You are on page 1of 34

R/6664120/029

REMBANG CEMENT PLANT PROJECT


LAPORAN MINGGUAN FABRICATION
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 25
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 24-04-2016 s/d 30-04-2016
PROGRESS BY COST PROGRESS BY PHISIK
NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

1 PREPARATION ENGINEERING Ls 1.00 10.00 #REF! 10.000 #REF!


1.10 Shop Drawing Ls 1.00 10.00 #REF! 10.000 #REF! #REF! 100.00% #REF!

2 MATERIAL PROCUREMENT Ls 1.00 15.00 #REF! 14.372 #REF!


2.10 Purchase Order Ls 1.00 5.00 #REF! 5.000 #REF! #REF! 100.00% #REF!
2.20 Material Recheived Ls 1.00 10.00 #REF! 9.372 #REF! #REF! 93.72% #REF!

3 FABRICATION STEEL Kg 235,238.83 45.00 #REF! 42.264 #REF!


3.10 Coloumn & Post Kg 60,738.89 11.62 #REF! 11.619 #REF!
- Marking/ Cutting 2.32 #REF! 2.324 #REF! #REF! 100.00% #REF!
- Machinning/ Drilling 3.49 #REF! 3.486 #REF! #REF! 100.00% #REF!
- Welding 5.23 #REF! 5.229 #REF! #REF! 100.00% #REF!
- Finishing 0.58 #REF! 0.581 #REF! #REF! 100.00% #REF!

3.20 Balok Kg 93,728.01 17.93 #REF! 17.930 #REF!


- Marking/ Cutting 3.59 #REF! 3.586 #REF! #REF! 100.00% #REF!
- Machinning/ Drilling 5.38 #REF! 5.379 #REF! #REF! 100.00% #REF!
- Welding 8.07 #REF! 8.068 #REF! #REF! 100.00% #REF!
- Finishing 0.90 #REF! 0.896 #REF! #REF! 100.00% #REF!

3.30 Bracing Kg 35,951.69 6.88 #REF! 5.976 #REF!


- Marking/ Cutting 1.38 #REF! 1.197 #REF! #REF! 87.02% #REF!
- Machinning/ Drilling 2.06 #REF! 1.795 #REF! #REF! 87.02% #REF!
- Welding 3.09 #REF! 2.693 #REF! #REF! 87.02% #REF!
- Finishing 0.34 #REF! 0.291 #REF! #REF! 84.59% #REF!

3.40 Roofing Kg 22,326.44 4.27 #REF! 3.437 #REF!


- Marking/ Cutting 0.85 #REF! 0.688 #REF! #REF! 80.60% #REF!
- Machinning/ Drilling 1.28 #REF! 1.033 #REF! #REF! 80.60% #REF!
- Welding 1.92 #REF! 1.549 #REF! #REF! 80.60% #REF!
- Finishing 0.21 #REF! 0.166 #REF! #REF! 77.91% #REF!
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 25
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 24-04-2016 s/d 30-04-2016

PROGRESS BY COST PROGRESS BY PHISIK


NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

3.50 Platform Kg 8,596.11 1.64 #REF! 1.235 #REF!


- Marking/ Cutting 0.33 #REF! 0.247 #REF! #REF! 75.12% #REF!
- Machinning/ Drilling 0.49 #REF! 0.371 #REF! #REF! 75.12% #REF!
- Welding 0.74 #REF! 0.556 #REF! #REF! 75.12% #REF!
- Finishing 0.08 #REF! 0.062 #REF! #REF! 75.12% #REF!

3.60 Handrail Kg 1,979.62 0.38 #REF! - #REF!


- Marking/ Cutting 0.08 #REF! - #REF! #REF! 0.00% #REF!
- Machinning/ Drilling 0.11 #REF! - #REF! #REF! 0.00% #REF!
- Welding 0.17 #REF! - #REF! #REF! 0.00% #REF!
- Finishing 0.02 #REF! - #REF! #REF! 0.00% #REF!
ARCHITECTURAL WORKS
3.70 Siding Kg 10,796.49 2.07 #REF! 1.917 #REF!
- Marking/ Cutting 0.41 #REF! 0.383 #REF! #REF! 92.83% #REF!
- Machinning/ Drilling 0.62 #REF! 0.575 #REF! #REF! 92.83% #REF!
- Welding 0.93 #REF! 0.863 #REF! #REF! 92.83% #REF!
- Finishing 0.10 #REF! 0.096 #REF! #REF! 92.83% #REF!

3.80 Stairway Kg 1,121.58 0.21 #REF! 0.150 #REF!


- Marking/ Cutting 0.04 #REF! 0.030 #REF! #REF! 69.90% #REF!
- Machinning/ Drilling 0.06 #REF! 0.045 #REF! #REF! 69.90% #REF!
- Welding 0.10 #REF! 0.067 #REF! #REF! 69.90% #REF!
- Finishing 0.01 #REF! 0.007 #REF! #REF! 69.90% #REF!

4 PRE ASSEMBLY Ls 1.00 5.00 #REF! 4.378 #REF! #REF! 87.55% #REF!

5 INSPECTION Ls 1.00 10.00 #REF! 8.755 #REF! #REF! 87.55% #REF!

6 PAINTING Ls 1.00 5.00 #REF! 4.592 #REF!


- Primer 1.25 #REF! 1.167 #REF! #REF! 93.32% #REF!
- Intermediet 1.25 #REF! 1.167 #REF! #REF! 93.32% #REF!
- Finishing 2.50 #REF! 2.259 #REF! #REF! 90.37% #REF!

7 PACKING Ls 1.00 5.00 #REF! 4.323 #REF! #REF! 86.46% #REF!


PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 25
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 24-04-2016 s/d 30-04-2016
PROGRESS BY COST PROGRESS BY PHISIK
NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

8 DELIVERY Ls 1.00 5.00 #REF! 4.254 #REF! #REF! 85.08% #REF!

JUMLAH 100.00 #REF! 92.938 #REF!

Surabaya, 30 April 2016


Checked by, Approved by, Prepared by,
PT. Aldaberta Indonesia PT. Semen Gresik PT. Bangun Karya Perkasa Jaya

Suhatsyah Yudha Ananta Wijaya Pramana Budiharjo


Fabrication Manager Staff of Head Rembang Project Project Manager
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 25
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 24-04-2016 s/d 30-04-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

1 PREPARATION ENGINEERING 1.00 10.00 #REF! #REF! 10.000


1.1 Shop Drawing 1.00 10.00 #REF! #REF! 10.000

2 MATERIAL PROCUREMENT 1.00 15.00 #REF! #REF! 14.372


2.1 Purchase Order 1.00 5.00 #REF! #REF! 5.000
2.2 Material Recheived 1.00 10.00 #REF! #REF! 9.372

3 FABRICATION STEEL 235,238.83 45.00 #REF! #REF! 42.264


3.10 Coloumn & Post 60,738.89 11.62 #REF! #REF! 11.619
- Marking/ Cutting 2.32 #REF! #REF! 2.324
- Machinning/ Drilling 3.49 #REF! #REF! 3.486
- Welding 5.23 #REF! #REF! 5.229
- Finishing 0.58 #REF! #REF! 0.581

3.20 Balok 93,728.01 17.93 #REF! #REF! 17.930


- Marking/ Cutting 3.59 #REF! #REF! 3.586
- Machinning/ Drilling 5.38 #REF! #REF! 5.379
- Welding 8.07 #REF! #REF! 8.068
- Finishing 0.90 #REF! #REF! 0.896

3.30 Bracing 35,951.69 6.88 #REF! #REF! 5.976


- Marking/ Cutting 1.38 #REF! #REF! 1.197
- Machinning/ Drilling 2.06 #REF! #REF! 1.795
- Welding 3.09 #REF! #REF! 2.693
- Finishing 0.34 #REF! #REF! 0.291

3.40 Roofing 22,326.44 4.27 #REF! #REF! 3.437


- Marking/ Cutting 0.85 #REF! #REF! 0.688
- Machinning/ Drilling 1.28 #REF! #REF! 1.033
- Welding 1.92 #REF! #REF! 1.549
- Finishing 0.21 #REF! #REF! 0.166

3.50 Platform 8,596.11 1.64 #REF! #REF! 1.235


- Marking/ Cutting 0.33 #REF! #REF! 0.247
- Machinning/ Drilling 0.49 #REF! #REF! 0.371
- Welding 0.74 #REF! #REF! 0.556
- Finishing 0.08 #REF! #REF! 0.062
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 25
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 24-04-2016 s/d 30-04-2016
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 25
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 24-04-2016 s/d 30-04-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

3.60 Handrail 1,979.62 0.38 #REF! #REF! -


- Marking/ Cutting 0.08 #REF! #REF! -
- Machinning/ Drilling 0.11 #REF! #REF! -
- Welding 0.17 #REF! #REF! -
- Finishing 0.02 #REF! #REF! -
ARCHITECTURAL WORKS
3.70 Siding 10,796.49 2.07 #REF! #REF! 1.917
- Marking/ Cutting 0.41 #REF! #REF! 0.383
- Machinning/ Drilling 0.62 #REF! #REF! 0.575
- Welding 0.93 #REF! #REF! 0.863
- Finishing 0.10 #REF! #REF! 0.096

3.80 Stairway 1,121.58 0.21 #REF! #REF! 0.150


- Marking/ Cutting 0.04 #REF! #REF! 0.030
- Machinning/ Drilling 0.06 #REF! #REF! 0.045
- Welding 0.10 #REF! #REF! 0.067
- Finishing 0.01 #REF! #REF! 0.007

4 PRE ASSEMBLY 1.00 5.00 #REF! #REF! 4.378

5 INSPECTION 1.00 10.00 #REF! #REF! 8.755

6 PAINTING 1.00 5.00 #REF! #REF! 4.592


- Primer 1.25 #REF! #REF! 1.167
- Intermediet 1.25 #REF! #REF! 1.167
- Finishing 2.50 #REF! #REF! 2.259

7 PACKING 1.00 5.00 #REF! #REF! 4.323


PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 25
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 24-04-2016 s/d 30-04-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

8 DELIVERY 1.00 5.00 #REF! #REF! 4.254

JUMLAH 100.00 #REF! #REF! 92.938


Catatan :

Surabaya, 30 April 2016


Checked by, Approved by, Prepared by,
PT. Aldaberta Indonesia PT. Semen Gresik PT. Bangun Karya Perkasa Jaya

Suhatsyah Yudha Ananta Wijaya Pramana Budiharjo


Fabrication Manager Staff of Head Rembang Project Project Manager
MASTER SCHEDULE FABRICATION STEEL STRUCTURE

PROYEK : PT. SEMEN GRESIK


LOKASI :: CONCREATE,
REMBANG - JAWA
STEELTENGAH
STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING
PEKERJA

PERIODE PELAKSANAAN ( 75 Hari Kalender ) + ADDENDUM WAKTU ( 164 Hari Kalender )


INDEKS
Nopember Desember Januari Februari Maret April Mey skala
NO URAIAN PEKERJAAN Status Qty Sat %
Ket
% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
08-14 15-21 22-28 29-05 06-12 13-19 20-26 27-02 03-09 10-16 17-23 24-30 31-06 07-13 14-20 21-27 28-05 06-12 13-19 20-26 27-02 03-09 10-16 17-23 24-30 01-07 08-14 15-21 22-28 29-31

1 PREPARATION ENGINEERING 1.00 Ls 10.000 2.500 2.500 2.500 2.500 100%


2.000 1.000 1.000 1.000 1.000 1.000 0.250 0.100 0.100 0.250 0.250 0.215 0.048 0.102 0.230 0.190 0.200 0.180 0.070 0.007 0.808
Shop Drawing rencana 1.00 Ls 10.000 2.500 2.500 2.500 2.500
realisasi 2.000 1.000 1.000 1.000 1.000 1.000 0.250 0.100 0.100 0.250 0.250 0.215 0.048 0.102 0.230 0.190 0.200 0.180 0.070 0.007 0.808
2 MATERIAL PROCUREMENT 1.00 Ls 15.000 10.000 5.000
12.350 0.637 1.113 0.272 0.150
Porchase Order rencana 1.00 Ls 5.000 5.000
realisasi 5.000
Material Rechieved rencana 1.00 LS 10.000 5.000 5.000
realisasi 7.350 0.637 1.113 0.272 0.150
3 FABRICATION STEEL
STEEL STRUCTURE TRANSPORT PALLETIZER 235,238.83 Kg 45.000 5.910 8.202 8.202 13.311 9.374
PEKERJAAN STRUKTUR BAJA 1.243 2.330 3.050 2.346 0.347 0.764 2.558 6.547 2.936 2.703 0.361 2.126 2.757 0.130 0.671 2.137 0.308 1.019 1.959 2.024 2.427 1.523 0.430
Coloumn & Post rencana 60,738.89 Kg 11.619 2.324 2.324 2.324 2.324 2.324
realisasi 1.243 2.330 3.050 1.372 0.083 1.245 0.028 0.038 0.003 0.006 0.368 1.016 0.823 0.015
Balok rencana 93,728.01 Kg 17.930 3.586 3.586 3.586 3.586 3.586
realisasi 0.974 0.264 0.764 1.312 6.519 0.727 1.810 1.047 0.333 1.232 0.222 0.130 1.450 0.443 0.504 0.199
Bracing rencana 35,951.69 Kg 6.877 2.292 2.292 2.292
realisasi 0.578 0.417 0.361 0.976 1.185 0.130 0.414 0.315 0.044 0.457 1.100
Roofing rencana 22,326.44 Kg 4.271 2.135 2.135 50%
realisasi 0.396 0.476 0.104 0.216 0.218 0.590 0.039 0.427 0.141 0.355 0.475 0.430
Platform rencana 8,596.11 Kg 1.644 1.644
realisasi 1.235
Handrail rencana 1,979.62 Kg 0.379 0.189 0.189
realisasi
ARCHITECTURAL WORKS
Siding rencana 10,796.49 Kg 2.065 1.033 1.033
realisasi 1.023 0.210 0.684
Stairway rencana 1,121.58 Kg 0.215 0.107 0.107
realisasi 0.150
4 PRE ASSEMBLY rencana 1.00 Ls 5.000 2.500 2.500
realisasi 0.313 0.763 0.263 0.141 0.085 0.182 0.264 0.999 0.157 0.055 0.250 0.205 0.183 0.170 0.353 0.483
5 INSPECTION rencana 1.00 Ls 10.000 5.000 5.000
realisasi 0.500 1.500 0.435 0.430 0.240 0.316 0.714 1.924 0.236 0.260 0.433 0.333 0.390 0.339 0.705 0.977
6 PAINTING rencana 1.00 Ls 5.000 1.250 1.250 1.250 1.250
realisasi 0.237 1.000 0.054 0.239 0.323 0.477 0.152 0.286 0.114 0.178 0.139 0.169 0.340 0.077 0.509 0.298 0.264
7 PACKING rencana 1.00 Ls 5.000 1.250 1.250 1.250 1.250
realisasi 0.494 0.242 0.586 0.183 0.017 0.177 0.254 0.651 0.179 0.143 0.127 0.310 0.127 0.533 0.298 0.533
8 DELIVERY rencana 1.00 Ls 5.000 0.417 0.833 3.750 0%
realisasi 0.494 0.242 0.391 0.212 0.056 0.266 0.254 0.623 0.175 0.143 0.127 0.310 0.127 0.535 0.298 0.602

TOTAL PROGRESS/WEEK (Plan) 100.00 12.500 13.410 11.952 13.202 23.311 19.791 2.083 3.750
TOTAL PROGRESS/WEEK (Actual) 14.350 1.000 1.000 2.243 3.330 4.050 2.596 1.260 0.864 3.681 11.048 4.386 4.538 1.181 3.230 3.849 2.092 6.295 3.241 1.390 2.126 3.464 2.929 4.513 4.283 3.440

COMMULATIVE PROGRESS/WEEK (Plan) - 12.500 25.910 37.862 51.064 74.376 94.167 96.250 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000
COMMULATIVE PROGRESS/WEEK (Actual) - 14.350 15.350 16.350 18.593 21.923 25.973 28.569 29.829 30.692 34.374 45.422 49.807 54.345 55.526 58.756 62.605 64.697 70.992 74.233 75.623 77.748 81.213 84.142 88.654 92.938 96.378

DEVIASI - 1.850 (10.560) (21.512) (32.471) (52.453) (68.194) (67.681) (70.171) (69.308) (65.626) (54.578) (50.193) (45.655) (44.474) (41.244) (37.395) (35.303) (29.008) (25.767) (24.377) (22.252) (18.787) (15.858) (11.346) (7.062) (3.622)

- 1 2 3 4 5 6 7 8 9 10 8 9 10 10 10 10 10 10 10 10

Surabaya, 07 Mei 2016


Approved by, Checked by, Prepared by,
PT. Semen Gresik PT. Aldaberta Indonesia PT. Bangun Karya Perkasa Jaya

Yudha Ananta Wijaya Suhatsyah Pramana Budiharjo


Staff of Head Rembang Project Fabrication Manager Project Manager
R/6664120/029

REMBANG CEMENT PLANT PROJECT


LAPORAN MINGGUAN FABRICATION
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 26
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 01-05-2016 s/d 07-05-2016
PROGRESS BY COST PROGRESS BY PHISIK
NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

1 PREPARATION ENGINEERING Ls 1.00 10.00 10.000 10.000 -


1.10 Shop Drawing Ls 1.00 10.00 10.000 10.000 - 100.00% 100.00% 0.00%

2 MATERIAL PROCUREMENT Ls 1.00 15.00 15.000 14.522 (0.478)


2.10 Purchase Order Ls 1.00 5.00 5.000 5.000 - 100.00% 100.00% 0.00%
2.20 Material Recheived Ls 1.00 10.00 10.000 9.522 (0.478) 100.00% 95.22% -4.78%

3 FABRICATION STEEL Kg 235,238.83 45.00 45.000 42.695 (2.305)


3.10 Coloumn & Post Kg 60,738.89 11.62 11.619 11.619 -
- Marking/ Cutting 2.32 2.324 2.324 - 100.00% 100.00% 0.00%
- Machinning/ Drilling 3.49 3.486 3.486 - 100.00% 100.00% 0.00%
- Welding 5.23 5.229 5.229 - 100.00% 100.00% 0.00%
- Finishing 0.58 0.581 0.581 - 100.00% 100.00% 0.00%

3.20 Balok Kg 93,728.01 17.93 17.930 17.930 -


- Marking/ Cutting 3.59 3.586 3.586 - 100.00% 100.00% 0.00%
- Machinning/ Drilling 5.38 5.379 5.379 - 100.00% 100.00% 0.00%
- Welding 8.07 8.068 8.068 - 100.00% 100.00% 0.00%
- Finishing 0.90 0.896 0.896 - 100.00% 100.00% 0.00%

3.30 Bracing Kg 35,951.69 6.88 6.877 5.976 (0.901)


- Marking/ Cutting 1.38 1.375 1.197 (0.179) 100.00% 87.02% -12.98%
- Machinning/ Drilling 2.06 2.063 1.795 (0.268) 100.00% 87.02% -12.98%
- Welding 3.09 3.095 2.693 (0.402) 100.00% 87.02% -12.98%
- Finishing 0.34 0.344 0.291 (0.053) 100.00% 84.59% -15.41%

3.40 Roofing Kg 22,326.44 4.27 4.271 3.867 (0.404)


- Marking/ Cutting 0.85 0.854 0.773 (0.081) 100.00% 90.54% -9.46%
- Machinning/ Drilling 1.28 1.281 1.160 (0.121) 100.00% 90.54% -9.46%
- Welding 1.92 1.922 1.740 (0.182) 100.00% 90.54% -9.46%
- Finishing 0.21 0.214 0.193 (0.020) 100.00% 90.54% -9.46%
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 26
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 01-05-2016 s/d 07-05-2016

PROGRESS BY COST PROGRESS BY PHISIK


NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

3.50 Platform Kg 8,596.11 1.64 1.644 1.235 (0.409)


- Marking/ Cutting 0.33 0.329 0.247 (0.082) 100.00% 75.12% -24.88%
- Machinning/ Drilling 0.49 0.493 0.371 (0.123) 100.00% 75.12% -24.88%
- Welding 0.74 0.740 0.556 (0.184) 100.00% 75.12% -24.88%
- Finishing 0.08 0.082 0.062 (0.020) 100.00% 75.12% -24.88%

3.60 Handrail Kg 1,979.62 0.38 0.379 - (0.379)


- Marking/ Cutting 0.08 0.076 - (0.076) 100.00% 0.00% -100.00%
- Machinning/ Drilling 0.11 0.114 - (0.114) 100.00% 0.00% -100.00%
- Welding 0.17 0.170 - (0.170) 100.00% 0.00% -100.00%
- Finishing 0.02 0.019 - (0.019) 100.00% 0.00% -100.00%
ARCHITECTURAL WORKS
3.70 Siding Kg 10,796.49 2.07 2.065 1.917 (0.148)
- Marking/ Cutting 0.41 0.413 0.383 (0.030) 100.00% 92.83% -7.17%
- Machinning/ Drilling 0.62 0.620 0.575 (0.044) 100.00% 92.83% -7.17%
- Welding 0.93 0.929 0.863 (0.067) 100.00% 92.83% -7.17%
- Finishing 0.10 0.103 0.096 (0.007) 100.00% 92.83% -7.17%

3.80 Stairway Kg 1,121.58 0.21 0.215 0.150 (0.065)


- Marking/ Cutting 0.04 0.043 0.030 (0.013) 100.00% 69.90% -30.10%
- Machinning/ Drilling 0.06 0.064 0.045 (0.019) 100.00% 69.90% -30.10%
- Welding 0.10 0.097 0.067 (0.029) 100.00% 69.90% -30.10%
- Finishing 0.01 0.011 0.007 (0.003) 100.00% 69.90% -30.10%

4 PRE ASSEMBLY Ls 1.00 5.00 5.000 4.861 (0.140) 100.00% 97.21% -2.79%

5 INSPECTION Ls 1.00 10.00 10.000 9.732 (0.268) 100.00% 97.32% -2.68%

6 PAINTING Ls 1.00 5.00 5.000 4.856 (0.144)


- Primer 1.25 1.250 1.214 (0.036) 100.00% 97.12% -2.88%
- Intermediet 1.25 1.250 1.214 (0.036) 100.00% 97.12% -2.88%
- Finishing 2.50 2.500 2.428 (0.072) 100.00% 97.12% -2.88%

7 PACKING Ls 1.00 5.00 5.000 4.856 (0.144) 100.00% 97.12% -2.88%


PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 26
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 01-05-2016 s/d 07-05-2016
PROGRESS BY COST PROGRESS BY PHISIK
NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

8 DELIVERY Ls 1.00 5.00 5.000 4.856 (0.144) 100.00% 97.12% -2.88%

JUMLAH 100.00 100.00 96.378 -3.622

Surabaya, 07 Mei 2016


Checked by, Approved by, Prepared by,
PT. Aldaberta Indonesia PT. Semen Gresik PT. Bangun Karya Perkasa Jaya

Suhatsyah Yudha Ananta Wijaya Pramana Budiharjo


Fabrication Manager Staff of Head Rembang Project Project Manager
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 26
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 01-05-2016 s/d 07-05-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

1 PREPARATION ENGINEERING 1.00 10.00 10.000 - 10.000


1.1 Shop Drawing 1.00 10.00 10.000 - 10.000

2 MATERIAL PROCUREMENT 1.00 15.00 14.372 0.150 14.522


2.1 Purchase Order 1.00 5.00 5.000 - 5.000
2.2 Material Recheived 1.00 10.00 9.372 0.150 9.522

3 FABRICATION STEEL 235,238.83 45.00 42.264 0.430 42.695


3.10 Coloumn & Post 60,738.89 11.62 11.619 - 11.619
- Marking/ Cutting 2.32 2.324 - 2.324
- Machinning/ Drilling 3.49 3.486 - 3.486
- Welding 5.23 5.229 - 5.229
- Finishing 0.58 0.581 - 0.581

3.20 Balok 93,728.01 17.93 17.930 - 17.930


- Marking/ Cutting 3.59 3.586 - 3.586
- Machinning/ Drilling 5.38 5.379 - 5.379
- Welding 8.07 8.068 - 8.068
- Finishing 0.90 0.896 - 0.896

3.30 Bracing 35,951.69 6.88 5.976 - 5.976


- Marking/ Cutting 1.38 1.197 - 1.197
- Machinning/ Drilling 2.06 1.795 - 1.795
- Welding 3.09 2.693 - 2.693
- Finishing 0.34 0.291 - 0.291

3.40 Roofing 22,326.44 4.27 3.437 0.430 3.867


- Marking/ Cutting 0.85 0.688 0.085 0.773
- Machinning/ Drilling 1.28 1.033 0.127 1.160
- Welding 1.92 1.549 0.191 1.740
- Finishing 0.21 0.166 0.027 0.193

3.50 Platform 8,596.11 1.64 1.235 - 1.235


- Marking/ Cutting 0.33 0.247 - 0.247
- Machinning/ Drilling 0.49 0.371 - 0.371
- Welding 0.74 0.556 - 0.556
- Finishing 0.08 0.062 - 0.062
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 26
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 01-05-2016 s/d 07-05-2016
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 26
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 01-05-2016 s/d 07-05-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

3.60 Handrail 1,979.62 0.38 - - -


- Marking/ Cutting 0.08 - - -
- Machinning/ Drilling 0.11 - - -
- Welding 0.17 - - -
- Finishing 0.02 - - -
ARCHITECTURAL WORKS
3.70 Siding 10,796.49 2.07 1.917 - 1.917
- Marking/ Cutting 0.41 0.383 - 0.383
- Machinning/ Drilling 0.62 0.575 - 0.575
- Welding 0.93 0.863 - 0.863
- Finishing 0.10 0.096 - 0.096

3.80 Stairway 1,121.58 0.21 0.150 - 0.150


- Marking/ Cutting 0.04 0.030 - 0.030
- Machinning/ Drilling 0.06 0.045 - 0.045
- Welding 0.10 0.067 - 0.067
- Finishing 0.01 0.007 - 0.007

4 PRE ASSEMBLY 1.00 5.00 4.378 0.483 4.861

5 INSPECTION 1.00 10.00 8.755 0.977 9.732

6 PAINTING 1.00 5.00 4.592 0.264 4.856


- Primer 1.25 1.167 0.048 1.214
- Intermediet 1.25 1.167 0.048 1.214
- Finishing 2.50 2.259 0.169 2.428

7 PACKING 1.00 5.00 4.323 0.533 4.856


PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 26
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 01-05-2016 s/d 07-05-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

8 DELIVERY 1.00 5.00 4.254 0.602 4.856

JUMLAH 100.00 92.938 3.440 96.378


Catatan :

Surabaya, 07 Mei 2016


Checked by, Approved by, Prepared by,
PT. Aldaberta Indonesia PT. Semen Gresik PT. Bangun Karya Perkasa Jaya

Suhatsyah Yudha Ananta Wijaya Pramana Budiharjo


Fabrication Manager Staff of Head Rembang Project Project Manager
MASTER SCHEDULE FABRICATION STEEL STRUCTURE

PROYEK : PT. SEMEN GRESIK


LOKASI :: CONCREATE,
REMBANG - JAWA
STEELTENGAH
STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING
PEKERJA

PERIODE PELAKSANAAN ( 75 Hari Kalender ) + ADDENDUM WAKTU ( 164 Hari Kalender )


INDEKS
Nopember Desember Januari Februari Maret April Mei skala
NO URAIAN PEKERJAAN Status Qty Sat %
Ket
% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
08-14 15-21 22-28 29-05 06-12 13-19 20-26 27-02 03-09 10-16 17-23 24-30 31-06 07-13 14-20 21-27 28-05 06-12 13-19 20-26 27-02 03-09 10-16 17-23 24-30 01-07 08-14 15-21 22-28 29-31

1 PREPARATION ENGINEERING 1.00 Ls 10.000 2.500 2.500 2.500 2.500 100%


2.000 1.000 1.000 1.000 1.000 1.000 0.250 0.100 0.100 0.250 0.250 0.215 0.048 0.102 0.230 0.190 0.200 0.180 0.070 0.007 0.808
Shop Drawing rencana 1.00 Ls 10.000 2.500 2.500 2.500 2.500
realisasi 2.000 1.000 1.000 1.000 1.000 1.000 0.250 0.100 0.100 0.250 0.250 0.215 0.048 0.102 0.230 0.190 0.200 0.180 0.070 0.007 0.808
2 MATERIAL PROCUREMENT 1.00 Ls 15.000 10.000 5.000
12.350 0.637 1.113 0.272 0.150 0.233
Porchase Order rencana 1.00 Ls 5.000 5.000
realisasi 5.000
Material Rechieved rencana 1.00 LS 10.000 5.000 5.000
realisasi 7.350 0.637 1.113 0.272 0.150 0.233
3 FABRICATION STEEL
STEEL STRUCTURE TRANSPORT PALLETIZER 235,238.83 Kg 45.000 5.910 8.202 8.202 13.311 9.374
PEKERJAAN STRUKTUR BAJA 1.243 2.330 3.050 2.346 0.347 0.764 2.558 6.547 2.936 2.703 0.361 2.126 2.757 0.130 0.671 2.137 0.308 1.019 1.959 2.024 2.427 1.523 0.430 0.901
Coloumn & Post rencana 60,738.89 Kg 11.619 2.324 2.324 2.324 2.324 2.324
realisasi 1.243 2.330 3.050 1.372 0.083 1.245 0.028 0.038 0.003 0.006 0.368 1.016 0.823 0.015
Balok rencana 93,728.01 Kg 17.930 3.586 3.586 3.586 3.586 3.586
realisasi 0.974 0.264 0.764 1.312 6.519 0.727 1.810 1.047 0.333 1.232 0.222 0.130 1.450 0.443 0.504 0.199
Bracing rencana 35,951.69 Kg 6.877 2.292 2.292 2.292
realisasi 0.578 0.417 0.361 0.976 1.185 0.130 0.414 0.315 0.044 0.457 1.100 0.901
Roofing rencana 22,326.44 Kg 4.271 2.135 2.135 50%
realisasi 0.396 0.476 0.104 0.216 0.218 0.590 0.039 0.427 0.141 0.355 0.475 0.430
Platform rencana 8,596.11 Kg 1.644 1.644
realisasi 1.235
Handrail rencana 1,979.62 Kg 0.379 0.189 0.189
realisasi
ARCHITECTURAL WORKS
Siding rencana 10,796.49 Kg 2.065 1.033 1.033
realisasi 1.023 0.210 0.684
Stairway rencana 1,121.58 Kg 0.215 0.107 0.107
realisasi 0.150
4 PRE ASSEMBLY rencana 1.00 Ls 5.000 2.500 2.500
realisasi 0.313 0.763 0.263 0.141 0.085 0.182 0.264 0.999 0.157 0.055 0.250 0.205 0.183 0.170 0.353 0.483 0.096
5 INSPECTION rencana 1.00 Ls 10.000 5.000 5.000
realisasi 0.500 1.500 0.435 0.430 0.240 0.316 0.714 1.924 0.236 0.260 0.433 0.333 0.390 0.339 0.705 0.977 0.182
6 PAINTING rencana 1.00 Ls 5.000 1.250 1.250 1.250 1.250
realisasi 0.237 1.000 0.054 0.239 0.323 0.477 0.152 0.286 0.114 0.178 0.139 0.169 0.340 0.077 0.509 0.298 0.264 0.101
7 PACKING rencana 1.00 Ls 5.000 1.250 1.250 1.250 1.250
realisasi 0.494 0.242 0.586 0.183 0.017 0.177 0.254 0.651 0.179 0.143 0.127 0.310 0.127 0.533 0.298 0.533 0.101
8 DELIVERY rencana 1.00 Ls 5.000 0.417 0.833 3.750 0%
realisasi 0.494 0.242 0.391 0.212 0.056 0.266 0.254 0.623 0.175 0.143 0.127 0.310 0.127 0.535 0.298 0.602 0.101

TOTAL PROGRESS/WEEK (Plan) 100.00 12.500 13.410 11.952 13.202 23.311 19.791 2.083 3.750
TOTAL PROGRESS/WEEK (Actual) 14.350 1.000 1.000 2.243 3.330 4.050 2.596 1.260 0.864 3.681 11.048 4.386 4.538 1.181 3.230 3.849 2.092 6.295 3.241 1.390 2.126 3.464 2.929 4.513 4.283 3.440 1.715

COMMULATIVE PROGRESS/WEEK (Plan) - 12.500 25.910 37.862 51.064 74.376 94.167 96.250 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000
COMMULATIVE PROGRESS/WEEK (Actual) - 14.350 15.350 16.350 18.593 21.923 25.973 28.569 29.829 30.692 34.374 45.422 49.807 54.345 55.526 58.756 62.605 64.697 70.992 74.233 75.623 77.748 81.213 84.142 88.654 92.938 96.378 98.092

DEVIASI - 1.850 (10.560) (21.512) (32.471) (52.453) (68.194) (67.681) (70.171) (69.308) (65.626) (54.578) (50.193) (45.655) (44.474) (41.244) (37.395) (35.303) (29.008) (25.767) (24.377) (22.252) (18.787) (15.858) (11.346) (7.062) (3.622) (1.908)

- 1 2 3 4 5 6 7 8 9 10 8 9 10 10 10 10 10 10 10 10

Surabaya, 14 Mei 2016


Approved by, Checked by, Prepared by,
PT. Semen Gresik PT. Aldaberta Indonesia PT. Bangun Karya Perkasa Jaya

Yudha Ananta Wijaya Suhatsyah Pramana Budiharjo


Staff of Head Rembang Project Fabrication Manager Project Manager
R/6664120/029

REMBANG CEMENT PLANT PROJECT


LAPORAN MINGGUAN FABRICATION
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 27
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 08-05-2016 s/d 14-05-2016
PROGRESS BY COST PROGRESS BY PHISIK
NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

1 PREPARATION ENGINEERING Ls 1.00 10.00 10.000 10.000 -


1.10 Shop Drawing Ls 1.00 10.00 10.000 10.000 - 100.00% 100.00% 0.00%

2 MATERIAL PROCUREMENT Ls 1.00 15.00 15.000 14.755 (0.245)


2.10 Purchase Order Ls 1.00 5.00 5.000 5.000 - 100.00% 100.00% 0.00%
2.20 Material Recheived Ls 1.00 10.00 10.000 9.755 (0.245) 100.00% 97.55% -2.45%

3 FABRICATION STEEL Kg 235,238.83 45.00 45.000 43.596 (1.404)


3.10 Coloumn & Post Kg 60,738.89 11.62 11.619 11.619 -
- Marking/ Cutting 2.32 2.324 2.324 - 100.00% 100.00% 0.00%
- Machinning/ Drilling 3.49 3.486 3.486 - 100.00% 100.00% 0.00%
- Welding 5.23 5.229 5.229 - 100.00% 100.00% 0.00%
- Finishing 0.58 0.581 0.581 - 100.00% 100.00% 0.00%

3.20 Balok Kg 93,728.01 17.93 17.930 17.930 -


- Marking/ Cutting 3.59 3.586 3.586 - 100.00% 100.00% 0.00%
- Machinning/ Drilling 5.38 5.379 5.379 - 100.00% 100.00% 0.00%
- Welding 8.07 8.068 8.068 - 100.00% 100.00% 0.00%
- Finishing 0.90 0.896 0.896 - 100.00% 100.00% 0.00%

3.30 Bracing Kg 35,951.69 6.88 6.877 6.877 -


- Marking/ Cutting 1.38 1.375 1.375 - 100.00% 100.00% 0.00%
- Machinning/ Drilling 2.06 2.063 2.063 - 100.00% 100.00% 0.00%
- Welding 3.09 3.095 3.095 - 100.00% 100.00% 0.00%
- Finishing 0.34 0.344 0.344 - 100.00% 100.00% 0.00%

3.40 Roofing Kg 22,326.44 4.27 4.271 3.867 (0.404)


- Marking/ Cutting 0.85 0.854 0.773 (0.081) 100.00% 90.54% -9.46%
- Machinning/ Drilling 1.28 1.281 1.160 (0.121) 100.00% 90.54% -9.46%
- Welding 1.92 1.922 1.740 (0.182) 100.00% 90.54% -9.46%
- Finishing 0.21 0.214 0.193 (0.020) 100.00% 90.54% -9.46%
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 27
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 08-05-2016 s/d 14-05-2016

PROGRESS BY COST PROGRESS BY PHISIK


NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

3.50 Platform Kg 8,596.11 1.64 1.644 1.235 (0.409)


- Marking/ Cutting 0.33 0.329 0.247 (0.082) 100.00% 75.12% -24.88%
- Machinning/ Drilling 0.49 0.493 0.371 (0.123) 100.00% 75.12% -24.88%
- Welding 0.74 0.740 0.556 (0.184) 100.00% 75.12% -24.88%
- Finishing 0.08 0.082 0.062 (0.020) 100.00% 75.12% -24.88%

3.60 Handrail Kg 1,979.62 0.38 0.379 - (0.379)


- Marking/ Cutting 0.08 0.076 - (0.076) 100.00% 0.00% -100.00%
- Machinning/ Drilling 0.11 0.114 - (0.114) 100.00% 0.00% -100.00%
- Welding 0.17 0.170 - (0.170) 100.00% 0.00% -100.00%
- Finishing 0.02 0.019 - (0.019) 100.00% 0.00% -100.00%
ARCHITECTURAL WORKS
3.70 Siding Kg 10,796.49 2.07 2.065 1.917 (0.148)
- Marking/ Cutting 0.41 0.413 0.383 (0.030) 100.00% 92.83% -7.17%
- Machinning/ Drilling 0.62 0.620 0.575 (0.044) 100.00% 92.83% -7.17%
- Welding 0.93 0.929 0.863 (0.067) 100.00% 92.83% -7.17%
- Finishing 0.10 0.103 0.096 (0.007) 100.00% 92.83% -7.17%

3.80 Stairway Kg 1,121.58 0.21 0.215 0.150 (0.065)


- Marking/ Cutting 0.04 0.043 0.030 (0.013) 100.00% 69.90% -30.10%
- Machinning/ Drilling 0.06 0.064 0.045 (0.019) 100.00% 69.90% -30.10%
- Welding 0.10 0.097 0.067 (0.029) 100.00% 69.90% -30.10%
- Finishing 0.01 0.011 0.007 (0.003) 100.00% 69.90% -30.10%

4 PRE ASSEMBLY Ls 1.00 5.00 5.000 4.957 (0.043) 100.00% 99.14% -0.86%

5 INSPECTION Ls 1.00 10.00 10.000 9.914 (0.086) 100.00% 99.14% -0.86%

6 PAINTING Ls 1.00 5.00 5.000 4.957 (0.043)


- Primer 1.25 1.250 1.239 (0.011) 100.00% 99.14% -0.86%
- Intermediet 1.25 1.250 1.239 (0.011) 100.00% 99.14% -0.86%
- Finishing 2.50 2.500 2.478 (0.022) 100.00% 99.14% -0.86%

7 PACKING Ls 1.00 5.00 5.000 4.957 (0.043) 100.00% 99.14% -0.86%


PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 27
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 08-05-2016 s/d 14-05-2016
PROGRESS BY COST PROGRESS BY PHISIK
NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

8 DELIVERY Ls 1.00 5.00 5.000 4.957 (0.043) 100.00% 99.14% -0.86%

JUMLAH 100.00 100.00 98.092 -1.908

Surabaya, 14 Mei 2016


Checked by, Approved by, Prepared by,
PT. Aldaberta Indonesia PT. Semen Gresik PT. Bangun Karya Perkasa Jaya

Suhatsyah Yudha Ananta Wijaya Pramana Budiharjo


Fabrication Manager Staff of Head Rembang Project Project Manager
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 27
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 08-05-2016 s/d 14-05-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

1 PREPARATION ENGINEERING 1.00 10.00 10.000 - 10.000


1.1 Shop Drawing 1.00 10.00 10.000 - 10.000

2 MATERIAL PROCUREMENT 1.00 15.00 14.522 0.233 14.755


2.1 Purchase Order 1.00 5.00 5.000 - 5.000
2.2 Material Recheived 1.00 10.00 9.522 0.233 9.755

3 FABRICATION STEEL 235,238.83 45.00 42.695 0.901 43.596


3.10 Coloumn & Post 60,738.89 11.62 11.619 - 11.619
- Marking/ Cutting 2.32 2.324 - 2.324
- Machinning/ Drilling 3.49 3.486 - 3.486
- Welding 5.23 5.229 - 5.229
- Finishing 0.58 0.581 - 0.581

3.20 Balok 93,728.01 17.93 17.930 - 17.930


- Marking/ Cutting 3.59 3.586 - 3.586
- Machinning/ Drilling 5.38 5.379 - 5.379
- Welding 8.07 8.068 - 8.068
- Finishing 0.90 0.896 - 0.896

3.30 Bracing 35,951.69 6.88 5.976 0.901 6.877


- Marking/ Cutting 1.38 1.197 0.179 1.375
- Machinning/ Drilling 2.06 1.795 0.268 2.063
- Welding 3.09 2.693 0.402 3.095
- Finishing 0.34 0.291 0.053 0.344

3.40 Roofing 22,326.44 4.27 3.867 - 3.867


- Marking/ Cutting 0.85 0.773 - 0.773
- Machinning/ Drilling 1.28 1.160 - 1.160
- Welding 1.92 1.740 - 1.740
- Finishing 0.21 0.193 - 0.193

3.50 Platform 8,596.11 1.64 1.235 - 1.235


- Marking/ Cutting 0.33 0.247 - 0.247
- Machinning/ Drilling 0.49 0.371 - 0.371
- Welding 0.74 0.556 - 0.556
- Finishing 0.08 0.062 - 0.062
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 27
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 08-05-2016 s/d 14-05-2016
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 27
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 08-05-2016 s/d 14-05-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

3.60 Handrail 1,979.62 0.38 - - -


- Marking/ Cutting 0.08 - - -
- Machinning/ Drilling 0.11 - - -
- Welding 0.17 - - -
- Finishing 0.02 - - -
ARCHITECTURAL WORKS
3.70 Siding 10,796.49 2.07 1.917 - 1.917
- Marking/ Cutting 0.41 0.383 - 0.383
- Machinning/ Drilling 0.62 0.575 - 0.575
- Welding 0.93 0.863 - 0.863
- Finishing 0.10 0.096 - 0.096

3.80 Stairway 1,121.58 0.21 0.150 - 0.150


- Marking/ Cutting 0.04 0.030 - 0.030
- Machinning/ Drilling 0.06 0.045 - 0.045
- Welding 0.10 0.067 - 0.067
- Finishing 0.01 0.007 - 0.007

4 PRE ASSEMBLY 1.00 5.00 4.861 0.096 4.957

5 INSPECTION 1.00 10.00 9.732 0.182 9.914

6 PAINTING 1.00 5.00 4.856 0.101 4.957


- Primer 1.25 1.214 0.025 1.239
- Intermediet 1.25 1.214 0.025 1.239
- Finishing 2.50 2.428 0.050 2.478

7 PACKING 1.00 5.00 4.856 0.101 4.957


PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 27
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 08-05-2016 s/d 14-05-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

8 DELIVERY 1.00 5.00 4.856 0.101 4.957

JUMLAH 100.00 96.378 1.715 98.092


Catatan :

Surabaya, 14 Mei 2016


Checked by, Approved by, Prepared by,
PT. Aldaberta Indonesia PT. Semen Gresik PT. Bangun Karya Perkasa Jaya

Suhatsyah Yudha Ananta Wijaya Pramana Budiharjo


Fabrication Manager Staff of Head Rembang Project Project Manager
MASTER SCHEDULE FABRICATION STEEL STRUCTURE

PROYEK : PT. SEMEN GRESIK


LOKASI :: CONCREATE,
REMBANG - JAWA
STEELTENGAH
STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING
PEKERJA

PERIODE PELAKSANAAN ( 75 Hari Kalender ) + ADDENDUM WAKTU ( 164 Hari Kalender )


INDEKS
Nopember Desember Januari Februari Maret April Mei skala
NO URAIAN PEKERJAAN Status Qty Sat %
Ket
% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
08-14 15-21 22-28 29-05 06-12 13-19 20-26 27-02 03-09 10-16 17-23 24-30 31-06 07-13 14-20 21-27 28-05 06-12 13-19 20-26 27-02 03-09 10-16 17-23 24-30 01-07 08-14 15-21 22-28 29-31

1 PREPARATION ENGINEERING 1.00 Ls 10.000 2.500 2.500 2.500 2.500 100%


2.000 1.000 1.000 1.000 1.000 1.000 0.250 0.100 0.100 0.250 0.250 0.215 0.048 0.102 0.230 0.190 0.200 0.180 0.070 0.007 0.808
Shop Drawing rencana 1.00 Ls 10.000 2.500 2.500 2.500 2.500
realisasi 2.000 1.000 1.000 1.000 1.000 1.000 0.250 0.100 0.100 0.250 0.250 0.215 0.048 0.102 0.230 0.190 0.200 0.180 0.070 0.007 0.808
2 MATERIAL PROCUREMENT 1.00 Ls 15.000 10.000 5.000
12.350 0.637 1.113 0.272 0.150 0.233 0.080
Porchase Order rencana 1.00 Ls 5.000 5.000
realisasi 5.000
Material Rechieved rencana 1.00 LS 10.000 5.000 5.000
realisasi 7.350 0.637 1.113 0.272 0.150 0.233 0.080
3 FABRICATION STEEL
STEEL STRUCTURE TRANSPORT PALLETIZER 235,238.83 Kg 45.000 5.910 8.202 8.202 13.311 9.374
PEKERJAAN STRUKTUR BAJA 1.243 2.330 3.050 2.346 0.347 0.764 2.558 6.547 2.936 2.703 0.361 2.126 2.757 0.130 0.671 2.137 0.308 1.019 1.959 2.024 2.427 1.523 0.430 0.901 0.241
Coloumn & Post rencana 60,738.89 Kg 11.619 2.324 2.324 2.324 2.324 2.324 -
realisasi 1.243 2.330 3.050 1.372 0.083 1.245 0.028 0.038 0.003 0.006 0.368 1.016 0.823 0.015
Balok rencana 93,728.01 Kg 17.930 3.586 3.586 3.586 3.586 3.586
realisasi 0.974 0.264 0.764 1.312 6.519 0.727 1.810 1.047 0.333 1.232 0.222 0.130 1.450 0.443 0.504 0.199
Bracing rencana 35,951.69 Kg 6.877 2.292 2.292 2.292
realisasi 0.578 0.417 0.361 0.976 1.185 0.130 0.414 0.315 0.044 0.457 1.100 0.901
Roofing rencana 22,326.44 Kg 4.271 2.135 2.135 50%
realisasi 0.396 0.476 0.104 0.216 0.218 0.590 0.039 0.427 0.141 0.355 0.475 0.430 0.093
Platform rencana 8,596.11 Kg 1.644 1.644
realisasi 1.235
Handrail rencana 1,979.62 Kg 0.379 0.189 0.189
realisasi
ARCHITECTURAL WORKS
Siding rencana 10,796.49 Kg 2.065 1.033 1.033
realisasi 1.023 0.210 0.684 0.148
Stairway rencana 1,121.58 Kg 0.215 0.107 0.107
realisasi 0.150
4 PRE ASSEMBLY rencana 1.00 Ls 5.000 2.500 2.500
realisasi 0.313 0.763 0.263 0.141 0.085 0.182 0.264 0.999 0.157 0.055 0.250 0.205 0.183 0.170 0.353 0.483 0.096 0.003
5 INSPECTION rencana 1.00 Ls 10.000 5.000 5.000
realisasi 0.500 1.500 0.435 0.430 0.240 0.316 0.714 1.924 0.236 0.260 0.433 0.333 0.390 0.339 0.705 0.977 0.182 0.006
6 PAINTING rencana 1.00 Ls 5.000 1.250 1.250 1.250 1.250
realisasi 0.237 1.000 0.054 0.239 0.323 0.477 0.152 0.286 0.114 0.178 0.139 0.169 0.340 0.077 0.509 0.298 0.264 0.101 0.003
7 PACKING rencana 1.00 Ls 5.000 1.250 1.250 1.250 1.250
realisasi 0.494 0.242 0.586 0.183 0.017 0.177 0.254 0.651 0.179 0.143 0.127 0.310 0.127 0.533 0.298 0.533 0.101 0.003
8 DELIVERY rencana 1.00 Ls 5.000 0.417 0.833 3.750 0%
realisasi 0.494 0.242 0.391 0.212 0.056 0.266 0.254 0.623 0.175 0.143 0.127 0.310 0.127 0.535 0.298 0.602 0.101 0.003

TOTAL PROGRESS/WEEK (Plan) 100.00 12.500 13.410 11.952 13.202 23.311 19.791 2.083 3.750
TOTAL PROGRESS/WEEK (Actual) 14.350 1.000 1.000 2.243 3.330 4.050 2.596 1.260 0.864 3.681 11.048 4.386 4.538 1.181 3.230 3.849 2.092 6.295 3.241 1.390 2.126 3.464 2.929 4.513 4.283 3.440 1.715 0.339

COMMULATIVE PROGRESS/WEEK (Plan) - 12.500 25.910 37.862 51.064 74.376 94.167 96.250 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000
COMMULATIVE PROGRESS/WEEK (Actual) - 14.350 15.350 16.350 18.593 21.923 25.973 28.569 29.829 30.692 34.374 45.422 49.807 54.345 55.526 58.756 62.605 64.697 70.992 74.233 75.623 77.748 81.213 84.142 88.654 92.938 96.378 98.092 98.432

DEVIASI - 1.850 (10.560) (21.512) (32.471) (52.453) (68.194) (67.681) (70.171) (69.308) (65.626) (54.578) (50.193) (45.655) (44.474) (41.244) (37.395) (35.303) (29.008) (25.767) (24.377) (22.252) (18.787) (15.858) (11.346) (7.062) (3.622) (1.908) (1.568)

- 1 2 3 4 5 6 7 8 9 10 8 9 10 10 10 10 10 10 10 10

Surabaya, 21 Mei 2016


Approved by, Checked by, Prepared by,
PT. Semen Gresik PT. Aldaberta Indonesia PT. Bangun Karya Perkasa Jaya

Yudha Ananta Wijaya Suhatsyah Pramana Budiharjo


Staff of Head Rembang Project Fabrication Manager Project Manager
R/6664120/029

REMBANG CEMENT PLANT PROJECT


LAPORAN MINGGUAN FABRICATION
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 28
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 15-05-2016 s/d 21-05-2016
PROGRESS BY COST PROGRESS BY PHISIK
NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

1 PREPARATION ENGINEERING Ls 1.00 10.00 10.000 10.000 -


1.10 Shop Drawing Ls 1.00 10.00 10.000 10.000 - 100.00% 100.00% 0.00%

2 MATERIAL PROCUREMENT Ls 1.00 15.00 15.000 14.835 (0.165)


2.10 Purchase Order Ls 1.00 5.00 5.000 5.000 - 100.00% 100.00% 0.00%
2.20 Material Recheived Ls 1.00 10.00 10.000 9.835 (0.165) 100.00% 98.35% -1.65%

3 FABRICATION STEEL Kg 235,238.83 45.00 45.000 43.837 (1.163)


3.10 Coloumn & Post Kg 60,738.89 11.62 11.619 11.619 -
- Marking/ Cutting 2.32 2.324 2.324 - 100.00% 100.00% 0.00%
- Machinning/ Drilling 3.49 3.486 3.486 - 100.00% 100.00% 0.00%
- Welding 5.23 5.229 5.229 - 100.00% 100.00% 0.00%
- Finishing 0.58 0.581 0.581 - 100.00% 100.00% 0.00%

3.20 Balok Kg 93,728.01 17.93 17.930 17.930 -


- Marking/ Cutting 3.59 3.586 3.586 - 100.00% 100.00% 0.00%
- Machinning/ Drilling 5.38 5.379 5.379 - 100.00% 100.00% 0.00%
- Welding 8.07 8.068 8.068 - 100.00% 100.00% 0.00%
- Finishing 0.90 0.896 0.896 - 100.00% 100.00% 0.00%

3.30 Bracing Kg 35,951.69 6.88 6.877 6.877 -


- Marking/ Cutting 1.38 1.375 1.375 - 100.00% 100.00% 0.00%
- Machinning/ Drilling 2.06 2.063 2.063 - 100.00% 100.00% 0.00%
- Welding 3.09 3.095 3.095 - 100.00% 100.00% 0.00%
- Finishing 0.34 0.344 0.344 - 100.00% 100.00% 0.00%

3.40 Roofing Kg 22,326.44 4.27 4.271 3.960 (0.311)


- Marking/ Cutting 0.85 0.854 0.792 (0.062) 100.00% 92.72% -7.28%
- Machinning/ Drilling 1.28 1.281 1.188 (0.093) 100.00% 92.72% -7.28%
- Welding 1.92 1.922 1.782 (0.140) 100.00% 92.72% -7.28%
- Finishing 0.21 0.214 0.198 (0.016) 100.00% 92.72% -7.28%
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 28
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 15-05-2016 s/d 21-05-2016

PROGRESS BY COST PROGRESS BY PHISIK


NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

3.50 Platform Kg 8,596.11 1.64 1.644 1.235 (0.409)


- Marking/ Cutting 0.33 0.329 0.247 (0.082) 100.00% 75.12% -24.88%
- Machinning/ Drilling 0.49 0.493 0.371 (0.123) 100.00% 75.12% -24.88%
- Welding 0.74 0.740 0.556 (0.184) 100.00% 75.12% -24.88%
- Finishing 0.08 0.082 0.062 (0.020) 100.00% 75.12% -24.88%

3.60 Handrail Kg 1,979.62 0.38 0.379 - (0.379)


- Marking/ Cutting 0.08 0.076 - (0.076) 100.00% 0.00% -100.00%
- Machinning/ Drilling 0.11 0.114 - (0.114) 100.00% 0.00% -100.00%
- Welding 0.17 0.170 - (0.170) 100.00% 0.00% -100.00%
- Finishing 0.02 0.019 - (0.019) 100.00% 0.00% -100.00%
ARCHITECTURAL WORKS
3.70 Siding Kg 10,796.49 2.07 2.065 2.065 -
- Marking/ Cutting 0.41 0.413 0.413 - 100.00% 100.00% 0.00%
- Machinning/ Drilling 0.62 0.620 0.620 - 100.00% 100.00% 0.00%
- Welding 0.93 0.929 0.929 - 100.00% 100.00% 0.00%
- Finishing 0.10 0.103 0.103 - 100.00% 100.00% 0.00%

3.80 Stairway Kg 1,121.58 0.21 0.215 0.150 (0.065)


- Marking/ Cutting 0.04 0.043 0.030 (0.013) 100.00% 69.90% -30.10%
- Machinning/ Drilling 0.06 0.064 0.045 (0.019) 100.00% 69.90% -30.10%
- Welding 0.10 0.097 0.067 (0.029) 100.00% 69.90% -30.10%
- Finishing 0.01 0.011 0.007 (0.003) 100.00% 69.90% -30.10%

4 PRE ASSEMBLY Ls 1.00 5.00 5.000 4.960 (0.040) 100.00% 99.20% -0.80%

5 INSPECTION Ls 1.00 10.00 10.000 9.920 (0.080) 100.00% 99.20% -0.80%

6 PAINTING Ls 1.00 5.00 5.000 4.960 (0.040)


- Primer 1.25 1.250 1.240 (0.010) 100.00% 99.20% -0.80%
- Intermediet 1.25 1.250 1.240 (0.010) 100.00% 99.20% -0.80%
- Finishing 2.50 2.500 2.480 (0.020) 100.00% 99.20% -0.80%

7 PACKING Ls 1.00 5.00 5.000 4.960 (0.040) 100.00% 99.20% -0.80%


PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 28
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 15-05-2016 s/d 21-05-2016
PROGRESS BY COST PROGRESS BY PHISIK
NO. JENIS PEKERJAAN SATUAN QTY INDEK (%) UP TO THIS WEEK UP TO THIS WEEK KETERANGAN
RENCANA AKTUAL DEVIASI RENCANA AKTUAL DEVIASI

8 DELIVERY Ls 1.00 5.00 5.000 4.960 (0.040) 100.00% 99.20% -0.80%

JUMLAH 100.00 100.00 98.432 -1.568

Surabaya, 21 Mei 2016


Checked by, Approved by, Prepared by,
PT. Aldaberta Indonesia PT. Semen Gresik PT. Bangun Karya Perkasa Jaya

Suhatsyah Yudha Ananta Wijaya Pramana Budiharjo


Fabrication Manager Staff of Head Rembang Project Project Manager
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 28
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 15-05-2016 s/d 21-05-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

1 PREPARATION ENGINEERING 1.00 10.00 10.000 - 10.000


1.1 Shop Drawing 1.00 10.00 10.000 - 10.000

2 MATERIAL PROCUREMENT 1.00 15.00 14.755 0.080 14.835


2.1 Purchase Order 1.00 5.00 5.000 - 5.000
2.2 Material Recheived 1.00 10.00 9.755 0.080 9.835

3 FABRICATION STEEL 235,238.83 45.00 43.596 0.241 43.837


3.10 Coloumn & Post 60,738.89 11.62 11.619 - 11.619
- Marking/ Cutting 2.32 2.324 - 2.324
- Machinning/ Drilling 3.49 3.486 - 3.486
- Welding 5.23 5.229 - 5.229
- Finishing 0.58 0.581 - 0.581

3.20 Balok 93,728.01 17.93 17.930 - 17.930


- Marking/ Cutting 3.59 3.586 - 3.586
- Machinning/ Drilling 5.38 5.379 - 5.379
- Welding 8.07 8.068 - 8.068
- Finishing 0.90 0.896 - 0.896

3.30 Bracing 35,951.69 6.88 6.877 - 6.877


- Marking/ Cutting 1.38 1.375 - 1.375
- Machinning/ Drilling 2.06 2.063 - 2.063
- Welding 3.09 3.095 - 3.095
- Finishing 0.34 0.344 - 0.344

3.40 Roofing 22,326.44 4.27 3.867 0.093 3.960


- Marking/ Cutting 0.85 0.773 0.019 0.792
- Machinning/ Drilling 1.28 1.160 0.028 1.188
- Welding 1.92 1.740 0.042 1.782
- Finishing 0.21 0.193 0.005 0.198

3.50 Platform 8,596.11 1.64 1.235 - 1.235


- Marking/ Cutting 0.33 0.247 - 0.247
- Machinning/ Drilling 0.49 0.371 - 0.371
- Welding 0.74 0.556 - 0.556
- Finishing 0.08 0.062 - 0.062
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 28
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 15-05-2016 s/d 21-05-2016
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 28
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 15-05-2016 s/d 21-05-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

3.60 Handrail 1,979.62 0.38 - - -


- Marking/ Cutting 0.08 - - -
- Machinning/ Drilling 0.11 - - -
- Welding 0.17 - - -
- Finishing 0.02 - - -
ARCHITECTURAL WORKS
3.70 Siding 10,796.49 2.07 1.917 0.148 2.065
- Marking/ Cutting 0.41 0.383 0.030 0.413
- Machinning/ Drilling 0.62 0.575 0.044 0.620
- Welding 0.93 0.863 0.067 0.929
- Finishing 0.10 0.096 0.007 0.103

3.80 Stairway 1,121.58 0.21 0.150 - 0.150


- Marking/ Cutting 0.04 0.030 - 0.030
- Machinning/ Drilling 0.06 0.045 - 0.045
- Welding 0.10 0.067 - 0.067
- Finishing 0.01 0.007 - 0.007

4 PRE ASSEMBLY 1.00 5.00 4.957 0.003 4.960

5 INSPECTION 1.00 10.00 9.914 0.006 9.920

6 PAINTING 1.00 5.00 4.957 0.003 4.960


- Primer 1.25 1.239 0.001 1.240
- Intermediet 1.25 1.239 0.001 1.240
- Finishing 2.50 2.478 0.002 2.480

7 PACKING 1.00 5.00 4.957 0.003 4.960


PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT FROM PACKER TO PALLETIZING FABRICATION
NO. PERINTAH KERJA : 66000271 MINGGU KE : 28
KONTRAKTOR : PT. Bangun Karya Perkasa Jaya TANGGAL : 15-05-2016 s/d 21-05-2016
PROGRESS PEKERJAAN
NO JENIS PEKERJAAN QTY INDEK (%) KETERANGAN
LAST WEEK THIS WEEK UP TO THIS WEEK

8 DELIVERY 1.00 5.00 4.957 0.003 4.960

JUMLAH 100.00 98.092 0.339 98.432


Catatan :

Surabaya, 21 Mei 2016


Checked by, Approved by, Prepared by,
PT. Aldaberta Indonesia PT. Semen Gresik PT. Bangun Karya Perkasa Jaya

Suhatsyah Yudha Ananta Wijaya Pramana Budiharjo


Fabrication Manager Staff of Head Rembang Project Project Manager
R/6664120/028

REMBANG CEMENT PLANT PROJECT


REMBANG - CENTRAL JAVA

LAPORAN MINGGUAN FABRICATION

N0. PERINTAH KERJA : 66000271

PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT
FROM PACKER TO PALLETIZING

PERIODE : MASA PELAKSANAAN :


MINGGU KE : 26 ( 04-11-2015 s/d 18-01-2016 )
( 01-05-2016 s/d 07-05-2016 ) Add. I : ( 19-01-2016 s/d 31-03-2016 )
Add. II : ( 01-04-20165 s/d 30-04-2016 )
Add. III : ( 01-05-20165 s/d 31-05-2016 )

PLAN PROGRESS : 100.000 % MASA PELAKSANAAN : 206 hari


ACTUAL PROGRESS : 96.378 % WAKTU TERPAKAI : 182 hari
OVER/ ( UNDER ) : (3.622) % SISA WAKTU : 24 hari

Steel
Surabaya, 07 Mei 2016
R/6664120/028

REMBANG CEMENT PLANT PROJECT


REMBANG - CENTRAL JAVA

LAPORAN MINGGUAN FABRICATION

N0. PERINTAH KERJA : 66000271

PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT
FROM PACKER TO PALLETIZING

PERIODE : MASA PELAKSANAAN :


MINGGU KE : 27 ( 04-11-2015 s/d 18-01-2016 )
( 08-05-2016 s/d 14-05-2016 ) Add. I : ( 19-01-2016 s/d 31-03-2016 )
Add. II : ( 01-04-20165 s/d 30-04-2016 )
Add. III : ( 01-05-20165 s/d 31-05-2016 )

PLAN PROGRESS : 100.000 % MASA PELAKSANAAN : 206 hari


ACTUAL PROGRESS : 98.092 % WAKTU TERPAKAI : 189 hari
OVER/ ( UNDER ) : (1.908) % SISA WAKTU : 17 hari

Steel
Surabaya, 14 Mei 2016
R/6664120/028

REMBANG CEMENT PLANT PROJECT


REMBANG - CENTRAL JAVA

LAPORAN MINGGUAN FABRICATION

N0. PERINTAH KERJA : 66000271

PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT
FROM PACKER TO PALLETIZING

PERIODE : MASA PELAKSANAAN :


MINGGU KE : 28 ( 04-11-2015 s/d 18-01-2016 )
( 15-05-2016 s/d 21-05-2016 ) Add. I : ( 19-01-2016 s/d 31-03-2016 )
Add. II : ( 01-04-20165 s/d 30-04-2016 )
Add. III : ( 01-05-20165 s/d 31-05-2016 )

PLAN PROGRESS : 100.000 % MASA PELAKSANAAN : 206 hari


ACTUAL PROGRESS : 98.432 % WAKTU TERPAKAI : 196 hari
OVER/ ( UNDER ) : (1.568) % SISA WAKTU : 10 hari

Steel
Surabaya, 21 Mei 2016

You might also like