Professional Documents
Culture Documents
FACULTY OF ENGINEERING
PRODUCTION ENGINEERING DEPARTMENT
4TH YEAR
B.SC. PROJECT (2016-2017)
PIPELINE CONSTRUCTION
(CLASSIFICATION, WELDING, CONSTRUCTING, INSPECTION)
SUPERVISED BY:
PREPARED BY:
We would like to express our gratitude for everyone who helped us during the
graduation project (Pipeline construction) starting with endless thanks for our supervisor
Dr. Ismail A. Abdallah who didn’t keep any effort in encouraging us to do a great job,
providing our group with valuable information and advices to be better each time. Thanks for
the continuous support and kind communication which had a great effect regarding to feel
interesting about what we are working on.
Also, we would like to say many thanks for the Petroleum Marine Services Co.
(PMS) specially Eng. Ahmed Hafez and Eng. Mohamed El-Shabrawy, as the provided the
project team with the Industrial training and providing us with all what we need regarding
information.
Thanks extended to the Egyptian Academy (EGAC) for being our knowledge
lighthouse, the endless support and their huge effort in contacting.
i
ABSTRACT
ii
Table of Contents
Acknowledgement ...................................................................................................................... i
Abstract ......................................................................................................................................ii
Table of Contents ..................................................................................................................... iii
List of terms ............................................................................................................................... v
List of figures ............................................................................................................................ vi
List of tables .............................................................................................................................. ix
CHAPTER 1 Introduction ...................................................................................................... 1
1.1 DEFINITION AND SCOPE ....................................................................................... 1
1.2 BRIEF HISTORY OF PIPELINES ............................................................................. 1
1.3 EXISTING MAJOR PIPELINES ................................................................................ 2
1.4 IMPORTANCE OF PIPELINES ................................................................................. 3
1.5 FREIGHT (SOLIDS) TRANSPORT BY PIPELINES ................................................ 3
1.6 TYPES OF PIPELINES............................................................................................... 5
1.7 COMPONENTS OF PIPELINES................................................................................ 5
1.8 ADVANTAGES OF PIPELINES ................................................................................ 5
CHAPTER 2 pipeline ............................................................................................................. 9
2.1 Pipeline types .............................................................................................................. 9
2.1.1 On-shore pipelines ............................................................................................. 10
2.1.2 Off-shore pipelines............................................................................................. 18
2.2 Pipeline components ................................................................................................. 24
2.2.1 Pipes ................................................................................................................... 24
2.2.2 Pipes connections ............................................................................................... 32
2.2.3 Valves ................................................................................................................ 41
2.2.4 Pumps................................................................................................................. 51
2.3 Welding of Pipeline ................................................................................................... 58
2.3.1 Preparation for welding...................................................................................... 58
2.3.2 Welding Processes ............................................................................................. 61
2.4 Inspection of pipeline ................................................................................................ 65
2.4.1 Welding inspection ............................................................................................ 65
2.4.2 Pressure Test of Piping System.......................................................................... 68
2.4.3 Welding acceptance criteria ............................................................................... 69
CHAPTER 3 Case study ...................................................................................................... 70
3.1 Introduction ............................................................................................................... 70
iii
3.2 Project scope ............................................................................................................. 70
3.3 Pipeline Data ............................................................................................................. 71
3.4 Pipeline components ................................................................................................. 71
3.5 Route selection and soil preparation ......................................................................... 73
3.6 Pipeline construction process .................................................................................... 73
3.6.1 Assembly............................................................................................................ 73
3.6.2 Laying of the pipeline ........................................................................................ 75
3.6.3 Pipeline hydrostatic testing ................................................................................ 75
3.7 Selected Pipeline WPS .............................................................................................. 76
3.7.1 Applying the selected WPS to a sample of the pipeline .................................... 77
3.8 Procedure Qualification Record (PQR)..................................................................... 78
3.8.1 NDT stage .......................................................................................................... 78
3.8.2 Destructive testing ............................................................................................. 80
3.9 Pipeline sample ......................................................................................................... 83
References ................................................................................................................................ 85
iv
LIST OF TERMS
AC Alternative current
DC Direct current
KP Kilometric point
WD Water depth
OD Outer diameter
WT Wall thickness
v
LIST OF FIGURES
Figure 1-1 The Big Inch pipeline under construction in 1942 ................................................. 2
Figure 1-2 A pump house of the 273-mi-long Black Mesa Coal Slurry ................................. 4
Figure 1-3 the cargo loading station of a pneumatic capsule..................................................... 4
Figure 1-4 Comparison of petroleum transportation cost by pipeline with those by other
modes. ........................................................................................................................................ 7
Figure 2-1 Onshore pipelines ................................................................................................... 10
Figure 2-2 Construction of Land Pipeline ............................................................................... 11
Figure 2-3 pipe stringing .......................................................................................................... 14
Figure 2-4 Pipe Bending .......................................................................................................... 14
Figure 2-5 pipe welding ........................................................................................................... 14
Figure 2-6 Ditching assembled pipeline .................................................................................. 15
Figure 2-7 pipes backfilling ..................................................................................................... 16
Figure 2-8 Illustration of Tunnel Boring Machine cutter head showing drilling fluid
recirculation ............................................................................................................................. 16
Figure 2-9 types of seabed ....................................................................................................... 18
Figure 2-10 Pipes supply ship .................................................................................................. 20
Figure 2-11 pipes platform....................................................................................................... 20
Figure 2-12 (a) J-lay system, (b) S-lay system ........................................................................ 21
Figure 2-13 pipes aligned......................................................................................................... 21
Figure 2-14 pipes welding ....................................................................................................... 22
Figure 2-15 NDT by Automatic Ultrasonic ............................................................................. 22
Figure 2-16 Coating of Welded Area....................................................................................... 22
Figure 2-17 S-lay System......................................................................................................... 23
Figure 2-18 J-lay System ......................................................................................................... 23
Figure 2-19 Pipes classification ............................................................................................... 24
Figure 2-20 Metallic pipes ....................................................................................................... 25
Figure 2-21 Seamed pipes ........................................................................................................ 25
Figure 2-22 Seamless pipes ..................................................................................................... 25
Figure 2-23 Nonmetallic pipes................................................................................................. 27
Figure 2-24 Connections classification according to type ....................................................... 32
Figure 2-25 Flange assembly ................................................................................................... 33
Figure 2-26 Threaded flange .................................................................................................... 34
Figure 2-27 Blind flange .......................................................................................................... 34
Figure 2-28 Slip-on flange ....................................................................................................... 34
Figure 2-29 Socket-welded flange ........................................................................................... 34
Figure 2-30 Lapped flange ....................................................................................................... 34
Figure 2-31 Welding-neck flange ............................................................................................ 35
Figure 2-32 Flat-faced flange................................................................................................... 35
Figure 2-33 Raised-face flange ................................................................................................ 35
Figure 2-34 Ring-joint flange .................................................................................................. 35
Figure 2-35 Spiral-wound gasket ............................................................................................. 36
Figure 2-36 Metal ring-joint gasket ......................................................................................... 36
vi
Figure 2-37 sheet gasket .......................................................................................................... 36
Figure 2-38 Elbow ................................................................................................................... 37
Figure 2-39 Tee-joint ............................................................................................................... 37
Figure 2-40 Reducers ............................................................................................................... 38
Figure 2-41 lap joint................................................................................................................. 38
Figure 2-42 A-lateral joint ....................................................................................................... 38
Figure 2-43 Half-coupling ....................................................................................................... 38
Figure 2-44 (a) Pipe plug, (b) Pipe cap .................................................................................... 38
Figure 2-45 Gate valve............................................................................................................. 44
Figure 2-46 Full-Bore Ball Valve ............................................................................................ 44
Figure 2-47 Multi-Segment Plug Valve ................................................................................... 45
Figure 2-48 GLOBE VALVE .................................................................................................. 45
Figure 2-49 Straight Through Diaphragm Valve .................................................................... 46
Figure 2-50 figure 19 Typical Butterfly Valve ....................................................................... 46
Figure 2-51 Figure 20 Needle Valve ....................................................................................... 47
Figure 2-52 Swing Check Valve ............................................................................................. 47
Figure 2-53 Operation of Tilting Disk Check Valve .............................................................. 48
Figure 2-54 Lift Check Valve ................................................................................................. 48
Figure 2-55 Sample of valve main dimensions........................................................................ 50
Figure 2-56 Pumps station ....................................................................................................... 51
Figure 2-57 pumps classification according to type ................................................................ 52
Figure 2-58 Centrifugal Pump ................................................................................................. 52
Figure 2-59 Vertical turbine pump .......................................................................................... 53
Figure 2-60 Multistage centrifugal pump ................................................................................ 53
Figure 2-61 Self-Priming Pump ............................................................................................... 54
Figure 2-62 Piston pump.......................................................................................................... 54
Figure 2-63 Diaphragm Pump ................................................................................................. 55
Figure 2-64 Screw pump .......................................................................................................... 55
Figure 2-65 Gear pump ............................................................................................................ 56
Figure 2-66 Pipeline welding ................................................................................................... 58
Figure 2-67 Pipe cutting and beveling motorized .................................................................... 58
Figure 2-68 Angle iron serving as jig for small diameter pipe ................................................ 59
Figure 2-69 Bevel pipe end preparation................................................................................... 60
Figure 2-70 align pipe ends...................................................................................................... 60
Figure 2-71 tacking locations for pipe ends ............................................................................. 60
Figure 2-72 grind the end of the tack ....................................................................................... 60
Figure 2-73 Welding Types ..................................................................................................... 61
Figure 2-74 Pipes welding positions ........................................................................................ 62
Figure 2-75 Automatic pipe welding ....................................................................................... 63
Figure 2-76 Deposition of root, filler and finished weld beads ............................................... 64
Figure 2-77 Automatic ultrasonic test...................................................................................... 67
Figure 3-1 Pulling head ............................................................................................................ 72
Figure 3-2 S-lay method .......................................................................................................... 75
Figure 3-3 Selected WPS ......................................................................................................... 76
Figure 3-4 V-butt pipe preparation .......................................................................................... 77
Figure 3-5 Tack welded sample pipe ....................................................................................... 77
vii
Figure 3-6 Sample pipe welding process ................................................................................. 78
Figure 3-7 Visual inspection report ......................................................................................... 78
Figure 3-8 Radiographic Films of the welded pipe ................................................................. 79
Figure 3-9 position of each specimens for each test ................................................................ 80
Figure 3-10 Tensile specimens after the test............................................................................ 81
Figure 3-11 Root bend specimens after the test ....................................................................... 81
Figure 3-12 distractive test report ............................................................................................ 82
Figure 3-13 prototype simulating the pipeline ......................... Error! Bookmark not defined.
viii
LIST OF TABLES
ix
CHAPTER 1 INTRODUCTION
The term pipe is defined herein as a closed conduit, usually of circular cross section.
It can be made of any appropriate material such as steel or plastic. The term pipeline refers to
a long line of connected segments of pipe, with pumps, valves, control devices, and other
equipment/facilities needed for operating the system. It is intended for transporting a fluid
(liquid or gas), mixture of fluids, solids, fluid- solid mixture, or capsules (freight-laden
vessels or vehicles moved by fluids through a pipe). The term pipeline also implies a
relatively large pipe spanning a long distance. This book treats all important aspects, parts,
and types of pipelines.
The use of pipelines has a long history. For instance, more than 1,000 years ago, the
Romans used lead pipes in their aqueduct system to supply water to Rome. As early as 400
B.C., the Chinese used bamboo pipes wrapped with waxed cloth to transport natural gas to
their capital Beijing for lighting. Clay pipes were used as early as 4000 B.C. for drainage
purposes in Egypt and certain other countries.
An important improvement of pipeline technology occurred in the 18th century when
cast-iron pipes were manufactured for use as water lines, sewers, and gas pipelines. A
subsequent major event was the introduction of steel pipe in the 19th century, which greatly
increased the strength of pipes of all sizes. In 1879, following the discovery of oil in
Pennsylvania, the first long-distance oil pipeline was built in this state. It was a 6-inch-
diameter, 109-mi-long steel pipeline. Nine years later, an 87-mi-long, 8-inch-diameter
pipeline was built to transport natural gas from Kane, Pennsylvania to Buffalo, New York.
The development of high-strength steel pipes made it possible to transport fluids such as
natural gas, crude oil, and petroleum products over long distances. Initially, all steel pipes had
to be threaded together, which was difficult to do for large pipes, and they often leaked under
high pressure. The development of electric arc welding to join pipes in the late 1920s made it
possible to construct leak proof, high-pressure, large-diameter pipelines. Today, virtually all
high-pressure piping consists of steel pipe with welded joints. Large seamless steel pipe was
another major milestone achieved in the 1920s.
Major innovations in pipeline technology made since 1950 include:
I. Introduction of new pipeline materials such as ductile iron and large- diameter
concrete pressure pipes for water, and PVC (polyvinyl chloride) pipe for sewers
II. Use of pigs to clean the interior of pipelines and to perform other functions
III. Batching of different petroleum products in a common pipeline
IV. Application of cathodic protection to reduce corrosion and extend pipeline life
1
V. Use of large side booms to lay pipes, machines to drill or bore under rivers and
roads for crossing, machines to bend large pipes in the field, x- rays to detect
welding flaws, and so forth.
Since 1970, major strides have been made in new pipeline technologies including
trenchless construction (e.g., directional drillings, which allow pipelines to be laid easily
under rivers, lakes, and other obstacles, without having to dig long trenches), pipeline
integrity monitoring (e.g., sending intelligent pigs through pipes to detect pipe wall corrosion,
cracks, and other pipe flaws), computers to control and operate pipelines, microwave stations
and satellites to communicate between headquarters and remote stations, and new pipeline
technologies to transport solids over long distances (e.g., slurry pipelines for transporting coal
and other minerals, and capsule pipelines for bulk materials transport).
Most of the major oil and gas pipelines that exist today around the world were
constructed either during or after World War II. In most cases, they were built to meet
compelling national or international needs. For instance, the U.S. built the Big Inch and the
Little Big Inch pipelines during World War II to counter the threat of German submarine
attacks on coastal tankers.
The Big Inch was a 24-inch (61-cm) line designed to transport 300,000 bpd (barrels
per day) of crude oil, and the Little Big Inch was a 20-inch (51-cm) product pipeline designed
to deliver 235,000 bpd. Both lines extend from Texas to the East Coast. They were built
between 1942 and 1943 (during World War II) by the U.S. government, but were sold after
the war (in 1947) to the Texas Eastern Transmission Corporation (TETCO), and converted to
transport natural gas. Later, TETCO expanded both lines, and converted the Little Big Inch
back to a petroleum product line operated by a different company—the Texas Eastern
Products Pipeline Company (TEPPCO). Now it carries about 20 types of gasoline and 4 types
of fuel oil, in addition to kerosene, jet fuel, butane, propane, and alkylate. At present (2003),
both TETCO and TEPPCO are under Duke Energy, which has published an interesting
booklet on the history of the Big Inch and Little Big Inch pipelines. Figure 1-1 is a historic
photograph of the Big Inch during construction.
2
1.4 IMPORTANCE OF PIPELINES
Pipelines are the least understood and least appreciated mode of transport. Pipelines
are poorly understood by the general public because they are most often underground and
invisible—out of sight, out of mind! Despite the low degree of recognition by the public,
pipelines are vitally important to the economic well- being and security of most nations. All
modern nations rely almost exclusively on pipelines to transport the following commodities:
I. Water from treatment plants to individual homes and other buildings
II. Sewage from homes to treatment plants
III. Natural gas all the way from wells to the consumers who may be located more than
a thousand miles away—be it a home, a factory, a school, or a power plant
IV. Crude oil from oil fields to refineries
V. Refined petroleum products (gasoline, diesel, jet fuel, heating oil, etc.) from
refineries to various cities over hundreds of miles
In addition, hundreds of other liquid, gas, and solid commodities (freight) are
transported via pipeline over long and short distances. In the U.S., pipelines of various types
transport a total of about 2.5 trillion ton- miles of cargo in liquid, gas, and solid form, more
than the total quantity of freight transported by trucks and trains combined. As discussed in
Section 1.3, major pipelines in the U.S., including the Big Inch, the Little Big Inch, the
Colonial, and the Trans-Alaskan pipelines, were all built to solve problems caused by
national crises. The U.S. has a dense network of underground pipelines in every state and
under every city, mirroring the network of roads, highways, and streets above ground. Maps
of such pipelines can be obtained from various state, federal, and local agencies. It can be
said that pipelines are the lifelines of modern nations.
During the past century, pipelines have been used extensively to transport solids of
various kinds, including coal and other minerals, gravels and sand, grain, cement, mail and
parcels, etc. They are transported over short as well as long distances. Pipelines that transport
solids are usually referred to as freight pipelines. The three general types of freight pipelines
are slurry pipeline, pneumatic pipeline (also called pneumo conveying), and capsule pipeline.
The slurry pipeline is used to transport fine particles of solids mixed with a liquid,
usually water, to form a paste (slurry) that can be pumped through the pipeline. It is used
commonly in mining for transporting both minerals and mine wastes (tailings). An example is
the Black Mesa Coal Slurry Pipeline, which transports 5 million tons of coal each year from
Arizona to Nevada, over a distance of 273 mi (438 km), using 18-inch-diameter steel pipe.
The slurry in this pipeline is a mixture of fine coal particles (of less than 1 mm size) and
water, at the ratio of approximately 1 to 1 by weight. Figure 1-2 is a photograph of a pump
station of the Black Mesa Pipeline.
3
Figure 1-2 A pump house of the 273-mi-long Black Mesa
Coal Slurry
4
1.6 TYPES OF PIPELINES
For the transport of large quantities of fluid (liquid or gas), a pipeline is undisputedly
the most favored mode of transportation. Even for solids, there are many instances that favor
the pipeline over other modes of transportation. The advantages of pipelines are:
I. Economical in many circumstances. Factors that favor pipelines include large
throughput, rugged terrain and hostile environment (such as transportation through
swamps). Under ordinary conditions, pipelines can transport fluids (liquids or gases)
at a fraction of the cost of transportation by truck or train (see Figure 1-4). Solid
transport by pipeline is far more complex and costly than fluid transport. Still, in
many cases, pipelines are used to transport solids because the cost is lower than for
other modes of transportation, such as trucks.
5
II. Low energy consumption. The energy intensiveness of large pipelines is much lower
than that of trucks, and is even lower than that of rail. The energy intensiveness is
defined as the energy consumed in transporting unit weight of cargo over unit
distance, in units such as Btu per ton- mile. Table 1-2 compares the energy
intensiveness of pipelines to those for other modes of transport.
III. Friendly to environment. This is due mainly to the fact that most pipelines are
underground. They do not pose most of the environmental problems associated with
trucks and trains, such as air pollution, noise, traffic jams on highways and at rail
crossings, and killing animals that strayed on highways and railroads. Oil pipelines
may pollute land and rivers when a leak or rupture develops. However, far more spills
would occur if trucks and trains transported the same oil.
Table 1-1 Taxonomy of Pipelines
6
Figure 1-4 Comparison of petroleum transportation cost by
pipeline with those by other modes.
IV. Safe for humans. This is especially true for liquid pipelines and liquid- solid
pipelines. The safety of natural gas pipelines is always of strong concern. Gas
pipelines under high pressure can explode; however, if trucks and trains transported
the same natural gas, it would be much more dangerous to the public. So, in general, it
can be said that pipelines are much safer than all other land-based modes of freight
transport. For instance, based on statistics published by the U.S. Department of
Transportation, during the 12-year period between 1988 and 1999, the average
number of people killed (injured) by pipelines per year was 23 (107), which includes
21(92) for natural gas pipelines, and 2(15) for hazardous liquid pipelines. In contrast,
the number of people killed (injured) by large trucks per year during the same period
was 5,162 (133, 167). This shows that there were 200 times more people killed and
1000 times more people injured by trucks than by pipelines. It can be concluded that
pipelines are enormously safer than trucks and trains.
7
V. Unaffected by weather. Weather does not affect pipelines because most of them are
buried underground below the frost line.
VI. High degree of automation. This makes pipelines the least labor-intensive of all
transportation modes. Note that labor-intensive societies generally have low living
standards. The high living standard in the U.S. would not be possible without
automation.
VII. High reliability. Because pipeline operation is continuous, automatic, and unaffected
by weather, pipelines are highly reliable. Furthermore, they are least affected by labor
strikes, holidays, delivery schedules, etc. The system operates continuously around
the clock without stop.
VIII. Less sensitive to inflation. Due to high capital cost and low operational cost, pipeline
tariffs are less sensitive to inflation than tariffs for trucks and trains. However, high
capital cost is great when the interest rate is high.
IX. Convenience. Water and gas pipelines transport commodities directly to homes, a
great convenience to the public. Oil pipelines bring crude oil to refineries and bring
refined petroleum products, such as gasoline and diesel fuel, to the market without the
products leaving the pipelines. Even when one puts gasoline in a car at a filling
station, the gasoline moves through a short pipe (hose) fitted with a nozzle.
X. Less susceptible to theft. Because pipelines are mostly underground and enclosed,
the commodities transported by pipelines are less susceptible to theft than those
transported by truck and train.
XI. Efficient land use. Underground pipelines allow surface land to be used for other
purposes. This results in more efficient land use.
XII. High degree of security. Because pipelines are underground and fixed to the ground,
terrorists cannot hijack a pipeline, as they can trucks and aircraft, and use it as a lethal
weapon to destroy a major building or other important target. Also, it is far more
difficult for terrorists to attack an underground pipeline and inflict catastrophic
damage to it than to an aboveground structure such as a bridge or a power plant.
Moreover, underground pipelines are inaccessible to people except at the inlet and
outlet. Thus, they can be more easily guarded against attack or sabotage. Even though
any unguarded long pipeline right-of-way may be vulnerable to sabotage, the damage
that can be achieved is rather limited. Pipeline companies have the ability to repair a
damaged underground pipe and return it to service within hours. Such sabotage
activities can also be detected easily by spy satellites and other means of remote
sensing. For these reasons, pipelines must be low on the priority lists of targets of
terrorists. This is not to say that security should not be of concern to pipeline
companies. Two types of pipelines that require the greatest protection in terms of
security are pipelines that supply drinking water, and natural gas pipelines that pass
through densely populated areas.
8
CHAPTER 2 PIPELINE
Classification Acording to
Purpos
On-shore Off-shore
9
2.1.1 On-shore pipelines
10
2.1.1.1 Construction of Land Pipeline
11
2.1.1.3 PRE-CONSTRUCTION ACTIVITIES
2.1.1.3.1.1 Landowners
Prior to construction a Landowner Liaison Officer (LLO) will liaise with landowners
and occupiers and, where possible, agree certain items such as temporary fencing, security,
temporary relocation of water supplies and access requirements.
2.1.1.3.1.3 Public
In parallel with direct landowner liaison, regular community updates will be published
to provide relevant information to the local community and stakeholders prior to and during
the construction phase of the project.
Conventional ‘open-cut’ technique (‘spread technique’) will be used for the pipeline
which is on land, will be in grasslands, will be constructed through peatlands using the stone
road construction method.
12
2.1.1.4.1 Mobilization
Mobilization will include the putting in place of staff, temporary facilities, plant and
equipment, materials and systems for construction. Training in health, safety and
environmental issues will be provided for staff during the mobilization period.
The pipeline centerline and the temporary working area boundaries will be marked
out using wooden pegs. This process is known as ‘setting out’ and will be carried out in
accordance with co-ordinates detailed on project drawings and agreed in advance with
landowners/occupiers and the relevant authorities.
2.1.1.4.3 Fencing
Following the setting out process the temporary working area will be fenced off.
Linked palisade fence sections will form a continuous, 3m high fenced boundary to the
temporary working area.
Once the pipeline wayleave has been prepared (in grasslands or in peatland areas),
pipe laying activities (and installation of associated services) can begin.
The term ‘pipe stringing’ refers to the delivery and laying out of individual pipe
lengths (each approximately 12m long) along the pipeline route. Lengths of pipe will be
transported along the temporary working area or by public road from a local storage point
(the Terminal) or directly from its storage location in accordance with the Traffic
Management Plan (TMP). The water outfall pipeline, umbilical and services will be strung
out and laid in the same trench as the gas pipeline. Figure 2-3
13
Figure 2-3 pipe stringing
2.1.1.4.4.2 Pipe Bending
Pipe lengths will be bent on site where changes in elevation or direction occur along
the pipeline route. Special hydraulic bending machines will be used for this purpose. Pre-
formed or forged bends may also be used. Figure 2-4
14
2.1.1.4.4.4 Weld Testing and Coating
Weld quality is essential to pipeline integrity and the quality of all welds will be
checked using nondestructive inspection techniques. Strict acceptance criteria will be applied
in accordance with relevant standards. Any unacceptable defect detected will either be
repaired or the joint cut out and re-welded. The repair weld is subject to the same testing and
inspection requirements as the original weld. Additional tests may be required. Following
welding, coatings will be applied to the field joints and other areas where metal is exposed.
These coatings are electrical/thermal insulators and are resistant to the action of corrosion or
soil bacteria. The coating quality will be checked against strict acceptance criteria based on
governing codes (API, DNV,…etc).
2.1.1.4.4.5 Trenching
The trench in which the pipeline will be installed will be excavated using mechanical
excavators or a specialized trenching machine. The depth of the trench may vary but will
allow a minimum reinstated cover of 1.2m over the top of the pipeline on land, with 1.6m
provided below the clean bed of any watercourse (i.e. rivers, streams and ditches) and 1.6m
below the lowest point at road crossings (i.e. roadside drains).
2.1.1.4.4.6 Ditching
Before a length of the welded pipeline is lowered into the trench the complete section
will be inspected for adequacy of pipe coating. This will be carried out using a piece of
equipment called a holiday detector, which detects flaws in the external coating using an
electric / magnetic discharge. Any flaws identified will be rectified and re-tested.
15
2.1.1.4.4.7 Backfilling
The gas pipeline will typically be given a 150mm bedding and surround to protect its
coating and the trench will then be backfilled in suitable layers will be compacted at regular
intervals. This method prevents excessive settlement of the backfill at a later date.
Figure 2-8 Illustration of Tunnel Boring Machine cutter head showing drilling fluid
recirculation
16
2.1.1.5.1.1 Tunnel Arisings
Excavated cuttings will be crushed within the TBM and mixed with the drilling fluid
(bentonite slurry). The drilling fluid containing this material is pumped back to the bentonite
handling plant located at the tunneling compound via dedicated hoses through the advancing
tunnel bore.
As set out above, it is proposed to use bentonite mixed with water as a drilling fluid
during the tunneling process. However, it should be noted that suitable alternative drilling
fluids, such as water mixed with polymer additives, may also be used.
The tunneling methodology selected, including the size and power of the tunnel
boring machine (TBM), in combination with segment lining is not expected to require any
form of surface intervention. The need for surface intervention would only arise in
exceptional circumstances. The potential environmental impacts associated with the
construction of an intervention pit have been assessed for completeness only.
The main equipment and facilities required for a typical tunneling compound are
described below.
I. Tunnel Starting Pit & Ramp
II. Gantry Crane
III. Storage Area for Concrete Segments
IV. Power Generation Plant
V. Storage Tanks
VI. Settlement Lagoon
VII. Bentonite Handling Plan
17
2.1.2 Off-shore pipelines
(Also, known as marine, subsea or submarine pipeline) is a pipeline that is laid on the
seabed or below it inside a trench. In some cases, the pipeline is mostly on-land but in places
it crosses water expanses, such as small seas, straights and rivers. Submarine pipelines are
used primarily to carry oil or gas, but transportation of water is also important.
One of the earliest and most critical tasks in a submarine pipeline planning exercise is
the route selection. This selection has to consider a variety of issues, some of a political
nature, but most others dealing with geohazards, physical factors along the prospective route,
and other uses of the seabed in the area considered. This task begins with a fact-finding
exercise, which is a standard desk study that includes a survey of geological maps,
bathymetry, fishing charts, aerial and satellite photography, as well as information from
navigation authorities.
18
2.1.2.2.1 Other physical factors to be taken into account prior to building a pipeline
include the following
I. Seabed mobility: Sand waves and mega ripples are features that move with time
II. Submarine landslides: They result from high sedimentation rates and occur on steeper
slopes
III. Currents: High currents are objectionable in that they hinder pipe laying operations
IV. Waves: In shallow waters, waves can also be problematic for pipeline laying
operations
V. Ice-related issues: In freezing waters, floating ice features often drift into shallower
waters, and their keel comes into contact with the seabed
VI. Other pipelines: If and where the proposed pipeline intersects an existing one
VII. Fishing vessels: Commercial fishing makes use of heavy fishing nets dragged on the
seabed
VIII. Ship anchors
IX. Military activities
I. Submarine pipelines generally vary in diameter from 3 inches) for gas lines, to 72
inches for high capacity lines
II. Wall thicknesses typically range from 10 mm (0.39 in) to 75 mm (3.0 in).
III. The pipe can be designed for fluids at high temperature and pressure. The walls are
made from high-yield strength steel, 350-500 MPa (50,000- 70,000 psi),
IV. Weldability being one of the main selection criteria. The structure is often shielded
against external corrosion by coatings such as bitumastic or epoxy, supplemented by
cathodic protection with sacrificial anodes.
V. Concrete or fiberglass wrapping provides further protection against abrasion. The
addition of a concrete coating is also useful to compensate for the pipeline’s negative
buoyancy when it carries lower density substances.
VI. The pipeline’s inside wall is not coated for petroleum service. But when it carries
seawater or corrosive substances, it can be coated with epoxy, polyurethane or
polyethylene;
VII. It can also be cement-lined. In the petroleum industry, where leaks are unacceptable
and system 3 pipelines are subject to internal pressures typically in the order of 10
MPa (1500 psi), the segments are joined by full penetration welds
VIII. Mechanical joints are also used. A pig is a standard device in pipeline transport, be it
on-land or offshore. It is used to test for hydrostatic pressure, to check for dents and
crimps on the sidewalls inside the pipe, and to conduct periodic cleaning and minor
repairs.
19
2.1.2.4 Construction
The pipes is being supplied to the pipe-laying ships, it comes as a single pipe or as it
comes as double , triple, quad welded jointed pipes in case of large distance piping to speed
up the piping process. Figure 2-10
The pipe sections are placed in the middle of the platform and using grippers and
rollers raised up to the welding tower, where they are to be welded together at the girth join.
Figure 2-11
20
2.1.2.4.3 Process layout
(a) (b)
2.1.2.4.4 Alignment
The pipes are aligned in the tower and welded by automated welding machineries it
goes through several welding stations depending on the number of passes. Frist station is the
root filling then the hot pass then to the stations equal to remaining passes. Figure 2-14
21
Figure 2-14 pipes welding
2.1.2.5 Quality control
During this finishing procedure, the exposed welded joints are coated with two layers,
one made of epoxy resin and the other of polypropylene to maintain continuity with the rest
of the pipe.
22
2.1.2.7 Laying of the pipeline
Pipe lay Barge system will be used to build the offshore portion of the pipeline, which
consists of a mobile platform or barge where the pipeline is welded before being laid on the
seabed in a continuous fashion. Two pipe lay methods are commonly used for this type of
installation: the S-lay method and J-lay method.
Is suitable for use both in shallow and deep-water areas (up to 2500 meters water
depth depending on pipe diameter) and involves welding the pipe sections horizontally, and
continuously ‘feeding’ the jointed sections over the barge’s pipe lay stinger in such a way
that the pipeline forms an “S” shape from the barge’s exit point up to the touchdown point on
the seafloor.
The pipes are assembled and welded in a vertical mode in a tower erected on the
center or side of the barge and as the platform moves forward, the jointed pipeline is lowered
near vertically in a J-shape from the launching point down to the bottom of the sea. J-lay
method is considered to be suitable for 400 m. to 3500 m. water depth depending on pipeline
diameter. Figure 2-18
23
2.2 PIPELINE COMPONENTS
2.2.1 Pipes
2.2.1.1 Classification
Cast-Iron Pipe
Ductile-Iron Pipe
METALLIC PIPES
Aluminum Pipe
pipes
Copper Pipe
PP
24
2.2.1.1.1 METALLIC PIPES
Most metallic pipes are stronger and harder to break also they are more conductive to
heat and electricity and less corrosive-resistant than nonmetallic pipes. Figure 2-20
2. Seamless
Seamless steel pipe is made without a
longitudinal weld by hot working lengths of
steel to produce pipe of the desired size and
properties. Figure 2-22
25
2.2.1.1.1.2 Corrugated Steel Pipe
Thin-wall, large-diameter pipes made of galvanized steel sheets having either helical
or annular corrugations. Used extensively in sewer and drainage systems where both the
internal pressure (water pressure) and the external pressure (soil pressure) are low and where
leakage will not cause serious problems.
Two types: the ordinary or gray cast-iron pipe, and the ductile-iron pipe. The ordinary
cast-iron pipe made of iron containing 3 to 4% of carbon in the form of graphite flakes. Gray
cast-iron pipe has relatively strong corrosion- resistance ability and long life. Two strength
designations for cast-iron pipes: 18/40 and 21/45. In the first designation. The number 18
means that the minimum bursting tensile strength is 18,000 psi, and the number 40 means that
the minimum modules of rupture (i.e., the tensile stress that causes failure due to bending) is
40,000 psi. The meaning of the 21/45 designation is similar.
300 series such as SS304 or SS316, the most used stainless steel pipes. Steel contains
chrome-nickel alloys, and corrosion resistant. High price, used only in special applications
such as: when the fluid, or environment is rather corrosive, when no rusting of pipe can be
tolerated such as in pharmaceutical or food industries.
2.2.1.1.1.6 AluminumPipe
Corrosion resistant, Used in certain food plants and chemical plants. 1100 and 6000
series of aluminum are used for making pipes. Aluminum 1100 is low in strength but easy to
weld. 3000 or 6000 series is High-number aluminums are stronger mechanically and more
corrosion- resistant, and hard to weld. Pipes formed by a drawing or extrusion process; they
are seamless.
26
2.2.1.1.1.7 Copper Pipe
Corrosion-resistant but expensive, Used only for small pipes such as those used in
plumbing. Pipes can be formed by cold drawing, Note that many of the stainless steel,
aluminum and copper pipes are actually tubing rather than pipes.
Many other metal pipes are available, Made from different alloys and are used for
different purposes, such as corrosion resistance to a particular fluid, high- temperature,low-
temperatureresistance, etc.
Not be as strong as metallic pipes, lighter in weight and more economical which a Have
certain other advantages such as being more corrosion resistant. There different types of
nonmetallic pipes. Figure 2-23
27
2.2.1.2 Pipes types
Continuous welded pipe is defined as pipe that has one longitudinal seam produced by
the continuous welding (This is a type of butt-welded pipe).
Electric welded pipe is defined as pipe that has one longitudinal seam produced by the
electric welding process.
For grades higher than X42, the weld seam and the entire heat affected zone shall be
heat treated so as to simulate a normalizing heat treatment, except that by agreement between
the purchaser and the manufacturer alternative heat treatments or combinations of heat
treatment and chemical composition may be substituted. Where such substitutions are made,
the manufacturer shall demonstrate the effectiveness of the method selected using a
procedure that is mutually agreed upon. This procedure may include, but is not necessarily
limited to, hardness testing, microstructural evaluation, or mechanical testing. For grades X42
and lower, the weld seam shall be similarly heat treated, or the pipe shall be processed in
such a manner that no untampered martensite remains.
Electric welding shall be performed with a minimum welder frequency of 100 kHz.
For all grades, the weld seam and the entire heat affected zone shall be heat treated so as to
simulate a normalizing heat treatment, except that by agreement between the purchaser and
the manufacturer alternative heat treatments or combinations of heat treatment and chemical
composition may be substituted. Where such substitutions are made, the manufacturer shall
demonstrate the effectiveness of the method selected using a procedure that is mutually
agreed upon. This procedure may include, but is not necessarily limited to, hardness testing,
microstructural evaluation, or mechanical testing.
28
2.2.1.2.5 Laser Welded Pipe
Laser welded pipe is defined as pipe that has one longitudinal seam produced by the
laser welding process. The weld seam and the entire heat affected zone of laser welded pipe
shall be heat treated so as to simulate a normalizing heat treatment, except that by agreement
between the purchaser and manufacturer, an alternative process may be substituted. Where
such substitution is made, the manufacturer shall demonstrate the effectiveness of the method
selected, using a procedure that is mutually agreed upon. This procedure may include, but is
not necessarily limited to, hardness testing, microstructural evaluation, or mechanical testing.
Note: During the manufacture of laser welded pipe, the product is in motion through the
surrounding air. Normalizing is usually defined with "cooling in still air;" hence the phrase
"to simulate a normalizing heat treatment" is used here.
Longitudinal seam submerged-arc welded pipe is defined as pipe that has one
longitudinal seam produced by the automatic submerged-arc welding process At least one
pass shall be on the inside and at least one pass shall be on the outside. (This type of pipe is
also known as submerged- arc welded pipe)
Gas metal-arc welded pipe is defined as pipe that has one longitudinal seam produced
by the continuous gas metal-arc welding process. At least one pass shall be on the inside and
at least one pass shall be on the outside.
Combination gas metal-arc and submerged-arc welded pipe is defined as pipe that has
one longitudinal seam produced by a combination of the welding processes. The gas metal-
arc welding process shall be continuous and first, and followed by the automatic submerged-
arc welding process with at least one pass on the inside and at least one pass on the outside.
Double seam submerged-arc welded pipe is defined as pipe that has two longitudinal
seams produced by the automatic submerged-arc welding process .The seams shall be
approximately 1800 apart. For each seam, at least one pass shall be on the inside and at least
one pass shall be on the outside. All weld tests shall be performed after forming and welding.
29
2.2.1.2.10 Double Seam Gas Metal-Arc Welded Pipe
Double seam gas metal-arc welded pipe is defined as pipe that has two longitudinal
seams produced by the gas metal arc welding process. The seams shall be approximately
1800 apart. For each seam, at least one pass shall be on the inside and at least one pass shall
be on the outside. All weld tests shall be performed after forming and welding.
2.2.1.2.11 Double Seam Combination Gas Metal-Arc and Submerged-Arc Welded Pipe
Double seam combination gas metal-arc and submerged arc welded pipe is defined as
pipe that has two longitudinal seams produced by a combination of the welding processes.
The seams shall be approximately 1800 apart. For each seam, the gas metal-arc welding shall
be continuous and first, and followed by the automatic submerged-arc welding process with
at least one pass on the inside and at least one pass on the outside. All weld tests shall be
performed after forming and welding.
Helical seam submerged-arc welded pipe is defined as pipe that has one helical seam
produced by the automatic submerged- arc welding process. At least one pass shall be on the
inside and at least one pass shall be on the outside. (This type of pipe is also known as spiral
weld pipe.)
30
The published standards, therefore, represent the consensus viewpoint of all involved. Line
pipe and Oil Country products are manufactured and tested as prescribed by the American
Petroleum Institute (API). The API operates similarly to the ASTM except that producers,
consumers, and associations with primary interests in oil or gas are involved.
2.2.1.3.2 GRADE
Grade refers to divisions within different types of seamless and ERW pipe and
designates mechanical properties such as minimum yield and tensile strengths. Grade B has
higher tensile and yield strength than Grade A. It is manufactured to higher carbon content
steel. Grade A, being a softer steel, is easier to bend and is recommended for use in close
coiling and cold bending. Grade B has higher stress values and is better suited for machining
operations.
Grade C, which is available in ASTM-106, has higher tensile and yield strength than Grades
A & B.
2.2.1.3.3 DIMENSIONS
Many changes have been made to ASTM specifications over the years. One of the
more recent has been to make the specifications fit with metric, and more correctly, with the
measurements of pipe and the related fittings.
To change the pipe outside diameter (OD) and wall thickness, simply multiply the SI
dimensions by the appropriate factor to convert to metric. However, an inch is not a real inch.
Nowhere on pipe 12" and smaller is there a corresponding measurement because this size has
no real numerical value.
To solve this problem and still retain the intent of the size designation, the inch mark
was removed from the column showing the size, and the term NPS was added as were the
following words: The dimensionless designator NPS (nominal pipe size) has been substituted
in this standard for such traditional terms as “nominal diameter,” “size,” and “nominal size.”
They are now stated as NPS 1, NPS 2, NPS 6, NPS 12, NPS 14, etc.
31
2.2.2 Pipes connections
Straight pipe sections must be connected to each other and to valves and equipment,
have changes in direction, and be interconnected between systems. This is accomplished by
using flanges and fittings. Selecting a flange or fitting requires the engineer to:
I. Know the types of flanges and fittings that can be used based on industry standards.
II. Select a material specification, material group and class, given design pressure,
temperature, and pipe material.
2.2.2.1 Classification
pipe threaded
Connections Flanges Types
Flanges Blind
Socket
Slipp on
Lapped
Weld neck
Flat
Faces Types
Raised
Ring-joint
Spiral
Gaskets Types
Metal-ring
Sheet
45° elbow
Elbow
Fittings 90° elbow
Cross
Equal
Tee Reducing
concentric
Reducer eccentric
seamless
Later butt-weld
socket-weld
Full
Coupling
Hlaf
Caps&plugs
32
2.2.2.2 Connection types
2.2.2.2.1 Flanges
33
2.2.2.2.1.1 Threaded Flanges
34
2.2.2.2.1.6 Welding-Neck Flanges
The area of a flange where the gasket is positioned is called the face or facing
Different types of flange faces are used as the contact surfaces to seat the sealing gasket
material.
35
2.2.2.2.3 GASKET TYPES
The gasket provides the seal in a flange assembly. The three general gasket types that
are typically used in pipe flanges for process plant and pipeline applications are:
I. Sheet.
II. Spiral wound.
III. Solid metal ring
36
2.2.2.2.4 Fittings
Pipe fittings are an essential part of the piping systems. Therefore, it is important to be
familiar with their types; applications and limits imposed by associations and other industry
standards. These fittings assist the piping process in various aspects, such as diverting the
flow, tapping the process for temperature reading or pressure indication, draining or venting
the piping and so on. Therefore, to complete the picture of the piping system fittings should
be known and understood also, sometimes, it is necessary for two sections of pipe to intersect
when flows must be combined or separated. We will discusses various types of fitting to
serve this purpose. Sometimes, the intersection location between the two pipes is weakened
because a section of pipe wall must be removed to permit the two flows to split or combine.
Pipe fittings are used extensively in process plants as well as other piping systems.
They serve the overall process in many aspects such as the following:
I. Change the flow direction.
II. Bringing two or more pipes together.
III. Diverting a single flow into two branching flows or more.
IV. Altering the pipe diameter.
V. Tapping the process for temperature or pressure readings.
VI. Terminating a pipe.
There are many kinds of pipe fittings; some are standard types others could be
proprietary controlled by patent regulations. In general, there are three attachment methods
may be used for fittings, each of which has some limitations:
I. Threading.
II. Socket-welded.
III. Butt-welded.
2.2.2.2.4.1 Elbows
37
2.2.2.2.4.3 Reducers
2.2.2.2.4.5 A lateral
Figure 2-41 lap joint
Pipe caps are used to close off the end of a pipe section. A pipe cap rather than a blind
flange is used in situations where it is known that the pipe end will not have to be opened.
Figure 2-44
(a) (b)
Figure 2-44 (a) Pipe plug, (b) Pipe cap
38
2.2.2.3 Connections Selection
ASME B16.5, Pipe Flanges and Fittings, provides flange dimensional details and
pressure/temperature ratings for standard pipe sizes from 13 through 600 mm (1/2 through 24
in.). This Standard covers a wide range of material types, and will typically be the flange
standard used for process plant applications.
The pressure/temperature ratings that are contained within ASME B16.5 specify the
combinations of pressure and temperature that are acceptable for given flange sizes and
dimensions. The term class is used to designate groupings of acceptable
pressure/temperature combinations contained within ASME B16.5. ASME B16.5 contains
seven classes designated as classes 150, 300, 400, 600, 900, 1500, and 2500. As the number
of the class increases, the strength of the flanges within it increases. Therefore, higher flange
classes can withstand higher pressure/temperature combinations.
I. Manufacturing details.
II. Maximum hardness limitations.
III. Heat treatment.
IV. Material chemistry.
V. Mechanical strength testing.
VI. Impact testing.
VII. Hardness testing.
VIII. Nondestructive examination.
IX. Repairs.
X. Markings.
2.2.2.3.2 Selection Procedure of the Material Group for ASME Flanges and Flanged
Fittings
The following procedure may be used to select the correct flange material and
Material Group Number. Table 2-1
I. Identify the material chemistry (such as carbon steel, 1 1/4 Cr - 1/2 Mo) that is being
used for the connected piping.
II. Identify the design temperature.
III. For pipeline applications, identify the Specified Minimum Yield Stress of the pipe
material that is being used.
39
Table 2-1 ASME selection procedure for flanges and flanged fittings
Use the following procedure to determine the Class for ASME B16.5 flanges and
fittings:
I. Generic pipe material (such as Carbon Steel, C-1/2 M, 3-1/2 Ni)
II. Design Pressure, kPa (psig)
III. Design Temperature, °C (°F)
IV. Nominal Pipe Size, mm (in.)
V. Pipe material SMYS (pipeline applications), MPa (psi)
2.2.2.3.4 Dimensions
ASME B16.5, which provides dimensions for all classes. The flange & fittings
geometry is completely specified by the dimensions given. The flange dimensions for a
given class are the same for all possible flange materials.
The main requirements and factors to achieve reliable flanged joints are the following:
I. Flange type, material and rating.
II. Gasket material, type and quality.
III. Appropriate surface finish of the flange rating
IV. Right bolting procedure is followed
V. Good workman ship by the people assembling the flanges.
VI. Careful inspection during the above stages as required
40
2.2.3 Valves
In process operations, fluids and their movement and transfer from place to place,
plays a large part in the process. Fluids are contained in various types of vessels and are
transported in pipelines. In order to Start or Stop fluid flow, to Control flow and to Prevent
Back-flow, various types of valves are installed in the piping. To prevent over-pressure in
piping and vessels, we use Safety Relief valves and, to isolate equipment for maintenance etc,
Block valves are installed.
Over 95% of the valves that are used in process plant and pipeline applications will be
one of the types that are discussed in this module. A number of other specialty-type valves
are also used in specific applications. These include clamp or pinch valves, diaphragm
valves, needle valves, and ram-type sampling valves.
The engineer must know the possible functions of a valve before being able to select
the appropriate valve for a particular application. Fluid flows through a pipe, and valves are
used to control the flow. A valve may be used to block flow, throttle flow, or prevent flow
reversal. The following describes the basic valve functions.
The block-flow function provides completely on or completely off flow control of a
fluid in a piping system, generally without throttling or variable control capability. It might
be necessary to block flow in order to take a piece of equipment out of service for
maintenance, while the rest of the unit remains in operation, or to separate two portions of a
single system to accommodate various operating scenarios.
To throttle flow in a piping system may increase or decrease the amount of fluid
flowing in the system and can also help control pressure at points within the system. It might
be necessary to throttle flow in order to regulate the filling rate of a pressure vessel, or to
control unit operating pressure levels.
In some cases, it might be necessary to automatically prevent the reversal of flow
beyond the valve location and not allow fluid to reverse its direction during sudden pressure
changes or system upsets. Preventing reverse flow might be necessary to avoid damage to a
pump or a compressor, or to automatically prevent backflow into the upstream part of the
system due to process reasons.
Various types of valves may be used for each function. The gate valve is the type that
is most commonly used to block flow in a process plant. The ball-, plug-, butterfly-,
diaphragm-, and globe-type valves are used to block flow to a lesser extent. The globe valve
is the type most commonly used to throttle flow in a refinery. Butterfly and diaphragm valves
are also used to throttle flow. The check valve is the only valve-type that is used to prevent
flow reversal. There are three kinds of check valves: swing, ball, and lift.
The engineer must know the various types of valves because some valves have
advantages over others in particular applications. For example, numerous valve-types will
block flow. The gate valve is most commonly used; however, the ball valve may be a better
choice based on the particular application.
41
2.2.3.1 Classification
Special
ON.OFF REGULATION NON-RETURN
purpose
BUTTERFLY PISTON
The valves can further be classified based on the end connections. End connection
means the arrangement or attachment of the valves to the equipment or to the piping. The
types of end connections are:
I. Screwed ends.
II. Socket weld ends
III. Flanged ends
IV. Butt weld ends
V. Socketed ends
VI. Wafer type ends
42
2.2.3.1.3 Based on the materials of construction:
The valves could also be classified based on the materials of construction. There can
be any number of combinations possible with the materials of construction. It is for the
piping engineer to select the same in consultation with the process engineer to suit the
process fluid.
The environment in which the valves are installed is also to be considered for
selection of materials of construction. However, the most commonly available materials are:
I. Cast Iron
II. Bronze
III. Gun metal
IV. Carbon Steel
V. Stainless Steel
VI. Alloy Carbon Steel
VII. Poly Propylene UHMW-PE, UHMW-HDPE etc.
VIII. Special Alloys
Body could also be lined with elastomer so that process fluid will not be in contact
with the metal. The valve could also be classified based on the type of construction. Valve
manufacturers offer endless varieties of construction. Based on the operation, valves can be
broadly classified as operated valves and self-operated valves. Mainly the check valves are
self-operated and all other types come under operated valves.
43
2.2.3.2 Valves types
44
2.2.3.2.3 Plug Valve
45
2.2.3.2.5 Diaphragm Valves
I. A diaphragm valve is a linear motion valve that is used to start, regulate, and stop
fluid flow.
II. The name is derived from its flexible disk, which mates with a seat located in the
open area at the top of the valve body to form a seal. Figure 2-49
III. Diaphragm valves can also be used for throttling service.
IV. Diaphragm valves are particularly suited for the handling of corrosive fluids, fibrous
slurries, radioactive fluids, or other fluids that must remain free from contamination.
46
2.2.3.2.7 Needle Valves
Check valves are designed to prevent the reversal of flow in a piping system. These
valves are activated by the flowing material in the pipeline. The pressure of the fluid
passing through the system opens the valve, while any reversal of flow will close the valve.
Closure is accomplished by the weight of the check mechanism, by back pressure, by a
spring, or by a combination of these means. The general types of check valves are swing,
tilting-disk, butterfly, and stop.
I. A swing check valve allows full, unobstructed flow and automatically closes as
pressure decreases. Figure 2-52
II. These valves are fully closed when the flow reaches zero and prevent back flow.
III. Turbulence and pressure drop within the valve are very low.
47
2.2.3.2.8.2 Tilting Disk C heck Valves
I. The tilting disk check valve is similar to the swing check valve. Figure 2-53
II. The tilting disk type keeps fluid resistance and turbulence low because of its
straight-through design.
I. A lift check valve is commonly used in piping systems in which globe valves are
being used as a flow control valve. Figure 2-54
II. Lift check valves are suitable for installation in horizontal or vertical lines with
upward flow.
III. They are recommended for use with steam, air, gas, water, and on vapor lines with
high flow velocities.
48
2.2.3.3 Valves selection
Selecting the appropriate valve depends on the fluid in a piping system, the system's
design conditions, the service application, the functions and types of valves (as discussed
earlier in this module), and the applicable SAES and SAMSS requirements. Other
considerations for selecting valves are discussed in further detail in this section. SAES-L-
008 and the 04-SAMSS-series provide requirements and limitations for valve selection. The
valve selection procedure, as described below and summarized in Work Aid 1, is a guide for
selecting the appropriate valve for the three primary functions discussed earlier. However, it
is important to understand that selecting valves may simply be a matter of duplicating valves
from a system that has provided good performance. Similarly, good experience with a
particular valve model in one service often justifies using the same model elsewhere in an
essentially identical service.
Basic piping system design and valve application data are required before a valve can
be selected.
Review of the data that is collected will begin to narrow the choices of potentially
suitable valves. For example, if a block valve is needed, all the check valve-types are
immediately eliminated from consideration.
49
2.2.3.3.2 Valve Sizing
In most cases, valve size is identical to pipe size. In some cases, a valve must be
larger than the pipe in order to pass the required flow-rate due to pressure drop across the
particular valve-type being used. In other cases, it might be advantageous for a valve to be
smaller for economic reasons.
When fluid is flowing steadily in a long, straight pipe of uniform diameter, the flow pattern
assumes a certain characteristic form.
Any disruption, such as due to friction, will cause a drop in pressure. Valves also disrupt the
flow pattern and, therefore, cause a pressure drop in the piping system. The loss of pressure
produced by a valve consists of:
I. The pressure drop within the valve itself.
II. The pressure drop in the upstream and downstream piping that exceeds what would
normally occur if there was no valve in the line.
Equations are used to calculate the pressure drop across a valve, based on the flow
characteristics of the particular valve- type. It must be determined whether the pressure drop
is acceptable for the process design requirements. Since the pressure drop caused by valves
can affect the size of the valve, it can also influence the selection of one valve-type over
another, since different valve-types have different pressure-drop characteristics. It is also
normally the process design engineer who determines whether the system pressure drop is
acceptable.
50
2.2.4 Pumps
In a broad sense, the word pump refers to any machine in a pipeline that forces the
fluid, be it a liquid or gas, to move through the pipe. The basic function of a pump is to
convert mechanical energy or power to fluid energy or power. Most commonly, a pump is
mechanically connected to an electrical motor through a shaft. The motor drives the pump,
which in turn drives the fluid. In doing so, electrical energy or power is converted to
mechanical energy or power, which in turn is converted to fluid energy or power.
Alternatively, a pump may be driven by something other than an electric motor, such as a
gasoline or diesel engine which converts the energy or power derived from burning fuel into
mechanical energy or power to drive the pump. In doing so, fluid energy or power is
converted to mechanical energy or power, which in turn is converted to electrical energy or
power. Mechanical pumps serve in a wide range of applications such as pumping water from
wells, aquarium filtering, pond filtering and aeration, in the car industry for water-cooling
and fuel injection.
2.2.4.1 Classification
Pumps may be classified on the basis of the applications they serve (figure 2-57), the
materials from which they are constructed, the liquids they handle. All pumps may be divided
into two major categories:
I. Dynamic, in which energy is continuously added to increase the fluid velocities
within the machine to values greater than those occurring at the discharge so
subsequent velocity reduction within or beyond the pump produces a pressure
increase.
II. Displacement, in which energy is periodically added by application of force to one
or more movable boundaries of any desired number of enclosed, fluid-containing
volumes, resulting in a direct increase in pressure up to the value required to move
the fluid through valves or ports into the discharge line.
51
Self-Priming
Centrifugal
Multistage
Dynamic
centrifugal
Jet Pumps
Piston
Diaphragm Pumps
single rotor
Positive
Rotary PD Pumps
displacement
multiple rotor
Screw Pumps
Gear
May be further subdivided into several varieties of centrifugal and other special-effect
pumps. Figure (2-57) presents in outline form a summary of the significant classifications and
sub classifications within this category.
52
Types of Centrifugal Pumps
53
c) Self-Priming Pumps
This type of pump differs from a standard centrifugal pump in that it has a water
reservoir built into the unit which enables it to rid pump and suction line of air by
recirculating water within the pump on priming cycle. This water reservoir may be above the
impeller or in front of the impeller. In either case, the "self-priming" capability of the pump
comes from the pump ability to retain water after the very first prime. As shown in figure 2-
61
Jet pumps are based on the conversion of fluid momentum (kinetic energy) to
pressure. When a jet is issued in a pipe in the main flow direction, the momentum of the jet
will be converted to fluid pressure downstream where the jet is diffused and dispersed.
However, since much of the kinetic energy of the jet is dissipated into heat during this
conversion. Most jet pumps have an efficiency of less than 30%, which is much lower than
those of the aforementioned types of pumps.
Displacement pumps are essentially divided into reciprocating and rotary types, depending on
the nature of movement of the Pressure- producing members. Each of these major
classifications may be further subdivided into several specific types of commercial
importance.
54
2.2.4.2.2.2 Diaphragm Pump
A screw pump is a more complicated type of rotary pump that uses two or three
screws with opposing thread. One screw turns clockwise and the other counterclockwise. The
screws are mounted on parallel shafts that have gears that mesh so the shafts turn together
and everything stays in place. The screws turn on the shafts and drive fluid through the pump.
As with other forms of rotary pumps, the clearance between moving parts and the pump's
casing is minimal. As shown in figure 2-64
55
2.2.4.2.2.5 Gear pumps
Gear pumps are widely used in modern hydraulic systems due to their high
performance, long service life and low pur-chase and maintenance costs. Product
development has made it possible to achieve high operating pressures, excellent volumetric
and mechanical efficiency, and lower noise levels, in operation.
The first step is to define the requirements and conditions under which the equipment
will operate. Then we selected pump and motor.
56
2.2.4.3.1 Pumps Selection
The choice of driver type for a pumping service is as important as the pump selection.
Factors that affect the driver choice are capital cost, driver type availability, operating
reliability and the availability and cost of utilities. Constant speed electric motors are most
economical when only the first cost is considered. Often there is excess steam available
within a facility that, when compared to the cost of electricity, will justify the extra cost of a
steam turbine.
57
2.3 WELDING OF PIPELINE
Pipe operating conditions in the handling of oil, gases, water, and other substances
range from high vacuum to pressure of several thousand pounds per square inch. Mechanical
joints are not satisfactory for many of these services. Electric arc or oxyacetylene welding
provide effective joints in these services and also reduce weight, increase the strength, and
lower the cost of pipe installations. As shown in figure 2-66
Pipe to be welded is usually supplied with a single V bevel of 32-1/2 degrees with a
1/16-in. (1.6-mm) root face for pipe thicknesses up to 3/4 in. (19.1 mm). A single U groove is
used for heavier pipe. If the pipe has not been properly beveled or has been cut in the field, it
must be beveled prior to welding.
58
2.3.1.3 Cleaning of Pipe
After beveling, remove all rust, dirt, scale, or other foreign matter from the outside of
the pipe in the vicinity of the weld with a file, wire brush, grinding disk, or other type of
abrasive. If the bevels are made by oxyacetylene cutting, the oxide formed must be entirely
removed. The inside of the pipe in the vicinity of the weld may be cleaned by a boiler tube
and flue cleaner, by sandblasting, by tapping with a hammer with an air blast follow up, or by
any other suitable method, depending on the inside diameter of the pipe. Care must be taken
to clean the scarf faces thoroughly.
A pipe lineup clamp should be used to align and securely hold the pipe ends before tack
welding. A spacing tool to separate the pipe ends can be made from an old automobile spring
leaf. The spacing for oxyacetylene welding should be approximately 1/8 in. (3.2 mm); for arc
welding, the spacing depends on the size of the electrode used for the root pass.
If a pipe lineup clamp is not available, the pipe section must be set in a jig so that their center
lines coincide and the spacing of the pipe ends is uniform prior to tack welding. An angle iron
will serve as a jig for small diameter pipe, while a section of channel or I-beam is satisfactory
for larger pipe. As shown in figure 2-68
Figure 2-68 Angle iron serving as jig for small diameter pipe
When a backing ring is used and it is desired to weld to the backing ring, the spacing
should not be less than the diameter of the electrode used for the root pass. When welding to
the backing ring is not desired, the spacing should not exceed one half the electrode diameter,
and varies from this diameter to zero, depending on whether a small or large angle of bevel is
used.
59
2.3.1.5 Open Root Joint Preparation
60
2.3.2 Welding Processes
2.3.2.1 General
The most commonly used processes for joining pipe are the manual oxyacetylene
process and manual shielded metal-arc process. Automatic and semiautomatic submerged arc,
inert gas metal-arc, and atomic hydrogen welding are also used particularly in shop
operations. The manual shielded metal-arc process may be used for welding all metals used
in piping systems, whereas manual oxyacetylene welding is generally limited to small size
piping or to welding operations where clearances around the joints are small. The equipment
required for the oxyacetylene process is also much less expensive and more portable than that
required for shielded metal-arc welding.
Types of Welding
Fusion Pressure
Welding Welding
Chemical
Electric Arc Gas Welding Cold Pressure
Reaction
Submerged Friction
Arc Welding Welding
61
2.3.2.3 Shielded Metal-Arc Process
The shielded metal-arc process can be used for welding pipe materials such as
aluminum, magnesium, and high chromium-nickel alloys that are difficult to weld by other
processes. In shielded metal-arc welding, the number of passes required for welding ferrous
metal piping varies with the pipe thickness, the welding position, the size of the electrode,
and the welding current used.
The number of passes required for welding low alloy and low carbon steel pipe
depends on the thickness of the pipe, the welding position, the size of the electrode, and the
current used but, in general, is approximately one pass for each 1/8 in. (3.2 mm) of pipe
thickness. When welding in the horizontal or rolled position, the number of layers is usually
increased 25 to 30 percent. Smaller electrodes are used to lessen the heat concentration and to
ensure complete grain refinement of the weld metal.
The electrodes used vary from 1/8 to 5/32 in. (3.2 to 4.0 mm) diameter for the first
pass, 5/32 in. (4.0 mm) diameter for the intermediate passes, and up to 3/16 in. (4.8 mm) for
the top passes and reinforcement.
In manual shielded metal-arc welding, as much welding as possible is done in the flat
or down hand position using suitable power driven equipment for rotating the pipe at a speed
consistent with the speed of welding. When the pipe is in a fixed horizontal position, the weld
is usually made from the bottom upward. With thin or medium thickness pipe, the welding is
done downward. More metal is deposited when welding upward. Complete grain refinement
is easier to achieve, and welding downward requires a much higher degree of manual skill.
As shown in figure 2-75
62
When the pipe is in a fixed vertical position, it is customary to deposit the filler metal
in a series of overlapping string beads, using 1/8 in. (3.2 mm) maximum electrodes, and
allowing 25 to 30 beads per square inch of weld area.
When welding by the oxyacetylene process, the directions of welding as described
above will, in general, apply. Backhand welding is used when welding downward, and
forehand welding is used when welding upward. As shown in figure 2-75
63
2.3.2.5 Multi pass Arc Welding
If a lineup clamp is used, the root bead is started at the bottom of the groove while the
clamp is in position. When no backing ring is used, take care to build up a slight bead on the
inside of the pipe. If a backing ring is used, the root bead must be carefully fused to it. As
much root bead as the bars of the lineup clamp permit should be applied before the will
clamp is removed. Complete the bead after the clamp is removed. As shown in figure2-77
Ensure the filler beads are fused into the root bead in order to remove any undercut
caused by the deposition of the root bead. One or more filler beads around the pipe will usually
be required.
The finish beads are applied over the filler beads to complete the joint. Usually, this is
a weave bead about 5/8 in. (15.9 mm) wide and approximately 1/16 in. (1.6 mm) above the
outside surface of the pipe when complete. The finish weld is shown at D.
64
2.4 INSPECTION OF PIPELINE
Focus NDT employees place an emphasis on safety and compliance while efficiently
using time and financial resources. Our technology-based procedures collect accurate and
valuable data to detect flaws and irregularities in pipelines before resulting in severe damage.
Both intrusive and non-intrusive methods are performed through every stage in the life-span
of pipeline equipment and assets. Such continual attention leads to early detection and
regularly scheduled repair and replacement, saving clients from unexpected losses.
Evaluation for the Pipeline Industry:
I. Automated / Advanced Ultrasonic examination of long seams and butt welds
II. Shear Wave Inspection (UT)
III. Magnetic Particle Inspection (MPI)
IV. Radiography Inspections (RT)
V. Liquid Penetrant Inspection (LPI)
Visual testing is the most commonly used test method in industry. Because most test
methods require that the operator look at the surface of the part being inspected, visual
inspection is inherent in most of the other test methods. As the name implies, VT involves
the visual observation of the surface of a test object to evaluate the presence of surface
discontinuities. VT inspections may be by Direct Viewing, using line-of sight vision, or may
be enhanced with the use of optical instruments such as magnifying glasses, mirrors,
borescopes, charge-coupled devices (CCDs) and computer-assisted viewing systems (Remote
Viewing). Corrosion, misalignment of parts, physical damage and cracks are just some of the
discontinuities that may be detected by visual examinations.
65
2.4.1.1.2 Magnetic Particle Testing (MT)
Magnetic Particle Testing uses one or more magnetic fields to locate surface and near-
surface discontinuities in ferromagnetic materials. The magnetic field can be applied with a
permanent magnet or an electromagnet. When using an electromagnet, the field is present
only when the current is being applied. When the magnetic field encounters a discontinuity
transverse to the direction of the magnetic field, the flux lines produce a magnetic flux
leakage field of their own. Because magnetic flux lines don't travel well in air, when very
fine colored ferromagnetic particles ("magnetic particles") are applied to the surface of the
part the particles will be drawn into the discontinuity, reducing the air gap and producing a
visible indication on the surface of the part. The magnetic particles may be a dry powder or
suspended in a liquid solution, and they may be colored with a visible dye or a fluorescent
dye that fluoresces under an ultraviolet ("black") light.
The basic principle of liquid penetrant testing is that when a very low viscosity
(highly fluid) liquid (the penetrant) is applied to the surface of a part, it will penetrate into
fissures and voids open to the surface. Once the excess penetrant is removed, the penetrant
trapped in those voids will flow back out, creating an indication. Penetrant testing can be
performed on magnetic and non-magnetic materials, but does not work well on porous
materials. Penetrants may be "visible", meaning they can be seen in ambient light, or
fluorescent, requiring the use of a "black" light. The visible dye penetrant process. When
performing a PT inspection, it is imperative that the surface being tested is clean and free of
any foreign materials or liquids that might block the penetrant from entering voids or fissures
open to the surface of the part. After applying the penetrant, it is permitted to sit on the
surface for a specified period of time (the "penetrant dwell time"), then the part is carefully
cleaned to remove excess penetrant from the surface. When removing the penetrant, the
operator must be careful not to remove any penetrant that has flowed into voids. A light
coating of developer is then be applied to the surface and given time ("developer dwell time")
to allow the penetrant from any voids or fissures to seep up into the developer, creating a
visible indication. Following the prescribed developer dwell time, the part is inspected
visually, with the aid of a black light for fluorescent penetrants. Most developers are fine-
grained, white talcum-like powders that provide a color contrast to the penetrant being used.
66
Gamma radiation is given off by decaying radioactive materials, with the two most
commonly used sources of gamma radiation being Iridium-192 (Ir-192) and Cobalt-60 (Co-
60). IR-192 is generally used for steel up to 2-1/2 - 3 inches, depending on the Curie strength
of the source, and Co-60 is usually used for thicker materials due to its greater penetrating
ability.
Ultrasonic testing uses the same principle as is used in naval SONAR and fish
finders. Ultra-high frequency sound is introduced into the part being inspected and if the
sound hits a material with a different acoustic impedance (density and acoustic velocity),
some of the sound will reflect back to the sending unit and can be presented on a visual
display. By knowing the speed of the sound through the part (the acoustic velocity) and the
time required for the sound to return to the sending unit, the distance to the reflector (the
indication with the different acoustic impedance) can be determined.
The most common sound frequencies used in UT are between 1.0 and 10.0 MHz,
which are too high to be heard and do not travel through air. The lower frequencies have
greater penetrating power but less sensitivity (the ability to "see" small indications), while the
higher frequencies don't penetrate as deeply but can detect smaller indications.
Traditionally, pipeline girth welds made during pipeline construction in the UK have
been manufactured using the Manual Metal Arc (MMA) welding process and inspected using
100% X-radiography. There is some degree of radiation hazard to the public and operators in
using x-rays and Transco have considered whether this can be reduced or removed. In 1981
work was conducted by British Gas to assess five ultrasonic scanner systems to replace x-rays
but they were all found to have deficiencies, especially in discriminating different defect
types. Since then there has been several technical
developments so that, today, the use of automated
ultrasonic testing (AUT) of girth welds is becoming
increasingly accepted as a reliable and beneficial
alternative to radiographic testing (RT). Confidence has
been generated by an extensive list of pipeline
construction projects where it has been used
successfully. While the basic approach is similar from
most suppliers, there are significant differences as well
as new developments in response to the demands of the
marketplace. It was decided to conduct a trial of several Figure 2-77 Automatic ultrasonic test
AUT systems to establish the capabilities.
67
Table 2-3 Traditional NDT Technique Comparison
As a rule, test shall be hydrostatic, using fresh water or industrial water. The water
shall have a suitable corrosion inhibitor which meets Owner approval. Where the use of sea
water is unavoidable, agreement between Owner and Construction Contractor shall be made,
before proceeding with the work. When sea water is used, quick draining and sufficient
cleaning by fresh water shall be performed after completion of the testing.
Where atmospheric temperature is 0 ºC or below water shall not be used unless water
is heated by steam or other heat source, and maintained at temperature of 4ºC or above during
the testing. If there is a possibility of damage due to freezing, or if the operating fluid or
piping material would be adversely affected by the water, any other suitable liquid such as oil
or kerosene may be used with agreement between Owner and Construction Contractor.
As a rule, test shall be pneumatic, using air. The use of other test fluid shall be
subject to agreement between owner Pneumatic testing shall be made with oil free air. If the
piping is tested pneumatically, the test pressure shall be 110% of the design pressure of the
system. If the test pressure exceeds 6 bars written approval of the Owner shall be obtained.
Welds of piping subject to pneumatic strength test above 6 bars shall be %100 radio graphed.
68
2.4.3 Welding acceptance criteria
69
CHAPTER 3 CASE STUDY
3.1 INTRODUCTION
General Petroleum Company "GPC" indents to construct two new offshore platforms
at NAO and HH oil fields in about 22 m water depth in the Gulf of Suez. The oil production
from the two new offshore platforms shall be transported to the existing Amer-8 platform via
a new 4" subsea pipeline (8 km long) and an In-line Tee required for the subsea gathering of
the two platforms oil production.
Enppi Company role is to design the required pipeline data and select the required
pipeline components, which meets the line required properties (pressure, life time,
permissible residual forces, etc.). And PMS Company is the contractor for this pipeline, the
company use the pipeline data from the designer company then use it to construct the
pipeline. Many factors must be considered during the construction process.
During this chapter we will pass through construction processes and considerations
which must be taken among the process.
The main scope of the project is to construct a new pipeline between NAO and HH oil
fields about 8 km long in about 22m water depth in the Gulf of Suez. Construction process
passes through many stages starting with the material supply plan and the required pipeline
component according to the design data, the selecting the pipeline route take place as the
selected route effects directly the construction process. The following stage is select the
proper pipe laying method and the required pipeline production stages will be needed. At the
end and before starting the constructing process the contractor must prepare a WPS which
describes the welding specification required for the pipeline, the PQR for the selected WPS to
ensure the quality of this welding which let them decide to start the construction process or
make an new WPS. Each of this stages will be described later in this chapter.
70
3.3 PIPELINE DATA
As mentioned before the following data are produced by the designer company Ennpi.
71
Table 3-3 4” pipeline pulling head
4"PIPELINE pulling heads
Item description QTY
Head pipe 4" x 6mm thickness 1
Main plate Steel grade 36 1
Cheek plate Steel grade 36 2
Split plate Steel plate thick. 20 mm grade 36 Trimmed at 45° 2
Ball valve 2" ball valve 2
Flange ANSI B16.5 ,ASTM A694 F52 , 4" 600 # RTJ , weld neck 1
Protection half pipe protection W.TH=4 mm -
Pig 1 contingency pig 1
Padeye Lifting Padeye fit to shackle 4.75 ton G-2130 2
Stopper welded 2" plug 1
Gasket Gaskets oval ring type, Soft Iron, 4"/R45 1
72
3.5 ROUTE SELECTION AND SOIL PREPARATION
Planning and designing are the first things to do before installing offshore pipeline
system. Before the pipeline design is made, a series of surveys is done to determine the best
plan (the safest, the cheapest, and the most environmental friendly) for the pipeline project.
One aspect of planning that impacts a pipeline project from beginning to end, is its route
selection. In the planning stage, there is one key component that all pipeline projects have in
common-how the initial routing of the pipeline will affect the eventual interface of all
activities required for the project.
3.6.1 Assembly
The required pipes type are being supplied to the pipe-laying ships by a material
suppling ship.
The pipe sections are placed in the middle of the platform and using grippers and
rollers raised up to the welding tower.
73
3.6.1.3 Process layout
During this finishing procedure, the exposed welded joints are coated with external
anti-corrosion protection in the form of Fusion Bonded Epoxy (FBE) and three-layer
polyethylene/polypropylene external pipe coating systems in alliance with international
coating companies.
74
3.6.2 Laying of the pipeline
According to our construction factors we are selecting the S-lay method (figure 3-1)
which the pipes continuously ‘feeding’ the jointed sections over the barge’s pipe lay stinger
in such a way that the pipeline forms an “S” shape from the barge’s exit point up to the
touchdown point on the seafloor.
75
3.7 SELECTED PIPELINE WPS
76
3.7.1 Applying the selected WPS to a sample of the pipeline
The previous WPS prevent all welding parameters starting from the pipe pre wilding
preparation. Then the welding process followed by its all required data. A sample 4” pipe are
welded according the previous WPS. This sample will be tested to ensure the quality of the
selected WPS.
1) Pipe preparation
77
3) Pipe welding
The procedure qualification record (PQR) take place after preparing the welding
sample of the 4” pipe. According to the API 1104 standard the sample which we want to test
must pass through two stages.
78
3.8.1.2 Radiographic Inspection
79
3.8.2 Destructive testing
After the sample passes the Visual and the radiographic inspection, a destructive tests
take place. According to API 1104, for the 4” pipe we must do 2 tensile tests and two root
bend test.
80
3.8.2.1 Tensile test
The two test specimen passes as it breaks out the welding area (Base metal break).
81
3.8.2.3 Destructive test report
82
3.9 PIPELINE SAMPLE
After the sample passes the PQR. The contractor could proceeds the construction
process.
At the end of our case study we made a small prototype simulating a part of the
previous pipeline. In order to complete our case study.
83
Figure 3-14 Exploded View for the prototype
84
REFERENCES
[1] PIPING HANDBOOK Mohinder L. Nayyar, P.E. ASME Fellow Seventh Edition.
[5] API (American Petroleum Institute), 2005, Welding Pipeline and Related Facilities,
20th edition, API STANDARD 1104, American Petroleum Institute.
[6] API, 2000, Specification for the Line Pipe, 47th ed., API Spec. 5L, American
Petroleum Institute, Washington, D.C.
[7] PIPELINE ENGINEERING, Henry Liu, Boca Raton London New York Washington,
D.C.
[8] Pipe welding, Egyptian Welding Academy Paper, Document NO. 001W/2004 PP.
85