Professional Documents
Culture Documents
To Study and Analyze Project o - Shahab Ali Khan (Syndicate Lea - 1708
To Study and Analyze Project o - Shahab Ali Khan (Syndicate Lea - 1708
I
BE CIVIL ENGINEERING
PROJECT REPORT
SUBMITTED BY
Syndicate 17
PC-2444 Shahab Ali Khan (Syndicate Leader)
PC-2442 Waseem Iqbal
PC-2446 Muhammad Ali Butt
ASC-2451 Rameez Shahzad
II
This to certify that the
SUBMITTED BY
Syndicate 17
PC-2444 Shahab Ali Khan (Syndicate Leader)
PC-2442 Waseem Iqbal
PC-2446 Muhammad Ali Butt
ASC-2451 Rameez Shahzad
Has been accepted towards the partial fulfilment of the requirements for
___________________________
III
Dedication
This work is especially dedicated to our parents who prayed for us tirelessly, our supervisor,
supportive friends and all faculty members of the Construction Management department.
For their support, encouragement and belief in us. We are truly indebted.
IV
ACKNOWLEDGEMENT
We are thankful to
ALMIGHTY ALLAH Who gave us the strength, ability and wisdom to achieve everything in our lives
Our Parents and Families who are a source of constant support for us and without whose prayers we may
never achieve anything.
Our Friends and Course Mates for helping us through thick and thin.
Our Project Supervisor Lt. Col. Mughees Aslam for his guidance, encouragement, patience,
knowledge and for providing us with freedom of action.
Maj Muhammad Ahmed, XEN Shahid and MES Risalpur Cantt staff, AGE Shabbir
Ahmed for their patience and constant support throughout the project.
V
TABLE OF CONTENTS
LIST OF FIGURES...................................................................................................................X
LIST OF TABLES.....................................................................................................................XI
LIST OF ABBREVIATIONS…………………………………………………………………XII
ABSTRACT...............................................................................................................................IX
Chapter 1………………………………………………………………………………………1
INTRODUCTION……………………………………………………………..........................1
1.1 Introduction to 100 BOQs…………………………………………….........................1
1.2 Scope………………………………………………………………………………….1
1.3 Objectives…………...………………………………………………………………...2
1.4 Methodology………………………………………………………………………….3
Chapter 2………………………………………………………………………………………4
LITERATURE REVIEW………….……………….,…………………………………………4
2.1 Definition of Project......................................................................................................4
2.2 The Project Life cycle...................................................................................................5
2.3 Project Management......................................................................................................5
2.3.1 Managing a Project usually includes..........................................................................6
2.3.2 Project Management areas……………………………………………………..........7
2.4 Project Planning………………………………………………………………………..8
2.5 Planning Process……………………………………………………………………….8
2.6 Delay…………………………………………………………………………………...10
2.7 Factors causing delay in Project execution…………………………………………….12
2.7.1 Contractor related factors…………………………………………………….……....12
2.7.2 Client related factors…………………………………………………………………12
2.7.3 Consultant related factors…………………………………………………………….13
2.7.4 Material related factors……………………………………………………………….13
2.7.5 Equipment related factors…………………………………………………………….13
2.7.6 Labour related factors………………………………………………………………...14
VI
Chapter 3…………………………………………………………………………………..........15
AUTOCAD DRAWING AND 3D MODEL (REVIT)...……………………………………….15
3.1 Introduction......................................................................................................................15
3.2 AutoCAD Drawing...........................................................................................................15
3.2.1 Site plan.........................................................................................................................16
3.2.2 Layout plan....................................................................................................................17
3.2.3 Footing Plan…………………………………………………………………………...18
3.2.4 X-Section……………………………………………………………………………...19
3.2.5 Detail of Openings…………………………………………………………………….20
3.2.6 Structural Drawing 1………………………………………………………………......21
3.2.7 Structural Drawing 2………………………………………………………………......22
3.3 3D model of 100 BOQs………………………………………………………………….23
3.3.1 Isometric view…………………………………………………………………………23
3.3.2 Back side view………………………………………………………………………...24
3.3.3 Side view………………………………………………………………………………24
Chapter 4………………………………………………………………………………………...25
ESTIMATION OF 100 BOQs CIVIL WORKS...........................................................................25
4.1 Definition..........................................................................................................................25
4.2 Type of Estimates..............................................................................................................25
4.3 Estimation Methods...........................................................................................................25
4.3.1 Preliminary Estimates.....................................................................................................26
4.3.2 Detailed Estimating Method...........................................................................................27
4.4 Quantity Estimation of 100 BOQs....................................................................................28
4.4.1 Estimation of 32 BOQs..................................................................................................28
4.4.2 Estimation of 36 BOQs..................................................................................................31
Chapter 5......................................................................................................................................34
SCHEDULING ON PRIMAVERA P6……………………………………................................34
5.1 Scheduling .......................................................................................................................34
5.2 The tripod of Good Scheduling System...........................................................................34
5.3 Types of Project Schedules .............................................................................................35
5.4 Critical Path Logic Diagram............................................................................................35
VII
5.5 CPM Scheduling.............................................................................................................35
5.6 Types of Float ................................................................................................................36
5.7 Project Planning Software .............................................................................................36
5.7.1 Primavera Project Planner P6………………………………………………………..37
5.8 Planning and Scheduling of 100 BOQs………………………………………………..37
5.8.1 Defining the Calendar………………………………………………………………..38
5.8.2 Creating a New Global or project Calendar ………………………………………....38
5.8.3 Enterprise Project Structure (EPS)…………………………………………………...40
5.8.4 Organizational Breakdown Structure (OBS)…………………………………………42
5.8.5 How to Create a project………………………………………………………………44
5.8.6 Work Breakdown Structure (WBS)………………………………………………….45
5.8.7 Adding Activities of 100 BOQs in Primavera P6…………………………………....47
5.8.9 Activities of Actual Scheduled Project……………………………………………....48
5.8.10 Understanding Relationship………………………………………………………...51
5.8.11 Understanding Lag and Leads…………………………………………....…………51
5.8.12 Resources……………………………………………………………………………51
5.9 Scheduling of Project…………………………………………………………………...52
5.9.1 Activates of Planned Scheduling Project…………………………………………......52
5.9.2 Task or Out-Turn Work………………………………………………………………52
5.9.3 Scheduling of Planned Project……………………………………………………......58
5.10 Comparison of the project at WBS level………………………………………………59
Chapter 6………………………………………………………………………………………..62
IDENTIFICATION AND EVALUATION OF CAUSE OF DELAY OF 100 BOQs…………62
6.1 Introduction......................................................................................................................62
6.2 Information about 1000 BOQs………………………………………………………….62
6.3 Key Stakeholders……………………………………………………………..................63
6.3.1 Client/ Consultant..........................................................................................................63
6.3.2 Project Monitoring Team..............................................................................................63
6.3.3 Contractor …………………………………………………………………………….63
6.4 Factors identified affecting “Time Overrun” in 100 BOQs..............................................64
6.5 Questionnaire Design........................................................................................................64
VIII
6.6 Analysis of data…………………….……………………………………………............64
6.7 Deductions of causes of Delay…………………………………………………………..66
6.8 Recommendations………………………………………………………………….........68
REFRENCES…………………………………………………………………………………….70
APPENDICES…………………………………………………………………………………...72
ANNEX A-Taking of Sheets (Estimation) Of 100 BOQs……………………………...……72
ANNEX B-Questionnaire Design………………………………………………………......135
IX
LIST OF FIGURES
X
Figure 5.10 –Table view of Activities of 100 BOQs…………………………………………….49
Figure 5.11 –Table view of Activities of 100 BOQs…………………………………………….50
Figure 5.12 –Gantt chart view of Activities…...............................................................................50
Figure 5.13 –Out Turn work…………………………………………………………………......55
Figure 5.14 –Table view of Planned activities…………………………………………………..56
Figure 5.15 –Table view of Planned activities…………………………………………………..57
Figure 5.16 –Gantt Chart view of Planned Activities.............................................. ……………58
Figure 5.17–Comparison of Planned VS Actual Schedule.................................... ……………..59
Figure 5.18– Comparison of Planned VS Actual Schedule …………………….........................60
Figure 6.1–Key Stakeholders…....................................................................... …………………63
XI
LIST OF TABLES
XII
LIST OF ABBREVIATIONS
FS Finish-to-Start
SS Start-to-Start
SF Start-to-Finish
NCO Non Commissioned Officers
B/R Buildings and Roads
Sqm Square meter
Cum Cubic meter
CFT Cubic Feet
PCC Portland Cement Concrete
RCC Reinforced Cement Concrete
DPC Damp Proof Course
BB Work Burnt Brick Work
XIII
PVC Poly Vinyl Chloride
CM Cement Mortar
WC Water Closet
XIV
ABSTRACT
XV
Chapter 1
INTRODUCTION
100 BOQs is a residential type of building, located at Liaqat road Risalpur Cantonment
near MCE officers Mess. The project was executed by MES Risalpur and the contract was awarded
to M/S Ch Abdul Ghaffar and Co. The project was initiated on 14th April 2013 and according to
the contract it was supposed to be completed in one year. Unfortunately there was a delay of 6
months in completion of the project.
1.1.1 Location
1.2 Scope
The study of a real time Project (100 BOQs at MCE Risalpur) was chosen, which revolve
around Planning, Scheduling and Estimation techniques using latest software and Project
Monitoring & Control. In this process an on ground Construction Plan and Schedule will be
1
prepared for building Construction of 100 BOQs by inserting pegs of various activities as and
when they terminated. Then to compare it with proposed Project Schedule. This contrast would
indeed help to understand the importance of Construction Project Management in a real time
scenario, difficulties involved, delay causing factors and further leading the students to arrive at
some definite and practical recommendations/solutions for timely execution of Projects within
stipulated time frame. That surely have obvious economic impacts. It also involve Estimation of
quantities in Construction of 100 BOQs using Detailed Estimate method.
1.3 Objectives
a. To make comprehensive Work break down Structure and realistic Project Schedule using
Primavera Software.
b. Making of 3D model of 100 BOQs
c. Quantity estimation and preparation of bills of quantities.
d. Cost estimation of 100 BOQs.
e. To draw contrast of proposed Vs Actual Schedule of Project on ground
f. Identify delays with probable causes.
2
1.4 Methodology
3
Chapter 2
LITRATURE REVIEW
4
Fig 2.1 - Project life cycle
5
Fig 2.2 - Project Phases
The main challenge of project management is to attain all the aims while keeping in mind
any kind of limitations. The main limitations are scope, time, quality and budget.
6
2.3.2 Project Management knowledge draws on ten areas
1. Integration o
2. Cost
o
3. Stakeholder
4. .Human resources o
5. .Scope
6. .Quality
7. Communications
8. Time
9. Procurement
7
Fig 2.3 - PM knowledge Areas
Following are the successive steps for planning a construction project or any project:
8
It organize, integrate and bring all the necessary primary and secondary plans. It provide
information for how the project can be completed without compromising all the necessities.
b. Generating Work breakdown structure
This is the method of splitting project works into smaller, more manageable components.
c. Defining Activities
This define the actions which give us important deliverables.
d. Sequence Activities
This includes the necessary relations amongst different activities to perform in an organize
manner.
g. Developing schedule
This is the process of analyzing activity sequences, durations, resource requirements, and
schedule limitations to create the project schedule.
h. Estimating costs
It defines the cost required for a task to be completed.
9
2.6 Delay
Delay is very critical factor in any construction project because it increases the total cost
of the project. If a project is completed on time then it will benefit all the stakeholders in terms of
time and money. Therefore it is very important to identify those major factors which are
responsible for delay in construction projects. Late completion of construction projects is very
common in many developing countries. Time is very critical factor for every plan that a company
is trying to implement. There is a relationship between project time allotted, scope of project and
conditions at which project is undertaken. A very minute change in any of areas affects the overall
efficiency of the project. Time overrun is considered as cost causing factor for owner as well as
for contractor. In case of delay in construction of any project owner lose the revenue and contractor
loses the opportunity of attracting more tenders because of engaged in already ongoing project.
Public also suffer due to delay in construction of public sector projects. If project is failed to
complete on time then automatically its cost increases from closing bid cost. Time is very critical
resource and it should be managed before the start of the project. Time overrun and its impacts is
considered as one of the important factor in construction industry of Pakistan. inefficient contract
management, impractical scheduling, a little financing by client, delay in payments, design
amendments through construction, and non-availability of construction material materials like
cement and steel. The issue had also been found as of equal importance in Arab countries. Assaf,
et al., conducted a study in construction industry of Pakistan and reported critical causes of delay
related to contractor, constructor and client in large building projects. They further classified the
causes into nine divergent clusters like financing, materials, contract relationships, government
relations, manpower, scheduling and control, equipment, and environment. Later on, El-Razek, et
al., used these causes and revise the lists of delay causes with respect to the Egyptian construction
industry. They further emphasized the important role of consultants and payment by owner in
reducing the delays in large construction projects.
Delays in construction industry have also been a matter of great concern in Pakistan. However,
only two researches have been conducted for classifying the causes of delay in construction
industry of Pakistan. Shaikh, et al., introduced a theoretical framework by analyzing the previous
studies highlighting the client, contractor, general and resource related problems are key factors
causing delay in construction industry. In the same vein, Haseeb, et al., concluded in their study
that the most important and highly ranked causes are related to financial matters causing delays in
10
Pakistani construction industry. They further elaborated and identified the delays like delay in
payment to supplier, inadequate fund allocation, inflation and monthly payment problems.
However, there is need to identify the client, contractor, consultant, material, equipment, labor
related and general factors causing delay in project execution.
11
2.7.4 Material related factors
Material is very important factor if we talk about construction project. A number of
people have put their efforts in this field. On time provision of material has got high
importance in construction project. Sambasivan and Soon identified that material quality
and insufficiency are the factors which causes delay. Koushki and Kartam studied that
material selection has got huge importance in construction industry.
12
Chapter 3
AUTO CAD DRAWING AND 3D MODEL (REVIT)
3.1 Introduction
Hard and soft copy of 100 BOQs Auto Cad drawings were collected from MES and 3D
Model of the building was made using Autodesk Rivet. Auto Cad drawings include Site plan,
Layout plan. Footing plan, Schedule of openings and Structural Drawings.
13
3.2.2 Layout Plan
14
3.2.3 Footing Plan
15
3.2.4 X-Sections
16
3.2.5 Detail of Openings
17
3.2.6 Structural Drawing 1
18
3.2.7 Structural Drawing 2
19
3.3 3D Model of 100 BOQs
20
3.3.2 Back Side View
21
Chapter 4
ESTIMATION OF 100 BOQS CIVIL WORKS
4.1 Definition
Estimation is the process in which we determine the probable construction costs of any
type of project.
Estimating is the scientific way of working out the approximate cost of a building or an engineering
project. It is the process of determining the financial feasibility of any project and its further
enhancement is framing the tender work and calculation of Bid prices.
4.2 Types of Estimates
ESTIMATES
22
4.3.1 Preliminary estimates
These estimates are used in the early stages of a project to provide at least a rough estimate
of the construction cost at a time when there is no detailed information available about the nature
of the proposed project. The preliminary estimating includes:-
Price per Unit Area Estimates
They are also called Plinth Area/Square-Foot Area Estimates. Per Unit Area Estimates are
prepared by multiplying the plinth area with cost per square foot of any project. Further the prices
are adjusted to compensate for variation in building project like location, orientation, storey,
height, specifications.
e. Assembly Estimating
If the assembly (instead estimating each of the individual components of the project, the estimates
of the components in groups known as assemblies are made) price comes from previously
completed projects, it is estimated with the assumption that this project is identical to on ground
executed project.
23
estimating method is taking off all the quantities from complete design specifications and then get
a complete picture of accurate construction cost involved in the project. Because of this
requirement and also because detailed estimating is such a time taking procedure.
Whether prepared by hand, by computer spreadsheet, or by means of a totally computerized
system, a detailed estimate can be analyzed in terms of six distinct procedures
2. Recap Quantities: The amounts of work taken off are sorted and leaned to consent to the
exchange breakdown to encourage the procedure of evaluating.
3. Pricing the Recap: Costs for the required work, gear, and materials are entered against
the amounts to decide the evaluated expense of the manufacturer's own particular work.
4. Pricing Subcontractor’s Work: Costs are acquired from contending sub exchanges who
quote to perform the work of their exchange then, as a rule, the most minimal offer from
every exchange is gone into the assessment.
6. Summary
All the estimated prices are summarized and the contractor’s markup is added.
24
4.4.1 Estimation of 32 BOQs
1 Excavation 383.33
2 Backfilling 296.8
(Lean)
25
6 Cement Plaster (1:4) 1034.4 sqm
26
Cement Consumption
Net requirement of cement = 3929 bags
Services
Detail of Services are attached in appendices
1 Excavation 537.23
2 Backfilling 418.87
27
Table 4.8 Cement Concrete Work
(Lean)
28
Table 4.10 Steel Reinforcement
7 Stairs 624.945
8 Mumty 1014.97
Cement Consumption
Net requirement of Cement = 4348 Bags
Services
Detail of Services are attached within appendices
29
Chapter 5
SCHEDULING ON PRIMAVERA P6
5.1 Scheduling
Scheduling is determination of timing of events in the project i.e., When tasks will be
performed? Simply, it’s a reflection of plan.
The critical path logic diagram shows a logical interface between schedule activities. It is
also called PERT chart; that is Programmed Evaluation Review Technique. In this each activity
30
can be shown through a box. The activities and their precedence combined to form precedence
network.
Critical Path Method Scheduling is based on Critical Path Method (CPM) which can be
defined as "The Calculation of the earliest and latest start and finish dates of activities based
on their durations and relationship to other activities" CPM Calculations overview:
a. The calculation of early start and finish date, and latest start and finishing date for
each activity.
b. Early dates mean an activity can be start and finish as early as possible if all the
predecessor activities are completed.
c. Late dates mean an activity can be start and finish as late as possible without
delaying the succeeding activities.
a) Total Float
b) Free Float
a) Total Float
It can be found either by subtracting the early finish date from the late finish date or by
subtracting the early start date from late start date.
TF= LF-EF
TF= LS-ES
An activity that has zero total float is a critical activity. An activity’s start may be critical
even though an activity itself may not be critical.
b) Free Float
Free float is the difference between an activity’s early finish time and early start time for
any succeeding activity.
FF= EF-ES (next activity)
The free float of an activity is an amount by which that activity can be delayed without delaying
the early start of any following activity or any other activity in the network.
31
5.7 Project planning software
A number of soft wares are available in market which professionals & engineers use to
manage project and plan the project. These soft wares use a variety of paths to determine the critical
path of the project. These allow professional users and engineers to control the overall cost &
budget of the project. Most commonly used software for project planning is Primavera P6.
The study of a real time Project (100 BOQs at MCE Risalpur) was chosen , studied and
analyzed to apply first hand Civil Engineering knowledge at UG level. The study revolve around
Planning and Scheduling techniques using latest software and Project Monitoring & Control.
In this process an on ground Construction Plan and Scheduling will be prepared for building
Construction of 100 BOQs by inserting pegs of various activities as and when they terminated.
Then to compare it with proposed Project Schedule. This contrast would indeed help to understand
the importance of Construction Project Management in a real time scenario, difficulties involved,
delay causing factors and further leading the students to arrive at some definite and practical
32
recommendations/solutions for timely execution of Projects within stipulated time frame. That
surely have obvious economic impacts.
While Planning and scheduling for real time Project we used following sequence
33
Fig 5.2 – Global Calendar
35
Fig 5.4 - Chart view of EPS
36
Fig 5.5 - Table View of OBS
37
Fig 5.6 - Chart View of OBS
38
Fig 5.7 - Project of 100 BOQs
39
Fig 5.8 - Table view of WBS
40
Fig 5.9 - Chart view of WBS
41
5.8.8 Activity Types and Milestones
An Activity may be assigned one of the following default Activity Types using the drop
down box in the Project Defaults tab:
a. Finish Milestone
b. Level of Effort
c. Start Milestone
d. Task Dependent
e. WBS Summary
42
Fig 5.10 - Table view of Activities of 100 BOQs
43
Fig 5.11 - Table view of Activities of 100 BOQs
44
5.8.10 Assigning Relationships
There are four types of dependencies available in Primavera P6. We will be defining only two of
them.
a. Finish-to-Start (FS) (also known as conventional): The successor activity can begin
only when the predecessor activity completes.
b. Start-to-Start (SS): In this both the activities can start simultaneously but with
certain amount of lag between them.
5.8.12 Resources
Resources are all those requirements which need for the fulfillment of any task or activity. It
comes in three flavor in P6.
a. Labor (personnel)
b. Non-labor (Equipment)
c. Material
After assigning relationship to each activity, the project was scheduled and the following
deductions have been made.
a. The start date of the actual Scheduled project is 16 April, 2013.
b. The project Finished date is 16 October, 2014
c. Actual duration of the Project is 18 months
Hence the Project has a time overruns of six months
45
5.9.2 Task or Out-Turn work
The capacity of doing work by a skilled labor in the form of quantity of work per day is
known as the task-work or out-turn of the labor.
The out-turn of work per labor varies to some extent according to the nature, size, height, situation,
location, etc. In developed areas the out-turn of a skilled labor is more as compared to small
villages. Labor quantity also depends upon by managing and organizing the labor force.
The following may be taken as the approximate quantity of work or out-turn or task for an average
labor per day taken from a book “Estimating and Costing” by Dutta’s.
46
47
48
Fig 5.13 - Out turn work
49
Fig 5.14 - Table view of planned Activities
50
Fig 5.15 - Table view of planned Activities
51
Fig 5.16 - Gantt chart view of Planned Activities
52
5.10 Comparison of the project at WBS level
In order to identify the areas where time overruns occurred during actual project execution,
a comparison at WBS level is performed between actual Scheduled and Planned Scheduled Project
using MS Project.
53
Fig 5.18 Comparison of Actual vs Planned schedule
54
Graph 5.1 - % 0f Delay vs Major Affected areas
55
Chapter 6
IDENTIFICATION AND EVALUATION OF CAUSES OF DELAY
OF 100 BOQS
6.1 Introduction
The term delay is the time overrun in a construction of particular project beyond its
completion date written in a contract, or beyond the date that is given as contingency in terms of
time for delivery of a project. It is very common problem in construction projects. For delay in
construction of particular facility owner losses the revenue and rent if we are talking about present
constructed facility. In some cases, the contractor, has higher overhead costs because of long work
duration at same project, high material costs due to inflation, and high labor costs.
Despite of the fact that delay causes serious problems, construction industry simply ignores this
aspect in construction projects and only adds compensation for that in terms of contingency. This
delay factor is very high in construction projects of developing countries where time overruns
sometimes exceed 100% of the actual time of the project.
In Pakistan, construction industry is an important industry although this industry is not working to
its full potential but still it is very significant to the country’s development. Development in this
industry is critical for increase in national income as it is among the largest employment generating
sectors of country as well as a key driving force for economic development of Pakistan. Like many
other countries Pakistan is also facing very much issues in construction industry among which
delay in projects completion is quite important one. There are many factors that are responsible
for these delays.
56
6.3 Key stakeholders
6.3.1 Client / Consultant
1. Shabir Ahmad Usmani, AGE Army Risalpur Cantonment
2. Habib Ahmad , AE Risalpur Cantonment
3. Pervaiz Akhtar , AE Risalpur Cantonment
4. Hassan Jan , SDO B/R Army Risalpur Cantonment
5. Khalil Haider , SDO E/M Army Risalpur Cantonment
6. Zia-Ur-Rehman ,Sub Engineer B/R gde-II
7. Sajid Rahim , Sub Engineer
8. Hav Muhammad Irfan , Project NCO
6.3.3 Contractor
1. Chaudhary Abdul Ghaffar , Contractor
2. Fayaz Hussain , Project In charge
3. Kamal , Sub Engineer
4. Abdullah , Supervisory staff
57
The studies include to find out main problem involved in time overrun in construction
project of 100 BOQs in Risalpur Cantonment. In this regard 14 major areas were identified
where probable delay could occur.
They are
∑( 𝒇𝒊 ∗ 𝒊)
𝐼𝑚𝑝𝑎𝑐𝑡 𝑜𝑓 𝑓𝑎𝑐𝑡𝑜𝑟 =
𝒏
58
In this relation
i is the extent score from 1 to 5 (1=strongly disagree, 2=Disagree , 3=Neither agree nor
Disagree, 4= Agree, 5= Strongly Agree)
f i is the frequency of factor getting score i
n = number of responses from the stakeholders
By performing these calculation 15 total factors were got responsible for causing delay in
construction of 100 BOQs. The table given below shows impact of resultant factor
59
Graph 6.1 - Impact of Factor vs Factor
60
4. Misinterpretation of Drawings
a. Results in Suspension of work
b. Rework
c. Changes
5. Change in specification of Material during construction
It will lead to
a. Increase or decrease in cost due to change in material
b. Rework of different activities of the Project
6. Labor Disputes / Strikes / security issues
Time delay due to high official oftenly visiting Risalpur cantonment
7. Lack of Co-ordination between Design team and Contractor
a. Contractor would not be able to implement the design strategy
b. Due to communication gap on the part of contractor, the design team would not
be able provide requisite design amendments to the contractor
8. Slow Decision Making by the client/consultant
a. Labor force will remain idle
b. Construction machinery will remain idle
c. Material management issues
9. Delay in payment by the Client
a. Demotivation for labor
b. Material Procurement issues
10. Some factors which contribute to price fluctuations are
a. World prices for basic construction materials
b.Local economy’s present worth
c. Quality of materials and labor required
d.Supply and demand Fluctuating Prices of Raw Material / fitting fixtures
11. Adverse effects of weather resulting in delay
a. Decrease in labor Productivity
b. Slow execution of the project
c. Result in Rework
12. Non-conducive Law and Order / Security Situation
Time delay due to high official oftenly visiting Risalpur cantonment
13. Approval of variation order
Delay in approval of variation order will cause
a. Overall delay in construction Project
b. Lower the efficiency/output of the Project team
14. In-adequate quality of material used
It will result in
a. Suspension of work
b. Redoing of Work
c. Wastage of both material and cost
15. In-adequate duration of contract period
61
6.8 Recommendations
6. Inadequate Quality
Proper Supervision and Time to time visits by the Consultant on every single activity during
execution should be done to insure Quality management.
9. Misinterpretation of Drawings
Contractor should be competent enough to undertake such projects. Misinterpretation of
drawing would not tolerated
62
REFRENCES
1. Assaf, S.A., M. Al-Khalil, and M. Al-Hazmi, Causes of delay in large building
2. Sweis, G., et al., Delays in construction projects: The case of Jordan. International
5. Haseeb, M., A. Bibi, and W. Rabbani, Problems of Projects and effects of delays in the
6. Odeh, A.M. and H.T. Battaineh, Causes of construction delay: traditional contracts.
7. Baldwin, J.R., et al., Causes of delay in the construction industry. Journal of the
MS Thesis, King Fahd University of Petroleum and Minerals, Dhahran, Saudi Arabia,
1987.
9. Al-Khalil, M.I. and M.A. Al-Ghafly, Important causes of delay in public utility projects
63
11. Orozco, F., Serpell, A., Molenaar, K., and Forcael, E. (2011). “Modeling
12. Faridi, A. S., and El-Sayegh, S. M. (2006). “Significant factors causing delay in the UAE
13. Chang, A. S. (2002). “Reasons for cost and schedule increase for engineering design
14. Alarcon, L. F., Diethelm, S., Rojo, O., and Calderon, R. (2005). “Assessing the impacts
of implementing lean construction.” Proc., Int. Group for Lean Construction Annual
15. Flyvbjerg, B., Mette, K., Holm, S., and Buhl, S. L. (2004). “What causes cost overrun in
16. Galloway, P. D. (2006). “Survey of the construction industry relative to the use of CPM
64
Annex A
TAKING OF SHEETS (ESTIMATION) OF 100 BOQs
Estimation of 32 BOQs
Excavation
I. Excavation in foundation & pipe trenches up to 1.5 M wide, wells and
independent holes up to 30 sqm
II. Excavation over areas as in foundation / areas etc. or for shafts, wells
exceeding 30 sqm each.
65
PCC In Foundation (1:4:8)
Tot
Description N0 Length(ft) Width(ft) Depth(ft) Qty(cft)
((1198425*.25)/3+1
Total Qty(cft) 1149.35 50.71)
DPC
No Length Depth Total Qty(sqft)
4 18.87 0.75 56.61
4 18.87 1.12 84.5376
4 63.75 0.75 191.25
8 13 1.12 116.48
16 10 1.12 179.2
8 14.5 0.75 87
1 10.75 0.75 8.0625
1 7 0.75 5.25
8 14.5 0.37 42.92
16 5 0.37 29.6
Net Qty (Sqft) 800.9101
Net Qty (Sqm) 74.4450941
66
Brick Work
67
BB Work (upto GF Roof Level)
Description No Length Width Depth Qty-cft
9" Wall
4 18.87 0.75 12.5 707.625
4 63.75 0.75 12.5 2390.625
8 14.5 0.75 12.5 1087.5
1 7 0.75 12.5 65.625
13.5" Wall
4 18.87 1.12 12.5 1056.72
4 13 1.12 12.5 728
16 10 1.12 12.5 2240
Dwarf Wall
1 10.75 0.75 2 16.125
Total 9021.2
Total 987.4
NET QUANTITY OF BB WORK(IN CFT)
8033.8
NET QUANTITY OF BB WORK(IN CUM)
227.67
Total Quantity of BB work for 9" & 13.5" Wall 268.9
68
BB Work (Upto First Floor Roof lvl)
Description No Length Width Depth Qty-cft
4.5" Wall
16 14.5 0.37 12.5 1073
16 5 0.37 12.5 370
16 12 0.37 3.08 218.8032
Total 1661.803
Deduction
16 6.37 0.37 7 263.9728
16 2.5 0.37 7 103.6
367.5728
Net Qty(cft) 1294.23
Net Qty(cum) 36.67668
69
BB Work in Parapet Wall
Sum(cft) 1033.785
Sum(cum) 29.29602
Termite Proofing
Total
Description No Length Width Depth Qty(cft)
Room 16 12 10 0.25 480
Dress 16 7.12 5 0.25 142.4
70
Balcony 16 4.5 10 0.25 180
Gallary 2 65.62 7 0.25 229.67
Gallary 1 32.75 7 0.25 57.3125
Room 16 7 5 0.25 140
Sum(cft) 1229.383
Sum(cum) 34.83899
Cement Concrete Type B Laid in Floor Slabs, as under layer for Terrazzo
(GF+First Floor)
71
Cement Concrete Type C in Plinth Protection, Surface Finish (GF+First
Floor)
2 31.37 3 188.22
Sum(sqft) 1352.16
Sum(sqm) 125.684117
Cement Plaster(1:4)
Description No Length Width Tot Qty(sqft)
4 18.87 1.12 84.5376
8 18.87 0.75 113.22
8 14.5 0.75 87
16 14.5 0.37 85.84
8 10 1.12 89.6
16 5 0.37 29.6
4 65.62 0.75 196.86
13mm Thick(with 2X 8 13.75 1.12 123.2
layer of building Sum(sq ft) 809.86
paper) Sum(sqm) 75.277
2 44.75 27 2416.5
2 8.87 27 478.98
4 65.62 27 7086.96
64 27 1 1728
Sum(sq ft) 11710.44
13mm Thick Sum(sqm) 1088.49
Deduction
32 4.5 6 864
32 3 4 384
4 6 6 144
72
Sum(sq ft) 1392
Sum(sqm) 129.387269
Net Quantity(sqm) 959.11
Cement Plaster(1:6)
Description No Length Width Tot Qty(sqft)
64 12 10.5 8064
64 10 10.5 6720
64 7.12 10.5 4784.64
64 5 10.5 3360
64 7 10.5 4704
64 5 10.5 3360
32 10 10.5 3360
32 12 3.08 1182.72
32 5 10.5 1680
32 2.5 10.5 840
8 65.62 10.5 5512.08
8 7 10.5 588
4 45.37 10.5 1905.54
13mm Thick(2x 4 7 10.5 294
course of Sum(sq ft) 46354.98
distempering) Sum(sqm) 4308.72435
64 3.5 7 1568
64 2.5 7 1120
32 4.5 6 864
32 3 4 384
Deduction 4 6 6 144
Sum(sq ft) 4080
Sum(sqm) 379.238548
Net Qty(Sqm) 3929.4858
73
RCC Work
RCC in Foundation
Description Tot Qty(cft) Tot Qty(cft)
74
First Floor Sum(cum) 14.83285
Total Quantity(GF+FF) 29.6657
Steel Reinforcement
32 22.33 714.56
16 61.45 983.2
32 16.83 538.56
32 10.71 342.72
32 12.25 392
Distribution Bars 4 4.58 18.32
#4 @ 9" c/c Sum(ft) 2989.36
Net Total length 8139.04
Wt of Steel(lbs) 5428.73968
75
Column Steel Reinforcement
42 5.58 234.36
36 5.58 200.88
48 5.58 267.84
42 5.58 234.36
Ties 96 4.16 399.36
#3 @ 6" c/c Sum(ft) 1336.8
54 5.58 301.32
36 5.58 200.88
48 5.58 267.84
770.04
#3 @ 12" c/c Sum(ft) 2106.84
Wt of Steel(lbs) 790.065
Column 2
24 16 384
24 13.33 319.92
Main bar #8 Sum(ft) 703.92
Wt of Steel(lbs) 1877.35464
76
Beams
Beam of Ground Floor Roof
Description No Cut Length Total length
32 16.66 533.12
80 3.33 266.4
3 8.5 25.5
Bottom and Top 2 29.7 59.4
Bars (#6) Sum(ft) 884.42
5 8.5 42.5
3 8.5 25.5
6 27.7 166.2
Description #5 Sum(ft) 234.2
32 16.66 533.12
15 5.33 79.95
48 5.33 255.84
56 4.83 270.48
Stirrups #3 Sum(ft) 1139.39
77
Net length of bars #5 in GF roof & First
Floor 3755.32
78
276 5.25 1449
128 6.25 800
136 5.5 748
Sum(ft) 21487.23
79
40 17.5 700
32 65.62 2099.84
72 15.62 1124.64
56 17.87 1000.72
8 10.37 82.96
Sum(ft) 6664.16
80
Cement Bags
Description Qty Unit C/F Cement
CC 1:4:8 32.57 Cum 3.51 114.32
CC Type B 4.06 Cum 6.54 26.55
CC Type B 69.67 Cum 6.54 455.64
CC Type B 21.19 Cum 6.54 138.58
CC Type B 141.57 Cum 6.54 925.87
BB Work in
CM 1:6 54.01 Cum 1.4 75.61
Do 268.9 Cum 1.4 376.46
do but 1:4 44.12 Cum 1.95 86.03
do but 1:6 190.98 Cum 1.4 267.37
do but 1:4 29.29 Cum 1.95 57.12
Do 27.83 Cum 1.95 54.27
50mm PCC
1:2:4 3.75 Cum 6.54 24.53
CC 1:6:12 34.84 Cum 2.4 83.62
CC Type B 57.2 Cum 6.54 374.09
20mm thick
terrazzo 913.76 Sqm 0.38 347.23
10mm thick
terrazzo 180.29 Sqm 0.214 38.58
Glazed Tiles 104.1 Sqm 0.214 22.28
Do 349.5 Sqm 0.214 74.79
75mm thick
CC type C 123.06 Sqm 0.34 41.84
13mm thick
C/Plaster 1:4 2068.77 Sqm 0.12 248.25
do but 1:6 3929.48 Sqm 0.087 341.86
81
Manhole exc
600mm 7 No 7.4 51.80
Sum 4315.20
OMIT
20mm thick
terrazzo Floor 913.76 Sqm 0.38 347.23
10mm thick
terrazzo Floor 180.26 Sqm 0.217 39.12
Sum 386.35
Net Cement 3928.85
3929 Bags
Services
Total Qty(Sq
Description No Length Width ft)
White Light Glazed non
Skid Tiles 32 7 5 1120
Net Sum(Sq m) 104.10
64 7 4 1792
64 5 4 1280
Dark color Glazed Non
Skid Tiles 96 3.5 3 1008
Sum 4080
Deduction
32 2.5 4 320
Net Sum(Sq ft) 3760
Net Sum(Sq m) 349.49
First Class Soft wood 32 3.5 7 784
Framed and Paneled Doors,
Gates 32 2.5 7 560
82
Net Sum(Sq ft) 1344
Net Sum(Sq m) 124.9256395
32 4.5 6 864
Box Type steel sliding/Fix
windows 6 6 6 216
Net Sum(Sq ft) 1080
Net Sum(Sq m) 100.387
Box Pipe Type openable &
Fix side hung windows 32 3 4 384
Net Sum(Sq ft) 384
Net Sum(Sq m) 35.6930
32 4.5 6 864
6 6 6 216
Wooden steel Grill 32 2.5 7 560
Net Sum(Sq ft) 1640
Net Sum(Sq m) 152.439
Plain galvanised steel sheets 1 44.75 3 134.25
Net Sum(Sq m) 12.479
32 0.75 0.5 12
83
16 0.75 1.5 18
16 9 144
84
32 8 256
Net Sum( ft) 400
Net Sum( m) 121.95
RCC Pipes 150mm
1 59.62 59.62
1 50.75 50.75
1 146 146
Net Sum(ft) 256.37
Net Sum(m) 78.16
Total Total
No Length Width Height Qty(Ft^3) Qty(m^3)
Description Quantity
85
Estimation of 36 BOQs
Excavation
Excavation over Areas
86
Excavation in Foundation and Pipe Trenches
Description No Length(ft) Width(ft) Depth(ft) Qty-
CFT
301.87
WF-3 20 5.75 1.5 1.75 5
122.32
WF-3 20 2.33 1.5 1.75 5
1254
1 61 1.5 2 183
1 70 1.5 2 210
1113
2367
Net QTY ( CFT )
67.077
Net QTY ( CUM )
87
PCC in Foundation (1:4:8)
Width(ft Tot
Description N0 Length(ft) ) Depth(ft) Qty(cft)
((16590.45
1463 *.25)/3+169.55)
Total Qty(cft)
41.46
Total Qty(cum)
DPC
No Length Depth Total Qty(sqft)
8 18.87 0.75 113.22
6 18.87 1.12 126.8064
6 63.75 0.75 286.875
6 13 1.12 87.36
20 10 1.12 224
8 14.5 0.75 87
6 10.75 0.75 48.375
6 7 0.75 31.5
10 14.5 0.37 53.65
18 5 0.37 33.3
88
1092.0864
Net Qty (Sqft)
101.51
Net Qty (Sqm)
Brick Work
89
BB Work (upto GF Roof Level)
Description No Length Width Depth Qty-cft
9" Wall
6 18.87 0.75 12.5 1061.438
8 63.75 0.75 12.5 4781.25
10 14.5 0.75 12.5 1359.375
2 7 0.75 12.5 131.25
13.5" Wall
6 18.87 1.12 12.5 1585.08
10 13 1.12 12.5 1820
16 10 1.12 12.5 2240
Dwarf Wall
1 10.75 0.75 2 16.125
12994.52
Total
Deduction of Doors, Windows, Ventilators & Columns
90
Description No Length Width Depth Qty-cft
4.5" Wall
20 14.5 0.37 12.5 1341.25
18 5 0.37 12.5 416.25
24 12 0.37 3.08 328.2048
2085.705
Total
Deduction
12 6.75 0.37 7 209.79
10 2.75 0.37 7 71.225
367.5728
1804.69
Net Qty(cft)
51.14
Net Qty(cum)
91
Total Qty of BB Work for 4.5"
wall(cum) 30.80293
Sum(cft)
1665.99
Sum(cum)
47.21183
Termite Proofing
Sum 1951.61
92
Cement Concrete Work (PCC)
Total
Description No Length Width Depth Qty(cft)
Room 18 12 10 0.25 540
Dress 18 7.12 5 0.25 160.2
Balcony 16 4.5 10 0.25 180
Gallary 4 65.62 7 0.25 459.34
Gallary 1 32.75 7 0.25 57.3125
Room 16 7 5 0.25 140
Sum(cft) 1536.853
Sum(cum) 43.55
Total
No Length Width Depth Qty(cft)
34 4.5 1.12 0.25 42.84
34 3 1.12 0.25 28.56
8 6 0.75 0.25 9
6 75.62 1 0.17 77.1324
6 46.25 1 0.17 47.175
2 7 1 0.17 2.38
Sum(cft) 207.0874
Sum(cum) 5.87
93
Cement Concrete Type B Laid in Floor Slabs, as under layer for
Terrazzo(GF+First Floor)
Sum(sqm) 178.10
Cement Plaster(1:4)
94
Sum(sqm) 90.14
4 44.75 27 4833
6 8.87 27 1436.94
6 65.62 27 10630.44
62 27 1 1674
Sum(sq ft) 18574.38
13mm Thick Sum(sqm) 1726.50
Deduction
30 4.5 6 810
30 3 4 360
4 6 6 144
Sum(sq ft) 1314
Sum(sqm) 122.137121
Net Quantity(sqm) 1604.36
Cement Plaster(1:6)
Description No Length Width Tot Qty(sqft)
68 12 10.5 8568
68 10 10.5 7140
68 7.12 10.5 5083.68
68 5 10.5 3570
66 7 10.5 4851
66 5 10.5 3465
36 10 10.5 3780
36 12 3.08 1330.56
36 5 10.5 1890
36 2.5 10.5 945
14 65.62 10.5 9646.14
10 7 10.5 735
6 45.37 10.5 2858.31
13mm Thick(2x 8 7 10.5 588
course of Sum(sq ft) 54450.69
distempering) Sum(sqm) 5061.22565
Deduction 68 3.5 7 1666
95
68 2.5 7 1190
32 4.5 6 864
34 3 4 408
4 6 6 144
Sum(sq ft) 4272
Sum(sqm) 397.085068
Net Qty(Sqm) 4664.14
RCC Work
RCC in Foundation
Description Total Qty(cft) Total Qty(cft)
96
Description No Length Width Depth Qty(sq ft)
18 5 0.75 0.5 33.75
18 6 0.75 0.75 60.75
18 4.5 1.12 0.75 68.04
5 7.5 0.75 1 28.125
4 1.5 1.12 12.5 84
2 1.04 1.12 12.5 29.12
18 7.5 0.375 0.75 37.96875
18 3.5 0.375 0.5 11.8125
18 16.37 0.75 1 220.995
1 8.5 0.75 1.75 11.15625
Ground Floor+ First 1 34.75 0.75 1.5 39.09375
Floor Sum(cft) 624.8113
First Floor Sum(cum) 17.71
35.41
Total Quantity(GF+FF)
Steel Reinforcement
97
16 61.45 983.2
40 16.83 673.2
32 10.71 342.72
32 12.25 392
4 4.58 18.32
3982.8
Sum(ft)
Net Total length 11340.96
Wt of Steel(lbs) 7564.42032
Column 1
Main Bars
#5 36 16 576
24 16 384
42 5.58 234.36
36 13.33 479.88
12 7.04 84.48
Sum(ft) 1758.72
Wt of Steel(lbs) 1832.58624
42 5.58 234.36
36 5.58 200.88
Ties 48 5.58 267.84
#3 @ 6" c/c 42 5.58 234.36
98
96 4.16 399.36
Sum(ft) 1336.8
54 5.58 301.32
36 5.58 200.88
48 5.58 267.84
770.04
#3 @ 12" c/c Sum(ft) 2106.84
Wt of Steel(lbs) 790.065
Column 2
24 16 384
24 13.33 319.92
Main bar #8 Sum(ft) 703.92
Wt of Steel(lbs) 1877.35464
Wt of Steel(lbs) 112.995
BEAMS
Beam of Ground Floor Roof
Description No Cut Length Total length
32 16.66 533.12
80 3.33 266.4
3 8.5 25.5
Bottom and Top 2 29.7 59.4
Bars (#6) Sum(ft) 884.42
5 8.5 42.5
3 8.5 25.5
Description #5 6 27.7 166.2
99
Sum(ft) 234.2
32 16.66 533.12
15 5.33 79.95
48 5.33 255.84
56 4.83 270.48
Stirrups #3 Sum(ft) 1139.39
100
Net length of bars #6 in GF roof & First
Floor 2375.66
101
528 8.62 4551.36
Bottom Bars First Floor 456 6.45 2941.2
#4 Sum(ft) 7492.56
102
40 17.5 700
32 65.62 2099.84
72 15.62 1124.64
56 17.87 1000.72
8 10.37 82.96
Sum(ft) 6664.16
74796.07
Total length #3 Bars
28048.52625
Wt of Steel #3 bars
103
Stairs
Description No Cut Length Total length
44 19 836
44 8.33 366.52
116 4 464
#3 Sum(ft) 1666.52
44 4.33 190.52
44 6 264
5 8.75 43.75
14 4.33 60.62
52 4 208
28 4 112
#4 Sum(ft) 878.89
Wt of steel #3 (lbs) 624.945
Mumty
14 21.37 299.18
66 3.37 222.42
642.8
104
Total length of #4 Bars(ft) 1521.69
Cement Bags
BB Work in
CM 1:6 76.9 Cum 1.4 107.66
105
50mm PCC
1:2:4 3.75 Cum 6.54 24.53
20mm thick
terrazo 913.76 Sqm 0.38 347.23
10mm thick
terrazo 180.29 Sqm 0.214 38.58
75mm thick
CC type C 153.05 Sqm 0.34 52.04
13mm thick
C/Plaster 1:4 2014.08 Sqm 0.12 241.69
106
Construction
of M/hole
n.exc 600mm 12 No 5.13 61.56
Provision of
Roof
Insulation 491.48 Sqm 0.033 16.22
Manhole exc
600mm 7 No 7.4 51.80
4709.53
Sum
OMIT
20mm thick
terrazzo Floor 913.76 Sqm 0.38 347.23
10mm thick
terrazzo Floor 180.26 Sqm 0.217 39.12
Sum 386.35
4324Bags
107
Services
Total Qty(Sq
Description No Length Width ft)
White Light Glazed non
Skid Tiles 36 7 5 1260
Net Sum(Sq m) 117.12
60 7 4 1792
62 5 4 1280
Dark color Glazed Non
Skid Tiles 88 3.5 3 1008
Sum 3884
Deduction
38 2.5 4 380
Net Sum(Sq ft) 3504
Net Sum(Sq m) 321.98
First Class Soft wood 40 3.5 7 980
Framed and Paneled Doors,
Gates 41 2.5 7 717.5
Net Sum(Sq ft) 1697.5
Net Sum(Sq m) 157.78
38 4.5 6 1026
Box Type steel sliding/Fix
windows 8 6 6 288
Net Sum(Sq ft) 1314
Net Sum(Sq m) 122.14
Box Pipe Type openable &
Fix side hung windows 51 3 4 612
Net Sum(Sq ft) 612
Net Sum(Sq m) 56.89
108
34 4.5 6 918
12 6 6 432
Wooden steel Grill 34 2.5 7 595
Net Sum(Sq ft) 1945
Net Sum(Sq m) 180.79
Plain galvanised steel sheets 1 44.75 3 134.25
Net Sum(Sq m) 12.479
109
Curtain Rail type C
No Length Total Qty(ft)
36 4 144
36 5.5 198
36 8.12 292.32
Sum(ft) 634.32
Sum(m) 193.39
22 9 198
38 8 304
Net Sum( ft) 502
Net Sum( m) 153.05
RCC Pipes 150mm
1 75.75 75.75
1 80.25 80.25
1 220 220
Net Sum(ft) 376
Net Sum(m) 114.63
110
Man Holes (230mm thick Brick walls)
Total Total
No Length Width Height Qty(Ft^3) Qty(m^3)
Description Quantity
Bills of Quantities
Bills of quantities generally know and conversed as BQ is written document representing
simple estimate of work.
It is arranged on some definite format.
It describes not only different quantities and rates but also refers to drawings etc.
Initially BQs are prepared unpriced because its main purpose is to calculate the scope of work
but later on they are priced to evaluate exact cost of a project on some schedule (At Par Cost).
Tenderers then submit their priced BQ in support of their quotation in tender document which
when accepted becomes the contract document For calculation and correct application of rates,
description of item should be strictly in accordance with discipline give in Schedule of Rates for
different items.
We extracted Description of items and application of rates from MES Schedule of Rates 2009
111
BOQ of 32 BOQs
112
Providing and laying RCC Type
‘B,’ using Crushed or broken
stone in columns, beams, stairs,
6 posts, struts, piers, lintels, and the 29.66 Cum 6473.66 192008.75
like requiring shuttering, as
specified. Reinforcement
measured and paid separately.
Providing & laying of CC Type
‘B’ using Crushed or broken stone
as specified, in walls, sills,
copings, channels, drains, steps,
7 4.06 Cum 5068.85 20579.531
string courses, corbels pier caps,
hinge stone, bed plates etc, incl
formwork & fair faces to exposed
surfaces.
Burnt brick work, in walls 115mm
thick, laid and jointed in CM 1:4,
8 straight or to curve with inner 44.12 Cum 5612.79 247636.29
radius of 6m and over, upto G.F
roof level.
113
Burnt brick work, in wall over
115mm thick, laid and jointed in
12 CM 1:6, straight or to curve with 53.7 Cum 5317.26 285536.86
inner radius of 6m and over, upto
4.25m depth.
114
Providing and laying, CC Type
‘B,’ using shingle or gravel, laid
20 in floor, slabs as under layer for 69.68 Cum 3501.12 243958.04
Terrazzo / Stonolithic / tiles top
finished.
115
Supply & fix, Box Pipe type open-
able and fixed side hung window
or CSW using 16 gauge frame
section 50mm x 25mm and panel
"Z" shape 38mm x 31mm x 38mm
& 10mm x 10mm square gola, not
25 35.69 Sqm 2760.13 98509.039
exc 1.48 Sqm, super, each with all
necessary fitting/iron mongery,
hold fast etc and two coats of S/E
paint in addition to one coat of
primer / rust proof paint, except
wire gauze and glass panes, grill.
Supply and fix, plain galvd steel
sheet 24 BG in ridges hips, valleys
and straight and stepped flashing,
26 12.48 Sqm 1063.94 13277.971
roof plates and sleeve pieces etc,
without wooden battens as
required.
Supply and fix, 13mm thick Soft
board sheet, fixed in ceiling and
27 partitions, with 1st Class Soft 8.34 Sqm 550.31 4589.5854
wood, beveled edge, cover fillet,
50mm x 13mm, screwed on.
116
Supply and fix, RCC pipes,
150mm bore, laid and jointed with
31 78.16 metre 443.86 34692.097
spigot socket or collars, as
specified.
117
S/F, Toilet shower, best quality,
36 32 Each 630.44 20174.08
Pak made, 15 mm dia.
118
Supply and fix, uPVC, Vent
44 Cowel 75mm dia, on top of 16 Each 100.62 1609.92
ventilating pipes.
119
Excavation as in Ordinary Soil
upto 1.5 M depth, in foundation
and pipe trenches upto 1.5 M
wide, in shafts, wells and
independent holes upto 30 sqm
2 each and throw earth clear of 67.08 Cum 205.67 13796.34
edges of excavation within 10m.
Timbering to be paid extra
(Foundation and Trench over 1.5
M widths will be treated as
Areas).
120
Providing & laying of CC Type
‘B’ using Crushed or broken stone
as specified, in walls, sills,
copings, channels, drains, steps,
7 4.06 Cum 5068.85 20579.531
string courses, corbels pier caps,
hinge stone, bed plates etc, incl
formwork & fair faces to exposed
surfaces.
121
Burnt brick work, in walls 115mm
thick, laid and jointed in CM 1:4,
14 straight or to curve with inner 47.21 Cum 5828.58 275167.2618
radius of 6m and over, upto 2nd
floor roof level.
122
Supply and fix, 1st Class Soft
wood framed and paneled doors,
23 gates etc, incl hanging chowkats, 157.78 Sqm 5459.42 861387.28
hold fats, and iron mongery as
described, 38 mm thick.
123
Supply and fix, u-PVC Soil and
waste pipe 110mm (outside dia)
29 268.6 metre 567.45 152417.07
complete with "Z" joint and
rubber ring, all as specified.
124
Supply and fix, WHB with
pedestal, glazed ware, size 660
mm x 560 mm in light color, one
hole, complete with waste pipe,
coupling, CP chain & plug and
35 36 Each 4496.62 161878.32
pedestal etc (except mixer) best
quality, (IFO pattern or
equivalent), fixed to concrete,
brick, stone or wood work, Pak
made.
125
Supply and fix, uPVC, Equal Tee,
110mm dia, complete with "Z"
42 104 Each 699.87 72786.48
joint and rubber ring, all as
specified.
126
Annex B
SAMPLE OF QUESTIONNAIRE
General Information
1. GENERAL INFORMATION ABOUT PERSON FILLING THIS FIRM
a. Name:
b. Qualifications:
c. Designation
d. Working Experience in Construction Industry
e. Name of the Employer
f. Address
g. Cell No
c. Project Duration:
Contractual Actual
Start Date Completion Completion Contract Actual Actual Delay
Date Date Duration Duration
127
Factors Causing Delays in Construction Projects
1.Feasibility Study of the Project
Serial Factors Strongly Disagree Neither Agree Strongly Agree
Disagree Agree nor
Disagree
A Inadequate Feasibility Study of the project
(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor
e. Ambitious Completion 1 2 3 4 5
Period of the Project
128
f. Vague Conception of 1 2 3 4 5
Demand of
Construction Material
g. Poor Planning and 1 2 3 4 5
Scheduling by the
Contractor
4. ESTIMATION RELATED
Serial Factors Strongly Disagree Neither Agree Stron
Disagree Agree Nor gly
Disagree Agree
a. In-accurate cost 1 2 3 4 5
estimates
b. Absence of 1 2 3 4 5
construction cost data
129
5. CONTRACT RELATED
Serial Factors Strongly Disagree Neither Agree Strongl
Disagree Agree Nor y
Disagree Agree
a. Incomplete contract 1 2 3 4 5
documentation
b. Work suspension 1 2 3 4 5
owning to conflicts
c. Litigations 1 2 3 4 5
d. Low Bid procurement 1 2 3 4 5
method resulting in
un-realistic rates
e. Bureaucracy in 1 2 3 4 5
Bidding/Tendering
method
f. Disputes at site 1 2 3 4 5
g. In-adequate duration 1 2 3 4 5
of contract period
h. Poor contract 1 2 3 4 5
management
i. Re-tendering 1 2 3 4 5
6. SITE RELATED
Serial Factors Strongly Disagree Neither Agree Strongly
Disagree Agree Nor Agree
Disagree
a. Problem in Land 1 2 3 4 5
Acquisition
b. Site Variations 1 2 3 4 5
c. In-adequate site 1 2 3 4 5
investigation
d. Encroachment of 1 2 3 4 5
Land during Project
Implementation
130
7. WORK FORCE RELATED
a. Poor workmanship 1 2 3 4 5
b. Non-availability of 1 2 3 4 5
skilled
persons/craftsmen
c. In-adequate 1 2 3 4 5
contractor’s experience
d. Labor Disputes / 1 2 3 4 5
Strikes / security issues
e. Shortage of Labor / 1 2 3 4 5
Skilled persons
g. Absence of Qualified Supervisory staff
(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor
a. Non availability / 1 2 3 4 5
shortage of local
materials
b. Non availability of 1 2 3 4 5
specialized equipment
131
on site at appropriate
time
c. Material Management 1 2 3 4 5
Problem
d. Equipment 1 2 3 4 5
Management Problem
e. Delay in 1 2 3 4 5
Transportation/Delivery
of Construction
Material
(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor
f. Inadequate Site Inspection
132
(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor
g. Inadequate Project monitoring system through reports and returns
(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor
a. Delay in payment by 1 2 3 4 5
the Client
b. Delay in processing/ 1 2 3 4 5
Request for payment
by the Contractor
c. Poor disbursement 1 2 3 4 5
procedure by the
Client
d. Inadequate Client 1 2 3 4 5
financing
e. Mal-practices resulting 1 2 3 4 5
in pilferage and
wastage of funds
g. Poor accounting procedure
(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor
133
11. COST RELATED
Serial Factors Strongly Disagree Neither Agree Strongly
Disagree Agree Nor Agree
Disagree
a. Cost escalation / 1 2 3 4 5
inflation
b. Higher 1 2 3 4 5
Transportation Cost
134
13. WEATHER RELATED
Serial Factors Strongly Disagree Neither Agree Stron
Disagree Agree Nor gly
Disagree Agree
a. Adverse effects of 1 2 3 4 5
weather resulting in
delay
b. Earthquakes 1 2 3 4 5
c. Unforeseen ground 1 2 3 4 5
conditions
d. Accident on site 1 2 3 4 5
a. In appropriate 1 2 3 4 5
government policies/
procedures
b. Non-conducive Law 1 2 3 4 5
and Order / Security
Situation
c. Lack of Co-ordination 1 2 3 4 5
between different
Agencies
135