anchors which may have liftott
loads slightly lower than specified and where it is believed
that this may be due to excess movement at either
anchorage in 'bedding in', the test should be repeated and
re-assessed.
(b) Permanent anchors
Every working anchor should be subjected to the loading
cycles as described in Section 6.7.3(b}. If at 24 hours after
lock-off, the loss of load does not exceed 6% Tw, and at
3 days after lock-off, the loss of load does not exce ed 7%
Tw, the anchor should be deemed to be in accordance with
this clause and no further testing will be required. If
protection against corrosion of the free length is to be
provided by cement grouting, the anchor may be grouted
along its free length at any time after this second liftoff test,
but should preferably be done within 10 days of completion
of the tests. If protection of the free length against corrosion
is by means of sheathing, any further testing called for may
be considered as �nly long term monitoring of the structure.
(See Chapter 8 for Monitoring.) If at the 24-hour liftoff test
or· at the 3 day liftoff test the loss of prestress exceeds the
allowable (6% ) 7% Tw respectively}, the anchor should
again be locked off at 1_ 10% Tw and subjected to further
tests at 24 hours and 3 days. If after either the second 24
hour or 3 day re-test, the loss of prestress is still greater
than the allowable, an investigation as to the cause of failure
should be carried out, and · dependent upon the
circumstances, the anchor should be:
(i} abandoned and replaced
or (ii) reduced in capacity
or (iii) subjected to a remedial restressing and testing
programme.
NOTE:
1. Where it is possible, using load cells accurate to within 0,5%, to simulate
a 24 hour test in 50 minutes (See Figure 6.9 and refer to Littlejohn
.
{1981 )), this may be accepted in lieu of th e 24 hour test described above
ld
2. In all th e foregoing tests, th e apparent free length of the anchor shou
turer's
be calculated from the load/extension curve, using the manufac
of temperature,
values of Young's modulus and allo wing for the effects
ements. T he
bedding in of t h e anchor head and other extraneous mov
curv over e
e t
analysis should be carried out on th e load/extension
h
horages. T he
range 25% Tw to 125% Tw or 150% Tw for all anc
of th e designed
apparent anchor free length sh ould not be less than 90%
of the
free length, nor more th an the intended free length plus 50%
ld fall outside
designed fixed anchorage length. If th e free length shou
ed before any
these limits the full implications of this sh ould be examin
further action is taken.
10 5
CHAPTER 7
GROUNDWATER CONTROL
7.1 INTRODUCTION
The impact of groundwater on the excavation and the lateral support
system can be significant. Water affects the design, the construction
procedures and the overall cost.
Three important factors to be consi.dered are how water moves
through the soil, the effect of water on the engineering properties of
the soil, and the pressures exerted by water on the support system.
Hence it is important to understand the stratigraphy of the site and
the permeability of the various soil �orizons. {See Section 2.2).
There are three basic methods of ·controlling groundwater during
construction, namely: to exclude it, to reduce its flow or to lower the
surface level. If the groundwater is to be cut off then the consequences
of full groundwater pressures must be considered in the design. The
method of control chosen depends on:
7 .2.3 Electro-osmosis
In very fine grained soils, the capillary f_orces acting on the
porewater prevent free flow under gravity to_ a filter well or sump.
In the electro-osmosis system,_ direct_ current is made to flow
from anodes which are steel ro_ds driven into the soil to filter
wells forming cathodes. The positively charged p�rticles of
water flow through the pores in the soil and collect at the
cathodes where the water is pumped to the surface. Owing to
high cost, this method is only employed as a remedy in very
difficult situations and is not used as a common construction
technique.
r
Standpipe plezometer
-· _ ·- _, l--·
to seepage
Clay
. .. .. . . . .. .. . . .. .. .. . .. .. .. .. .. ... .. ..
-:_ · -·� ·- · r
.. ... . . .. ... .. . . .. .. . . . '•. . . . . . . . .
.. .. .. ... �. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. ... ..
Support
Sand
.
.. . .. .. .. .. . .. .. .. .. .... . .. .. .. .. .. .. .. .. .. ..
·
syste111 Slow
Uplift head
Clay
Sand
--
-------
------ --------------
-------..i------
----------
------------ ----
-----
:.• • • • • • • • • • • !. _: I
-----
-- - ----
------
---- - -------------
- - - - - - - - - - - - - - --
- -------------------- -----
Clay -------------------
----- -------- - - -- ---
----- - -- - - - - -- - -- -.----
---------------------
FIGURE 7.1 AQUIFER BENEATH EXCAVATION LEVEL
·. ••
��-w"l
Sup�rt · :/
t-���/n 1··: /
Original gr�� nci _ 1ev_e1 ✓ system / . , •.
7 ��rigl�g
m��-
�
T
·: wat�r surface
Excavation level
Surface of ground
water If rechargi ng
not adopted
112
CHAPTER 8
CONTROL OF THE WORKS
MONITORING AND RECORDS
8.1 INTRODUCTION
All civil engineering structures are mo
nitored as� matter of routine.
The purpose of monitoring is to verify the
stability of the lateral support
system and to provide warning <?f untowa
rd developments.
8.2 CONTROL OF THE WORKS
8.2.1 Extent of control measures
The extent of measures to be exercised for the control of any
excavation should be decided by the design engineer
responsible for the planning of the lateral support system. In
resolving decisions on the· scope of control measures
appropriate to the scale, difficulty and permanence of the
proposed works, the engineer should bear in mind the possibility
of loss of life or limb and of damage to property.
The duration and intensity of the monitoring should be
commensurate with the permanence of the works and the
experience with the type of lateral support system used.
Distinction should be made between observations requiring
the services · of a qualified land surveyor and on-site
observations such as piano. wire measurements, normally
carried out by the contractor. Sho�ld the former be necessary
consideration should be given to appointing a profession�! land
surveyor to carry out this survey under a separate contract with
the owner.
c) Vertical movements
Measurements of vertical movements of the _surface should
be taken, frequently at first and then at l�ast �eekly, over
a distance from the face of the excavation not less than the
depth of the completed excavation. Measurements should
also be taken whenever untoward horizontal movem ents
t
have been detected at the face. The points of measuremen
loca l
should be sufficiently closely spaced to detect
t of
differential settlements. The accuracy of measuremen
vertical movements should be 1, 0mm .
117
d) Rebound of floor of excavation
Rebound of the floor of the excavation should be measured
and taken into account in so far as it may affect falsework
or other supports or give warning of untoward movement
of supported material.
119
APPENDICES
K - REFERENCES
121
APPENDIX A
STEP-BY-STEP GUIDELIN
ES
·FOR INVESTIGATION AND
. ACTION. FOR LATERAL
�UPPORT OF A BUILDING
BASEMENT
Step 1:
Activity: Examine the title deeds ..
Considerations: The extent of the site, rights of way or servitudes, and
restrictions imposed by mining conditions or environmental conditions.
Limitations under Town Planning Regulations .
.••
Step 2:
Activity: Examine l�nd surveyor's diagram
Considerations: Compare -land surveyor's diagram •in the·title deeds.
Ascertain if surveyor's pegs or location� of boundaries are clearly indicated
on site. If so, and there is certainty that pegs have not been displaced,
arrange for offset pegs to· be established so that should the original
surveyor's pegs be disturbed during excavation, they can be re-established
with accuracy. Ensure there are no encroachments from adjoining
structures. If encroachments do exist, ascertain if the owner is aware of
the extent of the encroachment.
Step 3:
Activity: Examine information on the site provided by owner or his
principal agent
Considerations: The engineer should acquaint himself with the a�c�itect's
conception and his proposals with regar d to the means of retaining. the
adjoining buildings by lateral support, under pinnin� or tempo�ary sho�ing.
_
Examine any test holes already completed and obtain inform�t,?n provi�ed
by the owners or consultants for adjoining buildings. Obtain mform�t,on
if available, from principal agent on the location and depth of all serv,�es,
including water supply mains, stormwater drains, sewers, gas mains,
123
f not available,
. . J Post Office telephone ins tallations. I
electr_icity cab · es and
seek mf orm a t °
,on n t hese se rvices from Local Authority and government
departments.
(See Table 1.1.)
Step 4:
Activity: Initial desk and field study
structures and examine all
Considerations: Conduct a survey of existing
from Local Authority's
available geological data. Obtain information
io d whe�her it is
Engineer. Study particularly the groundwate r situat � �
suitable for incorporating this water in some of the building services, i.e.
fire services, etc.
If information is inadequate, arrange for further geotechnical investigation
as set out in Chapter 2. Should such investigation take place on the
sidewalk or road, obtain permission from the City/Town Engineer and Traffic
departments. Particular care should be taken not to damage underground
services. Ensure that plant is protected during the day and illuminated at
night.
If water or fire mains on the perimeter of the site are large (i.e. 100mm
diameter or more) and if they should be damaged by ground movement
due to inadequate lateral support, the consequences could be serious. The
results may be not only flooding of the site, triggering further ground
movement, but also possibly depriving a portion of the city/town of a water
supply.
Discussions on this subject should therefore be held with the City/Town
Engineer to consider whether such mains should be re-routed b efore
commencing excavation.
Other services around the site should be identified and the risk of damage
to the excavation and/or the services themselves evaluated.
{See Table 2.2.)
Step 5:
Activity: Legal precautions and agreements with adjoining owners and
Local Authority
Considerations: Ensure that the principal agent has obtained written
permis�io� from the adjoining owners for any encroachment of
underp1�mng or anchors. If permission has not been obtained, proceed
to_ explain the �roposals to adjoining owners with the co-operation of the
chent an d confirm the ag reements in writing. Where
anchors are to pass
below str�ets, obtain permission from the City/Town Engineer.
Take particular care if the demolition of the existi
ng building and the
excavation are likely to remove the lateral support
to adjoining structures.
(See Appendix D.)
124
Step 6:
Activity: Report on condition of surrounding kerbs, pavm
g s labs,
stormwater gutte rs and roads
Considerations: In view of expected ground movements and the dam
age
that may occur to pave men ts,. gutters, kerb s and roads, an .inspecti.on of
these should be conducted with the City/Town Engineer. A photographic
record a.nd report should be prepared for the Local Authority ' the owner,
the engineer, the arch·tI ect and the quantity surveyor.
Step 7:
Activity: Preparation of plans for the excavation and receipt of approval
for the procedures from the Local Authority
Considerations: Having ascertained the extent of excavation and
established, the nature of the rock or soil, select a system of lateral support.
Step 8:
Activity: Insurances
Co nsiderat ions: Provide the owner's insurance adviser with details of the
Proposed works. Negotiate a premium with appropriate conditions whi�h
can be recommended to the owner. Obtain the insurance company s
agreement in writing. Ensure that all members of the professional team
and contractors have adequate insurance cover.
(See Section 1.3.4.)
St ep 9:
Activity: Photo
graphic record of adjoining buildings
C onsiderati g is nec�s��ry,
ons: If the excavation is deep and/or dewaterin
Predict move affect adJommg
ments ' and decide whether these may
125
ce
. .
s. If so, arran ge for eve ry building with in a reasonable distan
building
ed and a photograph"1c record mad e of · all
of the excavat.10 n to be ·in spect a separate file
•
er na 1 an d exte rna l cra cks · Each building shou.ld have . . '
mt d and i ts pos1t1on recorded on
ul d be clea rly illust rate
and each crack sho
the pla n of each floor.
Step 10:
Activity: Photographic record
s ou be
considerations: The external walls of adjoining buildings h ld
photographed on a regular basis during excavation.
Step 11:
Activity: Excavation of column bases and foundation straps
Considerations: Where bases and straps are large, it may be
advantageous to excavate these at the same time as the excavation
contractor's equipment is on the site. Dis�ussions on the setting out of
the bases and straps should be held·with the professional team.
Step 12:
Activity: Geological description of excavated material; for the quantity
surveyor
Considerations: Where the excavation is to be ·measured by a quantity
surveyor, a comple!� profile inclu_ding a _(ult description of the ground
conditions, is vital for the preparation of a Bill of Quantities.
The plan· of the excavation mentioned in Step 7 should indicate the stages
of the exc�vation to allow the anchor drilling•rigs to have suitable platforms
from which to operate.
This must be clearly defined for the quantity surveyor so that the description
in the Bill of Quantities can cover the requirements.
Step 13:
Activity: Control of noise from excavating operations
Considerations: The contract agreement between the owner and the
excavating contractor should include a clause to ens ure that the contractor
is respon sible for abatement of noise from all machines and bla5ting
?Pera!ions that might cause annoyance to the surroundi ng population. AnY
interdict on the owner will be passed on to the contractor, who maY
negotiate terms with the offended persons to l imit noise to certain hours
of the day or night. Any delay in this regard will not be considered b� th�
owner, and due allowance must be made i n a separate item ·;n the 6111 0
Quantities.
(See Section 8.2.2(f).)
126
APPENDIX B
LABORATORY & FIELD TESTS
TABLE 81 - LABORATORY TESTS ON SOILS
TABLE 82 - FIELD TESTS
TABLE 83 - LABORATORY TESTS ON ROCKS
127
-
TABLE B. 1 L�BORATORY TESTS ON SOILS
TEST MATERIAL SAMPLE REMARKS REFERENCE
TYPE
Grading Analysls: 1
(a) Sieving Granular solls and D Usually carried out in conjunction with Atterberg Limit Tests to give an TMH1(1986)
gravels indication of soil behaviour and to classify the soil. 8S1377(1975)
(b) Sedimentation Cohesive and fine D
grained soils
Atterberg Um its 1 Cohesive and fine D Plastic Limit, Liquid Limit, Plasticity Index and Linear Shrinkage2 • Used for TMH1(1986)
grained soils indication of soil behaviour. 8S1377(1975)
Moisture Content Soils or rocks 0/U Frequently carried out as part of other tests .. Allows determination of degree TMH1(1986)
of saturation. BS1377(1975)
Specific Gravity Soils or rocks D Used in conjunction with other tests such as density consolidation and TMH1{1986)
sedimentation. BS1377(1975)
Bulk Density Soils U/1 May be carried out on undisturbed samples in the lab. Cohesionless soils TMH1(1986)
require in situ testing. Used with S.G. and moisture content to determine B$1377(1975)
void ratio and degree of saturation
(a) Undrained Saturated, normally u Undrained shear strength (c"; dJ = 0). Short term stability and anchor Akroyd (1957)
unconsolidated consolidated clays behaviour under rapid loading with fissured clays, sample size may have Bishop &
significant effect. Henkel (1957)
Saturated, u Marsland
overconsolidated/fis- (1971)
sured clays
(b) Consolidated Saturated, normally u Effective strength parameters (c'; a; Bishop &
undrained with consolidated clays. Henkel (1957)
p.w.p Partially saturated u Long term stability. Akroyd (1957)
measurements clays (soaked)
(c) Consolidated Clayey sands, u Effective strength parameters (c'; CJ') Long term stability. Bishop &
drained sandy clays, silts Henkel (1957)
Akroyd (1957)
Partially saturated · u
cl�s (soaked)
(a) Multiple reversal Stiff fissured and u Shear box method most common. Used for assessment of overall stability Skempton
shear box or jointed soils in fissured or jointed soils. (1964)
(b) Ring shear particularly Marsh (1972)
slickensided soils or Bishop et al
\
existing failure
'
(1971)
surfaces.
\ j
\.l = \.lnd\s\urbed sample O ... O\sturbed sample R = Recompacted sample I • In situ test
TABLE B. 1 LABORATORY TESTS ON SOILS Continued
MATERIAL SAMPLE REMARKS lREFERENCE,
TEST
TYPE
Cohesive and fine Akroyd (1957)
One Dimensional
Consolidation grained soils
Gives measure of compressibility (c0 ,m.), preconsolidation pressure (pJ and
Triaxial Cohesive and fine u coefficient of consolidation (cJ Triaxial consolidation gives measure of Akroyd (1957)
Consolidation grained soils elastic modulus. Rowe cell uses larger. samples and confining pressure may
be varied. Results' used for prediction of settlement and base heave.
Recompacted sands R Bishop &
Henkel (1957)
Permeability:
Constant head test Sands and gravels R For permeabilities of 1-10·2 cm/sec. Akroyd (1957)
Falling head test Cohesive and fine u For permeabilities < 10·2 cm/�ec .. Akroyd (1957)
granular soils
Triaxial permeability Generally cohesive u Allows effect of confin'ing pressure to be determined. Akroyd (1957)
and fine granular Bishop &
soils Henkel (1957)
Rowe cell test Generally cohesive u Ditto plus allows vertical or radial flow. Rowe &
and fine granular Barden (1966)
soils
Static cone tests (Dutch Loose granular soils Gives point resistance (cone) and total resistance (cone and friction TMH6 (1984)
Probe) and soft to firm clays sleeve). Results correlated with bearing capacity and compressibility. Webb (1976)
SAICE & NITRR (1978)
Sanglerat (1972)
Ervin (1983)
Piezocone Saturated, loose, Tip resistance, sleeve resistance and dynamic pore pressure are Clemence (Ed) (1986)
granular soils and soft measured while continuously driving the probe into the ground. Weitman and Head
to firm clays (1982)
Pressuremeter Soils and weak rocks Pressuremeters may either be inserted into boreholes, be driven into SAICE & NITRR (1978)
the ground in a slotted casing or be self boring. Results give Menard (1965)
indication of elastic modulus and soil strength. Windle & Wroth (1977)
'. ' Ervin (1983)
Goodman Jack Soft or hard rocks Jack inserted into NX sized borehole. Rock loaded by curved plates Goodman et al (1968)
and deformations measured. May be installed in horizontally drilled
�ol�s and rotated_to determine degree of anisotropy. Results give
indication of elastic modulus of in situ rock mass.
Constant Head Soils or rocks generally Water introduced into soil or rock via piezometer. SAICE & NITRR (1978)
Permeability Test below W.T. BS 5930 (1981)
Schmid (1967)·
Ervin (1983)
Variable Head Soils or rocks generally Either a falling or rising head upset test. SAICE & NITRR (19781/
)
Permeability iest \belowW.i. BS 5930 (1981)
Schmid {1967)
Ervin (1983)
\
TABLE B.2 FIELD TESTS Continued
1
I TEST APPLICABILITY REMARKS REFERENCE
'Packer Tests Generally applied to Test measures the acceptance of the in situ rock of water under SAICE & NITRR (1978)
rocks and clayey soils pressure between packers inserted in the hole. Used to assess the Lugeon (1933)
grout acceptance of the rock or to check the effectiveness of Ervin (1983)
Pumping Tests Soils or rocks below fff�b\�Qi· pumping at a steady
known flow and observing the· SAICE & NITRR (1978)
W.T. drawdown in observation wells at various distances from the Lugeon (1933)
pumped well. Gives permeability of in situ material. Ervin (1983)
Piezometer All soils and rocks Used to determine ground water pressure at various depths in the SAICE & NITRR (1978)
ground. In permeable ground, standpipe piezometers are used but BS 5930 (1981)
in impermeable conditions or where rapid response is required, Penman (1960)
hydraulic, pneumatic or electric piezometers are used.
Vane Shear Test Saturated cohesive Normally restricted to saturated clays with an undrained shear SAICE & NITRR (1978)
soils strength of less than 100 kPa. This method can give peak and BS 5930 (1981)
residual undrained shear strengths. Ervin (1983)
Plate Bearing Test Most soils and soft Test performed in trench or auger hole by jacking circular plates Ervin (1983)
.
rocks. Generally above
W.T.
against the soil/rock. May be carried out horizontally (across width
of hole) or vertically Gacking against a kentledge). Size of plate
Wrench (1984)
'
,est rock discontinuities requirements of jointing or weathered rock mass.
\
\ or intact rock.
n
Soil type - This is described for each stratum o a
basis of grain size.
. determ ines
Origin - The geological history of a site .
t The
the origin of the soil on that si ��d or
division of the soil into tran5P? ce the
51 n
resi dual horizons is important . eerin9
g in
origin strongly influences the en
behaviour.
136
TABLE C2 CONSISTENCY
OF COHESIVE
SOILS
' SILTS AND C
LAYS AND CO
OF SILTS AND MBINATIONS
CLAYS WITH UNCONFIN
GENERALLY SL SAND, ED
OW-DRAINING COMPRESS
MATERIALS COHESIVE IV E
STRENGTH
(kPa)
'Code of Practic
e No. 4, (1954)
137
GGING
C.2 CORE LO
g Com m ittee of the SA Association of Engineerin
The core Loggin ha s als o recommended
a six descriptio�
(19 76 ) ised below:
Geologists gging, as summar
classificati on to r c or e lo
nant colour with
- Describe in profile predomi
Colour d, stained, etc.)
(sp eckl ed, m ottle
as per Burland Colour
secon dary colours
)).
Chart (Burland (1960
a rock should
- The state of weathering of
Weathering of Table C3.
be des cribed in terms
G
TABLE C3 WEATHERIN
RE SURFACE
DESCRIPTION DISCOLOURA· FRACTU CHARACTERIS·
ION
TERM TION EXTENT CONDIT TICS
closed or unchanged
Unweathered none
discoloured
discoloured, partial
<20% of
Slightly
may contain discolouration
weathered fracture
spacing on thin filling
both sides of
fracture
138
Discontinuity, - Describe spacing of joints/be
dding and
surface texture of material (Table C4 and C5).
spacing
and fabric
139
TABLE C5 GRAIN SIZE CLASSIFICATION
140
TABLE C6 HARDNESS
�
CLASSI-
RANGE OF
FICATION FIELD TEST
MINIMUM
COMPRESSIVE
STRENGTH
(MPa)
Very soft rock Can be peeled with a knife, 1 to 3
material crumbles under firm
blows with the sharp end of a
geological pick
Soft rock Can just be scraped with a knife, 3 to 10
indentations of 2 to 4mm with firm
blows of the pick point
Medium hard Cannot be scraped or peeled with 10 to 25
rock a knife, hand held specimen
breaks with firm blows of the pick
Hard rock Point load tests must be carried 25 to 70
out in order to distinguish
Very hard rock 70 to 200
between these classifications.
Extremely hard These results may be verified by > 200
rock uniaxial compressive strength
tests on selected samples
.
Rock type - e.g. granite, sandstone, quartzite, etc
nte Chri5to
Stratigraphic horizon - e.g. Vryheid Formation, Mo oup, etc.
Formation, Table Mountain Gr
1 41
APPENDIX D
LEGAL ASPECTS OF
LATERAL SUPPORT FOR
SURFACE EXCAVATIONS
(a) his not interfering with the support his land naturally affords his
neighbour's land, without substituting adequate artificial support;
and
D.2.3 The duty of an owner not to remove the lateral support of his
neighbour's land without substituting an adequate artificial support,
extends to land in its natural state, and not to land, the burden of
which has been artificially increased by the erection of buildings.
D.2.4 There is some authority for the contrary view that the duty to maintain
lateral support extends to buildings as well as land.
Johannesbuig Board of Executors and Trust Co. Ltd. vs Victoria Building Co. Ltd.
1894 Vol. 1 Official Reports p. 43
Phillips vs Independent Order of Mechanics
1916 Cape Provincial Division p. 61.
D.2.5 The better view is probably that an owner is liable for damage
through subsidence of his neighbour's building if the land upon
which the building stands would have subsided even if the building
had not been there at all.
D. 3 DEWATERING OPERATIONS
D.3.1 An owner may drain water from an excavation on his land even if
this results in the subsidence of other properties in the
neighbourhood. If the substance drained is 'of the nature of mud
or silt', however, he may be absolutely liable on the basis discussed
in Section 0.2.
NOTE: The terms ·•mud', 'silt', 'muddy water', and 'wet sand' are not defined in a
technical manner for legal processes. Descriptions would be an arguable question of
degree in any particular case. An engineer should therefore take care to err on the
safe side in assessing the acceptable amount of solids in water being pumped or drained
from adjoining sites.
D .4 DISPOSAL OF STORMWATER
D.4.1 Stormwater flowing over the surface of a higher-lying property on
to the surface of a lower-lying property could adversely affect the
145
stability of an excavation on the lower-lying property and the
measures necessary to maintain support for the higher-lying
property. The general principles relating to the disposal of
stormwater are shortly stated below, but they may be varied in given
cases.
Bishop vs Humphries
1919 Witwatersrand Local Division p.99.
Barklie vs Bridle
1956 (2) South African Law Reports p. 103 Southern Rh odesia·
INDEMNITY
2.
147
ER FOR DAMAGE OR
D.6 LIABILITY OF OWNER AND ENGINE SED
INJURY NEGLIGENTLY OR WILFULLY CAU
ons D.2 and 0.3 aforegoing are
D.6.1 The concepts discussed in Secti
special inasmuch as they apply
The owner of land, the contractor and the engineer may, however,
owe a duty to a much wider field of persons not to cause injury
wilfully or through negligence. Such a duty would be owed to the·
owner of a neighbouring property, the tenants of the neighbouring
property, the employees of such tenants, passers-by in a street
which might collapse into an excavation, the local authority in
respect of the services in such street, etc. Indeed, the duty might
loosely be stated as extending to all persons who could reasonably
be expected to suffer damage or injury by any want of care on the
part of any person responsible for the excavation.
'In deciding what is reasonable the Court will have regard to the general level of skill
and diligence possessed and exercised at the time by members of the branch of the
profession to which the practitioner belongs.'
(Innes, CJ in Van W)rk vs Lewis
1924 Appellate Division p. 438 at p.444)
D.6.4 It is possible that this Code, insofar as it may embody the best and
most up-to-date engineering techniques, could come to be accepted
by the Courts as the standard by which the conduct of engineers
in this field should be judged .
• Delictual liability is liability arising in consequence of a wrong caused otherwlse than by breach of conlracl.
148
D. 7 LIABILITY FOR NUISANCE
o. 7.1 Nuisance is any unreasonable use of land which injuriously affects
the use and enjoyment of neighbouring land. Examples of possible
nuisances in the case of large excavations would be excessive
noise, dust, vibration, etc.
(d) The person liable is the originator of the nuisance, who, in the
case of excavations, would generally be the contractor. An action
based on nuisance could involve others too, however, depending
on circumstances.
(a) abatement
{b) interdict
{c) damages
150
0.9.3 Where wilfulness or negligence is not an ingredient of the offence,
the charge would generally relate to the breach of some statutory
provision or regulation. As most of the people who will use this Code
have, in any event, to familiarise themselves with these statutory
provisions and regulations, it is not deemed necessary to discuss
them fully. Attention might, however, be drawn to one example, i.e.
Factories, Machinery and Building Work Act, 1941, Sections 34 to
37 (Buildings and excavations to be subject to inspection).
151
APPENDIX E
REMOVAL OF LATERAL
SUPPORT RISKS:
CONTRACTUAL ASPECTS AND
INSURANCE
E.1 INTRODUCTION
This risk could exist notwithstanding the fact that some forms
of construction contract may attempt to transfer some of this risk
to the Contractor to an extent which varies from one document
to another.
The Contracto r's risks of liability to others arise.in three ways, viz:
b) that_ t_he 'policy sh all be kept in force until the issue of the final
c� rt ,ficate ... ' �h�n the indemnity cover may be requi red beyond
this date as indicated in E.2.1 a) above.
In view of th e fore
g oin · _,t should be app r
�hould ensure a ent that the Employer
that h; is adequate
insurance for an ly pr otected by a policy of
y t·manciat lo th
r moval of supp
e ort. ss a he may incur relative to the
t
158
There may be a duty on the Professional Team, particularly wh
dealing with a layman owner, to advise such owner to insure agaiis�
such risks.
It is apparent from the foregoing that the Employer carries the major
risk of liability in co�nection with the removal of support to property.
As he cannot readily transfer all of such risk to the Contractor or
Engineer, he has a vested interest in the insurances that are to be
effected to provide indemnity in respect of such risks.
b) Whilst the contract may require that this insurance should extend
to indemnify the Employer, such indemnity would generally only
relate to claims arising from the activities of the Contractor or
his subcontractors.
E.6.1 Scope
E.G.4 Deductible
161
The alternative is to apply the d eductible as an exclusion of the fi t
rs
amount of each claim, but, as for example, an underpinnin
operation could result in a number of cracks appearing at differe �
times, Insurers could then argue that each crack constituted a clai�
and that each claim should be reduced by the deductible amount
This alternative however is likely to result in disputes with insurers:
E.6.5 Premium
164
APPENDIX F
CASE HISTORIES OF
WALL M O V E M E N T S
F .1 INTRODUCTION
165
1---�:.:'..
2
1 _:_H:____�--- No damage
:i
3m
--....,Damage
0,6rn C
-
Lateral
Point Settlement movement
A1 B1 c, mm mm
H= 10m to 15m
25 to so
A .. 50 to 150 12 to 38
Soft clay or wet B -25 to 75
loose silty sand C 6to 19 3 to 12
.: . 30 to 75
/
. . ... A
: . . .1.
50
B, 12 25 to 38
: '· -·
: C .·- ..
. .
, , 3 ,•; 3
', l • .'-
01 ,
•
- ·:·': .
. S
t, •
(1) Wall acts as cantilever .(2) Wall propped at ground level
(horizontal movements greater (horizontal movem ents less th an
than vertical) vertical)
i
. .
I
Soft clays 2 .
Loose sands and gravels 2 , ,
0,2 (dense sand� and tills) 0,5
Stiff clays 0,5 <0,15
F I G U RE F1 T (1 9�
YPICAL WAL oos1
L MOVEMENTS OUTSIDE AN EXCAVATION [after
156
TABLE F1 MOVEMENTS OF ANCHORED WALLS (SOILS GROUP IN ACCORDANCE WITH PECK, 1969) (AFTER BS 8081, 1989)
Shannon & Strazer (1970) 24,6 75 0,30 75 0,30 King-post and guniting Bearing capacity failure of
king-posts required emergency
- - measures
Dietrich et al (1971) 17,4 46 0,25
-- King-post and poling board King-posts settled 63mm
Trow (1974) 10,5
10,0
25
25
0,25
0,25
-
-- King-post and poling board
Saxena (1975) 17,0 67 0,39 Reinf. concrete diaphragm Bending moments measured
- -
Jelinek & Ostermayer
19,50
20,0
146
140
0;75
0,7' - - Reinf. concrete diaphragm
(1976)
- -
I
Rizzo et al (1968) 11,3 20 to 38 0,18 to j King-post and poling· board Active method
0,34
Group two. Cohesive granular soils (e.g. clayey sands, silty sands, sandy clays)
' .
Phillips & James (1973) 10,4 10 0,10 - - Reinf. concrete diaphragm Bending moments also
- -
Sandegren et al (1972)
Cunningham & Fernandez
6,7
7,0
28 ' 0,42
.100 to. 18 · 1.4;3 to - - Sh�et pile.
Reinforced concrete
Deflection due to frost heave
After wall heated
(1972) 0,27 diaphragm
Murphy et al (1975) 10,0 5 0 '05
',
1
- - King-post an'd poling bo'ard Varied clay underlain by dense
till
Broms & Stille (197�) 6,3 50 to 1_50 1,60 17,5 to 4,0 0,28 to
0,06 Sheet pile Block Manfred, Vasteras
settlements measured 6m and
\ ";: -
0,34 and rock
-
S\.\\\e 8,. 'l"redr\\<.sson (."\979)
\ '\O
\
0.'\3 Sheet pile Ground settled 50mm st 7.5m
J behind wall
TABLE Ft MOVEMENTS OF ANCHORED WALLS (SOILS GROUP IN ACCORDANCE WITH PECK, 1969) (AFTER BS 8081, 1989) Continued
I REFERENCE I DEPTH
OF
1 CREST
DIS- MH
SETTLE-
MENT c5/H
WALL TYPE REMARKS
Malijian & Van Beveren 28,0 50,0 0,15 - - settlements may be high
King-post and poling board Settlements of king-posts of
(1974) 100mm to 150mm caused
cracks in roads and broke
Mullane 11,2(5)* 17 0,15 6 0,05 Steel soldiers Very dense silty sand Anchor force
(1989) 11,7)(N)* 3 0,03 6 0,05 residual quartzite and very 640-670kN/m. 400kN
stiff silt residual diabase anchors. Water table
9-10m(S).
Mullane 12,S(S) 24 0,19 25 0,20 Steel soldiers - , top 2 .Residual· quartzltic and Anchor force
(1989) 9,7(N) 3 0,03 4 0,04 metres lagged shale soils 730-S00kN/m. 400kN
anchors. No water.
Mullane 16,S(S) 33 0,20 40 0,24 Steel soldiers - top 2 Sm of dense silty sand
(1989) 18,0(N) ., 8 0,04 16 ' 0,09 metres lagged hillwash overlying very Anchor force
' dense silty. sand residual 1600-1800kN/m.
diabase 400-SOOkN anchors. No
water.
Mullane 8,6(S) 13 0,15 5 0,06 Steel soldiers Sm of fill and stiff sandy silt Anchor force
(1989) 6,6(N) 3 0,05 3 0,05 overlying very soft rock 410-675kN/m. 450kN
shale anchors. No water.
Rauch 10,0 7,5 0,08 6,5 0,07 Reinforced concrete Sm of transported silty Anchor force
(1984) 13,7 24 0,18 25 0,18 diaphragm wall sand overlying stiff residual 930-1470kN/m.
\
clayey silt with hard shale
'
600-900kN anchors.
at 12m Water table at 4m.
• \S) deno'\es aou'\hem 1ace, (.N) denotes northern 1ace, (W) denotes weatem face and (E) denotea e-tem face tor excavation• In JohanneabUl'fl.
TABLE F2 MOVEMENTS OF ANCHORED WALLS - SOUTH AFRICAN CASE HISTORIES Continued
*(S) denotes southern face, (N) denotes northern face, (W) denotes western face and (E) denotes eastern face for excavations In Johannesburg
APPENDIX G
EXTRACTS FROM CERTAIN
RELEVANT REGULATIONS
AND ACTS
The Factories, Machinery and Building Work Act (1941) (Act 22 of 1941 ),
has been replaced in part by the Machinery and Occupational Safety Act
1983 (Act 6 of 1983), and therefore the latter applies where certain chapters
of the former Act have been replaced by new regulations.
173
BUILDING REGULATIONS
G.2 EXTRACTS FROM -NATIONAL
AND BUILDING STANDARDS ACT, 1977,
AS PUBLISHED AS PART OF SABS
0400-1987 THE APPLICATION OF THE
NATIONAL BUILDING REGULATIONS.
174
(3) No part of such fence, hoarding or barricade shall be rem
oved
without the permission, in writing, of the local authority
until the
work has been completed.
(1) Where any local authority has reason to believe that there may
be unstable subsoils or unstable slopes in the area in which a
site, upon which a building is to be erected, is situated, it shall
so inform the applicant.
(2) Whether or not such local authority has informed such applicant
in terms of subregulation (1), the applicant shall, if any unstable
soil or unstable slope is evident within the boundaries of such
site, submit to the local authority particulars specifying the
measures he considers necessary to make provision for any
differential movements or other effects which could be
detrimental to such building and the local authority may require
such particulars to be prepared by a professional engineer or
other approved competent person.
(b) obtain the written authorization of the local authority for such
excavation; and
(3) While any excavation remains open, and during the placing of
the foundation within it, such excavation shall be maintained
in a safe condition.
(4) Any owner who fails to comply with any requirement of this
regulation, shall be guilty of an offense.
(1) The owner of any site shall provide an approved means for the
control and disposal of accumulated stormwater which may run
off from any earthworks, building or paving.
(ii) fess than three metres but more than 1,5 metres if the width
of the adjacent working or traveling space is less than the
vertical height of the face or sidewall.
179
APPENDIX H
DRAFT SPECIFICATION FOR
BLASTING IN BUilT-UP AREAS
(a) The Engineer shall have the power to prohibit the use of explosives
in cases where in his opinion, the risk of injury or damage to
persons, property or adjoining structures is too high. Such action
by the Engineer shall not entitle the Contractor to any additional
payment for having to resort to other less economical methods
of construction unless otherwise provided in the Special Provisions
or Schedule of Quantities.
Prior to starting any drilling for the first section of blasting, the
Contractor shall submit for approval to the Engineer, details of
the proposed overall method of blasting that will be used on site,
including spacing, depth and pattern of holes, charging levels
(kg/m3), spacing and positioning of relays, method of blast
initiation, precautions to prevent 'fly rock', maximum change per
relay, traffic arrangements during blasting, and any other detai!s
he may consider relevant. These details shall be submitted in
writing and supported with sketches at least 7 days before the
commencement of drilling and blasting.
182
Engineer will evaluate these details in relation to the given
· e· ·
Th
. .
11mItations and prior
· t o giving his approval, will indicate to the
Contractor any changes that may possibly be needed to comply
with the limitations.
183
ATION)
E H1 MA XI MU M PARTICLE VELOCITIES (VIBR
TABL
MAXIMUM PEAK
PARTICLE EFFECT ON PEOPLE AND BUILDINGS
VELOCITY (mm/s)
ly
0,5 Threshold of human perception unlike to cause
damage of any type
V = (k)'
-
m n
E
D
where k, m and n are constants for a part of
circumstances. V is in mm/s, D is in metres and icular set
E is in kilograms.
Experim entation has shown that n = 0,5,
be determined for each site by means of vib but k and m have to
at
However, blasting can be safely conducr ion measurements.
measurements or expert advice if the ted without vibration
following relationship is
used:
V=�Eo, s
D
which gives the maximum charge levels for v = somm/s listed
in Table H2.
184
TABLE H2 MAXIMUM CHARGE LEVELS
The above relationship can be used to calculate charge mass for other
velocity limits. However, if higher charge levels have to be used for practical
reasons, expert advice and possibly vibration measurements will be
required.
Notwithstanding the above blasting limits, the Contractor shall at all times
be responsible for the safety of the Works, persons, animals and property
in the vicinity of the Site during blasting operations.
H.3 BIBLIOGRAPHY
SASS 0120: Part 5, Section D (1982). Code of practice for use with
standardised specifications for civil engineering construction and
contract documents. Earthworks: Clause 3.2.3. Explosives. South
African Bureau of Standards, Pretoria.
South Afric�n Republic (1980). Mines and Works Act (Act 27 of 1956)
and regulations. Lex Patria Publishers (Pty) Ltd. Johannesburg.
�an �iekerk, Kleyn & Edwards (1988). Data from numerous blasting
v1brat1on measurements in southern Africa._
1 86
APPENDIX I
SUGGESTED METHODS OF
MEASUREMENT FOR LATERAL
. SUPPORT, EXCAVATION AND
ASSOCIATED WORKS
This Appendix offers guidelines for methods of measurement of the works
associated with excavation and lateral support. Section 1 is an abstract
from the Standard System of Measuring Builder's Work (5th Edition, 1987),
issued by the Association of South African Quantity Surveyors in
consultation with the Building Industries Federation (South Africa), covering
Earthworks and Piling. Section 2 is the suggested method of measurement
of lateral support covering ground anchoring and associated works, as well
as planking, strutting and shoring. This has been adapted from the Standard
System of Measuring Builder's Work issued by the Association of South
African Quantity Surveyors in consultation with BIFSA, since the
Association of South African Quantity Surveyors are at present updating
this section of their Standard System of Measuring Builder's Work (5th
Edition, March 1987)
1.1.1 EARTHWORKS
1.1.1.5 Demolitions
Demolition and removal of buildings and other structures shall be
s,
given in number, giving general descriptions and sizes. Fence
s. (Th e
boundary walls, etc., may be given separately in metre
188
removal of foundations shall
be dealt With
. I .1 . 1 . 2. ) i. n accordanc
e w,'th clause
The manner of disposal
of m at
materials are to become the enals shall be stated and ,
roperty of the c wh er
sh aII be made for allowin cP ontractor, provis e
ion
g redit.
1.1.1.6 Scope of measurement
The quantities of all e
xc avatio s . s h_all b
formed in accordan ce with e th e net voids to
the. � rawings and be
shall be not" less than the specification and
h onzontal area of th e bott
reIevant structures, multiplie om of the
d bY th� average d e p
surface. Where undercuttin i ths from the
s prescnb d, ho
work shall be kept separateg w v r, the undercut
all n �
e e
at an angle of 45 degrees� Ex e
�:�n ;:0��;:�!� i: �:�ic:
e
��
The description shall indicate
that th e contractor is to make
allowance for bulking
1• 1 · 1 .8 Bulk excavations
t tn
Bulk excavations shall be given in cubic metres and, exce�
s,
open face excavations such as cutting or levelling of slop in� site
ons to
shall be separated into successive depths of 2m. Exc�vat,
ng stated.
open face shall be so described, the extreme depth bei
189
in successive depths of 2m shall
The classification of excavafons
�ound or red uced level, as the case
be related to th e average 9
may be.
and holes
1.1.1.9 Excavat.ions for trenches ll eac h be
.
given
.
in
.
cubi c
or tren ches and hol es sha
Excavations f . depths of 2m. Th e
siv e
metres an d k ept separa te in suc ces
· e d epthsof 2m shall be
classification of excavations in successiv
el, as the case may
related to the average ground or reduced lev
be.
1.1.1.13 FIiiing
�illing_ shall be measured to the compacted volume and given
'" cubic metres stating the method and/or degree of compaction.
1.1.1.17 Gabions
Retaining structures formed of filled gabion boxes and mattresses
shall each be given in cubic metres, stating the sizes of boxes
and mattresses and the diaphragm spacing.
1.1.1.19 Tests
Prescribed tests to establish the degree of compaction or other
properties of the ground or filling shall be given in number.
191
1.1.2 PILING
GENERAL
Separate items shall be given for trial piles, raking piles, piles
driven in contact with one another, piles driven clos� together
in groups or to form sheeting, piles sunk from basement or from
any level other than natural ground level, piling carried out under
water, and piles sunk under other special conditions.
1.1.2.3 Reinforcement
Reinforcement shall be included in this trade and given as
provided for in 'Concrete, Formwork and Reinforcement'.
1.1.2.4 Testing
Testing of piles shall be given in number.
1.1.2.5 Plant
·
An item shall be given for transporting plant to the site and
removal.
DRIVEN PILING
SHEET PILING
194
1.2 SECTION 2 : GROUND ANCHORING, PLANKING, STRUTTING
AND SHORING
1.2.1 GENERAL
1.2.1.2 Insurance
• Insurance against claims arising from the remov�I of lateral
support shall be allowed for by provisional sum.
1.2.2.2 Establishment
An item shall be given for establishment of plant, etc., on the site,
which shall include for disestablishment on· completion of the
contract. Reestablishments for testing, retensioning or
destressing shall be given in number.
196
1.2.3 PLANKING, STRUTTING AND SHORING
Bolts and clamps shall be given in tons and may be included with
the relevant items.
197
APP·ENDIX J
DEFINITIONS OF SOME
ANC�QR TEA.MS
Anchor head
The component of a ground anchor that is capable of transmitting the tensile
load from the anchor to the surface of the ground or structure requiring
support._
Coating
A term sometimes used to describe the grease filling in the annulus between
the sheathing �nd t�e ten_don. (Se� Section 6.6.1.)
Characteristic strength
The characteristic strength of prest�essing steel is the tensile.strength below
which no more than 5 per cent of test results in a statistical p�pulation
may fall.
Corrugated sheathing
A corr ugated plastic tube sometimes u�ed �to proviqe both corrosion
protection and· effective load transfer through shear across the corrugations
in the fixed anchor length.
Creep
The change in strain of the tendon with time, under constant stress.
Debonding
The breakdown of bond at the grout/tendon or ground/grout interfaces.
Decoupling
The separation of components when tendons are to be debonded from
the surrounding grout by greasing and sheathing, sheathing only, or by
other methods to eliminate lo�d transfer.
Design load
See working toad.
199
Draw�in . . n caused by relative movement
on°f the tendo
Draw-in is the loss in elongati on ents owing to seating and
h� ge o pier comp
betw�en th� anc ra
.
cti on du rin g or 1
�� � :d i ately after transfer of load
gripping a
Gra�e
A chemical compound normally resembling grease, used sometimes to
protect the tendon against corrosion where no bond is required to the
surrounding material. Usually located in t�e annulus between the tendon
and the sheathing in the free length, or
· as· a filler nea r the anch or head.
(See Section 6.6.1.)
Ground anchor
An installati on that is ca p a ble of transmitting an applied tensile load to a
load-bearing stratum. The installation consists basically of an anchor head,
free anchor length and fixed a nchor (See Figu_re 6·. 1.)
G.U.T.S
Guaranteed ultimate tensile strength, a term
characteristic strength.
no I anger used. s ee
!J��ir��
Hydrogen embrittlement
ind c�d crack ing or severe loss of
ductility caused by absorption
en �unng a �1c
_ _
klmg, cleaning or plating pr
ocess.
Initial load (Ti)
The minimum load to wh
ich an anchor 1s rebou
nded during stressing.
King post
See soldier.
200
Lagging
Planks or boards inserted behind or between soldiers to assist in the
transfer of the anchor or supp Jrting loads via the soldiers and/or walers
to the supported material.
Liftoff load
The minimum load monitored during a restressing operation at which the
anchor head just lifts off its seating.
Lock-off load
The load transferred to the anchor head immediately on completion of a
stressing operation.
Permanent anchor
An anchor that is required to ensure the stability and satisfactory service
performance of the permanent structure being supported. The service life
is greater than 2 years and the anchor is protected against corrosion. (See
Table 6.1.)
Pitting
Corrosion of a metal surface, confined to small surface cavities or pits rather
than general surface corrosion, the formation of which is ·attributed to
processes such as fatigue, load adhesion or cavitation. A width/depth ratio
of one is commonly recognised for a pit.
Pitting factor
The ratio of the depth of the deepest pit resulting from corrosion divided
by the average loss due to corrosion often calculated from weight loss.
Planking
See lagging.
Poling board
See lagging.
Residual load
The load remaining in the anchorage at any time during service.
Rock bolt
A specific form of ground anchor where a bar of steel or other appropriate
material is fixed in rock.
Sheathing
A smooth plastic tube over the free length of the tendon to ensure
decoupling and in some cases to assist in corrosion protection.
Skin fri�tion
The frictional resistance developed between the ground and the grout in
the fixed anchorage.
Soldier
A vertical member of a supporting system for distributing anchor or strut
loads to the_ supported soils. ..
Soldier piles
Soldiers which are cast in situ in holes drilled prior to construction to form
a continuous structure.
Temporary anchor
An �nchor that is often used during the construction
phase of a project
to withstand forces for a known short period of
time usually less than 2
years. These anchors are normally destressed
when they have serve.d their
purpose.
202
Note: l_f aggressive corrosive ac�ion is likely during service, special
protective measures may be mqu1red. (See Table 6.1.)
Tendon
Tha� element of the _ground anchor which is capable of transmitting the
tensile load from the fixed anchor to the anchor head (i.e wire, bar or strand).
Tieback
See ground anchor.
(a) The load which can be maintained without excessive creep movements.
(b) The load which is the product of the characteristic strength of the
material and the cross-sectional area of the tendon.
Waler
A horizontal member of the support system spanning between soldiers in
order to distribute restraining forces to the soldiers.
Working anchor
An anchor, either temporary or permanent, which is installed to form part
of the supporting system either during or after construction or both. Some
working anchors may be specially tested and monitored as site suitability
test anchors.
203
APPENDIX K
REFERENCES
AE&CI (1982). The effects, measurement and control of ground vibrations.
Explosives Today, Series 2, No.27, March.
Bishop AW (1948}. A large shear box for testing sands and gravels. Proc.
2nd Int. Cont. Soil Mech. Found. Eng. Rotterdam. Sub Section lie.
Bishop AW (1954}. The use of the slip circle in the stability analysis of
slopes. Proc. Europ. Cont. Stab. Earth Slopes, Stockholm. Vol 1.
205
} . The us e of slip cir cle in the stability analysis of earth
Bishop AW (1955
Vol 5 No 1 ·
slopes. Geotechnique,
s in
W d He nk el DJ (19 62 }. The measurement of so il prop ertie
Bishop A an
Arnold, Lond0n.
the triaxial test. Edward
een GE , Ga rga VK , An d ersen A and Brown JD (1971). A
Bishop AW, Gr
application to the measurement of residual
new ring shear apparatus and its
strength. Geotechnique, Vol 21.
tability coefficients for ea rth slopes.
Bishop AW and Morgenstern N (1960). S
Geotechnique, Vol 10.
Brink ABA (1979-1985}. Engineering Geology of southern Africa. Volumes
1-4, Building Publications, Silve rton.
Broch E and Franklin JA (1972). The point load strength test. Int. J. Rock
Mech. Min. Sci. Vol 9.
Broms BB and Stille H (1976}. Failure of anchored shear pile walls. Proc.
ASCE 102(GT3) March.
Bruce DA and Jewell RA (1986, 1987). Soil nailing: application and practice.
Pa rt s 1 and 2, Ground Eng. Nov. and Jan.
B� 1377 (1975). Methods of test for soils for civil engineering purposes.
Bnt. Stand. Inst. London.
B� 1501 (1973) (Part 3). Corrosion and heat resisting steels. Imperial units.
Bnt. Stand. Inst. London.
BS 4486 (1980) S
high ten sile all�y
:i:�� ·
'f at,o for hot rolled and hot rolled and processed
�
ars ;or the prestressing of concrete. Brit. St and.
Inst. London.
Cedergren HR {1977). Seepage, drainage and flow nets. John Wiley and
Sons, N.York. 2nd Ed.
Clo ugh GW, Weber PR and Lamont J {1972). Design and observations
of a tied-back wall. Proc. Spec. Conf. Performance of earth and earth
supported structures {ASCE), Perdu Univ. Part 2, June.
207
les de s maximis et
b CA (177 6 ). E ssa ·
1 sur une application de. s reg
. ). '
om
. • s a. quelques probl·emes de statiq ue relat1fs a larch 1tecture. Mem.
Coul
mm,mu
ris.
Acad. R. pres. p. div sav vii, Pa
cathodic protection. Brit. Stand. Inst.
CP 1021 (1973). Code of practice for
72). Performance of two slurry wall
Cunningham JA and Fernandez JI (19 Performance of earth and earth
systems in Chicago. Proc. Spec. Cont.
iv. Part 2, June.
supported structures (ASCE), Perdu Un
DJ (1967). Behaviour of a
D'Appollonia E, Alperstein A and D'Apollonia
colluvial slope. Proc. ASCE 93(SM4), July.
Day PW (1989). Personal communication.
208
Gassler G and Gud ehus G (1981). Soil nailing - some aspects of a new
technique. Proc. 10th Int. Cont. Soil Mech. Found. Eng. Stockholm, Vol3.
Haines EC, O'Leary EM and Watkins HJM (1980). Crown offices, Cathays
Park, Cardiff. The Structural Engineer; 58A(4).
Hobst and Zajic (1982). Anchoring in rock and soil, 2nd Ed. Elsevier Sci.
Publ. Co. N. York .
210
Kovari K and Fritz P (1976). Stability analysis of rock slopes for plane and
wedge failu�e with the aid of a programmable calculator. Proc. 16 Symp.
Des. Meth. m Rock Mech., (ASCE), Univ. Minnesota.
Ladd CC (1971 ). Settlement analyses for cohesive soils. Res. Rep. R71-2,
Soils Publ. 272, Dept. Civ. Eng., MIT.
Lambe TW and Whitman RV (1969). Soil mechanics. John Wiley and Sons.
N. York.
. - -
- .
Larson ML, Willette WR, Hall HC and Gnaedinger JP (1972)._A case study
of a soil anchor tie-back system. Proc. Spec. Cont. Performance of e·arth
and earth supported structures, (ASCE), Perdue Univ.
211
onal co mmun
icatio n .
Lou don PA (1989) Pers
nal co mmunication.
Lourens JP (1986) Perso
• . ounod· Pa ris.
et geoI og1e
Lugeon M (1933) · Barrages
. .
JL (19 74). Tie-ba ck excavations tn Los
Malij ian PA and Van B � e e n
c � l 100 (C03).
Angeles area. Proc. AS o
Marsl and A (1971). The shear strength of stiff fissured clays. Proc. Roscoe
Memori al Symp., Cambridge Univ.
NTC (1978). Specifications for Contract No. NVK 101013. Vol 3, Special
Provisions. Clause SP 3406 (f)(iii): Limitations for blasting. National
Transport Commission, Pretoria. ·
NTC (1980). Standard specificati_ons for road and bridge works. Section
1200: General requirements ·and provisions. Clause· 1224: ·use of
explosives. National Transport Commission, Pretoria.
Rowe PW (1952). Anchored sheet pile walls. Proc. ICE Vol 7(1 ).
214
SABS 1200 Part B (1982). Standardized specification for civil engineering
con struction. South African Bureau of Standards, Pretoria.
SABS 0400 (1987). The application of the National Building Regulations.
South African Bureau of Standards, Pretoria.
215
z owski MK (1977). Behaviour of anchored
Sills GC, Burland. JB nd C ech Cont. Soil Mech. Found. Eng.
1 clay • Proc • 9th Int.
diaphragm wall in st.;
Tokyo, Vol 2.
. DD (1979). A computer model for the
Simps?n B' O'R'iordan NJ and Croft
don clay. Geotechnique, Vol 29(2)
analysis of groun d movements in Lon
lity of clay slopes. Geotechnique
Skempton AW ( 1964). Long term stabi
Vol 14 (4th Ranki ne Lecture).
r
Somerville SH (1986). Control of groundwater for tempo ary works.
Construction Industry Research and Information Assa. Report 113.
South African Republic (1980). Mines and Works Act (Act 27 of ·1956) and
regulations. Lex Patria Publishers (Pty) Ltd. Johannesburg, 1980.
South African Republic (1983). Machi nery and Occupational Safety Act
(Act 6 of 1983) and regulations. Lex Patria Publishers (Pty) Ltd.
Johannesburg. . .
South African Re public, (1985 and 1987). Building Standards Act (Act 103
of 1977) and National Buil ding Regulations. Lex Patria Publishers (Pty)
Ltd. Johannesburg, Amend. 1987.
St John HD (1975). Discussion on Papers 14 to
17. Proc. Cont. Diaphragm
walls and Anchorages. ICE, London.
216
Terzaghi K and Peck RB (1967). Soil mechanics in engineering practice.
John Wiley Sons, N. York. 2nd Ed.
TMH6 (1984). Special methods for testing roads. NITRR CSIR. Pretoria.
Van Niekerek, Kleyn Edwards (1988). Cape Town. Data from numerous
blasting vibration measurements in southern Africa.
Webb DL (1976). State of the art report. Penetration testing in South Africa.
Europ. Symp. on Pen. Testing, Stockholm.
White RE (1975). Anchored walls adjacent to vertical rock cuts. Proc. Conf.
Diaphragm Walls and Anchorages. ICE, London, and Discussion.
217
Winterkorn HF and Fang H (Ed)(1975).; Foundation engineering handbook.
Van Nostrand Reinhold, N. York.
Wrench BP (1984). Plate tests for the measurement of modulus and bearing
capacity of gravels. Civil Engineer in S.Africa (SAICE), September.
218