4 PRE ASSEMBLY Ls 1.00 5.00 #REF! 4.378 #REF! #REF! 87.55% #REF!
TOTAL PROGRESS/WEEK (Plan) 100.00 12.500 13.410 11.952 13.202 23.311 19.791 2.083 3.750
TOTAL PROGRESS/WEEK (Actual) 14.350 1.000 1.000 2.243 3.330 4.050 2.596 1.260 0.864 3.681 11.048 4.386 4.538 1.181 3.230 3.849 2.092 6.295 3.241 1.390 2.126 3.464 2.929 4.513 4.283 3.440
COMMULATIVE PROGRESS/WEEK (Plan) - 12.500 25.910 37.862 51.064 74.376 94.167 96.250 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000
COMMULATIVE PROGRESS/WEEK (Actual) - 14.350 15.350 16.350 18.593 21.923 25.973 28.569 29.829 30.692 34.374 45.422 49.807 54.345 55.526 58.756 62.605 64.697 70.992 74.233 75.623 77.748 81.213 84.142 88.654 92.938 96.378
DEVIASI - 1.850 (10.560) (21.512) (32.471) (52.453) (68.194) (67.681) (70.171) (69.308) (65.626) (54.578) (50.193) (45.655) (44.474) (41.244) (37.395) (35.303) (29.008) (25.767) (24.377) (22.252) (18.787) (15.858) (11.346) (7.062) (3.622)
- 1 2 3 4 5 6 7 8 9 10 8 9 10 10 10 10 10 10 10 10
4 PRE ASSEMBLY Ls 1.00 5.00 5.000 4.861 (0.140) 100.00% 97.21% -2.79%
TOTAL PROGRESS/WEEK (Plan) 100.00 12.500 13.410 11.952 13.202 23.311 19.791 2.083 3.750
TOTAL PROGRESS/WEEK (Actual) 14.350 1.000 1.000 2.243 3.330 4.050 2.596 1.260 0.864 3.681 11.048 4.386 4.538 1.181 3.230 3.849 2.092 6.295 3.241 1.390 2.126 3.464 2.929 4.513 4.283 3.440 1.715
COMMULATIVE PROGRESS/WEEK (Plan) - 12.500 25.910 37.862 51.064 74.376 94.167 96.250 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000
COMMULATIVE PROGRESS/WEEK (Actual) - 14.350 15.350 16.350 18.593 21.923 25.973 28.569 29.829 30.692 34.374 45.422 49.807 54.345 55.526 58.756 62.605 64.697 70.992 74.233 75.623 77.748 81.213 84.142 88.654 92.938 96.378 98.092
DEVIASI - 1.850 (10.560) (21.512) (32.471) (52.453) (68.194) (67.681) (70.171) (69.308) (65.626) (54.578) (50.193) (45.655) (44.474) (41.244) (37.395) (35.303) (29.008) (25.767) (24.377) (22.252) (18.787) (15.858) (11.346) (7.062) (3.622) (1.908)
- 1 2 3 4 5 6 7 8 9 10 8 9 10 10 10 10 10 10 10 10
4 PRE ASSEMBLY Ls 1.00 5.00 5.000 4.957 (0.043) 100.00% 99.14% -0.86%
TOTAL PROGRESS/WEEK (Plan) 100.00 12.500 13.410 11.952 13.202 23.311 19.791 2.083 3.750
TOTAL PROGRESS/WEEK (Actual) 14.350 1.000 1.000 2.243 3.330 4.050 2.596 1.260 0.864 3.681 11.048 4.386 4.538 1.181 3.230 3.849 2.092 6.295 3.241 1.390 2.126 3.464 2.929 4.513 4.283 3.440 1.715 0.339
COMMULATIVE PROGRESS/WEEK (Plan) - 12.500 25.910 37.862 51.064 74.376 94.167 96.250 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000 100.000
COMMULATIVE PROGRESS/WEEK (Actual) - 14.350 15.350 16.350 18.593 21.923 25.973 28.569 29.829 30.692 34.374 45.422 49.807 54.345 55.526 58.756 62.605 64.697 70.992 74.233 75.623 77.748 81.213 84.142 88.654 92.938 96.378 98.092 98.432
DEVIASI - 1.850 (10.560) (21.512) (32.471) (52.453) (68.194) (67.681) (70.171) (69.308) (65.626) (54.578) (50.193) (45.655) (44.474) (41.244) (37.395) (35.303) (29.008) (25.767) (24.377) (22.252) (18.787) (15.858) (11.346) (7.062) (3.622) (1.908) (1.568)
- 1 2 3 4 5 6 7 8 9 10 8 9 10 10 10 10 10 10 10 10
4 PRE ASSEMBLY Ls 1.00 5.00 5.000 4.960 (0.040) 100.00% 99.20% -0.80%
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT
FROM PACKER TO PALLETIZING
Steel
Surabaya, 07 Mei 2016
R/6664120/028
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT
FROM PACKER TO PALLETIZING
Steel
Surabaya, 14 Mei 2016
R/6664120/028
PEKERJAAN : CONCREATE, STEEL STRUCTURE FABRICATION, ERECTION & ARCHITECTURAL WORK AREA TRANSPORT
FROM PACKER TO PALLETIZING
Steel
Surabaya, 21 Mei 2016