Professional Documents
Culture Documents
2013-1 Thu Dufournet
2013-1 Thu Dufournet
Denis Dufournet
Chair CIGRE WG A3.28 & IEEE WG C37.011, Fellow IEEE
San Antonio (USA), 19/09/2013
GRID
Content (1/3)
Page
• Introduction & General Considerations 4 &13
• Capacitive Current Switching TRV 29
• Types of Fault TRVs 45
• TRV Modification 63
• Terminal Fault TRV 72
− First-pole-to-clear factor 73
− TRV rating & testing 88
− TRV & arcing times 120
− TRV for generator circuit breakers 138
• Short-Line Fault TRV 148
• ITRV (Initial TRV) 187
Page
• Out-of-Phase TRV 194
• Three-Phase Line Faults TRV 199
• Shunt Reactor Switching TRV 217
• Transformer Limited Fault TRV 229
• Series Reactor Limited Fault TRV 264
• Influence of Series Capacitors on TRV 271
• Harmonization of TRVs in IEC & IEEE 282
Page
• Annexes 306
− A: First-pole-to-clear factor 307
− B: Second-pole-to-clear factor 316
− C: Complement on line faults 321
− D: Equivalent circuit for 3-phase to ground fault 326
− E: Test circuit for kpp = 1.3 329
− F: Bibliography 333
GRID
Importance of TRV
GRID
General Considerations
A B
Xs CURRENT
Recovery
voltage
U
• During the interruption process, the arc loses rapidly its conductivity as
the instantaneous current approaches zero.
TRV (kV)
I (A) Gas circuit breakers:
Within a few microseconds
after current zero, arc
TRV resistance (RARC) rises to
one million ohm in a few
microseconds and current
stops flowing in the circuit.
Interruption when current passes through zero
• During the first microseconds after current zero, the TRV withstand is
function of the energy balance in the arc: it is the thermal phase of
interruption.
TRV HV Circuit Breakers P 17
General Considerations
CURRENT
Supply voltage
TRANSIENT RECOVERY
Current and TRV waveforms during interruption of inductive current
VOLTAGE
1,5
CAPACITIVE
CIRCUIT
1
0,5
0
0 0,005 0,01 0,015 0,02 0,025 0,03 0,035
-0,5
-1
RESISTIVE
CIRCUIT
-1,5
INDUCTIVE CIRCUIT
(with stray capacitance)
-2
• Combination of the former basic cases are possible, for example the
TRV for mainly active load current breaking is a combination of TRVs
associated with inductive and resistive circuits.
• They are specified for high-voltage switches only as circuit-breakers
are able to interrupt with more severe TRVs (in inductive circuits).
L
C
R
Z
N Lines, each with surge R
impedance
N
l
Z L: source inductance, lines excepted
c
C: source capacitance, lines excepted
(Vcb)
L
C
R
TRV (p.u.)
2
0.5
R / (L / C) = 10
1,8
4
1,6
2
1,4
1
1,2
0.75
1
0,8
0,6
0,5
0,4
0,3
0,2
0
t/RC
0 1 2 3 4 5 6 7 8 9
300
200
reflected and refracted when
100 REFLECTED WAVE reaching an open circuit or a
0
0 100 200 300 400 500 600 700 800 900 1000
discontinuity.
TIME (µs)
• The most severe TRV occurs across the first pole to clear of a circuit
breaker when it interrupts a three-phase terminal fault with a
symmetrical current and when the system voltage is maximum (see
section on Terminal fault).
GRID
Capacitive Current Switching
U (p.u.)
2,5
2
Recovery voltage
1,5
1
current
interruption
0,5
Supply voltage
0
Example of a single
-0,5
Load voltage phase interruption at
-1 50 Hz
-1,5
0,005 0,01 0,015 0,02 0,025 0,03 0,035
Time (s)
Supply-side voltage
Load-side voltage
Recovery voltage
Current
U (p.u.)
Overvoltage 3 p.u.
3,5
2,5
2
2 p.u.
Recovery voltage
1,5 instant of current
interruption
1
0,5
2 p.u.
0
-0,5
-1
Reignition Restrike
-1,5
no overvoltage overvoltage
0,005 0,01 0,015 0,02 0,025
Time (s)
I 1 E E
UA
C C 1 1 Ls C 2
Ls
C
TRV HV Circuit Breakers P 37
Three-Phase Capacitive Current Breaking
Capacitor Bank with Isolated Neutral
CR
A B
ER
CS
ES EN
CT N
ET
VB
1,5
1,0
2.5 p.u.
0,5
VN
0,0
-0 ,0 05 -0,003 -0,00 1 0,00 1 0 ,0 03 0,00 5 0,0 07 0 ,0 09 0,01 1 0,0 13 0 ,0 15
-0,5
-1,0
VA
-1,5
Due to neutral voltage shift (VN) after interruption by the first pole, the peak
recovery voltage is 2.5 p.u. instead of 2 p.u. for single-phase interruption.
RV on first-
pole-to-clear
Similar case as
Same case as overhead lines
capacitor bank
with grounded C1/C0=3 Ur ≤ 52kV
neutral
C1/C0=2 Ur > 52kV
Ur
• Test voltage for single-phase tests: U test k c
3
• Voltage factors in case of effectively grounded neutral systems
− Line-charging current kc = 1.2
− Cable-charging current kc = 1.0 (screened cable)
= 1.4/ 1.2 (belted cable ≤52kV / >52kV)
− Capacitor-bank current kc = 1.0/1.4 grounded/isolated neutral
• Voltage factors in case of non-effectively grounded neutral systems
− Line-charging current kc = 1.4
− Cable-charging current kc = 1.4
− Capacitor-bank current kc = 1.4
• Voltage factors in the case of fault on another line(s)
− Effectively grounded neutral systems kc = 1.4
− Non-effectively grounded neutral systems kc = 1.7
GRID
Types of Fault TRVs / Reminder
L
C
R
Z
N Lines, each with surge R
impedance
N
l
Z L: source inductance, lines excepted
c
C: source capacitance, lines excepted
when L0 3 L1
9 L1
Leq 1.3 L1
7
• Equivalent capacitance see Annex D: 3-phase
network representation
2 (C1 C0 ) C0 2 C1
Ceq C0
3 3
3 Z 0Z1
Z eq
N Z1 2Z 0
Z0 ZS 2 ZM
Z1 Z S Z M 3 Z0
Z 0 Z1 Z1 2 Z 0
ZM
3 see Annex D: 3-phase network
representation
ZS: self value
See section on SLF for the calculation of line
ZM: mutual value surge impedance
t
ucb u1 (1 e (cosh t sinh t ))
with
ucb is the voltage across the open circuit-breaker
u1 = 2 I ω Leq
= 2 f = 377 rad/s at 60 Hz and 314 rad/s at 50 Hz
I is the short-circuit current (rms)
1
=
2 Z eq Ceq
= 2 1 /( Leq Ceq )
ucb u1 (1 e t / )
where
Leq
Z eq
• RRRV
ducb dI
2 I ω Z eq Z eq
dt dt
− Equivalent capacitance
2 C1 C1
Ceq
3 1.5
with C1= C0
900
800
SYSTEM TRV
700 TRV CAPABILITY FOR A
STANDARD BREAKER
600
500
400
300
200
0
0 100 200 300 400 500 600 700 800 900 1000
TIME (µs)
Za Zb
line
Circuit breaker
TRV HV Circuit Breakers P 62
TRV Modification
GRID
Current Asymmetry and Circuit
Breaker Influence on TRV
SUPPLY VOLTAGE
CURRENT
TIME
• Correction factors of the TRV peak and rate of rise of recovery voltage
(RRRV) when interrupting asymmetrical currents are given in
X /R
with D degree of asymmetry (p.u.)
-D interruption after a major loop of current
+D interruption after a minor loop of current
X/R short-circuit reactance divided by resistance
• When time to peak TRV is relatively short (< 500 µs), the correction
factor for the TRV peak is also F1.
• Correction factor for the TRV peak in case of long time to peak TRV
(> 500 µs) :
GRID
Terminal fault TRV
First pole to clear factor
CURRENT
TRANSIENT RECOVERY
RECOVERY
VOLTAGE Current - TRV - Recovery Voltage VOLTAGE
Recovery Voltage
kpp
Ur
3
ES
ET
• When tests are performed on one pole (single-phase tests), the supply
voltage must be multiplied by kpp in order to have the recovery voltage
that would be met on the first pole during a three-phase interruption.
• The first–pole–to-clear factor (kpp) is a function of the grounding
arrangements of the system and of the type of fault.
Note: for UHV systems (rated voltages 1100 & 1200kV) the ratio X0/X1
is close to 2 and the standardized value of kpp is 1.2.
• For three-phase ungrounded faults, kpp is 1.5.
di
3-phase L eB 2 L eC 0
dt
ungrounded fault L di e eC
L B
in effectively- i dt 2
grounded neutral L di e eC
eP eB L eB B
i dt 2
e eC
eP B 0.5
When pole A 2
interrupts. e A eP 1 (0.5) 1.5
voltage eA is
maximum = 1 p.u. First-pole-to-clear
eB = eC = - 0.5 p.u. factor is 1.5
• In this case, kpp is 1.0 as the circuit breaker interrupts under the phase-
to-ground voltage.
I3 V3
E
I2 V2
I1 V1
3X 0
k pp
X1 2X 0
where X0 is the zero sequence reactance of the system,
X1 the positive sequence reactance of the system.
For systems up to 800 kV, the ratio X0/X1 is taken to be 3.0.
Hence, for systems with effectively grounded systems kpp is 1.3.
ES
ES - ET I
ET
I
Currents TRVs
I2 V2
I1 V1
effectively
3.0 1.3 1.27 1.0
grounded
see note 1.0 1.0 1.0 1.0
Note: values of the pole-to-clear factor are given for X0/X1 = 1.0 to
indicate the trend in the special case of networks with a ratio X0/X1 of
less than 3.0.
kpp= 1.5 is taken for all systems that are not effectively grounded, it
includes (but is not limited to) systems with isolated neutral (it is also
taken for three-phase ungrounded faults).
TRV HV Circuit Breakers P 87
Terminal fault TRV
Rating & Testing
Current
CURRENT
SupplySupply
voltage
voltage
Transient recovery
TRANSIENT RECOVERY
voltage
VOLTAGE
• The TRV ratings for circuit breakers are applicable for interruption
of three-phase faults with
− a rated symmetrical short circuit current
− at the rated voltage of the circuit breaker.
• In IEC
− While three-phase ungrounded faults produce the highest TRV
peaks, the probability of their occurrence is very low.
Therefore, in IEC 62271-100 the TRV ratings are based on
three-phase to ground faults.
− TRV parameters are given in subclause 4.102 of IEC 62271-
100.
− For values of fault current other than rated and for line faults,
related TRV capabilities are given in subclause 6.104.5 of IEC
62271-100.
• In ANSI/IEEE
− TRV withstand capabilities are given in ANSI/IEEE C37.04 and
IEEE C37.06.
− In the case of terminal faults, for circuit-breakers of rated
voltages equal or higher than 100 kV, separate Tables give
TRVs for three-phase to ground and three-phase ungrounded
faults.
• For circuit breakers applied on systems 72.5 kV and below, the TRV
ratings assume that the system neutrals can be non-effectively
grounded.
• For circuit breakers applied on systems 245 kV and above, the TRV
ratings assume that the system neutrals are effectively grounded.
Ur
uc 2 k pp k af
3
u ' uc / 3
Ur Ur
u1 2 k pp 0.75 uc 2 k pp k af u ' u1 / 2 t 2 4 t1
3 3
TRV HV Circuit Breakers P 96
Terminal Fault TRV Rating
Ur
U c k af k pp 2
3
where
kpp is the first pole to clear factor
kaf is the amplitude factor (ratio between the peak value of TRV and
the peak value of the recovery voltage at power frequency).
In IEC 62271-100 and IEEE C37.04, kaf is 1.4 at 100% rated breaking
current.
0.1 I
0.3 I
0.6 I 1.0 I
TIME
I is the rated short-circuit current
Envelope of Envelope of
Line system TRV Cable system TRV
Uc
t3
ClassCS
Class S1 SLF ?
Cable-system No
Class
Class S2
LS Direct connection
Line-system to OH line Yes
Direct connection
Cable-system
to OH line Yes
Class S2
Class LS
Short-line fault breaking performance is required only for class S2
1,8
1,7
Amplitude factor (p.u.)
1,6
1,5
1,4
1,3
1,2
T10 T30 T60 T100
(kV/µs) 1,4
1.33
1.21 52kV
1,2
1.05 38kV
1
0.91 24kV
15kV
0,8
0,6
Ur
0,4
12,5 22,5 32,5 42,5 52,5 62,5 72,5
(kV)
72.5 2
uc 1.5 1.54 137 kV
3
137
− RRRV is the ratio of uc and t3 : VATR 1.47 kV / µs
93
it is the present value in IEC and IEEE standards.
(kV/µs) 1,4
1.33
1.21 52kV
1,2
1.05 38kV
1kV/µs 1
0.91 24kV
15kV
0,8
20kV Ur
0,4
12,5 22,5 32,5 42,5 52,5 62,5 72,5
(kV)
1,6
1,5
IEEE k pp=1.5
1,4
1,3
1,2
1,1
1
10 20 30 40 50 60 70 80 90 100 % Isc
Case 10 % Isc: kpp x kaf = 2.46 (IEEE kpp=1.5) and 2.29 (IEC & IEEE kpp=1.3)
6
RRRV (kV/µs)
1
T10 T30 T60 T100
Voltage
time
• The parameters that define the circuit breaker TRV capabilities vary
with the circuit breaker voltage rating and short-circuit current
interrupting level.
• The circuit breaker TRV capabilities at 10%, 30%, 60% and 100% of
rated short-circuit interrupting current (Isc), corresponding to terminal
fault test duties T10, T30, T60 and T100, are given in IEEE Std
C37.06.
• The circuit breaker TRV withstand capability envelope at any other
short-circuit interrupting current below rated can be derived using the
multipliers given in Table 1 of IEEE C37.011-011.
• TRV studies are sometimes carried out to determine if a system TRV
is covered by the circuit breaker TRV capability demonstrated by type
tests, either when new circuit breakers are to be installed or following
a system change.
• The Working Group in charge of IEEE Guide C37.011 has defined that
the TRV capability between T30 and T60 can be considered to have a
rate-of-rise (u1/t1) and a first reference voltage (u1) that have
intermediate values between those of T30 and T60.
• TRV parameters (u1, t1, uc, t2) for any terminal fault current between
30 % and 60 % of Isc can be obtained as follows:
245kV Breaker TRV Envelope
500
450 T100
T75
400
T60
350 T55
T50
300
T45
kV
250 T40
T35
200
T30
150 T10
u1,t1
100
50
0
0 50 100 150 200 250
Time (µs)
• Tests are required at 100% (T100), 60% (T60), 30% (T30) and 10%
(T10) of rated short-circuit current with the corresponding rated TRVs
and recovery voltages.
• In IEC 62271-100, 3 tests are required with a symmetrical current for
each test duty, except T100 that is performed as follows
− 3 tests with symmetrical current and
− 3 tests with asymmetrical current (when interrupting asymmetrical
currents, the rate-of-rise and peak value of TRV are reduced but the
energy in the arc is higher).
• In IEEE Std C37.09
− for each test duty T10, T30, T60: 2 tests are required with
symmetrical current and 1 test with asymmetrical current.
− test duty T100 is performed as in IEC
• During testing, the envelope of the test TRV (in red) must be equal or
higher than the specified TRV envelope (in blue).
U
(kV) A C
Envelope of prospective test TRV
uc
Prospective test TRV
B
u1
Reference line of specified TRV
u'
0 td t' t1 t2 t (µs)
Arcing time
1,5
Contacts separation
1
Arcing time = 13 ms
0 0,005 0,01 0,015 0,02 0,025 0,03 0,035 0,04 0,045 0,05
Time
-0,5
1st passage
through zero
-1
-1,5
phenomena, durations
can be expressed in 1
milliseconds or in
electrical degrees. 0,5 10 ms
For a system frequency
of 50 Hz, the duration of 0
0 0,002 0,004 0,006 0,008 0,01 0,012 0,014 0,016 0,018 0,02
one half loop is 10 ms, it
corresponds to 180° el., it -0,5
of 60 Hz the duration of
one half loop is 8.33 ms -1,5
Current
Arcing time
1st pole
Arcing time
last poles
Example
three-phase
fault
interruption
Fr = 50 Hz
Pole 3
interrupts first
Arcing time
pole 3 = 8.4ms
(minimum arcing
time)
Arcing time
pole 1 = 8.4ms
Pole 1 interrupts
first with the same
arcing time as in
Case 1 by pole 3
i.e. same breaking
conditions in
terms of arcing
times
10000
Iarc
0
Contact separation
Current (A)
-10000
18°
-20000
Iarc
-30000
Contact separation
-40000
0 5 10 15 20 25 30 35 40
Time (ms)
Tmin = 12 ms
15000 three-phase ungrounded faults
10000
Minimum arcing time (blue
5000
Iarc phase) Tmin = 12 ms
current [A]
0 5 10 15
time [ms]
20 25 30 35 40
Arcing time 1st phase (red
20000
phase) = 14.33 ms
15000
(Tmin + 60° - 18°
10000
= Tmin + 42°)
5000
Iarc Maximum arcing time (blue
current [A]
-5000
phase) = 19.33 ms
Contact
-10000 separation (14.33 ms + 90°
-15000
= Tmin + 132°)
T max = 19.33 ms
-20000
Tmin = 12 ms
15000
three-phase ungrounded faults
10000
0 phase) Tmin = 12 ms
-5000 Contact
-10000
separation Contact separation delayed
by 18° el.
-15000
18° el.
-20000
(or 0.83 ms)
0 5 10 15
time [ms]
20 25 30 35 40
Arcing time 1st phase (red
20000
phase) = 13.94 ms
15000
(Tmin + 60° - 18°
10000
= Tmin + 42°)
5000
Iarc
current [A]
Current
A B
ER
ES
ET
Contact
separation
Time
Interruption of current in a first pole, followed ¼ cycle later by
interruption of the two other poles in series
A B
ER
ES
ET
Contact
separation
Three-phase faults in
0.87 non-effectively grounded
systems or three-phase
90° ungrounded faults
Three-phase faults in
0.87 non-effectively grounded
systems or three-phase
90° ungrounded faults
Arcing time
° el.
Reference = Minimum arcing time first pole Minimum arcing time + 180° -18°
TRV HV Circuit Breakers P 134
Terminal Fault TRV & Arcing Times at 60Hz
Arcing time
° el.
0 1.95 3.55 4.15 5.5 6.1 7.5 ms
5.55
Reference = Minimum arcing time first pole to clear
TRV HV Circuit Breakers P 135
Terminal Fault TRV & Arcing Times
Increased
stress
° el.
Reference = Minimum arcing time first pole Minimum arcing time + 180° -18°
TRV HV Circuit Breakers P 136
Terminal Fault TRV & Arcing Times
1,5
Contacts separation
Current
0,5
Single-phase tests
Minimum arcing time
= 13 ms
0 0,005 0,01 0,015 0,02 0,025 0,03 0,035 0,04 0,045 0,05
Time
-1
-1,5
1,5
Contacts separation
Current
Mximum arcing time = 22 ms
0,5
= 13 ms + 10 ms - 1 ms
= 13ms + 180° el. - 18° el.
0 0,005 0,01 0,015 0,02 0,025 0,03 0,035 0,04 0,045 0,05
-1
-1,5
• For the two types of fault, the TRV has an oscillatory waveshape and
the first-pole-to-clear factor is 1.5 in order to cover three-phase
ungrounded faults.
• TRV parameters, i.e. peak voltage uc, rate-of-rise (RRRV) and time
delay, are listed in ANSI/IEEE C37.013.
TRV for system-source faults
• RRRV for system-source faults is 3 to 5 times higher than the value
specified for distribution or sub-transmission circuit breakers ANSI/IEEE
C37.04.
This is due to the fact that the TRV frequency is dominated by the
natural frequency of the step-up transformer.
• IEEE has defined TRV parameters in several ranges of transformer
rated power.
Inherent TRV
Transformer
Rating T2 -Time to - Peak E2 -Peak Voltage TRV Rate
(MVA) (µs) (kV) (kV / µs)
Line Column 1 Column 2 Column 3 Column 4
1 10 - 50 0.68 V 1.84 V 3.2
2 51 - 100 0.62 V 1.84 V 3.5
3 101 - 200 0.54 V 1.84 V 4.0
4 201 - 400 0.48 V 1.84 V 4.5
5 401 - 600 0.43 V 1.84 V 5.0
6 601 - 1000 0.39 V 1.84 V 5.5
7 1001 or more 0.36 V 1.84 V 6.0
t3 E2
T2
0.85 0.85 TRV rate
3,6
3,4
3,2
TRV RATE (kV/µs)
81MVA
100MVA
2,8
2,6
65,5MVA
2,4
2,2
2
0 2000 4000 6000 8000 10000 12000
increase (p.u.)
1,25
65.5 MVA
E2 MULTIPLIER (p.u.)
1,2
81 MVA
1,15
100 MVA
1,1
1,05
Capacitance
1 (pF)
0 2000 4000 6000 8000 10000 12000
CABLE CAPACITANCE (pF)
Inherent TRV
Generator
Rating T2 -Time - to – Peak E2 -Peak Voltage TRV Rate
(MVA) (µs) (kV) (kV / µs)
Line Column 1 Column 2 Column 3 Column 4
1 10 - 50 1.44 V 1.84 V 1.5
2 51 - 100 1.35 V 1.84 V 1.6
3 101 - 400 1.20 V 1.84 V 1.8
4 401 - 800 1.08 V 1.84 V 2.0
5 801 or more 0.98 V 1.84 V 2.2
• First-pole-to-clear factor
− Effectively earthed systems kpp = 1.3 (1.2 for UHV)
− Non-effectively earthed systems kpp = 1.5
• Rating
− TRV with 2 or 4 parameters
− Classes S1 and S2 for rated voltages < 100 kV
• Testing circuit breakers ≥ 100 kV
− RRRV: 7 – 5 – 3 – 2 kV/µs for resp. T10, T30, T60, T100s
− Interrupting window: 162° (kpp = 1.3) or 132° (kpp = 1.5)
• Generator circuit breakers higher RRRV for T100s
line
Circuit breaker
TRV, neglecting the contribution from
the supply-side
TRV HV Circuit Breakers P 153
Short-Line-Fault (SLF)
Current
Supply-side voltage
Um
t
U=0 Uo
UL Line-side voltage
Voltage at x = 0.75 L
Voltage half-way
to the fault x = 0.5 L Voltage at circuit-breaker
-2 Terminal x = 0
0,5
0
0 0,25 0,5 0,75 1 1,25 1,5 1,75 2
-0,5
-1
-1,5
Time / TL
Voltage (kV)
Line voltage
Time (µs)
L
Z Z is the surge impedance of the line (450 ohm)
C
L and C are respectively the self inductance and the capacitance of the
line per unit length
I fault current (kA)
at 50 Hz Z 2 0.2 10 6
ω pulsation
s multiplier = 0.20 (f = 50Hz) or 0.24 (f = 60 Hz), du/dt in kV/µs
• Assumptions: conductors of infinite length, the electrical field and magnetic field
do not penetrate the ground.
• Self surge impedance
D = 2 h with h = height of line r = radius of conductor
Ln = natural logarithm µ0 = magnetic constant = 4π×10−7 H/m
L D 2h
with
Z 60 Ln 60 Ln (1)
C
r r
• Mutual surge impedance (ZM) between 2 conductors is given by (1) where D is
the distance between one conductor and the image of the other conductor, and r
represents the distance between the two conductors (see next slide).
• A matrix equation is done in case of multi-conductors circuits with self and
mutual couplings. Modal analysis done by digital calculations gives the relevant
modes of travelling waves (see Annex C in [39] and [47]).
TRV HV Circuit Breakers P 164
SLF / Line Surge Impedance
d12 Bundle 2
Bundle 1 Bundle 3
D12
Ground
D
Z M 12 60 Ln 12
d12
Image of bundle of conductors 2
V VLG
I S LG IL
XS XS XL
uL
d
uO
uO
uL
u L Z eff di / dt 2 / v Z eff
d 2
uo X L I L 2 XL v
XL is the line reactance per unit length
v is the velocity of light (0.3 km/µs), is the line length
is 2 system power frequency (314 or 377 rad/s for 50 or 60 Hz)
U0 X L IL
US X S IS
U0 IL M IS
US XS
M
XS XL
or M X L X S M X S
U0 X L M IS
U0 X S M X S IS
U 0 1 M X S I S 1 M U S
U 0 1 M U S
• The rated values for the line surge impedance Z and the peak factor
d are defined in standards as follows:
Z 450 d U L / U 0 1.6
• The line side voltage contribution to TRV is defined as a triangular
wave as follows (where IS is the rated short-circuit current) :
2 du di
U L 1.6 (1 M ) Ur Z Z M IS 2
3 dt dt
the first peak UL decreases when M increases
the rate-of-rise of recovery voltage increases with M
• There is a critical value of the short-line-fault current for which the
circuit breaker has more difficulty to interrupt.
• The critical value of M is close to 90% for SF6 circuit breakers
(generally in the range 90%-95%). it is between 75% and 80% for
air blast circuit breakers.
TRV HV Circuit Breakers P 170
Short-line-fault
Current (kA) 36 30
UL (kV) 32 80
140
120
L60
Ur = 245kV
4.8 kV/µs
100 Isc = 40kA
80
fr = 50Hz
U (kV)
L75
6 kV/µs
60
40
L90
7.2 kV/µs
20
0
0 5 10 15 20 25 30 35
T (µs)
When current decreases (longer line), the slope decreases but the peak
value increases. It is generally considered that for SF6 circuit breakers
interruption is more influenced by the voltage slope (RRRV).
e e L eS
with (in a first approximation)
eS 2 M (TL t d )
where
• This rate-of-rise of TRV during SLF is much higher than the values
that are met during terminal fault interruption:
RRRV I F
Test duty
(kV/µs) (kA) (Hz)
SLF
10.8 45 60
L90 50 kA
SLF
9 45 50
L90 50 kA
SLF
8.64 36 60
L90 40 kA
Terminal fault
3 30 50/60
T60
Terminal fault
2 50 50/60
T100
For SLF, this table gives the RRRV of the line side voltage
IEC values are shown, ANSI/IEEE values cover rated voltages up to 800kV
TRV HV Circuit Breakers P 176
Short-Line-Fault
Influence of an Additional Capacitor
XS XL
C.B.
VLG
60
[ kV ]
50
40
30
1 2 3
20
10
0
0 4 8 12 16 [ u s] 20
(file t r v 2 .pl4 ; x - v ar t ) v :P 0 0 v :P 1 v :P 4 v :P 1 0
e(t ) Z (di / dt ) t Z C Z C e t / Z C
− If the capacitor is connected phase to ground on the line side, the
reduction of the line side RRRV can be estimated by a simple
calculation, as detailed in the next slide, with
Cadd additional line-to-ground capacitance;
L line inductance;
Z line surge impedance;
CL total line capacitance = L/Z2;
Ce equivalent line capacitance: capacitance which, together
with the inductance L, gives the line frequency of oscillation
1
− By definition of Ce fL
2 LCe
2u *L
− The period of oscillation is equal to with u *L 2 X L I L 2
du
du
and Z I L 2 dt L
dt L
Z
− It follows that fL
4X L
and 4L 4 CL
Ce 2 2 0.4 CL
Z 2
If an additional capacitance is added at the line entrance, the RRRV on
the line side is reduced in the same manner as the line frequency of
oscillation.
du 2 LCe
Z IL
dt 2 L(Ce Cadd )
du Ce
Z IL
dt Ce Cadd
du CL
Z IL 2
dt C L 2.5 Cadd
du Z R di Z R
I 2
dt Z R dt Z R