Request for INSPECTION/ WORK

Project: YBAÑEZ RESIDENCE


Code: 1/9/1952
Address: Pristina North, Bacayan, Talamban, Cebu City
As. Of: 7/7/2021
Package: Plumbing Works

CLOSED 12
STATUS
OPEN 4
TOTAL 16

DATE
TRANSMITTED
RECEIVED THRU DATE PROTOCOL DATE RECEIVED
Item No. WORK REQUEST (ref no.) LOCATION OVERLAP (to TRADE DATE REQUIRED RESPONDED BY CONSULTANT'S COMMENTS / CLIENT'S RESPONSE DATE REQUIRED RESPONDED BY DELAY STATUS
(HARDCOPY/EMAIL) (+2 DAYS) (by contractor)
CONTRACTOR /
PM)

Your activity has overlap with trade contractors. Please do let trade
contractor: Edge, which they will sign after INSPECTION OF
Arch't. Leanzza 14-May-21 Clyton 0 Delay
PLACEMENT of CORING WORKS. MSI, EHAES for his
awareness fo activity.

1 YRES-19002-Pipe Repiping Bedroom 1, 2 & 3 T&B Email YES 13-May-2021 15-May-2021 Approved. Please proceed as approved by AoR. Installation at site CLOSED
should not collide with Mechanical Works. Elevation of pipes
Arch't. Leanzza should be more than 3000mm. If Installation will have conflicts at 21-May-21 Clyton 6 Days
site with other trade roughing-ins, do halt and immediately
coordinate with Site Supervisor.

Please see attcahed file "How to Do IWR". Your cativity has


overlap with trade contractor. Please let them sign this. Do Clarify
YRES_19002 IWR-CUTTING/REMOVAL OF
3 Basement, Outdoor Laundry Email YES 13-May-2021 15-May-2021 Arch't. Leanzza why would you cut/remove pipes. I discern you are to deepen 14-May-21 Clyton 0 Delay OPEN
PROTRUDING PIPE
embedment of pipes. Why is drawing don’t not have any highlight
which pipe is to be cut or remove.

Please see attcahed file "How to Do IWR". Your cativity has


overlap with trade contractor. Please let them sign this. Why is your
4 YRES_19002 IWR- Maid's Room Water Line Basemeny, Maid's Room Email YES 13-May-2021 15-May-2021 Arch't. Leanzza attached drawings do not have elevation of provision for waterline. 14-May-21 15-May-21 Clyton 0 Delay CLOSED
No indicated date of work needed. Would you start working on
Staurday, May 15, 2021.

See attached file “HOW TO DO IWR”. Your activity has overlap


with trade contractors. Please do let trade contractor sign this. Next
do coordinate with Engr. Clyton with AOR concerns. (file name:
Basement, Service Lounge Ground floor, Main Kitchen 07052021_YRES-GL - AOR REMARKS) of your GAS LAYOUT.
6 YRES_19002 IWR- Gas Layout Email YES 13-May-21 15-May-21 Arch't. Leanzza 14-May-21 Clyton 0 Delay CLOSED
& Service Kitchen Clarify location of pipe FOR BASEMENT, is it INSIDE the building
or at SETBACK. Also if at setback please include embedment
detail (SECTION) showing depth of embedment of pipe. Why is
your attached drawing do not have any layout of gas pipe roughing-

YRES_19002 IWR- Covering of Coring Holes in the Ground Floor, Roof Garden Third Floor, Master's Inspection should be placement of provision of floor drain with
7 Email No 18-May-21 20-May-21 Arch't. Leanzza 19-May-21 Clyton 0 Delay OPEN
Previous Plan Bedroom T&B consideration to tile layout.

Proceed with chipping Works. Prepare shopdrawing for this matter


for approval of final depth and profile of AoR. Details that will be
8 YRES_19002- IWR-01Chipping Works Ground Floor, Swimming Pool Email No 19-May-21 21-May-21 Arch't. Leanzza
emposed by AoRlater on due to no approval of shopwdrawing will
19-May-21 21-May-21 Clyton 0 Delay CLOSED
be done by CG+R without additional cost.

Gas Layout should be approve first by Architect of Record, With


that, its seems for me there are areas for clarification that might
Arch't. Leanzza affect architectural concept, exterior. For Interior, please make sure 20-May-21 0 Delay
that roughing-ins will not collide with MECHANICAL, or
ELECTRICAL.
Basement, Service Lounge Ground floor, Main Kitchen
9 19002-IWR-RALOTA BROS - GAS LAYOUT Email No 20-May-21 22-May-21 Clyton CLOSED
& Service Kitchen

For the gas line leading to the service lounge and pipe chase,
Suzuki reroute line along the corridor ceiling, to pass between beam and 4-Jun-21 10 Days
steel deck, or existing openings in beams.

Please clarify why is theres a rerouting of waterline roughing-ins in


20-May-21 22-May-21 Arch't. Leanzza the beasmenent level. Please see email given last May 5, 2021 21-May-21 Clyton 0 Delay
with email subject YRES_Plumbing

Based on the email given last May 5, 2021 (YRES_PLUMBING), that


19002-IWR-RALOTA BROTHER-REROUTING wasn't followed to avoid coring holes. Please check the attached file that is
10 Basement, Indoor Laundry Email No 21-May-21 23-May-21 Angelito 21-May-21 0 Delay CLOSED
WATERLINE IN BASEMENT based on the actual layout on site except for the water line in the trench that
needs to be rerouted.

Page 1 of 2
Request for INSPECTION/ WORK
Project: YBAÑEZ RESIDENCE
Code: 1/9/1952
Address: Pristina North, Bacayan, Talamban, Cebu City
As. Of: 7/7/2021
Package: Plumbing Works

CLOSED 12
STATUS
OPEN 4
TOTAL 16

DATE
TRANSMITTED
RECEIVED THRU DATE PROTOCOL DATE RECEIVED
Item No. WORK REQUEST
19002-IWR-RALOTA (ref no.)
BROTHER-REROUTING LOCATION OVERLAP (to TRADE DATE REQUIRED RESPONDED BY CONSULTANT'S COMMENTS / CLIENT'S RESPONSE DATE REQUIRED RESPONDED BY DELAY STATUS
10 Basement, Indoor Laundry (HARDCOPY/EMAIL)
Email No (+2 DAYS) (by contractor) CLOSED
WATERLINE IN BASEMENT CONTRACTOR /
PM)

Would be the pipes be mounter or imbedded in slab or wall?. Although you


have commence at site with your work strategy concerning this.
28-May-21 30-May-21 Arch't. Leanzza 28-May-21 6 Days
Please clarify to us what is the direction: Would be the pipes be mounter or
imbedded in slab or wall?

This is not permanently fixed at site, no u-clips installed yetand not


connected to main water supply, yet. With this the action to
19002-IWR-RALOTA BROS- REROUTING PIPE
11 Third Floor, Master's T&B Email No 20-May-21 22-May-21 Arch't. Leanzza proceed at site, plumbing designer approves layout. Also do note, 21-May-21 Clyton 0 Delay CLOSED
(Master's T&B)
plumbing fixture be installed in pipe provision, this is also seen in
plumbing fixture matrix given.

Drawings is not yet approved by AoR. Please let this be approved


Arch't. Leanzza first thru RFA, do include in your drawings detail of the opening of 22-May-2021 0 Delay
the water descent.

YRES_19002 IWR- RALOTA BROTHERS-


12 Ground Floor, Swimming Pool Email No 21-May-21 24-May-21 Clyton CLOSED
INSTALLATION OF WATER DECENT

Suzuki Section is approved. Water descent 600 mm to FFL is approved. 7-Jun-2021 12 Days

As seen in your drawings, no tile starting point indicated. Fixtures


13 19002-IWR-RALOTA BROTHERS- TILE WORKS Ground Floor, Swimming Pool Email No 21-May-21 23-May-21 Arch't. Leanzza not yet approved by AoR. At site no provision of pool trench drain. 22-May-21 Clyton 0 Delay CLOSED
Why start installation of chipping works needed to be done.

Please proceed for "mock-up" for first step and a portion of a step
19002- IWR- RALOTA BROTHER- STAIR WORKS
14 Ground Floor Swimming Pool Email No 25-May-21 27-May-21 Arch't. Leanzza only. If Pool Shopdrawing will be approved by AoR, please do IWR 25-May-21 Clyton 0 Delay CLOSED
(Swimming Pool)
for the whole steps.

Drawing for approval of AoR. Please reflect site discussion in


15 19002-IWR- Installment of Water Decent (Flush) Ground Floor Swimming Pool Email No 26-May-21 28-May-21 Arch't. Leanzza 26-May-21 Clyton 0 Delay OPEN
drawing last Monday, May 24, 2021.

1.Beam Cladding To be extended to conceal horizontal PVC. 2.


Reroute soil pipe behind column so it will not be exposed above
floor and wall finish. 3.Move horizontal 4' pvc soil line below
basement level floor line. Line should not disturb 50mm concrete
16-Jun-21 18-Jun-21 Monitoshi topping to be placed. 4. Reroute behind column so that soil pipe 17-Jun-21 0 Delay
willl not be exposed beyond floor and wall finish.5. Allign
Downspout with divider wall. Downspout to be cladded concealed
with wall. 6. Reroute soil pipe behind column so it will not be
exposed above floor and wall finish.
(YRES-19002-IWR-RALOTA BROS.) PVC PIPE
16 INSTALLATION-INDOOR & OUTDOOR LAUNDRY AREA Basement, Indoor & Outdoor Laundry Email No Clyton CLOSED
(BASEMENT CEILING)

Plan is not aligned with correct section. Down facing elbow to be


18-Jun-2021 20-Jun-2021 Monitoshi 21-Jun-21 0 Delay
moved inside wall line as shown in section A.

YRES_19002_ IWR -RALOTA-BROS_I BEAM CORING


Basement, Indoor Laundry Email No 24-Jun-2021 26-Jun-2021 Engr. Chua This is approved, coring at midspan of beam. 18-Jun-21 Clyton 0 Delay Closed
WORKS (INDOOR LAUNDRY-BASEMENT CEILING)

YRES-19002-IWR-RALOTA BRO'S Basement, Landscape setback Email YES 1-Jul-2021 3-Jul-2021 Clyton 3 Dyas Open