1325.19-Mr.

Bahirat, Commercial Building, Strengthening results


Provision- B+L.G. +U.G. +12+4 (Additional Floor)

SR.NO. COLUMN / SHEAR WALL Strengthening  Required ( Slab Levels)


Nos.

1 C1 From Footing Top to 8nd Slab Level.

2 C2 From Footing Top to 6th Slab Level.

3 SW4,11 From Footing Top to 2nd Slab Level.

4 C6,8,10 From Footing Top to 4th Slab Level.

5 C12 From Footing Top to 5th slab Level.

6 C13 From Footing Top to 5th slab level.