You are on page 1of 150

In the name of Allah Almighty

The most Beneficent and


The most Merciful

I
BE CIVIL ENGINEERING
PROJECT REPORT

TO STUDY AND ANALYZE PROJECT OF 100 BOQs AT MCE


RISALPUR USING MODERN CONSTRCTION
MANAGEMENT TOOL PRIMAVERA P6

Project submitted in partial fulfillment of the requirements for the degree of


BE Civil Engineering

SUBMITTED BY

Syndicate 17
PC-2444 Shahab Ali Khan (Syndicate Leader)
PC-2442 Waseem Iqbal
PC-2446 Muhammad Ali Butt
ASC-2451 Rameez Shahzad

MILITARY COLLEGE OF ENGINEERING

NATIONAL UNIVERSITY OF SCIENCES & TECHNOLOGY

RISALPUR CAMPUS, PAKISTAN


(2016)

II
This to certify that the

BE Civil Engineering Project entitled

TO STUDY AND ANALYZE PROJECT OF 100 BOQs AT MCE RISALPUR


USING MODERN CONSTRCTION Management TOOL PRIMAVERA P6

SUBMITTED BY

Syndicate 17
PC-2444 Shahab Ali Khan (Syndicate Leader)
PC-2442 Waseem Iqbal
PC-2446 Muhammad Ali Butt
ASC-2451 Rameez Shahzad

Has been accepted towards the partial fulfilment of the requirements for

BE Civil Engineering Degree

___________________________

Lt Col Mughees Aslam


Syndicate Advisor

III
Dedication

This work is especially dedicated to our parents who prayed for us tirelessly, our supervisor,
supportive friends and all faculty members of the Construction Management department.

For their support, encouragement and belief in us. We are truly indebted.

IV
ACKNOWLEDGEMENT

We are thankful to
ALMIGHTY ALLAH Who gave us the strength, ability and wisdom to achieve everything in our lives

Our Parents and Families who are a source of constant support for us and without whose prayers we may
never achieve anything.

Our Friends and Course Mates for helping us through thick and thin.

Our Project Supervisor Lt. Col. Mughees Aslam for his guidance, encouragement, patience,
knowledge and for providing us with freedom of action.

Maj Muhammad Ahmed, XEN Shahid and MES Risalpur Cantt staff, AGE Shabbir
Ahmed for their patience and constant support throughout the project.

All Syndicate members

V
TABLE OF CONTENTS

LIST OF FIGURES...................................................................................................................X
LIST OF TABLES.....................................................................................................................XI
LIST OF ABBREVIATIONS…………………………………………………………………XII
ABSTRACT...............................................................................................................................IX
Chapter 1………………………………………………………………………………………1
INTRODUCTION……………………………………………………………..........................1
1.1 Introduction to 100 BOQs…………………………………………….........................1
1.2 Scope………………………………………………………………………………….1
1.3 Objectives…………...………………………………………………………………...2
1.4 Methodology………………………………………………………………………….3
Chapter 2………………………………………………………………………………………4
LITERATURE REVIEW………….……………….,…………………………………………4
2.1 Definition of Project......................................................................................................4
2.2 The Project Life cycle...................................................................................................5
2.3 Project Management......................................................................................................5
2.3.1 Managing a Project usually includes..........................................................................6
2.3.2 Project Management areas……………………………………………………..........7
2.4 Project Planning………………………………………………………………………..8
2.5 Planning Process……………………………………………………………………….8
2.6 Delay…………………………………………………………………………………...10
2.7 Factors causing delay in Project execution…………………………………………….12
2.7.1 Contractor related factors…………………………………………………….……....12
2.7.2 Client related factors…………………………………………………………………12
2.7.3 Consultant related factors…………………………………………………………….13
2.7.4 Material related factors……………………………………………………………….13
2.7.5 Equipment related factors…………………………………………………………….13
2.7.6 Labour related factors………………………………………………………………...14

VI
Chapter 3…………………………………………………………………………………..........15
AUTOCAD DRAWING AND 3D MODEL (REVIT)...……………………………………….15
3.1 Introduction......................................................................................................................15
3.2 AutoCAD Drawing...........................................................................................................15
3.2.1 Site plan.........................................................................................................................16
3.2.2 Layout plan....................................................................................................................17
3.2.3 Footing Plan…………………………………………………………………………...18
3.2.4 X-Section……………………………………………………………………………...19
3.2.5 Detail of Openings…………………………………………………………………….20
3.2.6 Structural Drawing 1………………………………………………………………......21
3.2.7 Structural Drawing 2………………………………………………………………......22
3.3 3D model of 100 BOQs………………………………………………………………….23
3.3.1 Isometric view…………………………………………………………………………23
3.3.2 Back side view………………………………………………………………………...24
3.3.3 Side view………………………………………………………………………………24
Chapter 4………………………………………………………………………………………...25
ESTIMATION OF 100 BOQs CIVIL WORKS...........................................................................25
4.1 Definition..........................................................................................................................25
4.2 Type of Estimates..............................................................................................................25
4.3 Estimation Methods...........................................................................................................25
4.3.1 Preliminary Estimates.....................................................................................................26
4.3.2 Detailed Estimating Method...........................................................................................27
4.4 Quantity Estimation of 100 BOQs....................................................................................28
4.4.1 Estimation of 32 BOQs..................................................................................................28
4.4.2 Estimation of 36 BOQs..................................................................................................31
Chapter 5......................................................................................................................................34
SCHEDULING ON PRIMAVERA P6……………………………………................................34
5.1 Scheduling .......................................................................................................................34
5.2 The tripod of Good Scheduling System...........................................................................34
5.3 Types of Project Schedules .............................................................................................35
5.4 Critical Path Logic Diagram............................................................................................35

VII
5.5 CPM Scheduling.............................................................................................................35
5.6 Types of Float ................................................................................................................36
5.7 Project Planning Software .............................................................................................36
5.7.1 Primavera Project Planner P6………………………………………………………..37
5.8 Planning and Scheduling of 100 BOQs………………………………………………..37
5.8.1 Defining the Calendar………………………………………………………………..38
5.8.2 Creating a New Global or project Calendar ………………………………………....38
5.8.3 Enterprise Project Structure (EPS)…………………………………………………...40
5.8.4 Organizational Breakdown Structure (OBS)…………………………………………42
5.8.5 How to Create a project………………………………………………………………44
5.8.6 Work Breakdown Structure (WBS)………………………………………………….45
5.8.7 Adding Activities of 100 BOQs in Primavera P6…………………………………....47
5.8.9 Activities of Actual Scheduled Project……………………………………………....48
5.8.10 Understanding Relationship………………………………………………………...51
5.8.11 Understanding Lag and Leads…………………………………………....…………51
5.8.12 Resources……………………………………………………………………………51
5.9 Scheduling of Project…………………………………………………………………...52
5.9.1 Activates of Planned Scheduling Project…………………………………………......52
5.9.2 Task or Out-Turn Work………………………………………………………………52
5.9.3 Scheduling of Planned Project……………………………………………………......58
5.10 Comparison of the project at WBS level………………………………………………59
Chapter 6………………………………………………………………………………………..62
IDENTIFICATION AND EVALUATION OF CAUSE OF DELAY OF 100 BOQs…………62
6.1 Introduction......................................................................................................................62
6.2 Information about 1000 BOQs………………………………………………………….62
6.3 Key Stakeholders……………………………………………………………..................63
6.3.1 Client/ Consultant..........................................................................................................63
6.3.2 Project Monitoring Team..............................................................................................63
6.3.3 Contractor …………………………………………………………………………….63
6.4 Factors identified affecting “Time Overrun” in 100 BOQs..............................................64
6.5 Questionnaire Design........................................................................................................64

VIII
6.6 Analysis of data…………………….……………………………………………............64
6.7 Deductions of causes of Delay…………………………………………………………..66
6.8 Recommendations………………………………………………………………….........68
REFRENCES…………………………………………………………………………………….70
APPENDICES…………………………………………………………………………………...72
ANNEX A-Taking of Sheets (Estimation) Of 100 BOQs……………………………...……72
ANNEX B-Questionnaire Design………………………………………………………......135

IX
LIST OF FIGURES

Figure 1.1 – Google image of 100 BOQs……………………………………………………….1


Figure 1.2 – Research Methodology ............................................................................................3
Figure 2.1 –Project Life Cycle…………………………………………………………………..5
Figure 2.2 – Project Phases........................................................................................ …..............6
Figure 2.3–PM Knowledge Areas.........................................................................................……8
Figure 3.1–Site/Layout Plan…………………………………………………………………….16
Figure 3.2–Layout Plan….........................................................…………………………………17
Figure 3.3– Footing Plan.................................................................................................... ……..18
Figure 3.4–X-Section Footing….............................................................................. ……………19
Figure 3.5–Detail of Openings…................................................................................... ..............20
Figure 3.6–First Floor Reinforcement Plan (Bottom Bars)..................................................... .....21
Figure 3.7– First Floor Reinforcement Plan (Top Bars)................................................................22
Figure 3.8–Isometric view of 100 BOQs…...................................................................................23
Figure 3.9–Back side View………………………………………………………………………24
Figure 3.10–Side View…………………………………………………………………………..24
Figure 5.1–Global Calendar ….....................................................................................................39
Figure 5.2–Global Calendar ….....................................................................................................40
Figure 5.3–Table view of EPS…………………………………………………………………..41
Figure 5.4–Chart view of EPS…………………………………………………………………..42
Figure 5.5–Table View of OBS.....................................................................................................43
Figure 5.6–Chart View of OBS.....................................................................................................44
Figure 5.7–Creating Project of 100 BOQs......................................................................……......45
Figure 5.8–Table view of WBS………………………………………………………………….46
Figure 5.9– Chart view of WBS …..........................................................................................….47

X
Figure 5.10 –Table view of Activities of 100 BOQs…………………………………………….49
Figure 5.11 –Table view of Activities of 100 BOQs…………………………………………….50
Figure 5.12 –Gantt chart view of Activities…...............................................................................50
Figure 5.13 –Out Turn work…………………………………………………………………......55
Figure 5.14 –Table view of Planned activities…………………………………………………..56
Figure 5.15 –Table view of Planned activities…………………………………………………..57
Figure 5.16 –Gantt Chart view of Planned Activities.............................................. ……………58
Figure 5.17–Comparison of Planned VS Actual Schedule.................................... ……………..59
Figure 5.18– Comparison of Planned VS Actual Schedule …………………….........................60
Figure 6.1–Key Stakeholders…....................................................................... …………………63

XI
LIST OF TABLES

Table 4.1 Earthwork of 32 BOQs….................................................................................………….28


Table 4.2 Brickwork of 32 BOQs….................................................................................………….28
Table 4.3 Cement Concrete work of 32 BOQs…...................................................................……...29
Table 4.4 RCC work of 32 BOQs…................................................................................ ………….29
Table 4.5 Steel Reinforcement of 32 BOQs…...................................................................... ………30
Table 4.6 Earthwork of 36 BOQs…................................................................................ …………..31
Table 4.7 Brickwork of 36 BOQs…................................................................................ …………..31
Table 4.8 Cement Concrete work of 36 BOQs….................................................................. ………31
Table 4.9 RCC work of 36 BOQs…................................................................................ …………..32
Table 4.10 Steel Reinforcement of 36 BOQs….................................................................................32

XII
LIST OF ABBREVIATIONS

PMBOK Project Management Body of Knowledge


PMI Project Management Institute
CPM Critical Path Method
PERT Program Evaluation Review Technique
BOQs Bachelor Officers Quarter
AGE Assistant Garrison Engineer
MCE Military College of Engineering
UG Under Grade
EPS Enterprise Project Structure

OBS Organizational Breakdown Structure

MES Military Engineering Services

WBS Work Breakdown Structure

OBS Organizational breakdown structure

FS Finish-to-Start
SS Start-to-Start
SF Start-to-Finish
NCO Non Commissioned Officers
B/R Buildings and Roads
Sqm Square meter
Cum Cubic meter
CFT Cubic Feet
PCC Portland Cement Concrete
RCC Reinforced Cement Concrete
DPC Damp Proof Course
BB Work Burnt Brick Work

XIII
PVC Poly Vinyl Chloride

CM Cement Mortar

WC Water Closet

WHB Wash Hand Basin

XIV
ABSTRACT

Construction Management is a Science as well as an Art, forming the back bone of


Construction Industry. Every Construction Project involves variety of activities which needs to be
managed and harmonized properly in a way to ensure successful completion and attaining
proposed deliverables of the Project within stipulated time frame.
The study of a real time Project(100 BOQs at MCE Risalpur) was chosen , studied and analyzed
to apply first hand Civil Engineering knowledge at UG level. The study revolve around study
analysis of Structural design, Geo Tech Analysis, Planning and Scheduling techniques using
latest software and Project Monitoring & Control.
In this process an on ground Construction Plan and Scheduling will be prepared for building
Construction of 100 BOQs by inserting pegs of various activities as and when they terminated.
Then to compare it with proposed Project Schedule. This contrast would indeed help to understand
the importance of Construction Project Management in a real time scenario, difficulties involved,
delay causing factors and further leading the students to arrive at some definite and practical
recommendations/solutions for timely execution of Projects within stipulated time frame. That
surely have obvious economic impacts.

XV
Chapter 1

INTRODUCTION

1.1 Introduction to 100 BOQs

100 BOQs is a residential type of building, located at Liaqat road Risalpur Cantonment
near MCE officers Mess. The project was executed by MES Risalpur and the contract was awarded
to M/S Ch Abdul Ghaffar and Co. The project was initiated on 14th April 2013 and according to
the contract it was supposed to be completed in one year. Unfortunately there was a delay of 6
months in completion of the project.

1.1.1 Location

Fig 1.1 - Google image

1.2 Scope

The study of a real time Project (100 BOQs at MCE Risalpur) was chosen, which revolve
around Planning, Scheduling and Estimation techniques using latest software and Project
Monitoring & Control. In this process an on ground Construction Plan and Schedule will be

1
prepared for building Construction of 100 BOQs by inserting pegs of various activities as and
when they terminated. Then to compare it with proposed Project Schedule. This contrast would
indeed help to understand the importance of Construction Project Management in a real time
scenario, difficulties involved, delay causing factors and further leading the students to arrive at
some definite and practical recommendations/solutions for timely execution of Projects within
stipulated time frame. That surely have obvious economic impacts. It also involve Estimation of
quantities in Construction of 100 BOQs using Detailed Estimate method.

1.3 Objectives

a. To make comprehensive Work break down Structure and realistic Project Schedule using
Primavera Software.
b. Making of 3D model of 100 BOQs
c. Quantity estimation and preparation of bills of quantities.
d. Cost estimation of 100 BOQs.
e. To draw contrast of proposed Vs Actual Schedule of Project on ground
f. Identify delays with probable causes.

2
1.4 Methodology

Fig 1.2 - Research Methodology

3
Chapter 2

LITRATURE REVIEW

2.1 Definition of project

“A project is a temporary endeavor undertaken to create a unique product, service or


result. The temporary nature of projects indicates a definite beginning and end. The end is reached
when the project’s objectives have been achieved or when the project is terminated because its
objectives will not or cannot be met, or when the need for the project no longer exists.” (PMBOK
4th Ed).
A project is temporary in that it has well-defined start and end in time, and therefore clear scope
and resources.
A Project has:
a. Set of Activities
b. Particular Objective
c. Deliverable (s) / Product (s)
d. Start and Finish Dates (Duration)
e. Price
f. Necessities
g. Conformance to Standards

2.2 The project Life cycle


A project life cycle is basically overall life starting from planning till the close out stage. It
includes different stages through which project passes like planning, designing, execution and
handing over to the client.
Every project passes through a fixed definite procedure which can be seen as below.

4
Fig 2.1 - Project life cycle

2.3 Project Management

“Project management is the application of knowledge, skills, tools and techniques to


project activities to meet the project requirements” (PMBOK4, PMI, USA).
Project management can be explained through following figure.

5
Fig 2.2 - Project Phases

The main challenge of project management is to attain all the aims while keeping in mind
any kind of limitations. The main limitations are scope, time, quality and budget.

2.3.1 Managing a project usually includes


a. Fulfilling several needs, wishes, and expectations of the stakeholders.
b. Balancing the challenging project constraints comprising, but not limited to:
1. .Scope
2. .Quality
3. .Schedule
4. .Budget
5. .Resources
6. .Risk

6
2.3.2 Project Management knowledge draws on ten areas

1. Integration o

2. Cost
o
3. Stakeholder

4. .Human resources o

5. .Scope

6. .Quality

7. Communications

8. Time

9. Procurement

10. Risk management


.

7
Fig 2.3 - PM knowledge Areas

2.4 Project Planning


Project Planning could be defined as selecting and adopting all the possible measures for a
project completion.
PMI defined as:
‘‘Those processes performed to establish the total scope of the effort, define and refine the
objectives, and develop the course of action required to acquire those objectives’’.

2.5 Planning Process

Following are the successive steps for planning a construction project or any project:

a. Developing Project Management Plan

8
It organize, integrate and bring all the necessary primary and secondary plans. It provide
information for how the project can be completed without compromising all the necessities.
b. Generating Work breakdown structure
This is the method of splitting project works into smaller, more manageable components.

c. Defining Activities
This define the actions which give us important deliverables.

d. Sequence Activities
This includes the necessary relations amongst different activities to perform in an organize
manner.

e. Estimating activity resources


This technique can be used to identify the quantity and type of material, equipment and
people in order to complete the tasks.

f. Estimating activity durations


This defines the time to complete an activity keeping in mind the available resources. The
unit of time used normally in hours or days but it should remain same.

g. Developing schedule
This is the process of analyzing activity sequences, durations, resource requirements, and
schedule limitations to create the project schedule.

h. Estimating costs
It defines the cost required for a task to be completed.

i. Develop human resource Plan


This defines advertisement, hiring, training, assigning responsibilities, performance
appraisal, transfer and firing out of the people in an organization.

j. Plan risk management


This is the process of describing how to carry out risk management activities for a project.

9
2.6 Delay

Delay is very critical factor in any construction project because it increases the total cost
of the project. If a project is completed on time then it will benefit all the stakeholders in terms of
time and money. Therefore it is very important to identify those major factors which are
responsible for delay in construction projects. Late completion of construction projects is very
common in many developing countries. Time is very critical factor for every plan that a company
is trying to implement. There is a relationship between project time allotted, scope of project and
conditions at which project is undertaken. A very minute change in any of areas affects the overall
efficiency of the project. Time overrun is considered as cost causing factor for owner as well as
for contractor. In case of delay in construction of any project owner lose the revenue and contractor
loses the opportunity of attracting more tenders because of engaged in already ongoing project.
Public also suffer due to delay in construction of public sector projects. If project is failed to
complete on time then automatically its cost increases from closing bid cost. Time is very critical
resource and it should be managed before the start of the project. Time overrun and its impacts is
considered as one of the important factor in construction industry of Pakistan. inefficient contract
management, impractical scheduling, a little financing by client, delay in payments, design
amendments through construction, and non-availability of construction material materials like
cement and steel. The issue had also been found as of equal importance in Arab countries. Assaf,
et al., conducted a study in construction industry of Pakistan and reported critical causes of delay
related to contractor, constructor and client in large building projects. They further classified the
causes into nine divergent clusters like financing, materials, contract relationships, government
relations, manpower, scheduling and control, equipment, and environment. Later on, El-Razek, et
al., used these causes and revise the lists of delay causes with respect to the Egyptian construction
industry. They further emphasized the important role of consultants and payment by owner in
reducing the delays in large construction projects.
Delays in construction industry have also been a matter of great concern in Pakistan. However,
only two researches have been conducted for classifying the causes of delay in construction
industry of Pakistan. Shaikh, et al., introduced a theoretical framework by analyzing the previous
studies highlighting the client, contractor, general and resource related problems are key factors
causing delay in construction industry. In the same vein, Haseeb, et al., concluded in their study
that the most important and highly ranked causes are related to financial matters causing delays in

10
Pakistani construction industry. They further elaborated and identified the delays like delay in
payment to supplier, inadequate fund allocation, inflation and monthly payment problems.
However, there is need to identify the client, contractor, consultant, material, equipment, labor
related and general factors causing delay in project execution.

2.7 Factors Causing Delay in Project Execution

2.7.1 Contractor related factors


Many researchers have put their efforts to find out the factors related to contractor that
causing delay. According to Sambasivan and Soon, these can be controlled by proper planning by
contractor, efficient site management and adequate experience of the contractor. Similarly, Yaw
Frimpong and Oluwoye also have the same view point regarding factors related to contractor.
Odeh and Battaineh concluded from their studies that these major issues can be controlled by
proper site management, avoiding sub-contractors, proper planning and sufficient experience of
the contractor.

2.7.2 Client related factors


Many researchers have put their efforts in this field as well. According to Mezher in
Lebanon, financial problem are more important for the client. Clients just love to have prime
contractor ship in order to have all the risk related to schedule delay and other liquidated damages
on the part of contractor. According to Al-Hazmi client approval is also the major cause of delay
in the construction projects. Al- Khalil and Al-Ghafly slow decision making by the client showing
the technical inexpertness is one of the causes of delay.

2.7.3 Consultant related factors


According to Assaf and Al-Hejji, it is the consultant point of view that most of the time
project delayed due to lack of planning by the contractor, lack of site management, poor payment
procedure by the client and non-availability of equipment and material.
Haseeb et al., say that the variation of drawing, consultants inefficiency, improper investigation of
site, contract management, and late action and visit of site are the major issues related to consultant.
Wong and Vimonsatit identified that consultant should be well aware of site condition and
execution of construction methods.

11
2.7.4 Material related factors
Material is very important factor if we talk about construction project. A number of
people have put their efforts in this field. On time provision of material has got high
importance in construction project. Sambasivan and Soon identified that material quality
and insufficiency are the factors which causes delay. Koushki and Kartam studied that
material selection has got huge importance in construction industry.

12
Chapter 3
AUTO CAD DRAWING AND 3D MODEL (REVIT)

3.1 Introduction
Hard and soft copy of 100 BOQs Auto Cad drawings were collected from MES and 3D
Model of the building was made using Autodesk Rivet. Auto Cad drawings include Site plan,
Layout plan. Footing plan, Schedule of openings and Structural Drawings.

3.2 Auto Cad Drawings


3.2.1 Site Plan

Fig 3.1- Site/Layout Plan

13
3.2.2 Layout Plan

Fig 3.2 - Layout Plan

14
3.2.3 Footing Plan

Fig 3.3 - Footing Plan

15
3.2.4 X-Sections

Fig 3.4-X - Sections Footings

16
3.2.5 Detail of Openings

Fig 3.5 - Detail of Openings

17
3.2.6 Structural Drawing 1

Fig 3.6-First Floor Rft Plan(Bottom Bars)

18
3.2.7 Structural Drawing 2

Fig 3.7 - First Floor Rft Plan(Top Bars)

19
3.3 3D Model of 100 BOQs

3.3.1 Isometric View

Fig 3.8 - Isometric view of 100 BOQs

20
3.3.2 Back Side View

Fig 3.9 - Back side View of 100 BOQs

3.3.3 Side View

Fig 3.10 - Side View of 100 BOQs

21
Chapter 4
ESTIMATION OF 100 BOQS CIVIL WORKS

4.1 Definition
Estimation is the process in which we determine the probable construction costs of any
type of project.
Estimating is the scientific way of working out the approximate cost of a building or an engineering
project. It is the process of determining the financial feasibility of any project and its further
enhancement is framing the tender work and calculation of Bid prices.
4.2 Types of Estimates

ESTIMATES

Conceptual Preliminary Detailed

4.3 Estimation Methods


Methods of estimating can be divided into two main categories:
a. Preliminary/Guess estimating methods
b. Detailed estimating methods

22
4.3.1 Preliminary estimates
These estimates are used in the early stages of a project to provide at least a rough estimate
of the construction cost at a time when there is no detailed information available about the nature
of the proposed project. The preliminary estimating includes:-
Price per Unit Area Estimates
They are also called Plinth Area/Square-Foot Area Estimates. Per Unit Area Estimates are
prepared by multiplying the plinth area with cost per square foot of any project. Further the prices
are adjusted to compensate for variation in building project like location, orientation, storey,
height, specifications.

a. Price Per Unit Estimates


The price per unit method of estimating is used on multi-unit projects. It is usually adopted for the
projects that are already being executed. After completing an apartment building, for example, the
analyst would divide the construction cost of the new building by number of suites it contains to
determine the cost per suite. This unit price can then be used as a guide to price future apartment
projects by multiplying the number of suites in the proposed facility by this unit price per suite.

b. Project Comparison Estimates


Project comparison estimates are prepared by comparing the cost of a proposed project to a
completed project. When preparing an estimate using this method, the estimator starts with the
costs of a comparable project and then makes adjustments for differences in the project.

c. Per Capita/Unit Basis Estimates


It consists in working out the approximate cost of a building based on the units of the users.It is
very approximate and seldom used in practice except for mere discussion on the project as it has a
number of limitations.

d. Cubical Contents Estimates


It consists in working the cubic contents of a building and then applying to it the rate per cubic
meter.

e. Assembly Estimating
If the assembly (instead estimating each of the individual components of the project, the estimates
of the components in groups known as assemblies are made) price comes from previously
completed projects, it is estimated with the assumption that this project is identical to on ground
executed project.

4.3.2 Detailed Estimating Method


The detailed estimating method, produce a very accurate budget of a project. This method
is used for bid preparation all over the building industry. The basic theory behind the detailed

23
estimating method is taking off all the quantities from complete design specifications and then get
a complete picture of accurate construction cost involved in the project. Because of this
requirement and also because detailed estimating is such a time taking procedure.
Whether prepared by hand, by computer spreadsheet, or by means of a totally computerized
system, a detailed estimate can be analyzed in terms of six distinct procedures

1. Quantity Takeoff: The activity or work to be executed by the contractor is measured in


terms of standards for measurement.

2. Recap Quantities: The amounts of work taken off are sorted and leaned to consent to the
exchange breakdown to encourage the procedure of evaluating.

3. Pricing the Recap: Costs for the required work, gear, and materials are entered against
the amounts to decide the evaluated expense of the manufacturer's own particular work.

4. Pricing Subcontractor’s Work: Costs are acquired from contending sub exchanges who
quote to perform the work of their exchange then, as a rule, the most minimal offer from
every exchange is gone into the assessment.

5. Pricing General Expenses


It includes all the anticipated overheads for a project.

6. Summary
All the estimated prices are summarized and the contractor’s markup is added.

4.4 Quantity Estimation of 100 BOQs


Estimation of 100 BOQs is done in two phases
3.4.1 Estimation of 32 BOQs
3.4.2 Estimation of 36 BOQs
Complete Estimation Sheets are attached in Appendix while summary of the quantities is shown
below.

24
4.4.1 Estimation of 32 BOQs

Table 4.1 Earthwork

S.NO Item Net Quantity (cum)

1 Excavation 383.33

2 Backfilling 296.8

Table 4.2 Brickwork

S.NO Item Net Quantity (cum)

1 BB work (Up to Ground 53.96


Floor level)

2 BB work (Up to Ground 313.02


Floor Roof level)

3 BB work ( Up to First Floor 221.78


Roof level)

4 BB work in Parapet wall 29.30

Table 4.3 Cement Concrete Work

S.NO Item Quantity

1 PCC (1:4:8) 32.57 cum

(Lean)

2 DPC 74.44 sqm

3 CC Under Floor 34.84 cum

4 CC Type B in walls, sills, 4.06 cum


channels

5 CC Type B laid in floor slabs 69.68 cum

25
6 Cement Plaster (1:4) 1034.4 sqm

7 Cement Plaster (1:6) 3929.49 sqm

8 CC Type C in Plinth protection 125.68

Table 4.4 RCC work

S.NO Item Quantity (cft)

1 RCC in foundation 84.9

2 RCC type B in roof slabs, landings 143.97


and plinth beams

3 RCC type B in beams, stairs, posts 29.6


and lintels

Table 4.5 Steel Reinforcement

S.No Item Weight of Steel (lbs)

1 Foundation Steel Reinforcement 5428.74 ( #4 bar)

2 Column Reinforcement 1832.58 (#5 bar) 1877.35


(#8 bar) 903.06 (#3 bar)

3 Beam Reinforcement 1326.63 (#6 bar) 244.03


(Ground Floor Roof) (#5 bar) 427.27 (#3 bar)

4 Beam Reinforcement (First Floor 3669.01 (#5 bar) 2236.86


Roof) (#6 bar) 1230.78 (#3 bar)

5 Slab Reinforcement 49716.33 (#3 bar)


18643.62 (#4 bar)

6 Doors and Windows Lintel 2185.68 (#3 bar)


1084.27 (#4 bar)

26
Cement Consumption
Net requirement of cement = 3929 bags

Services
Detail of Services are attached in appendices

4.4.2 Estimation of 36 BOQs


Table 4.6 Earthwork

S.NO Item Net Quantity (cum)

1 Excavation 537.23

2 Backfilling 418.87

Table 4.7 Brickwork

S.NO Item Net Quantity (cum)

1 BB work (Up to Ground 76.90


Floor level)

2 BB work (Up to Ground 378.28


Floor Roof level)

3 BB work ( Up to First Floor 221.78


Roof level)

4 BB work in Parapet wall 47.21

27
Table 4.8 Cement Concrete Work

S.NO Item Quantity

1 PCC (1:4:8) 41.46 cum

(Lean)

2 DPC 101.58 sqm

3 CC Under Floor 43.55 cum

4 CC Type B in walls, sills, 5.87 cum


channels

5 CC Type B laid in floor slabs 87.10 cum

6 Cement Plaster (1:4) 1694.5 sqm

7 Cement Plaster (1:6) 4664.14 sqm

8 CC Type C in Plinth protection 178.10 sqm

Table 4.9 RCC work

S.NO Item Quantity (cft)

1 RCC in foundation 117.54

2 RCC type B in roof slabs, landings 182.02


and plinth beams

3 RCC type B in beams, stairs, posts 35.41


and lintels

28
Table 4.10 Steel Reinforcement

S.No Item Weight of Steel (lbs)

1 Foundation Steel Reinforcement 7564.42 ( #4 bar)

2 Column Reinforcement 1832.58 (#5 bar) 1877.35


(#8 bar) 903.06 (#3 bar)

3 Beam Reinforcement 1326.63 (#6 bar) 244.03


(#5 bar) 427.27 (#3 bar)
(Ground Floor Roof)

4 Beam Reinforcement (First Floor 3669.01 (#5 bar) 2236.86


Roof) (#6 bar) 1230.78 (#3 bar)

5 Slab Reinforcement 28048.53 (#3 bar)

6 Doors and Windows Lintel 987.89 (#3 bar) 2168.55


(#4 bar)

7 Stairs 624.945

8 Mumty 1014.97

Cement Consumption
Net requirement of Cement = 4348 Bags

Services
Detail of Services are attached within appendices

29
Chapter 5

SCHEDULING ON PRIMAVERA P6

5.1 Scheduling

Scheduling is determination of timing of events in the project i.e., When tasks will be
performed? Simply, it’s a reflection of plan.

5.1 Why Schedule Project?

a. To determine project starting date.


b. To find out the total duration of the project.
c. To know about starting or finishing date of any activity.
d. To cater for the change order quickly and on time.
e. To have an effective control over all the project execution phase
f. To increase the output

5.2 The Tripod of Good Scheduling System


a. The Human Factor: All the team members who are working efficiently.
b. The Technology: It include all the effective hardware and software.
c. The Management: An effective, responsible and cooperative management.

5.3 Types of Project Schedules


a. Gantt Charts
b. Network Scheduling
c. PERT Network Scheduling

5.4 Critical Path Logic Diagram

The critical path logic diagram shows a logical interface between schedule activities. It is
also called PERT chart; that is Programmed Evaluation Review Technique. In this each activity

30
can be shown through a box. The activities and their precedence combined to form precedence
network.

5.5 CPM Scheduling

Critical Path Method Scheduling is based on Critical Path Method (CPM) which can be
defined as "The Calculation of the earliest and latest start and finish dates of activities based
on their durations and relationship to other activities" CPM Calculations overview:
a. The calculation of early start and finish date, and latest start and finishing date for
each activity.
b. Early dates mean an activity can be start and finish as early as possible if all the
predecessor activities are completed.
c. Late dates mean an activity can be start and finish as late as possible without
delaying the succeeding activities.

5.6 Types of float

a) Total Float
b) Free Float

a) Total Float
It can be found either by subtracting the early finish date from the late finish date or by
subtracting the early start date from late start date.
TF= LF-EF
TF= LS-ES
An activity that has zero total float is a critical activity. An activity’s start may be critical
even though an activity itself may not be critical.
b) Free Float
Free float is the difference between an activity’s early finish time and early start time for
any succeeding activity.
FF= EF-ES (next activity)
The free float of an activity is an amount by which that activity can be delayed without delaying
the early start of any following activity or any other activity in the network.

31
5.7 Project planning software

A number of soft wares are available in market which professionals & engineers use to
manage project and plan the project. These soft wares use a variety of paths to determine the critical
path of the project. These allow professional users and engineers to control the overall cost &
budget of the project. Most commonly used software for project planning is Primavera P6.

5.7.1 Primavera Project Planner P6


Primavera is a very useful software for managing any type of project whether it is a
construction project or not. It can perform multiple task for a project manager like planning,
scheduling, updating everyday progress work and overall control of project.
While working in Primavera P6, following procedure should be followed.
a. Defining the Calendars
b. Enterprise Project Structure(EPS)
c. Organizational Breakdown Structure(OBS)
d. Defining a project
e. Work Breakdown Structure(WBS)
f. Adding Activities in Primavera P6
g. Understanding Relationships
h. Understanding Lags and Leads
i. Resources

5.8 Planning and Scheduling of 100 BOQs

The study of a real time Project (100 BOQs at MCE Risalpur) was chosen , studied and
analyzed to apply first hand Civil Engineering knowledge at UG level. The study revolve around
Planning and Scheduling techniques using latest software and Project Monitoring & Control.
In this process an on ground Construction Plan and Scheduling will be prepared for building
Construction of 100 BOQs by inserting pegs of various activities as and when they terminated.
Then to compare it with proposed Project Schedule. This contrast would indeed help to understand
the importance of Construction Project Management in a real time scenario, difficulties involved,
delay causing factors and further leading the students to arrive at some definite and practical

32
recommendations/solutions for timely execution of Projects within stipulated time frame. That
surely have obvious economic impacts.

While Planning and scheduling for real time Project we used following sequence

5.8.1 Defining the Calendars


You have to define a calendar before entering activities in Primavera. For 100 BOQs
a calendar by the name of “100 BOQs 7d/week” was defined, in which there were 7 days
work per week @ 8 hours work per day.

5.8.2 Creating a New Global or Project Calendar


A project must be in .active state to create a Project Calendar. You can create a new
Project Calendar by copying an existing Global Calendar.

Fig 5.1 – Global Calendar

33
Fig 5.2 – Global Calendar

5.8.3 Enterprise Project Structure (EPS)


EPS shows a hierarchy of departments in an organization. .The EPS can be subdivided into as
many levels or nodes as needed to parallel work at your organization. Nodes at the highest, or root,
level might represent divisions within your company, project phases, site locations, or other major
groupings that meet the needs of your organization. Projects always represent the lowest level of
the hierarchy.

For EPS go to Enterprise and select EPS


34
Fig 5.3 - Table View of EPS

35
Fig 5.4 - Chart view of EPS

5.8.4 Organizational Breakdown Structure (OBS)


OBS shows a hierarchical order of responsible managers for different departments in an
organization. The OBS usually reflects the management structure of your organization, from top-
level personnel down through all levels.
OBS for both, the Planned and actual Schedule will remain same.

36
Fig 5.5 - Table View of OBS

37
Fig 5.6 - Chart View of OBS

5.8.5 How to Create a Project?


In this study as mentioned earlier, two projects has been Scheduled. The first one is actual
project executed by MES on ground completed within duration of 18 months. The later one is our
planned Scheduled Project whom duration we want to find.

38
Fig 5.7 - Project of 100 BOQs

5.8.6 Work Breakdown Structure (WBS)


The work breakdown structure (WBS) is used to provide the framework for organizing &
managing the work. The WBS helps break thousands of tasks into pieces that we can understand
& assimilate. WBS is also used to track costs related to various activities.
WBS for both Planned and actual Scheduled Projects will remain same.

39
Fig 5.8 - Table view of WBS

40
Fig 5.9 - Chart view of WBS

5.8.7 Adding Activities of 100 BOQs in Primavera P6


An activity is a single work entity that has a known beginning and end. Activities are time
consuming as well as it requires some resources for its completion. For 100 BOQs activities were
defined by discussing it with MES staff, field personnel and studying different research papers.

41
5.8.8 Activity Types and Milestones
An Activity may be assigned one of the following default Activity Types using the drop
down box in the Project Defaults tab:
a. Finish Milestone
b. Level of Effort
c. Start Milestone
d. Task Dependent
e. WBS Summary

5.8.9 Activities of Actual Scheduled Project


We were able to collect WBS based duration of 100 BOQs from MES office Risalpur as
they did not have exact date and duration for each activity performed. Each WBS duration was
subdivided into different activities contained in that WBS using “Three time Estimating
Technique”.
The following are activities of actual Project

42
Fig 5.10 - Table view of Activities of 100 BOQs

43
Fig 5.11 - Table view of Activities of 100 BOQs

Fig 5.12 - Gantt chart view of Activities

44
5.8.10 Assigning Relationships
There are four types of dependencies available in Primavera P6. We will be defining only two of
them.
a. Finish-to-Start (FS) (also known as conventional): The successor activity can begin
only when the predecessor activity completes.
b. Start-to-Start (SS): In this both the activities can start simultaneously but with
certain amount of lag between them.

5.8.11 Understanding Lags and Leads


A Lag is a duration that is applied to a dependency to make the successor start or finish
earlier or later. A successor activity will start later when a positive Lag is assigned. On the other
hand lead is also called negative lag where an activity can be started before successor activity.
Leads and Lags may be applied to any relationship type.

5.8.12 Resources
Resources are all those requirements which need for the fulfillment of any task or activity. It
comes in three flavor in P6.
a. Labor (personnel)
b. Non-labor (Equipment)
c. Material

5.9 Scheduling of Project

After assigning relationship to each activity, the project was scheduled and the following
deductions have been made.
a. The start date of the actual Scheduled project is 16 April, 2013.
b. The project Finished date is 16 October, 2014
c. Actual duration of the Project is 18 months
Hence the Project has a time overruns of six months

5.9.1 Activities of Planned Scheduled Project


Activities for the Planned Scheduled Project remained same, and the duration each activity was
assigned using concept of Task or Out-turn work.

45
5.9.2 Task or Out-Turn work
The capacity of doing work by a skilled labor in the form of quantity of work per day is
known as the task-work or out-turn of the labor.
The out-turn of work per labor varies to some extent according to the nature, size, height, situation,
location, etc. In developed areas the out-turn of a skilled labor is more as compared to small
villages. Labor quantity also depends upon by managing and organizing the labor force.
The following may be taken as the approximate quantity of work or out-turn or task for an average
labor per day taken from a book “Estimating and Costing” by Dutta’s.

46
47
48
Fig 5.13 - Out turn work

49
Fig 5.14 - Table view of planned Activities

50
Fig 5.15 - Table view of planned Activities

51
Fig 5.16 - Gantt chart view of Planned Activities

5.9.3 Scheduling of Planned Project


Similarly the relationship and resources were assigned to the Planned Project, and Scheduled
accordingly. The following deductions were made.
a. The starting date of the Planned Project remains the same i-e 16 April, 2013.
b. The Project finished on 15 April, 2014
c. Hence total duration of the project is 364 days which is the contractual period of the Project

52
5.10 Comparison of the project at WBS level

In order to identify the areas where time overruns occurred during actual project execution,
a comparison at WBS level is performed between actual Scheduled and Planned Scheduled Project
using MS Project.

Fig 5.17 - Comparison of Actual vs Planned schedule

53
Fig 5.18 Comparison of Actual vs Planned schedule

54
Graph 5.1 - % 0f Delay vs Major Affected areas

55
Chapter 6
IDENTIFICATION AND EVALUATION OF CAUSES OF DELAY
OF 100 BOQS

6.1 Introduction
The term delay is the time overrun in a construction of particular project beyond its
completion date written in a contract, or beyond the date that is given as contingency in terms of
time for delivery of a project. It is very common problem in construction projects. For delay in
construction of particular facility owner losses the revenue and rent if we are talking about present
constructed facility. In some cases, the contractor, has higher overhead costs because of long work
duration at same project, high material costs due to inflation, and high labor costs.
Despite of the fact that delay causes serious problems, construction industry simply ignores this
aspect in construction projects and only adds compensation for that in terms of contingency. This
delay factor is very high in construction projects of developing countries where time overruns
sometimes exceed 100% of the actual time of the project.
In Pakistan, construction industry is an important industry although this industry is not working to
its full potential but still it is very significant to the country’s development. Development in this
industry is critical for increase in national income as it is among the largest employment generating
sectors of country as well as a key driving force for economic development of Pakistan. Like many
other countries Pakistan is also facing very much issues in construction industry among which
delay in projects completion is quite important one. There are many factors that are responsible
for these delays.

6.2 Information about 100 BOQs


100 BOQs is a residential type of building, and its Construction was executed by MES
Army Risalpur Cantonment. It is located on Liaqat road Risalpur Cantonment. The contract was
awarded to M/S Ch Abdul Ghaffar and CO. It was supposed to be completed within time of one
year and budget of 100 million (approx.). But the project failed to achieve its objective due to
both time and cost overrun. The Project completed within one year and six months of duration
and the total cost reached to 110 million.
For identification and evaluation the causes of delay of 100 BOQs a interviews were conducted
in which a targeted sample of 15 stakeholders including management staff and supervisory staff
from client/Consultant, Monitoring team and Contractors were selected and interviewed
accordingly.

56
6.3 Key stakeholders
6.3.1 Client / Consultant
1. Shabir Ahmad Usmani, AGE Army Risalpur Cantonment
2. Habib Ahmad , AE Risalpur Cantonment
3. Pervaiz Akhtar , AE Risalpur Cantonment
4. Hassan Jan , SDO B/R Army Risalpur Cantonment
5. Khalil Haider , SDO E/M Army Risalpur Cantonment
6. Zia-Ur-Rehman ,Sub Engineer B/R gde-II
7. Sajid Rahim , Sub Engineer
8. Hav Muhammad Irfan , Project NCO

6.3.2 Project Monitoring Team


1. Lt. Col Ansar Zaman , G-1 Project
2. Hav Muhammad Irfan , Project NCO
3. Hav Yasir Mehmood Project NCO

6.3.3 Contractor
1. Chaudhary Abdul Ghaffar , Contractor
2. Fayaz Hussain , Project In charge
3. Kamal , Sub Engineer
4. Abdullah , Supervisory staff

Fig 6.1 - Key Stakeholders

57
The studies include to find out main problem involved in time overrun in construction
project of 100 BOQs in Risalpur Cantonment. In this regard 14 major areas were identified
where probable delay could occur.
They are

6.4 Factors identified affecting “Time Overruns” in 100 BOQs Risalpur


Cantonment.
1. Feasibility Study of the Project
2. Scope and Planning Related time overruns
3. Design / Drawing Related time overruns
4. Estimation Related time overruns
5. Contract Related time overruns
6. Site Related time overruns
7. Work Forces Related time overruns
8. Construction Material and Equipment Related delays
9. Construction Management Related time overruns
10. Finance Related time overruns
11. Cost Related time overruns
12. Quality Related time overruns
13. Weather / Hazards Related time overruns
14. Government Related time overruns

6.5 Questionnaire Design


A questionnaire consist of 59 factors of delays was developed in order to collect the data
and assess the reviews of different stakeholders involved in the construction process of 100 BOQs
Risalpur Cantonment, for the evaluation purpose of repeated occurrence and significance of the
main causes. We divided the questionnaire sample into two parts. In first part, we included the
information about the stakeholders. In second part, we included those factors which were very
frequent and important in construction delay of particular projects. First we met with key
stakeholders which were involved in the construction of 100 BOQs and explained the whole
situation and then we interviewed each stakeholder and filled the questionnaire.
The format of questionnaire is given in appendix

6.6 Analysis of Data


We applied a basic rule of getting average of the whole response from each stakeholder for
every factor to find out the relative impact of each factor that explains how much every factor is
contributing to delay in whole project. We adopted a scale from 1 (strongly disagree) to 5 (strongly
agree) and then for each factor an impact was found by using following relation.

∑( 𝒇𝒊 ∗ 𝒊)
𝐼𝑚𝑝𝑎𝑐𝑡 𝑜𝑓 𝑓𝑎𝑐𝑡𝑜𝑟 =
𝒏

58
In this relation
i is the extent score from 1 to 5 (1=strongly disagree, 2=Disagree , 3=Neither agree nor
Disagree, 4= Agree, 5= Strongly Agree)
f i is the frequency of factor getting score i
n = number of responses from the stakeholders
By performing these calculation 15 total factors were got responsible for causing delay in
construction of 100 BOQs. The table given below shows impact of resultant factor

Rank Factor description Impact


1 Drawing / Design Variation 4.43
2 Slow Decision Making by the 4.36
client
3 Approval of variation order 3.93
4 Change in specification of 3.79
Material during construction
5 Adverse effects of weather 3.64
resulting in delay
6 In-adequate quality resulting 3.5
in work suspension/redoing
7 Fluctuating Prices of Raw 3.5
Material / fitting fixtures
8 Cost escalation / inflation 3.43
9 Inadequate feasibility study
of the Project by the 3.36
client/Consultant
10 Less Co-ordination between 3.36
Design team and Contractor

11 Labor Disputes / Strikes / 3.36


security issues
12 Misinterpretation of 3.29
Drawings resulting in
Suspension of work
13 In-adequate duration of 3.21
contract period
14 Non-conducive Law and 3.14
Order / Security Situation
15 Vague Conception of 3.14
Demand of Construction
Material

Table no 5.1 – Factors and Their impact

59
Graph 6.1 - Impact of Factor vs Factor

6.7 Deductions of causes of delay


1. Inadequate feasibility study of the Project by the client/consultant
Normally includes inadequate
a. Schedule Feasibility study
b. Economic Feasibility study
2. Vague Conception of Demand of Construction Material
It includes
a. Wastage of construction material on site
b. Material management issues
c. Delay in planed construction activities
3. Drawing / Design Variation
Due to variation in design
a. Additional cost of rework
b. Increase in labor work
c. Wastage of material

60
4. Misinterpretation of Drawings
a. Results in Suspension of work
b. Rework
c. Changes
5. Change in specification of Material during construction
It will lead to
a. Increase or decrease in cost due to change in material
b. Rework of different activities of the Project
6. Labor Disputes / Strikes / security issues
Time delay due to high official oftenly visiting Risalpur cantonment
7. Lack of Co-ordination between Design team and Contractor
a. Contractor would not be able to implement the design strategy
b. Due to communication gap on the part of contractor, the design team would not
be able provide requisite design amendments to the contractor
8. Slow Decision Making by the client/consultant
a. Labor force will remain idle
b. Construction machinery will remain idle
c. Material management issues
9. Delay in payment by the Client
a. Demotivation for labor
b. Material Procurement issues
10. Some factors which contribute to price fluctuations are
a. World prices for basic construction materials
b.Local economy’s present worth
c. Quality of materials and labor required
d.Supply and demand Fluctuating Prices of Raw Material / fitting fixtures
11. Adverse effects of weather resulting in delay
a. Decrease in labor Productivity
b. Slow execution of the project
c. Result in Rework
12. Non-conducive Law and Order / Security Situation
Time delay due to high official oftenly visiting Risalpur cantonment
13. Approval of variation order
Delay in approval of variation order will cause
a. Overall delay in construction Project
b. Lower the efficiency/output of the Project team
14. In-adequate quality of material used
It will result in
a. Suspension of work
b. Redoing of Work
c. Wastage of both material and cost
15. In-adequate duration of contract period

61
6.8 Recommendations

1. Design and drawing variation


Modeling should be done using architecture/Design Software .Design and Specifications
should be agreed upon by each party in initial phase

2. Slow Decision Making by the Client


Contractor and Client/Consultant should work as a team so that both of them are actively
involved in the project and take quick decision where required.

3. Approval of variation orders


Proper Planning should be made so that there will be no variation in orders later in execution
of Project .But in case if there are some variations , then they should be documented and
approved as quickly as possible to avoid delay in planned construction activities.

4. Change in Specification of Material during Construction


Material specification should be decided in the initial phase and should not be changed later
on.

5. Adverse effects of weather


Risk management plan should be made in the early course before the execution of project.

6. Inadequate Quality
Proper Supervision and Time to time visits by the Consultant on every single activity during
execution should be done to insure Quality management.

7. Fluctuating Prices of Raw material


Risk Management Plan and activity Reserves should be made THOUGHT OUT in the initial
planning.

8. Lack of Co-ordination between Design Team and contractor


Contractor should be actively involved from the start of project with full dedication and
conviction to have strong mutual co-ordination with design team.

9. Misinterpretation of Drawings
Contractor should be competent enough to undertake such projects. Misinterpretation of
drawing would not tolerated

10. Inaccurate duration of contract period


Proper Scheduling should be done on some Software especially Primavera P6 to get a realistic
picture of Total Project Duration which would help a lot during contact formulation

62
REFRENCES
1. Assaf, S.A., M. Al-Khalil, and M. Al-Hazmi, Causes of delay in large building

construction projects. Journal of Management in Engineering, 1995. 11(2): p. 45-50.

2. Sweis, G., et al., Delays in construction projects: The case of Jordan. International

Journal of Project Management, 2008. 26(6): p. 665-674.

3. El-Razek, M.E.A., H. Bassioni, and A. Mobarak, Causes of delay in building

construction projects in Egypt.Journal of Construction Engineering and Management,

2008. 134(11): p. 831-841.

4. Zack Jr, J.G., “Claimsmanship”: Current Perspective. Journal of Construction

Engineering and Management, 1993. 119(3): p. 480-497.

5. Haseeb, M., A. Bibi, and W. Rabbani, Problems of Projects and effects of delays in the

construction industry of Pakistan. Australian Journal of Business and Management

Research Vol, 2011. 1(5): p. 41-50.

6. Odeh, A.M. and H.T. Battaineh, Causes of construction delay: traditional contracts.

International journal of project management, 2002. 20(1): p. 67-73.

7. Baldwin, J.R., et al., Causes of delay in the construction industry. Journal of the

Construction Engrg.Division, 1971. 97(2): p. 177-187.

8. Al-Hazmi, M.H., Causes of delay in large building construction projects. Unpublished

MS Thesis, King Fahd University of Petroleum and Minerals, Dhahran, Saudi Arabia,

1987.

9. Al-Khalil, M.I. and M.A. Al-Ghafly, Important causes of delay in public utility projects

in Saudi Arabia. Construction Management & Economics, 1999. 17(5): p. 647-655.

10. Dutta, BN (1984). Estimating and Costing. India

63
11. Orozco, F., Serpell, A., Molenaar, K., and Forcael, E. (2011). “Modeling

competitiveness factors and indexes for construction companies: Findings of Chile.” J.

Constr. Eng. Manage.

12. Faridi, A. S., and El-Sayegh, S. M. (2006). “Significant factors causing delay in the UAE

construction industry.” Constr. Manage. Econ., 24(11), 1167–1176.

13. Chang, A. S. (2002). “Reasons for cost and schedule increase for engineering design

projects.” J. Constr. Eng. Manage., 18(1), 29–36.

14. Alarcon, L. F., Diethelm, S., Rojo, O., and Calderon, R. (2005). “Assessing the impacts

of implementing lean construction.” Proc., Int. Group for Lean Construction Annual

Conf., Group for Lean Construction, Sydney, Australia, 387–393.

15. Flyvbjerg, B., Mette, K., Holm, S., and Buhl, S. L. (2004). “What causes cost overrun in

transport infrastructure projects?” Transp. Rev., 24(1), 3–18.

16. Galloway, P. D. (2006). “Survey of the construction industry relative to the use of CPM

scheduling for construction projects.” J. Constr. Eng. Manage., 132(7), 697–711.

64
Annex A
TAKING OF SHEETS (ESTIMATION) OF 100 BOQs

Estimation of 32 BOQs

Excavation
I. Excavation in foundation & pipe trenches up to 1.5 M wide, wells and
independent holes up to 30 sqm
II. Excavation over areas as in foundation / areas etc. or for shafts, wells
exceeding 30 sqm each.

Excavation over Areas

Description No Length(ft) Width(ft) Depth(ft) Qty-CFT


WF-1 8 23.5 5 3 2820
WF-2 4 59.71 5 3 3582.6
WF-2 8 16.875 5 3 2025
WF-2 16 9.37 5 3 2248.8
WF-1 8 10.43 5 3 1251.6

Net QTY ( CFT ) 11984.25

Net QTY ( CUM ) 339.617

65
PCC In Foundation (1:4:8)

Tot
Description N0 Length(ft) Width(ft) Depth(ft) Qty(cft)

16 5.75 1.5 0.5 69

16 2.33 1.5 0.5 27.96


PCC In
16 10.75 1.25 0.25 53.75
Foundation
(1:4:8) Sum 150.71

((1198425*.25)/3+1
Total Qty(cft) 1149.35 50.71)

DPC
No Length Depth Total Qty(sqft)
4 18.87 0.75 56.61
4 18.87 1.12 84.5376
4 63.75 0.75 191.25
8 13 1.12 116.48
16 10 1.12 179.2
8 14.5 0.75 87
1 10.75 0.75 8.0625
1 7 0.75 5.25
8 14.5 0.37 42.92
16 5 0.37 29.6
Net Qty (Sqft) 800.9101
Net Qty (Sqm) 74.4450941

66
Brick Work

BB Work (Up to Ground Floor level)


Description No Length Width Depth Qty-cft
9" Wall
1st Step 4 63.75 1.12 0.5 142.8
2nd Step 4 63.75 0.75 1.5 286.875
1st Step 8 13 1.12 0.5 58.24
2nd Step 8 13.19 0.75 1.5 118.71
1st Step 1 6.62 1.125 0.5 3.72375
2nd Step 1 7 0.75 1.5 7.875
4.5" Wall
1st Step 16 14.25 0.75 1.25 213.75
1st Step 16 4.81 0.75 1.25 72.15
1st Step 16 13 0.75 0.75 117
1st Step 4 18.87 0.75 2 113.22
13.5" Wall
1st Step 4 18.87 1.12 2 169.0752
1st Step 8 13 1.12 2 232.96
1st Step 16 10 1.12 2 358.4
Total Sum (cft) 1894.78
Total Sum (cum) 53.695

67
BB Work (upto GF Roof Level)
Description No Length Width Depth Qty-cft
9" Wall
4 18.87 0.75 12.5 707.625
4 63.75 0.75 12.5 2390.625
8 14.5 0.75 12.5 1087.5
1 7 0.75 12.5 65.625
13.5" Wall
4 18.87 1.12 12.5 1056.72
4 13 1.12 12.5 728
16 10 1.12 12.5 2240
Dwarf Wall
1 10.75 0.75 2 16.125
Total 9021.2

Deduction of Doors, Windows, Ventilators & Columns

D3 16 3.5 0.75 7 294


W2 16 4.5 0.75 6 324
V1 16 3 1.12 4 215.04
W1 3 6 0.75 6 81
W6 2 1.5 1.12 12.5 42
Column 2 1.12 1.12 12.5 31.36

Total 987.4
NET QUANTITY OF BB WORK(IN CFT)
8033.8
NET QUANTITY OF BB WORK(IN CUM)
227.67
Total Quantity of BB work for 9" & 13.5" Wall 268.9

68
BB Work (Upto First Floor Roof lvl)
Description No Length Width Depth Qty-cft
4.5" Wall
16 14.5 0.37 12.5 1073
16 5 0.37 12.5 370
16 12 0.37 3.08 218.8032
Total 1661.803
Deduction
16 6.37 0.37 7 263.9728
16 2.5 0.37 7 103.6
367.5728
Net Qty(cft) 1294.23
Net Qty(cum) 36.67668

Total Quantity of BB work for 4.5" Wall(cum) 44.12

Total Qty of BB Work for 9",13.5"


wall(cft) 6739.22 ((8033.8*10.5)/12.5)

Total Qty of BB Work for 9",13.5"


wall(cum) 190.98
Total Qty of BB Work for 4.5"
wall(cft) 1086.96 ((1294.23*10.5)/12.5)

Total Qty of BB Work for 4.5"


wall(cum) 30.80293

69
BB Work in Parapet Wall

No Length Width Depth Qty-cft


8 12.37 0.75 3 222.66

4 24.75 0.75 3 222.75


16 10.75 0.75 3 387

2 44.75 0.75 3 201.375

Sum(cft) 1033.785

Sum(cum) 29.29602

Termite Proofing

No Length Width Qty(sq ft) Qty(sqm)

2 139.08 44.75 12447.66 1157.018

Cement Concrete Work (PCC)

a. Cement Concrete under Floors(1:6:12)

Total
Description No Length Width Depth Qty(cft)
Room 16 12 10 0.25 480
Dress 16 7.12 5 0.25 142.4

70
Balcony 16 4.5 10 0.25 180
Gallary 2 65.62 7 0.25 229.67
Gallary 1 32.75 7 0.25 57.3125
Room 16 7 5 0.25 140
Sum(cft) 1229.383
Sum(cum) 34.83899

Cement Concrete Type B in Walls, Sills, Channels, Drains, Stairs, Copings

No Length Width Depth Total Qty(cft)


32 4.5 1.12 0.25 40.32
32 3 1.12 0.25 26.88
6 6 0.75 0.25 6.75
4 75.62 1 0.17 51.4216
2 46.25 1 0.17 15.725
2 7 1 0.17 2.38
Sum(cft) 143.4766
Sum(cum) 4.065927

Cement Concrete Type B Laid in Floor Slabs, as under layer for Terrazzo
(GF+First Floor)

Net Qty(cum) 69.67797 34.839x2

71
Cement Concrete Type C in Plinth Protection, Surface Finish (GF+First
Floor)

No Length Width Tot Qty


4 65.62 3 787.44
16 1.5 3 72
2 50.75 3 304.5

2 31.37 3 188.22
Sum(sqft) 1352.16

Sum(sqm) 125.684117

Cement Plaster(1:4)
Description No Length Width Tot Qty(sqft)
4 18.87 1.12 84.5376
8 18.87 0.75 113.22
8 14.5 0.75 87
16 14.5 0.37 85.84
8 10 1.12 89.6
16 5 0.37 29.6
4 65.62 0.75 196.86
13mm Thick(with 2X 8 13.75 1.12 123.2
layer of building Sum(sq ft) 809.86
paper) Sum(sqm) 75.277
2 44.75 27 2416.5
2 8.87 27 478.98
4 65.62 27 7086.96
64 27 1 1728
Sum(sq ft) 11710.44
13mm Thick Sum(sqm) 1088.49
Deduction
32 4.5 6 864
32 3 4 384
4 6 6 144

72
Sum(sq ft) 1392
Sum(sqm) 129.387269
Net Quantity(sqm) 959.11

Cement Plaster(1:6)
Description No Length Width Tot Qty(sqft)

64 12 10.5 8064
64 10 10.5 6720
64 7.12 10.5 4784.64
64 5 10.5 3360
64 7 10.5 4704
64 5 10.5 3360
32 10 10.5 3360
32 12 3.08 1182.72
32 5 10.5 1680
32 2.5 10.5 840
8 65.62 10.5 5512.08
8 7 10.5 588
4 45.37 10.5 1905.54
13mm Thick(2x 4 7 10.5 294
course of Sum(sq ft) 46354.98
distempering) Sum(sqm) 4308.72435
64 3.5 7 1568
64 2.5 7 1120
32 4.5 6 864
32 3 4 384
Deduction 4 6 6 144
Sum(sq ft) 4080
Sum(sqm) 379.238548
Net Qty(Sqm) 3929.4858

73
RCC Work

RCC in Foundation
Description Tot Qty(cft) Tot Qty(cft)

RCC concrete type B 2995.92 84.90 (11982.25*.75)/3

RCC Type B in Roof Slabs, Landings, Plinth beam & Bands:

No Length Width Depth Qty(sq ft)


4 65.62 39.75 0.42 4382.104
32 10.75 2 0.42 288.96
2 32.87 7 0.42 193.2756
32 27 1 0.25 216
Sum 5080.339
Sum(cum) 143.9697

RCC Type B in Columns, Beams, Stairs, Post and Lintels:

Description No Length Width Depth Qty(sq ft)


16 5 0.75 0.5 30
16 6 0.75 0.75 54
16 4.5 1.12 0.75 60.48
3 7.5 0.75 1 16.875
2 1.5 1.12 12.5 42
2 1.04 1.12 12.5 29.12
16 7.5 0.375 0.75 33.75
16 3.5 0.375 0.5 10.5
16 16.37 0.75 1 196.44
1 8.5 0.75 1.75 11.15625
Ground Floor+ First 1 34.75 0.75 1.5 39.09375
Floor Sum 523.415

74
First Floor Sum(cum) 14.83285
Total Quantity(GF+FF) 29.6657

Steel Reinforcement

Foundation Steel Reinforcement

Description No Cut Length Total length

240 5.16 1238.4


328 5.16 1692.48
184 5.16 949.44
112 5.16 577.92
128 5.16 660.48
6 5.16 30.96
Main Bars Sum(ft) 5149.68
#4 @ 6" c/c
No Cut Length Total length

32 22.33 714.56
16 61.45 983.2
32 16.83 538.56
32 10.71 342.72
32 12.25 392
Distribution Bars 4 4.58 18.32
#4 @ 9" c/c Sum(ft) 2989.36
Net Total length 8139.04
Wt of Steel(lbs) 5428.73968

75
Column Steel Reinforcement

Description No Cut Length Total length


Column 1
Main Bars
#5 36 16 576
24 16 384
42 5.58 234.36
36 13.33 479.88
12 7.04 84.48
Sum(ft) 1758.72
Wt of Steel(lbs) 1832.58624

42 5.58 234.36
36 5.58 200.88
48 5.58 267.84
42 5.58 234.36
Ties 96 4.16 399.36
#3 @ 6" c/c Sum(ft) 1336.8
54 5.58 301.32
36 5.58 200.88
48 5.58 267.84
770.04
#3 @ 12" c/c Sum(ft) 2106.84
Wt of Steel(lbs) 790.065
Column 2
24 16 384
24 13.33 319.92
Main bar #8 Sum(ft) 703.92
Wt of Steel(lbs) 1877.35464

#3 @ 5" c/c Ties 54 5.58 301.32


Wt of Steel(lbs) 112.995

76
Beams
Beam of Ground Floor Roof
Description No Cut Length Total length
32 16.66 533.12
80 3.33 266.4
3 8.5 25.5
Bottom and Top 2 29.7 59.4
Bars (#6) Sum(ft) 884.42
5 8.5 42.5
3 8.5 25.5
6 27.7 166.2
Description #5 Sum(ft) 234.2
32 16.66 533.12
15 5.33 79.95
48 5.33 255.84
56 4.83 270.48
Stirrups #3 Sum(ft) 1139.39

Beams of First Floor Roof


Description No Cut Length Total length
32 16.66 533.12
3 8.5 25.5
6 29.75 178.5
128 14.5 1856
Bottom and Top 64 14.5 928
Bars (#5) Sum(ft) 3521.12
64 16.66 1066.24
40 8.5 340
3 8.5 25.5
Bottom and Top 2 29.75 59.5
Bars (#6) Sum(ft) 1491.24
554 4.83 2675.82
15 5.33 79.95
48 5.33 255.84
56 4.83 270.48
Stirrrups #3 Sum(ft) 3282.09

77
Net length of bars #5 in GF roof & First
Floor 3755.32

Wt of Steel #5 bars(lbs) 3913.04344

Net length of bars #6 in GF roof & First


Floor 2375.66

Wt of Steel #6 bars(lbs) 3563.49

Net length of #3 Stirrup in GF roof &


First Floor 4421.48

Wt of Steel #3 Stirrups(lbs) 1658.055

Steel Reinforcement in Slabs


Description No Cut Length Total length
496 9.87 4895.52
128 11.25 1440
128 16.37 2095.36
128 13.87 1775.36
384 5.125 1968
228 6.87 1566.36
24 65.62 1574.88
65 6.87 446.55
Bottom Bars First Floor 12 32.87 394.44
#3 528 4.42 2333.76

78
276 5.25 1449
128 6.25 800
136 5.5 748
Sum(ft) 21487.23

528 8.62 4551.36


Bottom Bars First Floor 456 6.45 2941.2
#4 Sum(ft) 7492.56

144 11.5 1656


40 17.87 714.8
32 65.62 2099.84
12 15.62 187.44
28 17.87 500.36
48 10.37 497.76
Binding #3 Sum(ft) 5656.2

496 9.87 4895.52


112 11.25 1260
112 16.37 1833.44
112 13.87 1553.44
416 5.12 2129.92
264 6.87 1813.68
24 65.62 1574.88
66 6.87 453.42
12 32.87 394.44
Top Roof #3 Bars Sum(ft) 15908.74

432 8.65 3736.8


224 4.42 990.08
456 6.45 2941.2
12 5.25 63
128 5.5 704
Top Roof #4 Bars Sum(ft) 8435.08

Binding #3 144 11.5 1656

79
40 17.5 700
32 65.62 2099.84
72 15.62 1124.64
56 17.87 1000.72
8 10.37 82.96
Sum(ft) 6664.16

Total length #3 Bars 49716.33

Wt of Steel #3 bars 18643.62375

Doors & Windows lintels


Description No Cut Length Total length
#4 80 5 400
176 2.83 498.08
80 4 320
144 2.83 407.52
Sum(ft) 1625.6
#3 320 5.5 1760
576 2.83 1630.08
240 4.5 1080
480 2.83 1358.4
Sum(ft) 5828.48
Wt of steel #3 (lbs) 2185.68
Wt of steel #4(lbs) 1084.2752

80
Cement Bags
Description Qty Unit C/F Cement
CC 1:4:8 32.57 Cum 3.51 114.32
CC Type B 4.06 Cum 6.54 26.55
CC Type B 69.67 Cum 6.54 455.64
CC Type B 21.19 Cum 6.54 138.58
CC Type B 141.57 Cum 6.54 925.87
BB Work in
CM 1:6 54.01 Cum 1.4 75.61
Do 268.9 Cum 1.4 376.46
do but 1:4 44.12 Cum 1.95 86.03
do but 1:6 190.98 Cum 1.4 267.37
do but 1:4 29.29 Cum 1.95 57.12
Do 27.83 Cum 1.95 54.27
50mm PCC
1:2:4 3.75 Cum 6.54 24.53
CC 1:6:12 34.84 Cum 2.4 83.62
CC Type B 57.2 Cum 6.54 374.09
20mm thick
terrazzo 913.76 Sqm 0.38 347.23
10mm thick
terrazzo 180.29 Sqm 0.214 38.58
Glazed Tiles 104.1 Sqm 0.214 22.28
Do 349.5 Sqm 0.214 74.79
75mm thick
CC type C 123.06 Sqm 0.34 41.84
13mm thick
C/Plaster 1:4 2068.77 Sqm 0.12 248.25
do but 1:6 3929.48 Sqm 0.087 341.86

Surface Gullies 16 No 0.67 10.72


Construction
of M/hole
n.exc 600mm 12 No 5.13 61.56
Provision of
Roof
Insulation 491.48 Sqm 0.033 16.22

81
Manhole exc
600mm 7 No 7.4 51.80
Sum 4315.20
OMIT
20mm thick
terrazzo Floor 913.76 Sqm 0.38 347.23
10mm thick
terrazzo Floor 180.26 Sqm 0.217 39.12
Sum 386.35
Net Cement 3928.85

3929 Bags

Services
Total Qty(Sq
Description No Length Width ft)
White Light Glazed non
Skid Tiles 32 7 5 1120
Net Sum(Sq m) 104.10
64 7 4 1792
64 5 4 1280
Dark color Glazed Non
Skid Tiles 96 3.5 3 1008
Sum 4080
Deduction
32 2.5 4 320
Net Sum(Sq ft) 3760
Net Sum(Sq m) 349.49
First Class Soft wood 32 3.5 7 784
Framed and Paneled Doors,
Gates 32 2.5 7 560

82
Net Sum(Sq ft) 1344
Net Sum(Sq m) 124.9256395
32 4.5 6 864
Box Type steel sliding/Fix
windows 6 6 6 216
Net Sum(Sq ft) 1080
Net Sum(Sq m) 100.387
Box Pipe Type openable &
Fix side hung windows 32 3 4 384
Net Sum(Sq ft) 384
Net Sum(Sq m) 35.6930
32 4.5 6 864
6 6 6 216
Wooden steel Grill 32 2.5 7 560
Net Sum(Sq ft) 1640
Net Sum(Sq m) 152.439
Plain galvanised steel sheets 1 44.75 3 134.25
Net Sum(Sq m) 12.479

32 0.75 0.5 12

32 1.12 0.75 26.88

13 mm thick soft board


sheets fixed in ceilings &
Partitions 32 0.375 0.5 6

83
16 0.75 1.5 18

16 1.12 1.5 26.88

Net Sum(Sq ft) 89.76

Net Sum(Sq m) 8.343

Curtain Rail type C


No Length Total Qty(ft)
32 4 128
32 5.5 176
32 8.12 259.84
Sum(ft) 563.84
Sum(m) 171.90

UPVC soil & Waste pipe 110mm

No Length Total Qty(ft)


16 12 192
16 3 48
16 12.5 200
16 12.5 200
16 1.5 24
16 1.5 24
16 9 144
Net Sum(ft) 832
Net Sum(m) 253.66
UPVC soil & Waste pipe 75mm

16 9 144

84
32 8 256
Net Sum( ft) 400
Net Sum( m) 121.95
RCC Pipes 150mm

1 59.62 59.62
1 50.75 50.75
1 146 146
Net Sum(ft) 256.37
Net Sum(m) 78.16

Man Holes (230mm thick Brick walls)

Total Total
No Length Width Height Qty(Ft^3) Qty(m^3)

20 3.375 2.25 1.87 284.01 8.05

Description Quantity

RCC type B Manhole 20


cover

85
Estimation of 36 BOQs

Excavation
Excavation over Areas

Description No Length(ft) Width(ft) Depth(ft) Qty-CFT

WF-1 12 23.5 5 3 4230

WF-2 8 59.71 5 3 7165.2

WF-2 6 16.875 5 3 1518.75

WF-2 12 9.37 5 3 1686.6

WF-1 12 10.43 5 3 1877.4

WF-2 2 3.75 5 3 112.5

Net QTY ( CFT ) 16590.45

Net QTY ( CUM ) 470.150

86
Excavation in Foundation and Pipe Trenches
Description No Length(ft) Width(ft) Depth(ft) Qty-
CFT
301.87
WF-3 20 5.75 1.5 1.75 5
122.32
WF-3 20 2.33 1.5 1.75 5

WF-3 20 15.12 1.25 1 378

WF-3 20 18 1.255 1 451.8

1254

For Sewerage Line

1 61 1.5 2 183

1 70 1.5 2 210

1 160 1.5 3 720

1113
2367
Net QTY ( CFT )
67.077
Net QTY ( CUM )

87
PCC in Foundation (1:4:8)
Width(ft Tot
Description N0 Length(ft) ) Depth(ft) Qty(cft)

18 5.75 1.5 0.5 77.625

18 2.33 1.5 0.5 31.455


60.4687
18 10.75 1.25 0.25 5
PCC In 169.548
Foundation 75
(1:4:8) Sum

((16590.45
1463 *.25)/3+169.55)
Total Qty(cft)

41.46
Total Qty(cum)

DPC
No Length Depth Total Qty(sqft)
8 18.87 0.75 113.22
6 18.87 1.12 126.8064
6 63.75 0.75 286.875
6 13 1.12 87.36
20 10 1.12 224
8 14.5 0.75 87
6 10.75 0.75 48.375
6 7 0.75 31.5
10 14.5 0.37 53.65
18 5 0.37 33.3

88
1092.0864
Net Qty (Sqft)
101.51
Net Qty (Sqm)

Brick Work

BB Work (Upto Ground Floor level)


Description No Length Width Depth Qty-cft
9" Wall
1st Step 6 63.75 1.12 0.5 214.2
2nd Step 6 63.75 0.75 1.5 430.3125
1st Step 10 13 1.12 0.5 72.8
2nd Step 10 13.19 0.75 1.5 148.3875
1st Step 2 6.62 1.125 0.5 7.4475
2nd Step 2 7 0.75 1.5 15.75
4.5" Wall
1st Step 18 14.25 0.75 1.25 240.4688
1st Step 18 4.81 0.75 1.25 81.16875
1st Step 18 13 0.75 0.75 131.625
1st Step 6 18.87 0.75 2 169.83
13.5" Wall
1st Step 6 18.87 1.12 2 253.6128
1st Step 10 13 1.12 2 291.2
1st Step 18 10 1.12 2 403.2
Total Sum (cft) 2713.62

Total Sum (cum) 76.90

89
BB Work (upto GF Roof Level)
Description No Length Width Depth Qty-cft
9" Wall
6 18.87 0.75 12.5 1061.438
8 63.75 0.75 12.5 4781.25
10 14.5 0.75 12.5 1359.375
2 7 0.75 12.5 131.25
13.5" Wall
6 18.87 1.12 12.5 1585.08
10 13 1.12 12.5 1820
16 10 1.12 12.5 2240
Dwarf Wall
1 10.75 0.75 2 16.125
12994.52
Total
Deduction of Doors, Windows, Ventilators & Columns

D3 20 3.5 0.75 7 367.5


W2 20 4.5 0.75 6 405
V1 20 3 1.12 4 268.8
W1 7 6 0.75 6 189
W6 6 1.5 1.12 12.5 126
Column 6 1.12 1.12 12.5 94.08
1450.38
Total
Net quantity of BB work(in cft) 11544.14

Net quantity of BB work(in cum) 327.14

Total Quantity of BB work for 9" & 13.5" Wall 327.14

90
Description No Length Width Depth Qty-cft
4.5" Wall
20 14.5 0.37 12.5 1341.25
18 5 0.37 12.5 416.25
24 12 0.37 3.08 328.2048
2085.705
Total
Deduction
12 6.75 0.37 7 209.79
10 2.75 0.37 7 71.225
367.5728
1804.69
Net Qty(cft)
51.14
Net Qty(cum)

Total Quantity of BB work for 4.5" Wall(cum) 51.14

BB Work (Upto First Floor Roof lvl)

Total Qty of BB Work for 9",13.5"


wall(cft) 6739.22 ((8033.8*10.5)/12.5)

Total Qty of BB Work for 9",13.5"


wall(cum) 190.98
Total Qty of BB Work for 4.5"
wall(cft) 1086.96 ((1294.23*10.5)/12.5)

91
Total Qty of BB Work for 4.5"
wall(cum) 30.80293

BB Work in Parapet Wall

No Length Width Depth Qty-cft


12 12.37 0.75 3 333.99

8 24.75 0.75 3 445.5


20 10.75 0.75 3 483.75

4 44.75 0.75 3 402.75

Sum(cft)
1665.99

Sum(cum)
47.21183

Termite Proofing

No Length Width Qty(sq ft) Qty(sqm)

2 139.08 44.75 12447.66 1157.018

1 104.25 82 8548.5 794.59

Sum 1951.61

92
Cement Concrete Work (PCC)

Cement Concrete under Floors(1:6:12)

Total
Description No Length Width Depth Qty(cft)
Room 18 12 10 0.25 540
Dress 18 7.12 5 0.25 160.2
Balcony 16 4.5 10 0.25 180
Gallary 4 65.62 7 0.25 459.34
Gallary 1 32.75 7 0.25 57.3125
Room 16 7 5 0.25 140
Sum(cft) 1536.853
Sum(cum) 43.55

Cement Concrete Type B in Walls, Sills, Channels, Drains, Stairs, Copings

Total
No Length Width Depth Qty(cft)
34 4.5 1.12 0.25 42.84
34 3 1.12 0.25 28.56
8 6 0.75 0.25 9
6 75.62 1 0.17 77.1324
6 46.25 1 0.17 47.175
2 7 1 0.17 2.38
Sum(cft) 207.0874
Sum(cum) 5.87

93
Cement Concrete Type B Laid in Floor Slabs, as under layer for
Terrazzo(GF+First Floor)

Net Qty(cum) 87.10 43.55x2

Cement Concrete Type C in Plinth Protection, Surface Finish (GF+First


Floor)

No Length Width Tot Qty


6 65.62 3 1181.16
12 1.5 3 54
2 50.75 3 304.5
4 31.37 3 376.44
Sum(sqft) 1916.1

Sum(sqm) 178.10

Cement Plaster(1:4)

Description No Length Width Tot Qty(sqft)


6 18.87 1.12 126.8064
10 18.87 0.75 141.525
10 14.5 0.75 108.75
18 14.5 0.37 96.57
10 10 1.12 112
18 5 0.37 33.3
13mm Thick(with 2X 4 65.62 0.75 196.86
layer of building 10 13.75 1.12 154
paper) Sum(sq ft) 969.81

94
Sum(sqm) 90.14
4 44.75 27 4833
6 8.87 27 1436.94
6 65.62 27 10630.44
62 27 1 1674
Sum(sq ft) 18574.38
13mm Thick Sum(sqm) 1726.50
Deduction
30 4.5 6 810
30 3 4 360
4 6 6 144
Sum(sq ft) 1314
Sum(sqm) 122.137121
Net Quantity(sqm) 1604.36

Cement Plaster(1:6)
Description No Length Width Tot Qty(sqft)

68 12 10.5 8568
68 10 10.5 7140
68 7.12 10.5 5083.68
68 5 10.5 3570
66 7 10.5 4851
66 5 10.5 3465
36 10 10.5 3780
36 12 3.08 1330.56
36 5 10.5 1890
36 2.5 10.5 945
14 65.62 10.5 9646.14
10 7 10.5 735
6 45.37 10.5 2858.31
13mm Thick(2x 8 7 10.5 588
course of Sum(sq ft) 54450.69
distempering) Sum(sqm) 5061.22565
Deduction 68 3.5 7 1666

95
68 2.5 7 1190
32 4.5 6 864
34 3 4 408
4 6 6 144
Sum(sq ft) 4272
Sum(sqm) 397.085068
Net Qty(Sqm) 4664.14

RCC Work

RCC in Foundation
Description Total Qty(cft) Total Qty(cft)

RCC concrete type B


(16590.45*.75)/3
4147.6125 117.54

RCC Type B in Roof Slabs, Landings, Plinth beam & Bands:

No Length Width Depth Qty(sq ft)


5 65.62 39.75 0.42 5477.63
32 10.75 2 0.42 288.96
4 32.87 7 0.42 386.5512
40 27 1 0.25 270
Sum(cft) 6423.141
Sum(cum) 182.02

RCC Type B in Columns, Beams, Stairs, Post and Lintels

96
Description No Length Width Depth Qty(sq ft)
18 5 0.75 0.5 33.75
18 6 0.75 0.75 60.75
18 4.5 1.12 0.75 68.04
5 7.5 0.75 1 28.125
4 1.5 1.12 12.5 84
2 1.04 1.12 12.5 29.12
18 7.5 0.375 0.75 37.96875
18 3.5 0.375 0.5 11.8125
18 16.37 0.75 1 220.995
1 8.5 0.75 1.75 11.15625
Ground Floor+ First 1 34.75 0.75 1.5 39.09375
Floor Sum(cft) 624.8113
First Floor Sum(cum) 17.71
35.41
Total Quantity(GF+FF)

Steel Reinforcement

Foundation Steel Reinforcement

Description No Cut Length Total length

360 5.16 1857.6


406 5.16 2094.96
230 5.16 1186.8
168 5.16 866.88
192 5.16 990.72
70 5.16 361.2
7358.16
Main Bars Sum(ft)
#4 @ 6" c/c
No Cut Length Total length
Distribution Bars
#4 @ 9" c/c 48 22.33 1071.84

97
16 61.45 983.2
40 16.83 673.2
32 10.71 342.72
32 12.25 392
4 4.58 18.32
3982.8
Sum(ft)
Net Total length 11340.96
Wt of Steel(lbs) 7564.42032

Column Steel Reinforcement

Description No Cut Length Total length

Column 1

Main Bars

#5 36 16 576

24 16 384

42 5.58 234.36

36 13.33 479.88

12 7.04 84.48

Sum(ft) 1758.72

Wt of Steel(lbs) 1832.58624

42 5.58 234.36
36 5.58 200.88
Ties 48 5.58 267.84
#3 @ 6" c/c 42 5.58 234.36

98
96 4.16 399.36
Sum(ft) 1336.8

54 5.58 301.32
36 5.58 200.88
48 5.58 267.84
770.04
#3 @ 12" c/c Sum(ft) 2106.84

Wt of Steel(lbs) 790.065

Column 2

24 16 384
24 13.33 319.92
Main bar #8 Sum(ft) 703.92

Wt of Steel(lbs) 1877.35464

#3 @ 5" c/c Ties 54 5.58 301.32

Wt of Steel(lbs) 112.995

BEAMS
Beam of Ground Floor Roof
Description No Cut Length Total length
32 16.66 533.12
80 3.33 266.4
3 8.5 25.5
Bottom and Top 2 29.7 59.4
Bars (#6) Sum(ft) 884.42
5 8.5 42.5
3 8.5 25.5
Description #5 6 27.7 166.2

99
Sum(ft) 234.2
32 16.66 533.12
15 5.33 79.95
48 5.33 255.84
56 4.83 270.48
Stirrups #3 Sum(ft) 1139.39

Beams of First Floor Roof


Description No Cut Length Total length
32 16.66 533.12
3 8.5 25.5
6 29.75 178.5
128 14.5 1856
Bottom and Top 64 14.5 928
Bars (#5) Sum(ft) 3521.12
64 16.66 1066.24
40 8.5 340
3 8.5 25.5
Bottom and Top 2 29.75 59.5
Bars (#6) Sum(ft) 1491.24
554 4.83 2675.82
15 5.33 79.95
48 5.33 255.84
56 4.83 270.48
Stirrrups #3 Sum(ft) 3282.09

Net length of bars #5 in GF roof & First


Floor 3755.32

Wt of Steel #5 bars(lbs) 3913.04344

100
Net length of bars #6 in GF roof & First
Floor 2375.66

Wt of Steel #6 bars(lbs) 3563.49

Net length of #3 Stirrup in GF roof &


First Floor 4421.48

Wt of Steel #3 Stirrups(lbs) 1658.055

Steel Reinforcement in Slabs


Description No Cut Length Total length
620 9.87 6119.4
160 11.25 1800
160 16.37 2619.2
160 13.87 2219.2
504 5.125 2583
228 6.87 1566.36
24 65.62 1574.88
65 6.87 446.55
12 32.87 394.44
528 4.42 2333.76
276 5.25 1449
128 6.25 800
136 5.5 748
45 12.25 551.25
11 8.75 96.25
15 6 90
Bottom Bars First Floor Sum(ft) 25391.29
#3

101
528 8.62 4551.36
Bottom Bars First Floor 456 6.45 2941.2
#4 Sum(ft) 7492.56

144 11.5 1656


40 17.87 714.8
32 65.62 2099.84
12 15.62 187.44
28 17.87 500.36
48 10.37 497.76
Binding #3 Sum(ft) 5656.2

496 9.87 4895.52


112 11.25 1260
112 16.37 1833.44
112 13.87 1553.44
416 5.12 2129.92
264 6.87 1813.68
24 65.62 1574.88
66 6.87 453.42
12 32.87 394.44
Top Roof #3 Bars Sum(ft) 15908.74

564 8.65 4878.6


336 4.42 1485.12
912 6.45 5882.4
104 5.25 546
162 5.5 891
13683.12
Top Roof #4 Bars Sum(ft)

Binding #3 144 11.5 1656

102
40 17.5 700
32 65.62 2099.84
72 15.62 1124.64
56 17.87 1000.72
8 10.37 82.96
Sum(ft) 6664.16
74796.07
Total length #3 Bars
28048.52625
Wt of Steel #3 bars

Doors & Windows lintels


Description No Cut Length Total length
#4 80 5 400
176 2.83 498.08
80 4 320
144 2.83 407.52
Sum(ft) 1625.6
#3 80 5.5 440
192 2.83 543.36
80 4.5 360
160 2.83 452.8
1796.16
Sum(ft)
987.888
Wt of steel #3 (lbs)
2168.5504
Wt of steel #4(lbs)

103
Stairs
Description No Cut Length Total length

44 19 836
44 8.33 366.52
116 4 464
#3 Sum(ft) 1666.52

44 4.33 190.52
44 6 264
5 8.75 43.75
14 4.33 60.62
52 4 208
28 4 112
#4 Sum(ft) 878.89
Wt of steel #3 (lbs) 624.945

Mumty

Description No Cut Length Total length


#4 30 4.04 121.2

14 21.37 299.18

66 3.37 222.42

642.8

104
Total length of #4 Bars(ft) 1521.69

Wt of steel #4(lbs) 1014.96723

Cement Bags

Description Qty Unit C/F Cement

CC 1:4:8 41.46 Cum 3.51 145.52

CC Type B 4.06 Cum 6.54 26.55

CC Type B 87.1 Cum 6.54 569.63

CC Type B 29.19 Cum 6.54 190.90

CC Type B 141.57 Cum 6.54 925.87

BB Work in
CM 1:6 76.9 Cum 1.4 107.66

Do 327.14 Cum 1.4 458.00

do but 1:4 51.14 Cum 1.95 99.72

do but 1:6 190.98 Cum 1.4 267.37

do but 1:4 30.8 Cum 1.95 60.06

Do 47.21 Cum 1.95 92.06

105
50mm PCC
1:2:4 3.75 Cum 6.54 24.53

CC 1:6:12 43.55 Cum 2.4 104.52

CC Type B 57.2 Cum 6.54 374.09

20mm thick
terrazo 913.76 Sqm 0.38 347.23

10mm thick
terrazo 180.29 Sqm 0.214 38.58

Glazed Tiles 117.12 Sqm 0.214 25.06

Do 357.3 Sqm 0.214 76.46

75mm thick
CC type C 153.05 Sqm 0.34 52.04

13mm thick
C/Plaster 1:4 2014.08 Sqm 0.12 241.69

do but 1:6 3927.35 Sqm 0.087 341.68

Surface Gullies 16 No 0.67 10.72

106
Construction
of M/hole
n.exc 600mm 12 No 5.13 61.56

Provision of
Roof
Insulation 491.48 Sqm 0.033 16.22

Manhole exc
600mm 7 No 7.4 51.80
4709.53
Sum

OMIT

20mm thick
terrazzo Floor 913.76 Sqm 0.38 347.23

10mm thick
terrazzo Floor 180.26 Sqm 0.217 39.12

Sum 386.35

Net Cement 4323.18

4324Bags

107
Services
Total Qty(Sq
Description No Length Width ft)
White Light Glazed non
Skid Tiles 36 7 5 1260
Net Sum(Sq m) 117.12
60 7 4 1792
62 5 4 1280
Dark color Glazed Non
Skid Tiles 88 3.5 3 1008
Sum 3884
Deduction
38 2.5 4 380
Net Sum(Sq ft) 3504
Net Sum(Sq m) 321.98
First Class Soft wood 40 3.5 7 980
Framed and Paneled Doors,
Gates 41 2.5 7 717.5
Net Sum(Sq ft) 1697.5
Net Sum(Sq m) 157.78
38 4.5 6 1026
Box Type steel sliding/Fix
windows 8 6 6 288
Net Sum(Sq ft) 1314
Net Sum(Sq m) 122.14
Box Pipe Type openable &
Fix side hung windows 51 3 4 612
Net Sum(Sq ft) 612
Net Sum(Sq m) 56.89

108
34 4.5 6 918
12 6 6 432
Wooden steel Grill 34 2.5 7 595
Net Sum(Sq ft) 1945
Net Sum(Sq m) 180.79
Plain galvanised steel sheets 1 44.75 3 134.25
Net Sum(Sq m) 12.479

36 0.75 0.5 13.5

36 1.12 0.75 30.24

36 0.375 0.5 6.75

26 0.75 1.5 29.25

13 mm thick soft board


sheets fixed in ceilings &
Partitions 26 1.12 1.5 43.68

Net Sum(Sq ft) 123.42

Net Sum(Sq m) 11.47

109
Curtain Rail type C
No Length Total Qty(ft)
36 4 144
36 5.5 198
36 8.12 292.32
Sum(ft) 634.32
Sum(m) 193.39

UPVC soil & Waste pipe 110mm

No Length Total Qty(ft)


18 12 216
16 3 48
18 12.5 225
16 12.5 200
16 1.5 24
16 1.5 24
16 9 144
Net Sum(ft) 881
Net Sum(m) 268.60
UPVC soil & Waste pipe 75mm

22 9 198
38 8 304
Net Sum( ft) 502
Net Sum( m) 153.05
RCC Pipes 150mm

1 75.75 75.75
1 80.25 80.25
1 220 220
Net Sum(ft) 376
Net Sum(m) 114.63

110
Man Holes (230mm thick Brick walls)

Total Total
No Length Width Height Qty(Ft^3) Qty(m^3)

20 3.375 2.25 1.87 284.01 8.05

Description Quantity

RCC type B Manhole 20


cover

Bills of Quantities
Bills of quantities generally know and conversed as BQ is written document representing
simple estimate of work.
It is arranged on some definite format.
It describes not only different quantities and rates but also refers to drawings etc.
Initially BQs are prepared unpriced because its main purpose is to calculate the scope of work
but later on they are priced to evaluate exact cost of a project on some schedule (At Par Cost).
Tenderers then submit their priced BQ in support of their quotation in tender document which
when accepted becomes the contract document For calculation and correct application of rates,
description of item should be strictly in accordance with discipline give in Schedule of Rates for
different items.
We extracted Description of items and application of rates from MES Schedule of Rates 2009

111
BOQ of 32 BOQs

Sr.no Description of Work Quantity Unit Rate Amount

Excavation over areas as in


Ordinary Soil upto 1.5 M depth, in
foundation / to obtain earth for
1 filling under floors / areas etc, or 339.62 Cum 187.65 63729.693
for shafts, wells exc 30 sqm each,
throw earth clear of edges of
excavation within 10 M.

Excavation as in Ordinary Soil


upto 1.5 M depth, in foundation
and pipe trenches upto 1.5 M
wide, in shafts, wells and
independent holes upto 30 sqm
2 each and throw earth clear of 43.71 Cum 205.67 8989.84
edges of excavation within 10m.
Timbering to be paid extra
(Foundation and Trench over 1.5
M widths will be treated as
Areas).

Providing and laying of CC 1:4:8,


3 using Crushed or Broken stone 32.57 Cum 3246.74 105746.32
graded as specified

Providing and laying RCC Type


‘B’ using Crushed or broken stone
in foundation, independent
4 column footings, solid floors etc 84.9 Cum 4466.86 379236.41
incl from work as specified.
Reinforcement measured and paid
separately.

Providing and laying RCC Type


‘B,’ using Crushed or broken
stone in roof slabs, landings,
5 walls, plinth beams and bands etc 143.97 Cum 6311.38 908649.37
as specified requiring shuttering.
Reinforcement measured and paid
separately.

112
Providing and laying RCC Type
‘B,’ using Crushed or broken
stone in columns, beams, stairs,
6 posts, struts, piers, lintels, and the 29.66 Cum 6473.66 192008.75
like requiring shuttering, as
specified. Reinforcement
measured and paid separately.
Providing & laying of CC Type
‘B’ using Crushed or broken stone
as specified, in walls, sills,
copings, channels, drains, steps,
7 4.06 Cum 5068.85 20579.531
string courses, corbels pier caps,
hinge stone, bed plates etc, incl
formwork & fair faces to exposed
surfaces.
Burnt brick work, in walls 115mm
thick, laid and jointed in CM 1:4,
8 straight or to curve with inner 44.12 Cum 5612.79 247636.29
radius of 6m and over, upto G.F
roof level.

Burnt brick work, in wall over


115mm thick, laid and jointed in
9 CM 1.6, straight or to curve with 268.9 Cum 5026.23 1351553.2
inner radius of 6m and over, upto
G.F roof level.

Burnt brick work, in wall over


115mm thick, laid and jointed in
10 CM 1:6, straight or to curve with 190.98 Cum 5113.42 976560.95
inner radius of 6m and over, upto
1st floor roof level.

Burnt brick work, in wall 115mm


thick, laid and jointed in CM 1:4,
11 straight or to curve with inner 30.8 Cum 5720.09 176178.77
radius of 6m and over, upto Ist
floor roof level.

113
Burnt brick work, in wall over
115mm thick, laid and jointed in
12 CM 1:6, straight or to curve with 53.7 Cum 5317.26 285536.86
inner radius of 6m and over, upto
4.25m depth.

50mm thick P.C.C 1:2:4, using


3mm aggregate and finished
smooth with steel float, covered
13 with two coats, each of hot 74.44 Sqm 434.6 32351.624
bitumen 0.75 kg per Sqm and
blinded with 0.012 cum of sand
per Sqm.
Burnt brick work, in walls 115mm
thick, laid and jointed in CM 1:4,
14 straight or to curve with inner 29.3 Cum 5828.58 170777.39
radius of 6m and over, upto 2nd
floor roof level.

13mm thick Cement Plaster 1:4,


15 1088.49 Sqm 140.05 152443.02
finished as specified

13mm thick Cement Plaster 1:6,


16 finished as specified with 3 court 3929.49 Sqm 215.29 845979.90
of distempering.

13mm thick Cement Plaster 1:4,


17 finished as specified with 2X layer 75.28 Sqm 200.69 15107.943
of building paper

13mm thick Cement Plaster 1:4,


18 finished as specified with 3 court 959.11 Sqm 225.31 216097.07
of distempering.

Providing and laying CC 1:6:12,


19 laid under floor, using shingle or 34.84 Cum 2222.04 77415.873
gravel.

114
Providing and laying, CC Type
‘B,’ using shingle or gravel, laid
20 in floor, slabs as under layer for 69.68 Cum 3501.12 243958.04
Terrazzo / Stonolithic / tiles top
finished.

Providing and laying white / light


color/ glazed / non skid tiles exc
400 sq cm, but not exc 900 sq cm
area each, on walls and floors, set
21 104.1 Sqm 1119.03 116491.02
in neat cement and joints grouted
with white /colored cement,
complete, all as specified, Pak
made.
Providing and laying Dark
colored/ glazed / non skid tiles exc
400 sq cm, but not exc 900 sq cm
area each, on walls and floors, set
22 349.49 Sqm 1177.84 411643.30
in neat cement and joints grouted
with white /coloured cement,
complete, all as specified, Pak
made.
Supply and fix, 1st Class Soft
wood framed and paneled doors,
23 gates etc, incl hanging chowkats, 124.92 Sqm 5459.42 681990.74
hold fats, and iron mongery as
described, 38 mm thick.
Supply & fix, Box type steel
sliding/fixed window or CSW
using 16 gauge frame section
75mm x 30mm and panel section
25mm x 50mm & 10mm x 10mm
24 square gola, with all necessary 100.39 Sqm 2709.52 272008.71
steel fitting / iron mongery hold
fast etc and two coats of S/E paint
in addition to one coat of primer/
rust proof paint, except glass
panes, grill and wire gauze.

115
Supply & fix, Box Pipe type open-
able and fixed side hung window
or CSW using 16 gauge frame
section 50mm x 25mm and panel
"Z" shape 38mm x 31mm x 38mm
& 10mm x 10mm square gola, not
25 35.69 Sqm 2760.13 98509.039
exc 1.48 Sqm, super, each with all
necessary fitting/iron mongery,
hold fast etc and two coats of S/E
paint in addition to one coat of
primer / rust proof paint, except
wire gauze and glass panes, grill.
Supply and fix, plain galvd steel
sheet 24 BG in ridges hips, valleys
and straight and stepped flashing,
26 12.48 Sqm 1063.94 13277.971
roof plates and sleeve pieces etc,
without wooden battens as
required.
Supply and fix, 13mm thick Soft
board sheet, fixed in ceiling and
27 partitions, with 1st Class Soft 8.34 Sqm 550.31 4589.5854
wood, beveled edge, cover fillet,
50mm x 13mm, screwed on.

Supply and fix, Curtain rail 'C'


28 type with fitting complete best 171.9 metre 99.13 17040.447
quality as specified.

Supply and fix, u-PVC Soil and


waste pipe 110mm (outside dia)
29 253.66 metre 567.45 143939.36
complete with "Z" joint and
rubber ring, all as specified.

Supply and fix, u-PVC Soil and


waste pipe 75mm (outside dia)
30 121.95 metre 389.11 47451.964
complete with "Z" joint and
rubber ring, all as specified.

116
Supply and fix, RCC pipes,
150mm bore, laid and jointed with
31 78.16 metre 443.86 34692.097
spigot socket or collars, as
specified.

Manholes, complete, rectangular


or circular as described, not exc
600mm deep from invert to
32 8.05 Cum 16576.77 133442.99
surface of cover, incl main
channel, set in CM 1:1, 230 mm
thick brick walls

Providing and laying, RCC Type


’B’ manhole cover (precast)
33 complete with angle iron frame, 20 Each 2477.08 49541.6
embedded in concrete, all as per
Information Sheet # Svcs-341

Supply and fix, WC apparatus,


European Pattern, complete
(coupled set), comprising closet
13 lit flushing cistern glazed, in
34 white colour, seat cover, complete 32 Each 6193.76 198200.32
set ( IFO pattern or equivalent,
width not less than 380 mm) fixed
to concrete , brick ,stone or wood
work, best quality, Pak made.
Supply and fix, WHB with
pedestal, glazed ware, size 660
mm x 560 mm in light color, one
hole, complete with waste pipe,
coupling, CP chain & plug and
35 32 Each 4496.62 143891.84
pedestal etc (except mixer) best
quality, (IFO pattern or
equivalent), fixed to concrete,
brick, stone or wood work, Pak
made.

117
S/F, Toilet shower, best quality,
36 32 Each 630.44 20174.08
Pak made, 15 mm dia.

Supply and fix, Mirror, any shape


and pattern, circular, rectangular,
oval etc upto 2700 sqcm, 5 mm
thick, Imported (mirror foreign
37 made, but frame Pak made) with 32 Each 1094.97 35039.04
plastic frame, any color, edges
ground, complete, fixed to
concrete, brick, stone or wood
work.

Supply and fix, 100 mm dia CI


38 floor trap, incl reducer etc, 96 Each 1007.71 96740.16
complete.

Supply and fix, Casted Grating


39 64 Each 725.06 46403.84
CP, 150mm x 150 mm.

Fixing only, Bath set (Plastic)


consisting of shelf, towel rail,
40 towel ring, brush holder, toilet 32 Each 5785.1 185123.2
paper holder, soap dish and
mirror.

Supply and fix, 110mm dia, uPVC


Elbow/bend, 90°, complete with
41 128 Each 520.75 66656
"Z" joint and rubber ring, all as
specified.

Supply and fix, uPVC, Equal Tee,


110mm dia, complete with "Z"
42 48 Each 699.87 33593.76
joint and rubber ring, all as
specified.

Supply and fix, Eccentric Reducer


75mm x 110mm dia, complete
43 48 Each 308.85 14824.8
with solvent cement joint, all as
specified.

118
Supply and fix, uPVC, Vent
44 Cowel 75mm dia, on top of 16 Each 100.62 1609.92
ventilating pipes.

Supply and fix, bars round, using


deformed bars Grade-40 incl
45 15917.14 Kg 80.69 1284354.0
cutting, bending, binding and
placing reinforcement in position.

Supply and fix, bars round, using


deformed bars Grade-60, incl
46 cutting, bending, binding and 7516 Kg 84.5 635102
placing reinforcement in position.

NET AMOUNT 11256868.78

3.5.2 BOQ of 36BOQs:

Sr.no Description of Work Quantity Unit Rate Amount

Excavation over areas as in


Ordinary Soil upto 1.5 M depth, in
foundation / to obtain earth for
1 filling under floors / areas etc, or 470.15 Cum 187.65 88223.647
for shafts, wells exc 30 sqm each,
throw earth clear of edges of
excavation within 10 M.

119
Excavation as in Ordinary Soil
upto 1.5 M depth, in foundation
and pipe trenches upto 1.5 M
wide, in shafts, wells and
independent holes upto 30 sqm
2 each and throw earth clear of 67.08 Cum 205.67 13796.34
edges of excavation within 10m.
Timbering to be paid extra
(Foundation and Trench over 1.5
M widths will be treated as
Areas).

Providing and laying of CC 1:4:8,


3 using Crushed or Broken stone 41.46 Cum 3246.74 134609.84
graded as specified

Providing and laying RCC Type


‘B’ using Crushed or broken stone
in foundation, independent
4 column footings, solid floors etc 117.54 Cum 4466.86 525034.72
incl from work as specified.
Reinforcement measured and paid
separately.

Providing and laying RCC Type


‘B,’ using Crushed or broken
stone in roof slabs, landings,
5 walls, plinth beams and bands etc 182.02 Cum 6311.38 1148797.3
as specified requiring shuttering.
Reinforcement measured and paid
separately.

Providing and laying RCC Type


‘B,’ using Crushed or broken
stone in columns, beams, stairs,
6 posts, struts, piers, lintels, and the 35.41 Cum 6473.66 229232.30
like requiring shuttering, as
specified. Reinforcement
measured and paid separately.

120
Providing & laying of CC Type
‘B’ using Crushed or broken stone
as specified, in walls, sills,
copings, channels, drains, steps,
7 4.06 Cum 5068.85 20579.531
string courses, corbels pier caps,
hinge stone, bed plates etc, incl
formwork & fair faces to exposed
surfaces.

Burnt brick work, in walls 115mm


thick, laid and jointed in CM 1:4,
8 straight or to curve with inner 51.14 Cum 5612.79 287038.08
radius of 6m and over, upto G.F
roof level.

Burnt brick work, in wall over


115mm thick, laid and jointed in
9 CM 1.6, straight or to curve with 327.14 Cum 5026.23 1644280.8
inner radius of 6m and over, upto
G.F roof level.

Burnt brick work, in wall over


115mm thick, laid and jointed in
10 CM 1:6, straight or to curve with 274.8 Cum 5113.42 1405167.8
inner radius of 6m and over, upto
1st floor roof level.

Burnt brick work, in wall 115mm


thick, laid and jointed in CM 1:4,
11 straight or to curve with inner 30.8 Cum 5720.09 176178.77
radius of 6m and over, upto Ist
floor roof level.

Burnt brick work, in wall over


115mm thick, laid and jointed in
12 CM 1:6, straight or to curve with 75.9 Cum 5317.26 403580.03
inner radius of 6m and over, upto
4.25m depth.
50mm thick P.C.C 1:2:4, using
3mm aggregate and finished
smooth with steel float, covered
13 with two coats, each of hot 101.51 Sqm 434.6 44116.246
bitumen 0.75 kg per Sqm and
blinded with 0.012 cum of sand
per Sqm.

121
Burnt brick work, in walls 115mm
thick, laid and jointed in CM 1:4,
14 straight or to curve with inner 47.21 Cum 5828.58 275167.2618
radius of 6m and over, upto 2nd
floor roof level.

13mm thick Cement Plaster 1:4,


15 1604.36 Sqm 140.05 224690.61
finished as specified

13mm thick Cement Plaster 1:6,


16 finished as specified with 3 court 4664.14 Sqm 215.29 1004142.7
of distempering.

13mm thick Cement Plaster 1:4,


17 finished as specified with 2X layer 90.14 Sqm 200.69 18090.196
of building paper

13mm thick Cement Plaster 1:4,


18 finished as specified with 3 court 1164.87 Sqm 225.31 262456.85
of distempering.

Providing and laying CC 1:6:12,


19 laid under floor, using shingle or 43.55 Cum 2222.04 96769.842
gravel.
Providing and laying, CC Type
‘B,’ using shingle or gravel, laid
20 in floor, slabs as under layer for 87.1 Cum 3501.12 304947.55
Terrazzo / Stonolithic / tiles top
finished.
Providing and laying white / light
color/ glazed / non skid tiles exc
400 sq cm, but not exc 900 sq cm
area each, on walls and floors, set
21 117.12 Sqm 1119.03 131060.79
in neat cement and joints grouted
with white /colored cement,
complete, all as specified, Pak
made.
Providing and laying Dark
coloured/ glazed / non skid tiles
exc 400 sq cm, but not exc 900 sq
22 cm area each, on walls and floors, 321.98 Sqm 1177.84 379240.92
set in neat cement and joints
grouted with white /coloured
cement, complete, all as specified,
Pak made.

122
Supply and fix, 1st Class Soft
wood framed and paneled doors,
23 gates etc, incl hanging chowkats, 157.78 Sqm 5459.42 861387.28
hold fats, and iron mongery as
described, 38 mm thick.

Supply & fix, Box type steel


sliding/fixed window or CSW
using 16 gauge frame section
75mm x 30mm and panel section
25mm x 50mm & 10mm x 10mm
24 square gola, with all necessary 122.14 Sqm 2709.52 330940.77
steel fitting / iron mongery hold
fast etc and two coats of S/E paint
in addition to one coat of primer/
rust proof paint, except glass
panes, grill and wire gauze.
Supply & fix, Box Pipe type open-
able and fixed side hung window
or CSW using 16 gauge frame
section 50mm x 25mm and panel
"Z" shape 38mm x 31mm x 38mm
& 10mm x 10mm square gola, not
25 56.89 Sqm 2760.13 157023.79
exc 1.48 Sqm, super, each with all
necessary fitting/iron mongery,
hold fast etc and two coats of S/E
paint in addition to one coat of
primer / rust proof paint, except
wire gauze and glass panes, grill.
Supply and fix, plain galvd steel
sheet 24 BG in ridges hips, valleys
and straight and stepped flashing,
26 12.48 Sqm 1063.94 13277.9712
roof plates and sleeve pieces etc,
without wooden battens as
required.
Supply and fix, 13mm thick Soft
board sheet, fixed in ceiling and
27 partitions, with 1st Class Soft 11.47 Sqm 550.31 6312.0557
wood, beveled edge, cover fillet,
50mm x 13mm, screwed on.

Supply and fix, Curtain rail 'C'


28 type with fitting complete best 193.39 metre 99.13 19170.750
quality as specified.

123
Supply and fix, u-PVC Soil and
waste pipe 110mm (outside dia)
29 268.6 metre 567.45 152417.07
complete with "Z" joint and
rubber ring, all as specified.

Supply and fix, u-PVC Soil and


waste pipe 75mm (outside dia)
30 153.05 metre 389.11 59553.285
complete with "Z" joint and
rubber ring, all as specified.

Supply and fix, RCC pipes,


150mm bore, laid and jointed with
31 114.63 metre 443.86 50879.671
spigot socket or collars, as
specified.

Manholes, complete, rectangular


or circular as described, not exc
600mm deep from invert to
32 8.05 Cum 16576.77 133442.99
surface of cover, incl main
channel, set in CM 1:1, 230 mm
thick brick walls

Providing and laying, RCC Type


’B’ manhole cover (precast)
33 complete with angle iron frame, 20 Each 2477.08 49541.6
embedded in concrete, all as per
Information Sheet # Svcs-341

Supply and fix, WC apparatus,


European Pattern, complete
(coupled set), comprising closet
13 lit flushing cistern glazed, in
34 white color, seat cover, complete 36 Each 6193.76 222975.36
set ( IFO pattern or equivalent,
width not less than 380 mm) fixed
to concrete , brick ,stone or wood
work, best quality, Pak made.

124
Supply and fix, WHB with
pedestal, glazed ware, size 660
mm x 560 mm in light color, one
hole, complete with waste pipe,
coupling, CP chain & plug and
35 36 Each 4496.62 161878.32
pedestal etc (except mixer) best
quality, (IFO pattern or
equivalent), fixed to concrete,
brick, stone or wood work, Pak
made.

S/F, Toilet shower, best quality,


36 36 Each 630.44 22695.84
Pak made, 15 mm dia.

Supply and fix, Mirror, any shape


and pattern, circular, rectangular,
oval etc upto 2700 sqcm, 5 mm
thick, Imported (mirror foreign
37 made, but frame Pak made) with 36 Each 1094.97 39418.92
plastic frame, any color, edges
ground, complete, fixed to
concrete, brick, stone or wood
work.

Supply and fix, 100 mm dia CI


38 floor trap, incl reducer etc, 108 Each 1007.71 108832.68
complete.

Supply and fix, Casted Grating


39 72 Each 725.06 52204.32
CP, 150mm x 150 mm.

Fixing only, Bath set (Plastic)


consisting of shelf, towel rail,
40 towel ring, brush holder, toilet 36 Each 5785.1 208263.6
paper holder, soap dish and
mirror.

Supply and fix, 110mm dia, uPVC


Elbow/bend, 90°, complete with
41 180 Each 520.75 93735
"Z" joint and rubber ring, all as
specified.

125
Supply and fix, uPVC, Equal Tee,
110mm dia, complete with "Z"
42 104 Each 699.87 72786.48
joint and rubber ring, all as
specified.

Supply and fix, Eccentric Reducer


75mm x 110mm dia, complete
43 104 Each 308.85 32120.4
with solvent cement joint, all as
specified.

Supply and fix, uPVC, Vent


44 Cowel 75mm dia, on top of 36 Each 100.62 3622.32
ventilating pipes.

Supply and fix, bars round, using


deformed bars Grade-40 incl
45 15698.32 Kg 80.69 1266697.4
cutting, bending, binding and
placing reinforcement in position.
Supply and fix, bars round, using
deformed bars Grade-60, incl
46 cutting, bending, binding and 8504.23 Kg 84.5 718607.43
placing reinforcement in position.
13654987.73
NET AMOUNT

126
Annex B

SAMPLE OF QUESTIONNAIRE
General Information
1. GENERAL INFORMATION ABOUT PERSON FILLING THIS FIRM
a. Name:
b. Qualifications:
c. Designation
d. Working Experience in Construction Industry
e. Name of the Employer
f. Address
g. Cell No

2.GENERAL INFORMATION ABOUT PROJECT


a. Project Title:
b.Project Type: Residential Educational Commercial Industrial
Institutional

c. Project Duration:

Contractual Actual
Start Date Completion Completion Contract Actual Actual Delay
Date Date Duration Duration

Years Months Years Months Years Months

d. Project Cost (millions):

127
Factors Causing Delays in Construction Projects
1.Feasibility Study of the Project
Serial Factors Strongly Disagree Neither Agree Strongly Agree
Disagree Agree nor
Disagree
A Inadequate Feasibility Study of the project

1.By the Client 1 2 3 4 5


2.By the Consultant 1 2 3 4 5

3.By the Contractor 1 2 3 4 5


B Ambitious 1 2 3 4 5
Completion Period
of the Project
C Vague Conception 1 2 3 4 5
of Demand of
Construction
Material
D Poor Planning and 1 2 3 4 5
Scheduling by the
Contractor

2. SCOPE / PLANNING RELATED


Serial Factors Strongly Disagree Neither Agree Stron
Disagree Agree gly
Nor Agree
Disagree
a. Re-Designing 1 2 3 4 5
b. Variation Order 1 2 3 4 5
c. Additional Work 1 2 3 4 5

d. Inadequate Feasibility Study of the Project

(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor
e. Ambitious Completion 1 2 3 4 5
Period of the Project

128
f. Vague Conception of 1 2 3 4 5
Demand of
Construction Material
g. Poor Planning and 1 2 3 4 5
Scheduling by the
Contractor

3. DESIGN / DRAWING RELATED


Serial Factors Strongly Disagree Neither Agree Stron
Disagree Agree Nor gly
Disagree Agree
a. Availability of 1 2 3 4 5
Drawings
b. Drawing / Design 1 2 3 4 5
Variation
c. Misinterpretation of 1 2 3 4 5
Drawings resulting in
Suspension of work
d. Frequent issue of 1 2 3 4 5
supplementary
drawings

4. ESTIMATION RELATED
Serial Factors Strongly Disagree Neither Agree Stron
Disagree Agree Nor gly
Disagree Agree
a. In-accurate cost 1 2 3 4 5
estimates
b. Absence of 1 2 3 4 5
construction cost data

129
5. CONTRACT RELATED
Serial Factors Strongly Disagree Neither Agree Strongl
Disagree Agree Nor y
Disagree Agree
a. Incomplete contract 1 2 3 4 5
documentation
b. Work suspension 1 2 3 4 5
owning to conflicts
c. Litigations 1 2 3 4 5
d. Low Bid procurement 1 2 3 4 5
method resulting in
un-realistic rates
e. Bureaucracy in 1 2 3 4 5
Bidding/Tendering
method
f. Disputes at site 1 2 3 4 5
g. In-adequate duration 1 2 3 4 5
of contract period
h. Poor contract 1 2 3 4 5
management
i. Re-tendering 1 2 3 4 5

6. SITE RELATED
Serial Factors Strongly Disagree Neither Agree Strongly
Disagree Agree Nor Agree
Disagree
a. Problem in Land 1 2 3 4 5
Acquisition
b. Site Variations 1 2 3 4 5
c. In-adequate site 1 2 3 4 5
investigation
d. Encroachment of 1 2 3 4 5
Land during Project
Implementation

130
7. WORK FORCE RELATED

Serial Factors Strongly Disagree Neither Agree Strongly


Disagree Agree Agree
Nor
Disagree

a. Poor workmanship 1 2 3 4 5

b. Non-availability of 1 2 3 4 5
skilled
persons/craftsmen
c. In-adequate 1 2 3 4 5
contractor’s experience
d. Labor Disputes / 1 2 3 4 5
Strikes / security issues
e. Shortage of Labor / 1 2 3 4 5
Skilled persons
g. Absence of Qualified Supervisory staff

(1) By the 1 2 3 4 5
Client/consultant

(2) By the 1 2 3 4 5
Contractor

8. CONSTRUCTION MATERIAL/EQUIPMENT RELATED

Serial Factors Strongly Disagree Neither Agree Strongly


Disagree Agree Agree
Nor
Disagree

a. Non availability / 1 2 3 4 5
shortage of local
materials
b. Non availability of 1 2 3 4 5
specialized equipment

131
on site at appropriate
time
c. Material Management 1 2 3 4 5
Problem
d. Equipment 1 2 3 4 5
Management Problem
e. Delay in 1 2 3 4 5
Transportation/Delivery
of Construction
Material

9. CONSTRUCTION MANAGEMENT RELATED


Serial Factors Strongly Disagree Neither Agree Strongly
Disagree Agree Agree
Nor
Disagree
a. Poor Planning and 1 2 3 4 5
Scheduling by the
Contractor
b. Poor Site Management 1 2 3 4 5
c. Poor Financial control 1 2 3 4 5
on site by the
Contractor
d. Lack of Co- 1 2 3 4 5
ordination between
Design team and
Contractor
e. Slow Decision Making

(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor
f. Inadequate Site Inspection

132
(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor
g. Inadequate Project monitoring system through reports and returns

(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor

10. FINANCE RELATED


Serial Factors Strongly Disagree Neither Agree Strongly
Disagree Agree Agree
Nor
Disagree

a. Delay in payment by 1 2 3 4 5
the Client
b. Delay in processing/ 1 2 3 4 5
Request for payment
by the Contractor
c. Poor disbursement 1 2 3 4 5
procedure by the
Client
d. Inadequate Client 1 2 3 4 5
financing
e. Mal-practices resulting 1 2 3 4 5
in pilferage and
wastage of funds
g. Poor accounting procedure

(1) By the 1 2 3 4 5
Client/consultant
(2) By the 1 2 3 4 5
Contractor

133
11. COST RELATED
Serial Factors Strongly Disagree Neither Agree Strongly
Disagree Agree Nor Agree
Disagree

a. Cost escalation / 1 2 3 4 5
inflation

b. Higher 1 2 3 4 5
Transportation Cost

c. Higher cost of Skilled 1 2 3 4 5


Labor
d. Higher Machinery 1 2 3 4 5
hiring/Maintenance
Cost
e. Fluctuating Prices of 1 2 3 4 5
Raw Material / fitting
fixtures

12. QUALITY RELATED


Serial Factors Strongly Disagree Neither Agree Strongly
Disagree Agree Nor Agree
Disagree
a. In-adequate quality 1 2 3 4 5
resulting in work
suspension/redoing
b. Use of substandard 1 2 3 4 5
material/fitting
fixture not meeting
the desired
specification

134
13. WEATHER RELATED
Serial Factors Strongly Disagree Neither Agree Stron
Disagree Agree Nor gly
Disagree Agree

a. Adverse effects of 1 2 3 4 5
weather resulting in
delay
b. Earthquakes 1 2 3 4 5

c. Unforeseen ground 1 2 3 4 5
conditions
d. Accident on site 1 2 3 4 5

14. GOVERNAMENT RELATED


Serial Factors Strongly Disagree Neither Agree Stron
Disagree Agree Nor gly
Disagree Agree

a. In appropriate 1 2 3 4 5
government policies/
procedures
b. Non-conducive Law 1 2 3 4 5
and Order / Security
Situation
c. Lack of Co-ordination 1 2 3 4 5
between different
Agencies

135

You might also like