CLOSED 12
STATUS
OPEN 4
TOTAL 16
DATE
TRANSMITTED
RECEIVED THRU DATE PROTOCOL DATE RECEIVED
Item No. WORK REQUEST (ref no.) LOCATION OVERLAP (to TRADE DATE REQUIRED RESPONDED BY CONSULTANT'S COMMENTS / CLIENT'S RESPONSE DATE REQUIRED RESPONDED BY DELAY STATUS
(HARDCOPY/EMAIL) (+2 DAYS) (by contractor)
CONTRACTOR /
PM)
Your activity has overlap with trade contractors. Please do let trade
contractor: Edge, which they will sign after INSPECTION OF
Arch't. Leanzza 14-May-21 Clyton 0 Delay
PLACEMENT of CORING WORKS. MSI, EHAES for his
awareness fo activity.
1 YRES-19002-Pipe Repiping Bedroom 1, 2 & 3 T&B Email YES 13-May-2021 15-May-2021 Approved. Please proceed as approved by AoR. Installation at site CLOSED
should not collide with Mechanical Works. Elevation of pipes
Arch't. Leanzza should be more than 3000mm. If Installation will have conflicts at 21-May-21 Clyton 6 Days
site with other trade roughing-ins, do halt and immediately
coordinate with Site Supervisor.
YRES_19002 IWR- Covering of Coring Holes in the Ground Floor, Roof Garden Third Floor, Master's Inspection should be placement of provision of floor drain with
7 Email No 18-May-21 20-May-21 Arch't. Leanzza 19-May-21 Clyton 0 Delay OPEN
Previous Plan Bedroom T&B consideration to tile layout.
For the gas line leading to the service lounge and pipe chase,
Suzuki reroute line along the corridor ceiling, to pass between beam and 4-Jun-21 10 Days
steel deck, or existing openings in beams.
Page 1 of 2
Request for INSPECTION/ WORK
Project: YBAÑEZ RESIDENCE
Code: 1/9/1952
Address: Pristina North, Bacayan, Talamban, Cebu City
As. Of: 7/7/2021
Package: Plumbing Works
CLOSED 12
STATUS
OPEN 4
TOTAL 16
DATE
TRANSMITTED
RECEIVED THRU DATE PROTOCOL DATE RECEIVED
Item No. WORK REQUEST
19002-IWR-RALOTA (ref no.)
BROTHER-REROUTING LOCATION OVERLAP (to TRADE DATE REQUIRED RESPONDED BY CONSULTANT'S COMMENTS / CLIENT'S RESPONSE DATE REQUIRED RESPONDED BY DELAY STATUS
10 Basement, Indoor Laundry (HARDCOPY/EMAIL)
Email No (+2 DAYS) (by contractor) CLOSED
WATERLINE IN BASEMENT CONTRACTOR /
PM)
Suzuki Section is approved. Water descent 600 mm to FFL is approved. 7-Jun-2021 12 Days
Please proceed for "mock-up" for first step and a portion of a step
19002- IWR- RALOTA BROTHER- STAIR WORKS
14 Ground Floor Swimming Pool Email No 25-May-21 27-May-21 Arch't. Leanzza only. If Pool Shopdrawing will be approved by AoR, please do IWR 25-May-21 Clyton 0 Delay CLOSED
(Swimming Pool)
for the whole steps.
YRES-19002-IWR-RALOTA BRO'S Basement, Landscape setback Email YES 1-Jul-2021 3-Jul-2021 Clyton 3 Dyas Open
Page 2 of 2