You are on page 1of 55

 

Success & failures  
of grand concert halls and opera projects  
Harpa – Case study 

Jón Ólafur Ólafsson 

Thesis of 12 ECTS credits 
Master of Project Management (MPM) 
 
May 2014 
   
 

Success & failures 
 of grand concert halls and opera projects 
 Harpa – Case study 

Jón Ólafur Ólafsson 

Thesis of 12 ECTS credits submitted to the School of Science and Engineering 
 at Reykjavík University in partial fulfilment  
of the requirements for the degree of  
Master of Project Management 

May 2014 

Supervisor(s):  

Dr. Helgi Þór Ingason  
Associate professor, Reykjavík University, Iceland  
 
Examiner(s):  
___________________________________________ 

___________________________________________ 
   
 
Success & failures  
of grand concert halls and opera projects 
Harpa – Case study 

Jón Ólafur Ólafsson 

12 ECTS thesis submitted to the School of Science and Engineering 
 at Reykjavík University in partial fulfilment  
of the requirements for the degree of  
Master of Project Management (MPM). 

May 2014  

Student:  
      ___________________________________________ 

      Jón Ólafur Ólafsson 

Supervisor(s):  
      ___________________________________________ 

      Dr. Helgi Þór Ingason 

Examiner:  
      ___________________________________________ 

       

   
 

   
SUCCESS AND FAILURES 
 OF GRAND CONCERT HALLS AND OPERA PROJECTS 
CASE STUDY ‐ HARPA 
 
Jón Ólafur Ólafsson 

Reykjavík  University,  School  of  Science  and  Engineering,  MPM  ‐  Master  of  Project 
Management, Reykjavík, Iceland 

jonsi@arkitekt.is  

Paper  presented  as  part  of  requirements  for  the  degree  of  Master  of  Project 
Management  (MPM)  at  the  School  of  Science  and  Engineering,  Reykjavik  University  ‐  May 
2014 

ABSTRACT   

This paper studies the comparable attributes of grand concert halls and opera projects, and 
develops a method to evaluate and compare them. The study was based on a case study of 
Harpa, the new Concert and Concert Hall in Reykjavik, a questionnaire survey on the fulfilment 
of the feature objectives, and by applying four different, recognized assessment tools/lenses 
to evaluate projects and project success, with the intention of verifying their applicability for 
this  type  of  projects.  The  study  of  Harpa  and  the  questionnaire  survey  revealed  several 
comparable attributes and important feature objectives that should be taken in account when 
planning new concert halls. The outcome of these studies is a conceptual framework applied 
on the case – Harpa. The findings show that the method can be used to evaluate success and 
can provide to be a useful tool in the initiating and planning phase of new concert halls and 
opera projects.  

Keywords:  Project success; Project management; Concert hall projects; Opera projects; Harpa 
‐ Concert and Conference Centre. 

   


 

   

ii 
1. INTRODUCTION  

Between 2000 and 2012 more than 220 (239 halls or auditoriums) concert halls and 
opera buildings have opened for public worldwide (Wikipedia, 2014). On average 18 concert 
halls projects are finished each year with annual investment probably greater than $2.500‐
3.000 million. 

Can we learn from (grand) concert halls and opera construction projects?  
Do these projects differ from other types of public projects?  
What is the driving force behind realization of grand concert halls and opera projects? 

Concert halls and opera buildings are complex construction projects. They are generally 
grand  scale,  prominent  and  sensational,  and  have  great  influences  on  the  community  and 
their  near  surroundings.  They  are  often  designed  to  be  iconic,  attracting  national  and 
international musicians and tourists. Concert halls and operas are typically state‐owned, the 
antecedents  and  preparation  time  is  often  very  long  and  complicated,  involving  many 
stakeholders with different, conflicting and even incompatible views. The strategic decisions 
are likely to be made on a political level and they often need political justification. The output 
is complex buildings with complicated technical equipment. But to what degree do they have 
comparable attributes? What are the relevant factors? 

 
Figure 1: Harpa ‐ Concert and Conference Centre in Reykjavík – Source: Harpa: Pictures of Harpa 


In  this  paper  a  conceptual  framework  for  assessing  project‐outcome,  successes  and 
failures  are  defined  and  presented  and  tested  on  Harpa,  the  newly  finished  concert  and 
congress centre in Reykjavík Iceland. The paper explores the applicability of Flyvbjerg´s studies 
on  big  infrastructure  overruns  and  benefit  shortfalls,  the  success  dimensions  identified  by 
Shenhar & Dvir and proposes additional factors that might apply in large, high profile public 
projects such as concert halls and opera houses, using Snowdon’s Cynefin framework as a lens. 
The status of knowledge is explored and literature within the field reviewed. Accessible data 
and information is reviewed and evaluated. The outcome of the original objectives and future 
vision is assessed and interpreted trough a survey among stakeholders and non‐participants.  

 How can we evaluate the success of concert halls and opera projects? 
 What does the assessment tool say about the success or failure of the Harpa project? 
 Can we use the method to evaluate success of other Concert halls and opera projects? 

Key attributes to be looked at are the Characteristics of concert hall projects, Scope ‐ 
cost  and  budget  change,  Justification,  Accountability  in  decision  making,  Biased  estimates, 
Complexity and Retrospect evaluation of project success. 

2. LITERATURE REVIEW 

The objective of this literature review is to define concert halls and operas according to 
common standards, explore the reason for big infrastructure overruns and benefit shortfalls,  
describe the common definition of success and failure, the applicability of Shenhar and Dvir´s 
diamond approach and project success measures, as well as the use of Snowdens´s Cynefin 
framework. 

2.1 Definition and standards 
According to the German database Emporsis concert halls and operas are categorised 
as  two  of  ten  subcategories  under  Entertainment  buildings  (ESN  80707),  which  are  places 
where  people  go  for  fun,  for  non‐athletic  recreation,  or  to  enjoy  performances  or 
presentations” Concert location (ESN 83789) is defined as “…a hall, theatre, amphitheatre, or 
other facility designated for the performance and listening of live musical concerts … including 
… sites for rock concerts, philharmonic halls, orchestral venues, and recital halls. … ” whereas 


Theatre/opera (ESN 84117) “… includes any performance hall used for live musical or dramatic 
performances … with permanent seating. (Emporsis, án dags.)  

According to Emporsis, several concert halls and opera buildings rank among the most 
expensive buildings in the world with Elbphilharmonie, the new Music Hall, hotel and mixed 
use building in Hamburg Germany as the most expensive one among concert halls. It ranks as 
number six on the list with estimated building cost of $1,027,510,000 and estimated end of 
construction in 2016. Den Norske Opera & ballet ranks as the 42nd most expensive building 
with  building  cost  of  $511,440,162  and  end  of  construction  in  2008  following  four  years 
construction.  The  Danish  Koncerthuset  or  DR  Byen  in  Copenhagen  ranks  as  the  57  most 
expensive building with building cost of $430,000,000. (Emporsis, án dags.)  

Harpa Concert Hall and Conference Centre in Reykjavík, Iceland does not make it on to 
the list but according to the same resource it´s building cost was $160,000,000. Harpa was 
inaugurated in May 2011, but started construction late 2006.  

It is not possible to compare the initial cost difference of the mentioned concert halls 
and  opera  buildings,  as  their  different  sizes,  usage,  context,  building  year  and  complexity 
render them nom‐comparable.  

2.2 Definitions of success and failure of projects 
The project management literature offers great deal of studies on success and failures, 
and  definition  of  the  terms.  Most  common  project  success  is  defined  as  “to  produce  the 
project deliverables within time and budget” but according to IPMA project success is “the 
appreciation by the various interested parties of the project outcomes” achieving the project 
objectives within the agreed constraints (IPMA, 2006, p. 16 and 40). 

According to PMBOK Guide”… the success of the project should be measured in terms 
of completing the project within the constraints of scope, time, cost, quality, resources, and 
risk as approved between the project managers and senior management. …Project success 
should be referred to the last baselines approved by the authorized stakeholders…” (Project 
Management Institute, 2012, p. 35) 

In  his  book  Project  Management,  A  system  Approach  to  Planning,  Scheduling  and 
Controlling,  Harold  Kerzner  refers  to  the  classic  definition  of  project  success  as  “…the 
completion of an activity within the constraints of time, cost, and performance.” According to 


Kerzner “…today project success also includes the acceptance of the customer/user, minimum 
or mutually agreed scope changes, without disturbing the main work flow of the organization 
and changing the corporate culture” (Harold Kerzner, 2009, p. 7). Kerzner claims that it ”… is 
unrealistic to believe that all projects will be completed successfully. Some people contend 
that the only true project failures are the ones from which nothing is learned. Failure can be 
viewed  as  success  if  the  failure  is  identified  early  enough  so  that  the  resources  can  be 
reassigned to other more opportunistic activities.”  (Harold Kerzner, 2009, p. 59). 

Munns and Bjeirmi identify the overlap between the definition of the project and project 
management in their paper, The role of project management in achieving project success. They 
argue  that  as  objectives  of  a  project  and  project  management  are  different  improved 
distinction between success and failure for the project and project management interests is 
needed.  Successful  project  management  techniques  contribute  to  the  achievement  of 
projects, but it will not stop a project from failing to succeed. The right project will succeed 
almost without the success of project management, but successful project management could 
enhance its success. Selecting the right project at the outset and screening out potentially 
unsuccessful  projects,  will  be  more  important  to  ensuring  total  project  success,  (Munns  & 
Bjeirmi, 1996). 

In their paper, A Retrospective look at our evolving understanding of Project success, 
Judgev  and  Müller  assess  our  evolution  of  understanding  project  success  and  discuss 
conditions for success, critical success factors and success frameworks. They argue that the 
success of individual projects impacts the wider organization in several dimensions and that 
makes  the  concept  of  project  and  project  management  success  that  much  more  relevant. 
According to Judgev and Müller projects are about managing expectations, and expectations 
have  to  do  with  perception  on  success.  Project  success  as  a  concept  is  complex  and 
ambiguous.  It  changes  over  the  life  cycle  time  of  the  project  and  the  product,  (Judgev  & 
Müller, 2005) 

In their book Reinventing Project Management, Aaron J. Shenhar and Dov Dvir question 
the traditional definition; maintaining “… that project success depends on satisfying the triple 
constraint – on time, within budget, and according to specifications.” They claim, “…the triple 
constraint is no longer sufficient and a new model is needed.” and there still is “… no universal 
way to measure and assess project success.” “No matter what the motivation for a project, 


any assessment of project success must be linked to the parent organization´s success and to 
its well‐being in the long run.” (Shenhar & Dvir, 2007, p. 22) 

According  to  Shenhar  and  Dvir  the  key  question  is:  “what  do  organizations  need  to 
consider  before  they  launch  a  new  project  and  how  should  they  assess  a  project  in 
retrospect?” “… Projects should be assessed based on their contribution to overall business 
results…” Project benefits may be immediate or be realized only later. Therefore project goals 
must be set in “… advance to reflect expectations, both short and long term. “ Shenhar and 
Dvir believe that project and product success should not be separated, as they are two sides 
of the same coin. “It all boils down to a simple question: how did the project contribute to the 
organization´s success and effectiveness?” (Shenhar & Dvir, 2007, p. 23). 

2.3 Flyvbjerg´s studies of big infrastructure overruns and benefit shortfalls 
In  his  article  Policy  and  planning  for  large  infra‐structure  projects:  problems,  causes, 
cures,  Bent  Flyvbjerg  argues  that  misinformation,  biased  optimism  and  strategic 
misrepresentation  are  the  main  problem  in  the  planning  of  large‐infrastructure  projects, 
including  concert  halls,  causing  high  risk.  Flyvbjerg  represents  seven  factors  causing  the 
planning problem:  

1. Long planning horizons and complex interfaces 
2. Non‐standard technology 
3. Decision making process with many actors and conflicting interests 
4. Changing project scope and ambition level over time 
5. Inadequate budget contingencies 
6. Consequent misinformation about cost, benefits and risks 
7. Overruns and/or benefit shortfalls as result 

Flyvbjerg´s studies indicate that 90% of transportation projects have cost overruns and 
average world‐wide cost overrun in transportation projects is 20‐45% depending of the type 
of projects. Along with biased forecast in travel‐demand, 90% of rail projects overestimate 
traffic. The more complicated the projects are, the higher risk for cost overrun and benefit 
shortfalls. They lead to waste (inefficient allocation of resources), delays, destabilized policy, 
planning,  implementation  and  operation  of  projects.  Flyvbjerg  states  that  “the  problem  is 
getting bigger because the projects are getting bigger”. 


Flyvbjerg identifies three types of explanations for cost overruns and benefit shortfalls 
with technical explanation, as the most common type of inaccuracy in forecasts, caused by   
inadequate  data,  mistakes,  lack  of  experience  and  so  on.  The  second,  psychological 
explanation, often called the planning fallacy accounts for inaccuracy in forecasts in terms of 
biased  optimism,  causing  unprofitable  investments  of  money  and  time.  The  last,  political‐
economic explanation, refers to deliberate and strategically overestimation of benefits and 
underestimation  of  costs  when  forecasting  projects  outcome  to  increase  the  likelihood  of 
approval and funding.   

Flyvbjerg rejects the technical explanation as a primary cause of cost‐underestimation 
and  benefit  overestimation  based  on  his  research.  The  same  applies  for  optimism  bias 
according to Flyvbjerg, though the psychological explanation better fits the data. His studies 
show  that  in  situations  promoters  and  forecasters  intentionally  underestimate  cost  and 
overestimate benefits to get project approval. Thus the projects that look best on paper are 
the projects that get implemented. Flyvbjerg calls for better practice and methods to prevent 
biased  forecasts.  This  can  be  obtained  by  accountability  and  critical  questioning.  He 
recommends  that  claimed  cost,  benefits  and  risk  made  by  professional  experts  should  be 
examined by independent specialist and organizations, (Flyvbjerg, 2007).  

The  relevance  of  Flyvbjerg´s  seven  factors  causing  the  planning  problem  will  be 
evaluated in the case study of Harpa.  

2.4 Shenhar, Dvir, Levy & Maltz´s dimensions of project success  
According  to  Shenhar  and  Dvir  et.al.  project  success  is  a  dynamic  concept  and 
comprehensive assessment of project success should be defined by following five basic groups 
of  measures  (dimensions)  addressing  both  short  and  long‐term  implications  (Shenar,  Dvir, 
Levy, & Maltz, 2001):   

1. Project efficiency is a short‐term measure of project completion according to plan. 
2. Impact on the customer represents the major stakeholder’s perception of the project 
success, such as improvement of live or business and fulfilment of needs – the product 
performance measure and level of customer satisfaction. 
3. Impact on the team reflect how the project affects the team and its members. 


4. Business  and  direct  success  reflects  the  immediate  impact  the  project  has  on  the 
parent organization – the project´s commercial success. 
5. Preparation  for  the  future  addresses  the  long  range  benefits  of  the  project,  how  it 
creates new opportunities, new competences, ideas, innovations and products.   

    Project success     
           
                   
Project   Impact on  Impact on  Business and  Preparation 
       
efficiency  customer  team  direct success  for future 
                           
 Meeting schedule     Meeting     Team satisfaction     Sales      New technology 
 Meeting budget  requirements and   Team morale   Profits    New market  
 Yield  specifications   Skill development   Market shares    New product line 
 Other efficiencies   Benefit to the   Team member   ROI, ROE    New core 
customer  growth    Cash flow   competency  
 Extent of use   Team member   Service quality    New organizational 
  Customer  retention    Cycle time  capability 
satisfaction and   No burnout   Organizational 
loyalty  measures 
  Brand name   Regulatory 
recognition  approval 
Table 1: Specific success measures (Shenhar & Dvir, page 27) 

The importance of each dimension shifts depending on when they are looked at relative 
to the project´s process. The first can be assessed at the end of project completion, the second 
within  months  of  completion,  the  third  in  a  larger  organizational  context.  The  fourth 
dimension  can  usually  only  be  assessed  after  year  or  two  while  the  last  dimension  can  be 
assessed only much later when the long‐term benefits of the project start to pay of, (Shenhar 
& Dvir, 2007, pp. 26‐29). 

The relevance of these success factors will be evaluated in relation with the case study 
of Harpa. 

2.5 The Diamond approach – NTCP model 
Shenhar  and  Dvir  introduced  a  multidimensional  Diamond  shaped  framework  for 
understanding  key  dimensions  of  projects  and  systematically  assessing  their  uniqueness 
trough  coherent  methodology.  According  to  Shenhar  and  Dvir  despite  uniqueness  and 
considerable variability between projects they also have common features. All project can be 
classified trough three drivers: the goal, the task and the environment and each project can 
be  characterized  by  the  NTCP  diamond  model  which  encompasses  novelty,  technology, 
complexity and pace, (Shenhar & Dvir, 2007, pp. 39‐41). Distinguishing between similarities 


and differences of projects can both help assessing project benefits and risks and selecting the 
right  project  management  style  to  manage  projects  more  effectively,  and  in  retrospect 
explaining  the  gaps  between  expectations  and  project  outcome  to  point  out  the  possible 
failures of projects. 

 
Figure 2: The Diamond model (Shenhar & Dvir, 2007, page 14) 

According to Shenhar & Dvir each of the four dimensions of the diamond affects the 
project management in its own way. “Novelty affects the time it should take to freeze product 
requirements and the accuracy and reliability of marketing data. Technology affects how long 
it should take to get the design right and freeze it, the intensity of the technical activities and 
the  technical  skills  required  by  the  project  manager  and  the  team.  Complexity  affects  the 
project organizations and the level of bureaucracy and formality needed to manage it. Pace 
affects the planning and reviews, the autonomy of the project team and the involvement of 
top management…” (Shenhar & Dvir, 2007, pp. 13‐14). 

The diamond model will be used to asses Harpa, the case studied in this paper.  

2.6 Snowden’s Cynefin framework 
The Welsh word Cynefin is pronounced ku‐neh‐vin meaning “the multiple factors in our 
environment  and  our  experience  that  influence  us  in  ways  we  can  never  understand”  The 
Cynefin  framework  has  its  roots  in  complexity  science.  It  is  a  decision‐making  and  sense‐
making  model  that  recognises  the  causal  differences  that  exist  between  different  types  of 
systems, (Nilsen, 2013). Cynefin was developed by Dave Snowden for executives and leaders 


to  determine  the  prevailing  operative  context,  helping  them  to  make  appropriate  choices 
(Snowden & Boone, 2007, pp. 2‐4). 

Figure 3, The Cynefin Framework (Snowden & Boone, 2007, page 4) 

The domains of Cynefin are five: Simple, Complicated, Complex, Chaotic and Disorder. 
Each of the domains has its own characteristics and requires different actions or leadership 
style. 

In  the  last  domain  of  Disorder  cacophony  rules,  multiple  perspectives  jostle  for 
prominence and it is particularly difficult to recognize when one is in it. The leader´s job in this 
realm is to break down the situation into constituent parts and assign each to one of the four 
realms, (Snowden & Boone, 2007, p. 7). According to Snowden & Boone leaders face greater 
complexity today. They need tools and approaches to guide them as their intuition, intellect 
and charisma are no longer enough, (Snowden & Boone, 2007, p. 8). 

In  retrospect  the  Cynefin  framework  can  help  analysing  and  understanding  finished 
projects. In this context it is interesting to look at Harpa, the concert and conference centre 
and  figure  out  how  or  whether  the  Cynefin  framework  works  for  assessing  this  type  of 
projects. 


  Characteristics of domain  The leaders´s job  Danger signals  Response to danger 
signals 
Repeatable & predictable  Ensure prober processes  Complacency and comfort  Create communication channels to 
Clear cause‐effect relation  Delegate  Desire to make complex problems  challenge orthodoxy 
Simple

Right answer exists  Use best practices  simple  Stay connected without 


Known knowns  Communicate in a clear way  Entrained thinking  micromanaging 
Fact based management  No challenge of received wisdom  Don´t assume things are simple 
Overreliance on best practice if  Recognize both the value and 
context shifts  limitation of best practice 
Domain of experts  Create panels of experts  Experts overconfident in their own  Encourage external and internal 
Discoverable cause‐effect relation  Listen to conflicting advice  solutions or in the efficacy of past  stakeholders to challenge expert 
Complicated

More than one possible answer  solutions   opinions to combat entrained 


Known unknowns  Analysis paralysis   thinking  
Fact based management  Expert panels   Use experiments and games to 
Viewpoints of non‐experts  force people to think outside the 
excluded   familiar  

Flux & unpredictability  Experiment  Temptation to fall back into  Be patient and allow time for 


Cause‐effect relation coherent in  Allow patterns to emerge  habitual, command‐and‐control  reflection  
retrospect  Increase level of interaction &  mode   Use approaches that encourage 
Complex

No right answers  communication  Temptation to look for facts rather  interaction so patterns can emerge  


Many competing ideas  Help generate ideas  than allowing patterns to emerge  
Need for creativity & innovation  Open up for discussions  Desire for accelerated resolution 
Pattern‐based leadership  Stimulate attractors  of problems or exploitation of 
Encourage dissent and diversity  opportunities  
Manage starting conditions 
Monitor for emergence 
High turbulence  Look for what works instead of  Applying a command‐and‐control  Set up mechanisms (such as 
No clear cause‐effect relationship  seeking right answers  approach longer than needed   parallel teams) to take advantage 
No point looking for right answers  Take immediate actions to re‐ “Cult of the leader”  of opportunities afforded by a 
Chaotic

Unknowables  establish order  Missed opportunity for innovation   chaotic environment  


Many decisions, no time to think  Provide clear, direct  Chaos unabated   Encourage advisers to challenge 
High tension  communication  your point of view once the crisis 
Pattern‐based leadership  has abated  
Work to shift the context from 
chaotic to complex  
Table 2: Decision in Multiple Contexts: Based on A Leader´s guide (Snowden & Boone, 2007, page 7) 

3. METHOD 

The main objective of the research is to generate a framework to understand and enable 
comparison  of  grand  concert  hall  projects  to  assess  their  outcome  and  important  success 
factors. The framework is tested on Harpa, Reykjavík´s new concert and congress centre. The 
decision  making  process  is  studied  and  the  fulfilment  of  the  original  feature  objectives 
analysed. 

3.1 General  
Grand concert halls and opera houses as a phenomenon can physically be characterized 
by their auditorium, stage and back stages along with the audience foyer area, artist area and 
all  the  necessary  complex  technical  spaces,  equipment  and  supporting  areas.  But  grand 
concert  halls  and  opera  houses  differ  both  in  size,  appearance  and  structure.  Their  urban 
context and architecture varies, their operational model is different and the justification for 
their existence is based on different needs, desires and objectives. There are several ways to 
assess and understand this kind of projects and to compare their outcome. 

10 
Traditional methods for assessing success and failures of projects have roots in the “Iron 
triangle” approach stating that project success depends on the three constraints; time, cost 
and quality. Projects delivered within the agreed time and budget, according to the clients 
specifications are successful, other fail. Both IPMA ICB and PMBOK have added parameters to 
the iron triangle and scholars have questioned this method for assessing success, especially 
long term success. Among them are Shenhar and Dvir. 

3.2 The assessment tools 
Shenhar and Dvir developed a dynamic concept for assessing project success along with 
a Diamond shaped framework identifying key dimension of projects (Shenhar & Dvir, 2007). 
Their contribution adds to the methodical approach of project success and their nature, but it 
does  not  fully  explain  the  political  background  and  causes  for  scope  change  and  biased 
decisions. 

According  to  Flyvbjerg´s  studies,  most  projects  have  cost  overruns  and  suffer  from 
benefit shortfalls caused by biased overestimation of benefits and underestimation of costs, 
(Flyvbjerg,  2007).  Flyvbjerg´s  analytics  tool  indicates  that  most  project  fail,  but  his  seven 
causes of planning problems can add to the understanding of what to avoid and be aware of 
especially in the initiating and planning phase of projects.  

Snowden´s  Cynefin  decision‐making  and  sense‐making  model  helps  determine 


prevailing characteristics of projects both during the project and in retrospect.  

Project success can also be evaluated by building a model or framework trough analysis 
of existing data, trough surveys and interviews.  

Therefor the research method is based on building a conceptual framework based on 
the methods mentioned above, through a survey and by studying and evaluating data from 
the case study.  

3.3 The case study and definition of the framework 
To understand and analyse Harpa and the development of the project, the existing data 
describing the major milestones, decisions, change of project scope and estimated cost was 
reviewed, and set up in a frame that developed through the research. Among explored data 
and information are the following: 

11 
1. The cost estimate for the original winning proposal for a concert hall in Reykjavik from 1985, 
(Nefnd um málefni tónlistarhús, 1997). 
2. An opinion of the initial committee, appointed by the Minister of education, including the 
initial cost estimate for construction and operation, (Nefnd um málefni tónlistarhús, 1997). 
3. Concert  hall  and  Conference  centre,  Utilization  and  feasibility  assessment,  (VSÓ  Ráðgjöf, 
1998). 
4. Agreement between City of Reykjavík and the Government of Iceland for the construction of 
concert hall and conference centre, (2002). 
5. Information  Memorandum,  Proposed  Concert  Hall,  Conference  Centre  and  Hotel  Complex 
Reykjavik, (Austurhöfn‐TR ehf, 2003). 
6. Descriptive Document no. 13571 for PFI Works Concession for planning, designing, building, 
owing and operating a Concert & Conference Centre and Hotel (CCH), along with pertinent 
car  parking  facilities  in  the  east  harbour  in  Reykjavik,  (Austurhöfn‐TR;  Ríkiskaup;  VST; 
Landwell, January 2005).  
7. Article  about  the  signing  of  the  contract  between  the  Client  [Austurhöfn]  and  the  PFI 
contractor [Portus], March 09, 2006, (Morgunblaðið, 2006). 
8. Annual financial statements for Harpa, 2012 (2013) and 2013 (2014). 
9. Overview of the utilization of auditorium and halls in Harpa, year 2013, (Guðmundsson, 2014). 

3.4 Consulting interviews  
To get a deeper understanding of specific aspects of the project three major participants 
in  the  project  were  consulted  (rather  than  interviewed).  They  were  Sigurður  Einarsson 
responsible architect of Harpa (Einarsson, 2014), Sigurður R. Ragnarsson Program Manager of 
the Harpa project (Ragnarsson, 2014), and Ríkharður Kristjánsson Design Manager of Harpa 
and Project Manager for the glass envelope, (Kristjánsson, 2014). 

3.5 The questionnaire 
The  questionnaire  survey  was  conducted  in  SurveyMonkey  on  the  Internet.  It  was 
opened on  April 07, 2014 and the latest responses where gathered on April 25, 2014. The 
questionnaire  consisted  of  43  questions.  30  questions  based  on  rephrasing  the  feature 
objectives and future vision for Harpa as if they had come true. The participants were asked 
on Likert scale whether they: strongly agree, agree, neither/nor agree, disagree or strongly 
disagree with the presented statements. The rephrased feature objectives were divided into 
four  groups;  General  objectives  (6),  Location  objectives  (6),  Buildings  objectives  (6)  and 
operational objectives (4). Additionally the future vision for Cultural importance was broken 
down to eight (8) statements. Those questions were followed with nine (9) question about 

12 
“What went well and what could have been done better, along with question about the most 
important function in Harpa”, one (1) about the symbolic meaning of Harpa, one (1) question 
about  the  respondents  involvement  in  the  project  and  finally  one  (1)  question  about  the 
respondents role and responsibility in the Harpa project. 

3.6 The questionnaire survey participants 
The  purpose  of  the  questionnaire  survey  was  to  identify  the  perception  of  the 
respondents toward the feature objectives set at the start of the competitive dialogue of the 
Harpa in 2004/2005. The participants were divided into two target groups. Those involved (the 
stakeholders) in the project at some stage from antecedent stage to operation, and a control 
group not involved in the project. 

The involved group was put together by identifying names of people that at some stage 
have been mentioned in connection with the project, such as boosters, politicians, promoters 
and decision makers, members of several committees, client, advisory groups, members of 
the design and construction team, daily operators and art board of Harpa, residents in Harpa, 
music  and  architecture  critics,  professional  gatekeepers  of  music  and  architecture  and 
professionals connected to conference and tourism. The survey was sent to 183 recipients and 
93 answered the survey (8 partially and 85 completely), 51%. Additionally the questionnaire 
survey was sent to the staff (members) of the primary artistic companies residing in Harpa ‐ 
through email and Web Link. The sample size is unknown but gathered 36 responses.   

A Total of 129 responses were gathered from individuals identified as involved. 

A list of those not involved was sent to an email group of people known to the surveyor 
as probably not having connection to the project. The survey was sent to 95 recipients and 50 
answered  the  survey  (6  partially  and  44  completely),  53%.  Additionally  the  questionnaire 
survey was sent to an open group at Reykjavik University, University at Bifröst and the MPM 
alumni  network  through  email,  Facebook  and  Web  Link.  The  sample  size  is  unknown  but 
gathered 69 responses.   

A Total of 119 responses were gathered from those not involved. 

248  answered  the  questionnaire  survey  (33  partially  and  215  completely).  The  ratio 
between involved/not involved is 129 / 119 ‐ (52% / 48%). 

13 
3.7 Processing and interpretation of data 
The result of the survey was partly analysed with help of the internet survey program 
SurveyMonkey by filtering and comparing the responses. The results were also analysed in 
Excel spread sheet program, calculating average response for each feature objective group 
(General, Location, Buildings, Operation and Cultural importance). The relation between those 
involved in the Harpa project and those not involved was investigated as well as the relation 
between different roles and responsibility of those involved. 

4. RESULTS  

By  studying  existing  information,  and  by  comparing  the  different  phases  of  the 
development of Harpa, the Concert and Conference Centre in Reykjavik, the research resulted 
in a framework addressing four different major attributes that seem characteristic for grand 
concert  halls  and  opera  projects;  Planning,  Design  &  Construction  attributes,  Operational 
attributes, Context & Features and Project Management attributes. Additionally the utilization 
of four different assessment tools developed by Flyvbjerg, Shenhar and Dvir, and Snowden 
helped understanding and defining the speciality of concert halls.  Each of the major attributes 
is divided in several sub‐issues. 

Attributes   
Planning, Design & Construction  General 
attributes  Time span of the project 
Building Metrics  
Construction cost figures 
Operational attributes  Seat Capacity & type  
Annual number of events 
Operating figures 
Operational personnel & artists   
Context & Features  Urban context 
Architectural context 
Operational features 
Feature Objectives 
Project Management attributes  Project management data 
No. of drawings / documents 
Specific assessment tools  Flyvbjerg´s 7 causes for planning problems 
Diamond assessment ‐ NTCP 
Project success factors 
Snowden´s Cynefin lens 
Table 3, The main attributes of the Conceptual framework, 

4.1 Planning, Design & Construction attributes 
The planning, design & construction attributes are divided in four sub‐issues; General, 
Time  span,  Building  metrics  and  Construction  cost  figures.  Each  of  the  sub‐issues  include 

14 
several important parameters that has to be considered depending to the relevant project 
phase.   

Attributes  Relevance for  Parameter


project phases 
General  Planning Date of information
  Implementing  Scope of project 
Closing  Justification  
Operation  Funding 
Procurement process 
Time span of the project  Planning Antecedent period
Planning, Design and Construction attributes 

Implementing  Planning period 
Closing  Start of design 
Operation  Date of contract 
Start of Construction 
End of Construction 
Years under construction 
Excelled construction time acc. to plan 
Building Metrics   Planning Total Area (sqm)
Implementing  Increase of area from forecast (%) 
Closing  Total Volume (m3) 
Operation  Volume/Area Ratio 
Auditoriums / Total Area Ratio 
Height (architectural) 
Floors (above ground) 
No. of indoor parking valets 
Construction cost figures  Planning Building costs without VAT (MUSD)
Implementing  Increase from forecast (%) 
Closing  Building cost pr. sqm (USD)  
Building cost pr m3 (USD) 
Increase of sqm‐cost from forecast (%) 
Table 4, The Planning, Design & Construction attributes 

The Harpa case study indicates a considerable scope‐creep from the initial definition in 
1997.  It started as a concert hall with a single auditorium to be located 5 km away from the 
city centre. Six years later in the beginning phase of the competitive dialogue it was defined 
as  a  “…  major  complex  in  central  Reykjavik  comprising  a  Concert  Hall,  [Recital  Hall], 
Conference Centre and Hotel with a further opportunity to develop office or retail elements 
as an integral part of the scheme”, (Austurhöfn‐TR ehf, 2003). During the competitive dialogue 
a fourth hall was added to the scheme. The scheme that was chosen for implementation was 
31%  bigger  than  requested  in  the  programme.  The  investor  justified  this  scope  change  by 
arguing it better suited their business strategies. Due to the financial crisis of 2008 only the 
Concert  and  Conference  Centre  was  built.  The  justification  for  the  project  remained 
unchanged from the initiating phase in 1997, expressing an unanimous opinion that a new 
concert house should be built, due to the extremely flourishing music scene,  due to the poor 
facilities for concerts available, due to lack of residence for the Icelandic Symphony Orchestra, 
due to a demand for equal treatment of all the art forms, and finally that facilities for music 
performances  in  Iceland  remain  far  behind  neighbouring  countries,  (Nefnd  um  málefni 
tónlistarhús, 1997). Initially (1997), the funding was to be divided between the State and City 

15 
of  Reykjavík  (52%/48%).  The  idea  of  PFI‐Private  finance  initiative  and  operation  was 
introduced early in the planning phase (1998), and remained unchanged until 2009 when the 
Government and City of Reykjavik stepped in and took over the project due to insolvency of 
the  investor.  Despite  thorough  risk  assessments  of  many  project  factors  no  special  risk 
assessment for insolvency of the investor and bankruptcy of the Icelandic banking system was 
undertaken, (Kristjánsson, 2014). 

The  time  span  of  the  Harpa  project  covers  more  than  30  years.  The  facilities  for  the 
Icelandic symphony orchestra were sub‐standard for years. The 13 year long antecedent phase 
started in 1983 with the establishment of The Association for a New Concert hall. It defined a 
brief  for  a  new  concert  hall,  collected  funds  and  held  an  architectural  competition  for  the 
concert hall in 1985. That project was never realized. The nine year planning period started 
with a committee appointed by the Minister of Education in 1996. In June 1997 the committee 
delivered its report unanimously agreeing that a new concert house should be built. Several 
committees  followed  that  confirmed  that  opinion.  The  Government  of  Iceland  and  City  of 
Reykjavík signed an agreement for construction of the Concert & Congress Centre and Hotel 
(CCH) in April 2002. A year later, a request for prequalification was announced and the start 
of the competitive design phase started in late 2004. In the autumn of 2005 the winner, Portus 
group  was  announced.  The  concession  contract  was  signed  in  March  2006  follows  by  the 
design of the Concert and Conference Hall. The construction started late 2006, to be finished 
in September 2009. Due to the insolvency of the investor in 2008, the project was stalled for 
six  months,  until  the  company;  Austurhöfn,  owned  in  solidum  by  the  State  and  City  of 
Reykjavik, (54% / 46%) commenced work, deciding to extend the construction time by almost 
two years.  

After  the  insolvency  of  the  investor  2008,  a  fierce  debate  was  launched  whether  to 
proceed  with  Harpa  or  not.  According  to  the  total  responses  in  a  questionnaire  survey 
conducted in April 2014 a majority of the respondents disagree or strongly disagree with the 
statement that the decision to proceed with construction of the concert hall and conference 
hall Harpa in the wake of the economic crisis was wrong. Of 212 responses, 77,1% disagree or 
strongly disagree that decision was wrong. 14,2% agree or strongly agree that the decision 
was right  

16 
It took 4,8 years to build Harpa, and the exceeded construction time compared to the 
contracted plan was 23 months. 

In addition to the scope changes, the size requirements for Harpa changed increased 
during the planning period. The committee appointed by the Minister of Education concluded 
in 1997 that the size of the Concert Hall building was suitable at approx. 8‐8.500 sqm., more 
than 2.000 sqm smaller than the original requirement analysis for a new concert hall from 
1985.  A year and half later the size had grown by 61%, now almost 13.700 sqm. In April 2002 
the  Government  of  Iceland  and  City  of  Reykjavik  agreed  on  a  scheme  that  had  grown  by 
another 10%, to 15.000 sqm. At the start of the competitive design phase in late 2004 the 
requirement went up by 17% again and the competitors were meant to deliver a 17.500 sqm. 
Concert and Conference Hall.  

The final project is 29.865 sqm., almost 71% bigger than requested by the Client and 
almost 251% bigger than estimated by first committee in 1997 which made the grounds for 
the initiating decision to proceed with the project.  

With its volume of 249.046 m3 the Volume/Area, Ratio is 8,34 and the Auditorium / Total 
Area, Ratio is 0,15. 

It has proved difficult to elicit exact construction cost figures for the Harpa project.  

The building cost figures are uncertain to the public according to the total responses in 
a questionnaire survey conducted in April 2014. Of 212 responses, 2,8% consider it likely that 
the building cost of Harpa was within the estimated cost, 6,1% consider the excelled cost to 
be under 10%. 7,1% consider the excelled cost to be under 20%. 16,1% consider the excelled 
cost to be under 30% and 32,1% consider the excelled cost to be under 40%. 35,9% of the 
respondents  indicate  other.  Some  consider  the  he  criteria  of  question  to  unclear  to  be 
answerable. Other indefinite the cost to have excelled at least 50‐600% and consider it either 
a total failure or acceptable because of positive outcome of the project. 

As  well  as  the  scope  and  the  size  of  the  project  have  changed,  the  estimated 
construction cost has correspondingly changed. By the initiative cost estimate from 1997 the 
cost  was  equivalent  to  32  million  US  dollars  (MUSD)  present  value  (Dec.  2011),  3.809 
USD/sqm.  At the start of the competitive design phase in late 2004 the cost estimate was 
equivalent  to  127  MUSD  /  7.264  USD/sqm.  When  the  concession  contract  between  the 

17 
investor Portus and the Client Austurhöfn, on behalf of the Government of Iceland and City of 
Reykjavík, was signed, the estimated price tag on the building was 192 MUSD, 51% higher than 
the Clients estimated cost. 

The price tag on the final project final project is approx. 226 MUSD. The construction 
cost is 18% higher than the contract figure, 78% higher than the clients estimated cost at the 
start of the competitive dialogue in 2004 and the sqm‐cost of the final project is 4,2% higher 
than the clients estimated sqm‐cost at the start of the competitive dialogue.  

The building cost pr. sqm. is 7.568 USD and the cost pr. m3 is 908 USD.  

4.2 Operational attributes 
The operational attributes are divided in four sub‐issues; Seat Capacity, Annual number 
of  events,  Operating  figures  and  Operational  personnel  &  artists.  Each  of  the  sub‐issues 
include several important parameters that has to be considered depending to the relevant 
project phase.   

Attributes  Relevance for  Parameter


project phases 
Seat Capacity  Planning Auditorium A (seats)
Implementing  Auditorium B (seats) 
Closing  Auditorium C  (seats) 
Operation  Auditorium D (seats) 
Meeting facilities (Seats / rooms) 
Total number of auditoriums 
Total number of seats 
Annual number of events  Planning No. of concerts and opera events
Operation  No. of conference events & meetings 
No. of art events 
Operational attributes 

Other activities/events 
Total no. of events 
Average (daily) load (%) 
Annual days in use ‐ (Average) 
Annual number of concert guests 
Annual number of guests 
Upland‐market 
Inhabitants pr. seat 
Operating figures  Planning Annual revenue (MUSD)
Operation  Annual expenses (MUSD) 
EBIDTA (MUSD) 
Operational cost pr sqm (USD)  
Real Estate Value (MUSD) 
Annual property tax (MUSD) 
Operational personnel & artists   Planning No. of personnel 
(equivalent to full positions)  Operation  Sqm. pr staff member 
No. of artists  
Total no. of personnel and artists 
Table 5, The operational attributes 

The case study of Harpa indicates a continued development of the estimated need for 
auditoriums in the Concert Hall.  The requirement analysis for a new concert hall made by The 
Association for a New Concert Hall in 1985, assumed only one auditorium with 1200‐1300 seat 

18 
capacity.  The Committee for Concert Hall appointed by the Minister of education in 1996 
added a possible smaller auditorium with 300‐400 seats for conferences, In the 1998 feasibility 
assessment, the auditorium was slightly bigger >1300 seats, and the conference auditorium 
750 seats. In the agreement between the Government of Iceland and the City of Reykjavík in 
April 2002 the estimated need for concert auditorium has grown to 1300‐1500 seats and a 
smaller  recital  hall  with  450  seats  was  added  to  the  scheme  as  well  as  number  of  smaller 
meeting rooms. At the start of the competitive dialogue the grand auditorium was enlarged 
further  and  could  seat  1500‐1800  people.  The  fourth  auditorium  with  195  seats  was  also 
added.  Specific  justifications  for  these  scope  changes  are  nowhere  to  be  found  in  the 
exchangeable data. 

The final project has four auditoriums, the biggest one seating up to 1800 people. The 
total  capacity  in  the  auditoriums  is  3.355  seats.  Additionally  there  are  13  smaller  meeting 
rooms. 

The  primary  criteria  for  a  new  Concert  Hall  is  based  on  estimated  annual  number  of 
events  and  visitors.  The  initial  estimate  from  1997  assumes  the  total  number  of  events  to 
exceed  450,  with  more  than  158.000  visitors  and  average  seat  load  70%.  The  feasibility 
estimate from 1998 assumes 580 total number of events, with more than 320.000 visitors. 
The information memorandum dated 2003 assumes the total number of events of 619 and 
323.000 annual visitors. 

According to the an overview of the annual number of events in Harpa (Guðmundsson, 
2014) the total number of events in the year 2013 were 957, divided between 514 concert 
and opera events, 291 conference events, 40 art events and 112 other events. The average 
load was almost 66% and the average use of the auditoriums was 239 days. The total number 
of concert guest is estimated >325.000 and the total number of guests in the house exceeded 
1.300.000, an increase of 30% from year 2012. 

The  Information  memorandum  (May  2003)  forecasted  annual  revenue  of  6,0  MUSD, 
annual expenses of 5,2 MUSD and EBIDTA +0,8 MUSD.  

Harpa has now been in operation for two whole years. The operational figures show that 
in year 2013 the annual revenue was 7,8 MUSD (873,1 MISK), the annual expenses were 12,5 
MUSD (1.404,5 MISK) and the EBIDTA therefor ‐4,7 MUSD (‐531,4 MISK). The operational cost 

19 
pr. sqm. was 419 USD (47.028 ISK). The real estate value is 198,1 MUSD (22.224 MISK). Despite 
the operational cost pr. sqm. is up by 52 USD from year 2012 the EBIDTA has increased by 0,5 
MUSD (53,5 MISK). Harpa pays annually 3,3 MUSD (353,7 MISK) in property tax which is almost 
four times higher than estimated in initial figures.  

Harpa is a day to day workplace of 86 employees in 64,5 full positions whereof 62 are 
the operating staff of Harpa. The other 14 are employees of the Icelandic Symphony Orchestra 
and  the  Icelandic  Opera.  The  members  of  the  Icelandic  Symphony  Orchestra  are  81  and 
Reykjavik Big Band has 18 members. The members of the Icelandic Opera are contracted, and 
depending  on  the  performing  operas  performances,  their  number  varies  from  100‐200. 
Notably, the initial estimate from 1997 for operational personnel assumed only 3 employees. 
Already in the following feasibility assessment, dated 1998, their number had increased to 
22+34  in  temporary  positions  and  another  20  in  undefined  temporary  positions.  The 
difference between the first estimate and the actual figures remains unexplained. 

4.3 Context and Features 
The Context and Features are divided in four sub‐issues; Urban Context, Architectural 
context, Operational features and Feature objectives. Each of the sub‐issues includes several 
important parameters that have to be considered depending on the relevant project phase.   

Attributes  Relevance for  Parameter


project phases 
Urban context  Planning Location
Operation  Location objectives 
Architectural context  Planning Architectural objectives
Operation  Acoustics 
Nominations and awards 
Context and Features 

No. of articles in Architecture magazines 
Operational features  Planning Operational objectives
Implementing  Functionality 
Closing  Auditoriums 
Operation  Conference facilities 
Other specific facilities 
Feature Objectives  Planning General
Implementing  Location 
Closing  Buildings (Acousitcs) 
Operation  Operation 
Cultural importance 

Table 6, Context and Features 

The  earliest  estimate  (1997)  lists  3  to  4  possible  sites  for  the  new  Concert  Hall.  The 
feasibility  assessment  (1998)  proposes  a  location  near  the  old  harbour  in  Reykjavik.  The 
agreement between the Government of Iceland and City of Reykjavík (2002) consolidates the 
choice  of  location  in  the  East  harbour  Area  in  Reykjavik  with  reference  to  the  result  in  a 

20 
planning  competition  from  year  2000.  The  owner  sees  Harpa  as  an  important  factor  for 
renewal of the harbour and the city area. 

The location objectives were defined in the CCH‐Descriptive document at the start of 
the competitive dialogue in January 2005. According to the total responses in a questionnaire 
survey  conducted  in  April  2014,  87,7%  agree  or  strongly  agree  that  the  location  of  Harpa 
strengthens the heart of city centre, 85,3% agree or strongly agree that the location of Harpa 
strengthens the image & identity of the city centre and 79,5% agree or strongly agree that the 
location develops impressive settings for culture, tourism, business and services.  

The initial estimate (1997) does not mention the Concert hall in an architectural context. 
The feasibility assessment (1998) mentions the importance of good design and finishing. The 
Information Memorandum (2003) specifies, among other issues, the expectations to create a 
“beacon” or icon symbolising Reykjavik City Centre. The architectural objectives were defined 
in the CCH‐Descriptive document at the start of the competitive dialogue in January 2005. 
According to the total responses in a questionnaire survey conducted in April 2014, 78,04%  
agree or strongly agree that Harpa provides strong cultural image which draws the attention 
of  the  world  towards  Reykjavík  and  Iceland,  84,7%  agree  or  strongly  agree  that  Harpa 
represents high‐quality architecture, 85,3% agree or strongly agree that Harpa is a landmark 
near the city centre, a symbol for Iceland and the capital city. Furthermore when asked to sort 
by importance, 57,9% define Harpa as a Cultural flagship, 51,4% define Harpa as a Landmark 
and 30,3% define Harpa as a Destination Icon. The respondents were asked also to sort the 
attributes of Harpa by their relevance for the project outcome. The listed attributes appeared 
randomly for each respondent, to be rated by their importance. Of total 215 respondents, the 
acoustics in the main auditorium scored highest. The location was rated in second place, the 
overall architectural quality ranked as the third most important attribute. The 3‐dimensional 
quasi‐brick envelope ranked number four, the conference facilities ranked number five, to be 
followed by the open accessible spaces and the meeting facilities. The restaurants and the 
shops  had  the  lowest  score.  The  comparison  between  the  answers  of  the  stakeholders, 
inhabitants  and  the  control  group  did  not  show  any  significant  difference  in  ranking  the 
relevant attributes.  

The initial estimate (1997) did not specify acoustic demands for Harpa. The feasibility 
assessment (1998) specifies excellent acoustic as the determinant factor in the grand hall. At 

21 
that stage the American firm, Artec consultants that specializes in design of concert halls, were 
hired. The acoustic objectives were defined in the CCH‐Descriptive document at the start of 
the competitive dialogue in January 2005. According to the total responses in a questionnaire 
survey conducted in April 2014, 87,7% agree or strongly agree that Harpa ensures excellent 
acoustics. Furthermore when asked, 88,3 % agree or strongly agree that Harpa has proved 
useful  as  concert  hall,  and  61,8%  agree  or  strongly  agree  that  Harpa  has  proved  useful  for 
amplified rhythm music. 

Number  of  articles  have  been  written  about  Harpa  in  the  national  as  well  as 
international  press  and  architectural  magazines.  According  to  the  building  data  company 
Emporsis, modern concert halls have remarkable architecture offering audiences a great show 
even  before  they  have  taken  their  seats.    They  no  longer  just  rely  on  outstanding 
performances. In a released list by Emporsis, Harpa ranks among the 15 of the World’s most 
spectacular concert halls, (Emporsis, 2014). Harpa has been nominated and won number of 
architectural,  performance,  musical  and  conference  nomination  and  awards.  The  most 
honourable is probably the European Union Prize for Contemporary Architecture ‐ Mies van 
der Rohe Award 2013 (Fundació Mies van der Rohe, 2013). 

Requirements for specific operational features were specified in some context from the 
early  beginning.  A  requirement  analysis  was  made  before  the  architectural  competition  in 
1985. The initial estimate (1997) is partly based on the requirement analysis, but adds new 
features. The opinion of the committee is that the new concert hall must also be available for 
use by conferences and meetings, and a connection to conference facilities is considered of 
beneficial. This opinion is consolidated in the feasibility assessment from 1998, along with the 
requirement of a direct connection to a four star hotel. Only at this stage the importance of 
operational factors such as efficiency and flexibility are highlighted. 

The operational objectives were defined in the CCH‐Descriptive document at the start 
of  the  competitive  dialogue  in  January  2005.  According  to  the  total  responses  in  the 
questionnaire survey conducted in April 2014, 93,0% agree or strongly agree that Harpa is a 
centre for music, culture & tourism, 92,0% agree or strongly agree that Harpa ensures high 
quality conditions for the Icelandic Symphony Orchestra ‐ ISO. Another 81,8% agree or strongly 
agree that Harpa enables high level of utility for pertinent activities. Furthermore 86,0% agree 
or strongly agree that Harpa provides unique facilities for conferences & and associated events, 

22 
but 64,2% agree or strongly agree that Harpa has proved useful for conference centre. 84,3% 
of the respondents answer that Harpa is in line or exceeds their expectations, 77,4% agree or 
strongly agree that Harpa appeals to ordinary people and offers them welcome. 71,0% of the 
respondents had visited Harpa more than 10 times. 

Harpa neither has a stage tower nor a rotating stage. 

The responses for each of the main feature objectives groups was summarized. 215 of 
the 248 respondents answered all questions. The following radar chart shows the distribution 
of all the 215 answers, (Figure 4). 

 
Figure 4; Distribution of the 215 respondents who answered all the questions 

Of those who answered all questions, 86,7% agree or strongly agree that the six general 
objectives  for  Harpa  have  been  met,  3,8%  disagree  or  strongly  disagree.  65,5%  agree  or 
strongly  agree  that  the  six  Location  objectives  for  Harpa  have  been  met,  8,7%  disagree  or 
strongly disagree. 78,9% agree or strongly agree that the six buildings objectives for Harpa 
have been met, 4,3% disagree or strongly disagree. 76,6% agree or strongly agree that the 
four operating objectives for Harpa have been met, 3,3% disagree or strongly disagree. Finally, 
73,8%  agree  or  strongly  agree  that  the  seven  vision  statements  for  cultural  importance  of 
Harpa have been met, 5,1% disagree or strongly disagree.  

23 
The relation between the respondent’s relation to Harpa and their answers is significant. 
The  “stakeholders”  are  in  general  more  positive  than  the  “inhabitants”  and  the  “external 
control group”. The farther the respondents are from the project the less positive they are, 
(Figure 5, 6 and 7). 

 
Figure 5, Responses of the stakeholders, inhabitants and external control group that agree or strongly agree 

 
Figure 6, Responses of the stakeholders, inhabitants and external control group that are neutral  

 
Figure 7, Responses of the stakeholders, inhabitants and external control group that disagree or strongly disagree 

24 
There is also a visible relation between the roles and responsibility of the respondents 
and  their  answers.  The  group  of  the  designers,  constructors  and  investors  are  the  most 
positive towards Harpa. The group of those who are connected to conferences and tourism 
have  the  most  critical  attitude,  especially  towards  the  location  and  operational  objectives, 
(Figure 8, 9 and 10).  

 
Figure 8, Agreeing or strongly agreeing answers in relation with roles and responsibility 

 
Figure 9, Neutral answers in relation with roles and responsibility 

 
Figure 10, Disagreeing or strongly disagreeing answers in relation with roles and responsibility 

25 
4.4 Project Management  
The Project management attributes are divided in two sub‐issues; Project management 
data and No. of drawings / documents. Each of these sub‐issues include several important 
parameters that have to be considered depending to the relevant project phase.   

Attributes  Relevance for  Parameter


project phases 
Project management data  Planning Internal quality management and control  
Implementing  No. of certified Project managers (IPMA, PMI) 
Closing  WBS / Number of work tasks 
Project Management 

Registered official inspections / audits 
No. of project meetings 
No. of participating companies  
No. of main contractor staff  
Nationalities involved 
No. of drawings / documents  Planning No of published drawings to Building Officer 
Implementing  Total no. of drawings (excl. shop dwg´s) 
Closing  No. of drawings pr sqm 
No. of shop (manufacturing) drawings 
Table 7, Project Management 

The  case  study  of  Harpa  indicates  an  ambitious  and  complex  project.  It  demanded  a 
clear  organizational  structure.  The  main  contractor  IAV  (Iceland  Prime  Contractors)  was  in 
charge of the design and construction. The execution of the project was a novelty in project 
management with in the firm. Therefor the contractor hired experienced project managers to 
lead  and  manage  the  project.  An  on‐side  project  office  was  established  to  enforce 
collaboration and prevent gap between the design team and the contractor. It became the 
core of the project development. An open dialogue between the design/construction team 
and  the  Client  –  Austurhöfn,  was  considered  of  high  importance  as  well.  According  to  the 
responsible  architect  Sigurður  Einarsson  and  both  the  Programme  Manager  Sigurður  R. 
Ragnarsson and the Design Manager Ríkharður Kristjánsson, Harpa is the most complex and 
risky project they have participated in, (Einarsson, 2014), (Ragnarsson, 2014), (Kristjánsson, 
2014).  

The  contractor  is  certified  by  ISO  9001  quality  management  system.  More  than  30 
nationalities,  over  1.250  employees  and  almost  1.000  subcontractors  were  involved  in  the 
project at various times. At peak, the working force in the building exceeded 700, working on 
different work tasks that counted more than 5.000. Registered official inspections counted 
more 1.640 and estimated number of project meetings were more than 5.000, (IAV, 2013). 
According to the minutes from the final walk down, 5.174 drawing had been published to the 
building authorities during construction, many of them issued more than once or twice. It is 

26 
estimated that the total number of drawings exceeded 20.000. That means 0,67 drawings pr. 
sqm. of built space.  

4.5 Specific assessment tools 
The  Specific  assessment  tools  are  divided  in  four  sub‐issues;  Flyvbjerg´s  7  causes  for 
planning  problems,  Project  success  factors,  Diamond  assessment  –  NTCP  and  Snowden´s 
Cynefin lens. Each of the sub‐issues include several important assessment parameters. 

Attributes  Relevance for  Parameter


project phases 
Flyvbjerg´s 7 causes for planning  Planning Long planning horizons and complex interfaces 
problems  Implementing  Non‐standard technology 
Closing  Decision making process with many actors and conflicting interests 
Operation  Changing project scope and ambition level over time 
Inadequate budget contingencies 
Consequent misinformation about cost, benefits and risks 
Overruns and/or benefit shortfalls as result 
Specific assessment tools 

Project success factors  Planning Project efficiency


Implementing  Impact on Customer 
Closing  Impact on Team 
Operation  Business & direct success 
Preparation for future 
Diamond assessment ‐ NTCP  Planning Novelty
Implementing  Technology 
Closing  Complexity 
Operation  Pace 
Risk 
Snowden´s Cynefin lens  Initiating
Planning   
Implementing  Simple – Complicated – Complex – Chaotic ‐ Disorder 
Closing 
Operation 
Table 8, Specific assessment tools 

Flyvbjerg´s 7 causes for planning problems  
Flyvbjerg argues that seven following characteristics are the cause of planning problems 
in most infrastructures, including concert halls, (Flyvbjerg, 2007).  

Planning horizons and interfaces: Flyvbjerg argues that if the planning horizons are long 
and if the project interfaces are complex the risk for project derailment will be bigger. As for 
the Harpa project, the antecedent and planning period ranged over 20 years. During that time 
several shifts occurred within the political arena both on national plan and on regional level. 
That also applies for the representatives for the most active stakeholder – the music scene in 
Iceland.  

Technology: Flyvbjerg argues that non‐standard technology increases the risk for project 
derailment. This applies for the Harpa project. The design and construction of the building was 
new to the design team and the contractor.  The decision for the “Quasi‐brick“  structural and 

27 
glazing system was probably the single most risky part of the project, (Kristjánsson, 2014). It´s 
cost was more than 10% of the total construction cost. With more than 10,000 shop drawings 
it had never been done before and demanded very complicated calculations and late design 
freeze. Due to failure in the chemical composition of the steel elements, the first iteration of 
the 3‐dimensional structure was torn down and replaced with new structural elements.  

Decision  process,  actors  and  interests:  Flyvbjerg  argues  that  many  actors  and 
conflicting interests are likely to have negative or confusing impact on the decision process. 
During both the antecedent and planning period of the Harpa project, there were many actors 
and divergent interest. Several responsible politicians, committees and representatives from 
different sectors of the music scene along with representatives for the tourism and conference 
industry were involved. The study of the development of the Harpa project indicates that they 
had  different  views  on  i.e.  the  location,  the  scope,  the  acoustic  demands  and  additional 
services. The satisfaction with the acoustics in the main auditorium varies. It is meant to serve 
all music genres, but does not fulfill the expectations for amplified rhythm music according to 
information and outcome of the survey in this paper. 87,7% agree or strongly agree that Harpa 
ensures excellent acoustics, but only 61,8% agree or strongly agree that Harpa has proved 
useful for amplified rhythm music.  

Project scope and ambition: Flyvbjerg argues that changing project scope and ambition 
level  over  time  may  have  negative  impact  on  the  project  success.  The  study  of  the  Harpa 
project  reveals  significant  change  in  the  project  scope  and  the  ambition  level  trough  the 
planning and tender period of the project. The project scope and ambitions expanded almost 
every time a decision was taken or confirmed. It started as a stand‐alone concert hall of 8.500 
sqm.,  estimated  to  cost  32,4  MUSD.  When  the  project  was  out  for  PFI  tender  it  included 
17.500  sqm.  Concert  &  conference  centre,  estimated  to  cost  127,1  MUSD,  to  be  built  in 
connection with 18.000 sqm. Hotel complex and business area. The final project is a combined 
Concert and Conference Centre, 28.813 sqm. in size and the final cost is 226.000 MUSD. 

Budget contingencies: Flyvbjerg argues that inadequate budget contingencies can have 
significant impact on the decision process that can lead to cost overruns. The study of the 
Harpa  project  suggests  that  budget  contingencies  –  if  they  ever  existed  –  never  were 
published. 

28 
Misinformation  about  cost,  benefits  &  risks:  Flyvbjerg  argues  that  promoters  and 
forecasters  intentionally  underestimate  cost  and  overestimate  benefits  to  get  project 
approval.  Therefore  a  deliberate  and  strategically  consequent  misinformation  about  cost, 
benefits and risks is common in projects, causing unprofitable investments of money and time, 
(Flyvbjerg,  2007).  The  study  of  the  development  of  the  Harpa  project  corresponds  to 
Flyvbjerg´s  arguments  on  deliberate  misinformation.  The  original  cost  estimate  from  1997 
assumed a sqm. price of 3.809 USD. The final sqm. price is 7.568 USD, an increase by +98,7%. 
The initial space program for the building was 8.500 sqm., 2.000 sqm. smaller than the winning 
competition entry from 1985, which had only one auditorium, (1997).  In the end of the year 
1998 the size had increased with 61% and the sqm. price with 40%, (1998). The operational 
cost pr. sqm. was never calculated separately but the study of data indicates an operational 
sqm.  cost  of  187  USD  in  the  initial  estimate  (1997),  and  346  USD  in  the  Information 
Memorandum (2003). The actual operational cost pr. sqm for 2013 was 419 USD. There are 
no signs of second opinion nor critical questioning of the correctness of cost estimates, space 
programs,  nor  operational  calculations,  in  any  of  the  estimates  published.  The  term  “risk 
analysis” was first introduced when the project was out for PFI tender in 2004/2005, (January 
2005,  pp.  47,  55).  Risk  assessment  for  possible  insolvency  of  the  investor  was  not 
implemented.  

Nothing  in  the  data  examined  indicates  that  promoters,  politicians,  appointed 
committees or cost analysts ever raised questions about the accuracy of the estimates.  

Possible overruns and/or benefit shortfalls: Flyvbjerg argues that many projects suffer 
from  overruns  and/or  benefit  shortfalls  as  a  result  of  misinformation,  inadequate  budget 
contingencies etc. The study of the development of the Harpa project indicates significant cost 
overruns.  The  cost  overrun  is  approx.  18%  from  the  negotiated  project  to  the  final 
construction cost. The final cost is 78% higher than the clients final estimate in the tender 
documents (January 2005), and almost 600% higher than the original estimate from 1997. The 
cost  estimates  where  never  questioned  in  the  planning  period.  The  benefit  shortfall  is 
discernible as the operational revenue was estimated positive at earlier planning stages, and 
due to the legal interpretation by the Land Registry, the actual property tax is more than four 
times higher than predicted, having major influence on the negative business performance of 
Harpa. 

29 
Shenhar & Dvir´s dimensions of project success  
By applying Shenhar and Dvir five dimensions of project success on the Harpa project, it 
both failed and is successful, depending on the dimension. In this assessment, following scale 
is used for assessing respectively failure and success, 1 meaning total failure, 2 meaning mostly 
failure,  3  meaning  50/50  failure/success,  4  meaning  mostly  success  and  5  meaning  total 
success. 

Project efficiency: The project didn’t meet schedule constraint which was exceeded by 
23 months. Scope constraints (the size of the building) increased by 65% from the descriptive 
document to the accepted offer by the investor and constructed building. The project exceeds 
"original"  budget  constraint,  set  by  the  client,  by  78%.  It  final  cost  is  18%  higher  than  the 
investors  offer.  Finally,  the  sqm.  price  decreased  by  9,3%  from  the  investors  offer  in  the 
contract. The calculated final sqm. price is 4,2% higher than set by the client in the descriptive 
document.  

This indicates the project efficiency is equal to 1, meaning Total failure. 

Impact on Customer: According the outcome of the questionnaire survey, Harpa has 
met  the  client’s  specifications,  and  requirements  set  out  in  the  feature  objectives  for  the 
building  and  operations  by  76‐79%.  The  project  benefits  the  customers;  the  client,  the 
inhabitants and guests by 75‐90%. Harpa has provided excellent facilities for music according 
to  the  survey.  The  customer;  client,  inhabitants  and  guests,  are  very  satisfied  with  the 
outcome for classic music, but they are less satisfied with the outcome for amplified rhythm 
music  and  conference  facilities.  The  vast  majority  of  the  respondents  share  the  view  that 
Harpa  appeals  to  ordinary  people  and  is  in  line  or  exceeds  their  expectations.  The  survey 
reveals negative perception towards two main issues, the fact that the conference hotel has 
yet not been built and the surrounding area is still unfinished according to original plans. Harpa 
has been nominated and won several international awards, both for architecture and facilities 
for musical events. As such Harpa is already a brand.  

This indicates the impact on customer is equal to 4, meaning Mostly success.  

Impact on Team: The contractor’s top project  management team of the Harpa went 
through a lesson learned process en the end of the project, (Kristjánsson, 2014) but an overall 
assessment  on  the  team  satisfaction  and  morale  was  never  implemented.  The  Program 

30 
manager, who was the only IPMA‐B certified project manager on the project, went through 
IPMA‐A  certification  after  the  project  was  completed.  The  fact  that  Harpa  has  won 
international awards has, without any doubt, made the participating firms and team members 
proud of their involvement in the project.  

As the overall impact on the team has not been explored it is impossible to draw any 
conclusion on this aspect. 

Business & direct success: Harpa has been in operation for two full years. The Annual 
financial statement for the year 2013, indicates that the sales, profits, ROI, ROE and cash flow 
etc. still has not proved positive. The figures are improving, but there still is a way to go. 

This indicates the Business & direct success is equal to 2, meaning Mostly failure. 

Preparation for future: With the emergence of Harpa, the music scene in Iceland has 
received a long waited facility improvement, especially for classical music. The new facilities 
have  been  positively  welcomed,  by  the  artist,  guests  and  the  gatekeepers  of  the  musical 
profession and the musical scene is indeed flourishing. The conference facilities in Reykjavik 
improved with Harpa, but are still lacking the conference hotel part, it is too early to assert 
that Harpa is prepared for the future of international conferences. With Harpa, the capabilities 
of  attracting  international  artists  and  conferences  to  Iceland  have  greatly  improved.  The 
facilities have all the ingredients to meet a positive future and competitive supply of services. 
Having received international awards Harpa already has advantage in the competitive world 
of cultural tourism. 

This indicates the Project for future is equal to 4, meaning Mostly success. 

Diamond assessment – NTCP 
According  to  Shenhar  and  Dvir  it  is  possible  to  understand  the  key  dimensions  of 
projects, and explain the gaps between expectations and project outcome in retrospect by 
systematically using their multidimensional Diamond framework. By applying the framework, 
the  uniqueness  and  similarities  of  projects  emerges  as  well  as  project  benefits,  risks  and 
possible failures. In the following the Diamond framework, encompassing novelty, technology, 
complexity and pace, is used to assess the Harpa project in retrospect.  

Harpa´s four major components are; the general layout, the building as an architectural 
composition, the envelope, the auditoriums and acoustics.  

31 
Novelty: According to Shenhar and Dvir Novelty is “… determined by the nature of the 
project´s product – how the product is new to the market, the customers, and the potential 
users.”  (Reinventing  Project  Management,  2007,  p.  63).  In  the  start  of  the  competitive 
dialogue,  the  client  envisioned  a  strong  cultural  image,  high  quality  architecture  and  a 
landmark that was to become the symbol for Iceland and Reykjavik. The majority (78%‐86%) 
of respondents in the questionnaire survey agree or strongly agree that these objectives have 
been  met.  The  building,  and  specially  the  3‐dimensional  composition  of  the  envelope  is  a 
distinctive architectural novelty, but the layout, especially for the auditoriums are in general 
based  on  existing  knowledge,  tried  and  tested  before  in  other  contexts,  though  never  in 
Iceland, nor by this contractor. The originality of the 3‐dimensional quasi‐brick envelope is 
new‐to‐the‐world and probably until now the largest artwork of Olafur Eliasson. It demanded 
a  very  late  design  freeze  and  complicated  calculations  before  production  and  construction 
could start. It was also the production of this structure that failed and had to be reproduced. 

By  this,  Harpa  is  considered  an  architectural  composition,  is  considered  a  platform 
project. The 3‐dimensional envelope is considered a breakthrough project.   

Technology:  Shenhar  and  Dvir  “…define  Technology  as  knowledge,  capability,  and 
means  needed  to  create,  build,  manufacture,  and  enable  the  use  of  a  product,  process  or 
service.” (Reinventing Project Management, 2007, p. 81). Harpa can be described as a large, 
complicated  construction  project.  The  knowledge  and  capability  within  the  design  and 
construction  team  was  sufficient  to  meet  the  challenge,  and  as  most  large  prototype 
construction projects Harpa is technically complicated. The only part that can be considered 
as  new‐to‐company  was  meeting  the  technical  specifications  for  the  acoustics  in  the 
auditoriums and the production and construction of the 3‐dimensional quasi‐brick envelope, 
which turned out to be the most technical challenging component of project. 

By  this,  Harpa  is  considered  a  Low‐Tech  project.  The  new‐to‐the  company  acoustic 
specifications along with the 3‐dimensional envelope is considered Medium‐Tech project. 

Complexity:  Shenhar  and  Dvir  define  Complexity  as  “…a  hierarchy  of  systems  and 
subsystems  as  a  natural  way  to  distinguish  among  the  various  project  complexities”. 
(Reinventing Project Management, 2007, p. 102). Harpa is one of the largest and complicated 
buildings ever constructed in Iceland. The design team and major sub‐contractors were spread 
over  seven  countries  on  three  continents.  The  project  is  rather  to  be  considered  as  a 

32 
programme of projects than a single project. It demanded a thorough programme and project 
management on behalf of the main contractor. The Work breakdown structure counted more 
than  5.000  different  work  tasks.  This  demanded  high  degree  of  formality  and  bureaucracy 
along with high degree of communications, both within the design and construction team, 
with the local authorities, the client and the political decision makers. After the economic crisis 
in  2008,  especially  due  to  the  insolvency  of  the  investor,  the  project,  had  to  rely  on  the 
goodwill of political decision makers to get started again and finished. As such Harpa was an 
extremely complex project in Icelandic context, with the exception of the 3‐dimensional quasi‐
brick  envelope.  Despite  of  its  grand  novelty  and  complicated  technology,  the  project 
managerial complexity was not as complex as the rest of the project.  

By this, Harpa is considered an Array project. The 3‐dimensional envelope is considered 
System project.   

 
Figure 11, The Project Diamond for the Harpa project 

Pace:  According  to  Shenhar  and  Dvir  Pace  “…involves  the  urgency  and  criticality  of 
meeting project´s goals. … The time available to complete a project has substantial effect on 
how  a  project  is  managed.”  (Reinventing  Project  Management,  2007,  p.  123).  Harpa  has 
common with many infrastructure projects that pace of the project is to meet long term goals. 
Harpa was of course planned for completion on a certain date, but in the long run it did not 

33 
hurt  the  project  organizational  success  missing  this  deadline.  On  the  contrary  it  helped, 
especially for completing the 3‐dimensional envelope. Because of its own constraints within 
the overall project, and because of the production failure, the 3‐D envelope had to be carried 
out under more time pressure than the rest of the project.  

By this, Harpa is considered a Regular project. The 3‐dimensional envelope is considered 
Fast/competitive project. 

Risk: Shenhar and Dvir define Risk as “undesired event or condition that, if it occurs, has 
negative  impact  on  a  project  objective.”  (Reinventing  Project  Management,  2007,  p.  172). 
Furthermore, they suggest a method for assessing and calculating overall project risk and offer 
a simple formula, based on the Diamond framework, to do that. 

R = a x N + b x T + c x C + d x P 

They suggest values for the for the weights as (a=0,2, b=0,15, c=0,5, d=0,15), giving the 
possible highest risk score of 3,3 and lowest risk score of 1.  

By using Shenhar and Dvir´s calculation formula and suggested weight values the Risk, 
both for the overall Harpa project as well as the  3‐dimensional envelope is: R= 2,20. 

Snowdens Cynefin lens 
Snowden argues that the Cynefin framework helps determine the prevailing operative 
context and understand the key dimensions of project. In retrospect it can help analysing and 
understanding finished projects. By exploring the complexity trend over the lifetime of the 
Harpa project, the danger signals are of special interests, (A Leader´s Framework for Decision 
Making, 2007, p. 7).  

The first committee (1996‐1997) seems to have worked in the simple domain of Cynefin 
and it came to a conclusion based on best practices. In retrospect the dangers signals can be 
traced in the committee´s opinion. There are signs of overreliance on best practices and no 
signs of challenging available information. The reduction of the space programme, the low 
estimated  sqm.  cost,  the  miscalculation  for  need  of  personnel  for  daily  operation  and 
forecasted positive operational balance (Nefnd um málefni tónlistarhús, 1997) are either sign 
of entrained thinking, desire to make complex problem simple, biased optimism, or deliberate 
misinformation (Flyvbjerg, 2007) to increase the likelihood that the project would be realized. 

34 
The  second  available  information  about  the  decision  making  process  in  the  Harpa 
project was published December 1998. It is the first feasibility study prepared by consulting 
engineers (VSÓ Ráðgjöf, 1998). By applying the Cynefin lens, the project moved at this stage 
into  the  complicated  domain,  the  domain  of  experts,  and  stayed  there  for  the  next  seven 
years. A panel of experts was established and stakeholders were consulted. As well as the first 
committee´s  opinion,  this  feasibility  assessment  shows  signs  of  dangers  as  defined  by 
Snowden. (A Leader´s Framework for Decision Making, 2007, p. 7). The experts study does not 
challenge the conclusion of the first committee. Despite the expansion of space programme 
and budget, it is still considerably lower than in the descriptive document published at the 
start of the competitive dialogue (January 2005). The feasibility assessment, as well as all the 
following studies that became the basis of the Harpa project, never indicated signs of external 
challenging of the experts results, and no contingencies, neither for the budget, the space 
programme nor the forecasted operating figures.   

In January 2005, at the start of the competitive dialogue, the project moved into the 
complex domain of Cynefin, which is characterised by the need for creativity and innovation, 
and the many competitive ideas of the competitors for the project. The next eight months 
three teams of investors, contractors, architects, engineers, artists and specialist competed 
for  their  functional,  architectural  and  operational  ideas  based  on  the  clients  envisioned 
objectives.  The  evaluation  of  the  proposals  was  based  on  five  main  factors:  Solutions 
(architecture,  engineering,  etc.)  45%,  Operations  5%,  Program,  activity  and  services  20%, 
Quality and strength of the candidate 5% and Business and price 25%. The selected proposal 
–  Harpa  –  was  31%  bigger  than  requested  by  the  client,  and  exceeded  the  clients  cost 
estimation by 51%. It is noteworthy that the candidate was requested to deliver a special risk 
analysis for the business plan and price, but not for other factors to be evaluated, including 
the quality and strength of the candidate. It is interesting to note the danger signals in this 
complex domain of Cynefin, embodied in the temptation to look for facts rather than emerging 
patterns, and the desire to accelerate resolution of problems. It took the client a month to 
select the most promising proposal. As a part of the selection it was specifically mentioned 
that the company behind the offer was dynamic and financially strong, (Morgunblaðið, 2005). 
A  specific  risk  assessment  for  long  term  solvency  of  the  candidate  was  not  implemented 

35 
(Kristjánsson, 2014). The contract was signed in March 2006. In October 2008 the Icelandic 
banking system went bankrupt and the investor’s solvency no longer existed. 

 
Figure 12, The complexity of the Harpa project trough the lens of Cynefin 

The project remained in the complex domain with the exemption of the 6 month long 
period  of  Disorder  after  the  insolvency  of  the  investor.  In  this  period  there  was  fierce 
discussion whether to proceed or let the half built project remain as it was, as a reminder of 
a bankruptcy of a nation.  Finally the Minister of culture and education, and the Mayor of 
Reykjavik came to the conclusion to take over the project and proceed. It became a challenge 
to  proceed  in  an  atmosphere  of  anger  and  mistrust.  This  called  for  increased  level  of 
interactions and communications. It was decided to slow the project down and finally it took 
another 35 MUSD and 27 extra months to finish the project. Harpa opened preliminary to 
Beethoven’s Symphony no. 9 (Ode to Joy) at May 04, 2011. 

5. DISCUSSION 

The aim of this study is defining a conceptual framework to assess and compare grand 
concert  and  opera  projects,  their  success  and  failures.  The  study  is  based  on  exploring 
accessible  data  from  Harpa,  a  questionnaire  survey,  along  with  four  different  methods  to 
assess projects and project success, with the intention of verifying their applicability for this 
type of projects.  

The study of Harpa revealed several comparable attributes for concert halls. It confirms 
that the justification is basically a cultural statement to peer other cultural activities within 
society as well as other societies. The antecedent and planning time of concert hall and opera 
projects  is  very  long  with  the  probability  of  considerable  scope  creep  as  a  result.  With 
reference to Harpa, it can by asserted that the trend for concert halls is that they are getting 

36 
bigger and more magnificent, resulting in ever higher building costs. Comparable attributes 
that  are  both  important  and  interesting,  but  seldom  displayed  in  publications,  is  the 
Volume/Area Ratio and the Auditoriums/Total Ratio. They are both specific for concert halls 
as the difference is so vast. The volume is more than eightfold the total square meters of the 
building  and  the  total  size  of  the  auditoriums  only  15%  of  the  total  area.  This  helps 
understanding  both  a  high  total  building  cost  as  well  as  higher  building  cost  pr.  sqm.  This 
should be taken in account when planning for new concert halls. 

The explanations for determining the size of the biggest auditorium seem to be based 
on an emotional and strategic estimate, rather than hard facts. The hard fact is that Harpa is 
(still) not sustainable as the EBIDTA is negative.  

The comparable attributes for operations of grand concert halls is the operational cost 
pr.  sqm.  and  sqm.  pr.  staff  member  in  the  building.  These  attributes  should  be  taken  in 
account when forecasting the operational cost for new concert halls.  

The results of the survey offer one mode of assessing the project success of Harpa. The 
client envisioned the future outcome by defining 22 feature objectives and eight statements 
for cultural importance, gathered in five different categories. Somehow it shines through that 
the objectives are a result of the many involved stakeholders desires. Despite the numerous 
and to some extent conflicting objectives they provide a possibility to assess the outcome and 
the possible success of the project.  

The client, mainly the City of Reykjavík, saw Harpa as an important factor for renewal of 
the harbour and the city area. They wanted a “beacon”, an icon and impressive settings for 
culture, tourism and business, and they seem to have got what they desired according to the 
overall results of the survey. With reference to Smith and von Krogh Strand study of the Oslo 
Opera  (Oslo's  new  Opera  House:  Cultural  flagship,  regeneration  tool  or  destination  icon?, 
2011),  the  respondents  ranked  Harpa  primarily  as  a  Cultural  flagship  and  secondly  as  a 
Landmark.  This  indicates,  that  when  envisioning  the  objectives  for  a  concert  hall,  it  is 
important  not  to  forget  the  primary  purpose.  This  was  further  confirmed  by  how  the 
respondents ranked the most important attributes of Harpa. It did not come as a surprise that 
the acoustics were ranked as number one, and location number two. The overall architectural 
quality ranked as the third most important feature of Harpa, higher than the 3‐dimensional 
quasi‐brick envelope, the artwork of Olafur Eliasson that have had the greatest coverage in 

37 
architectural magazines and most discussed by the gatekeepers of architecture. This indicates 
that  when  defining  and  preparing  a  new  concert  hall  or  an  opera  building  one  should  not 
forget the main purpose of the project.  

The  feature  objectives,  both  have,  and  ought  to  have  influence  on  the  main 
characteristics of concert halls and this seems to stem to some point in Harpa. Despite that 
both  boosters  and  gatekeepers  of amplified rhythm  music  fought  for  perfect  amenities  on 
their behalf, this did not get through into to the main feature objectives, and did not get the 
needed  focus  when  the  acoustic  demands  were  finally  designed  and  implemented  in  the 
auditoriums, causing reduced satisfaction among rhythm musicians.  

One of the main objectives for the conference facilities was the connection to a four star 
conference  hotel  beside  Harpa.  The  responses  of  the  survey  indicate  that  Harpa  indeed 
provides unique facilities for conferences, but due to lack of the hotel, and the fact that the 
area around the building is yet not finished, the satisfaction with this part of the scheme is 
lower than aimed for. 

Overall  the  respondents  are  very  positive  towards  the  fulfillment  of  the  feature 
objectives. Following the crisis in 2008, and the re‐opening of the project, one extra attribute 
emerged; to appeal to the public. It became one of the main goals to welcome the public and 
ordinary people. In some extent this seems to be one of the main explanations for the success 
of the project. The building is, on day to day basis, accessible to public, without paying special 
fee for visiting, and according to the survey, over 70% of the respondents have visited Harpa 
more  than  10  times.  Probably  this  also  explains  the  justification  for  proceeding  with  the 
project despite the economic crisis in 2008 that caused to halt.  

The  project  management  attributes  indicate  a  complex  project,  with  great  many 
interfaces.  It  is  somewhat  difficult  to  point  to  one  particular  factor  but  in  future  the 
comparable attributes for project management may lay in the number of the work tasks of 
the  work  breakdown  schedule,  the  number  of  certified  project  managers,  the  number  of 
stakeholders and other measurable attributes as number of drawings pr. sqm.  

The  application  of  the  assessment  tools  revealed  the  usefulness  of  Flyvbjerg´s  seven 
causes of planning problems. It is no doubt that by applying the lens of Flyvbjerg, the question 
of  misinformation,  due  to  delusion  or  even  deception,  becomes  valid.  At  best,  the  Harpa 

38 
project has suffered from optimism bias, at worst from deliberate deception. This appears 
throughout  the  lifetime  of  the  project,  i.e.  due  to  the  total  lack  of  budget  contingencies, 
continuous underestimation of cost and overestimation of benefits, not at least the forecasted 
operational  revenue.  Flyvbjerg  argues  this  could  be  prevented  by  critical  questioning, 
accountability and independent review.  

Snowdens´s  Cynefin  framework  supports  Flybjerg´s  approach  and  vice  versa.  The 
Cynefin  framework  defines  danger  signals  for  each  of  the  domains.  It  warns  against 
complacency, entrained thinking and the desire to make complex problems simple, especially 
in the simple domain, which seem to have been the domain where the initial political decision 
was taken to proceed with the project. When the project moved into the complicated domain, 
the experts may have been too overconfident in the efficacy of the past that seem to have 
confused their estimates. If they i.e. had taken the high Volume/Area ratio in to account, they 
might  have  come  to  more  accurate  cost  estimates.  In  line  with  Flyvbjerg´s  approach,  the 
Cynefin framework suggest challenging the expert’s opinion and combat entrained thinking. 
It  encourages  to  recognize  both  the  value  and  limitation  of  best  practices  and  urges  for 
experiments, interaction and communication, diversity and dissent. 

Together, by combining Flybjerg´s approach and the Cynefin lens, we may ensure better 
decisions and estimates in the long run. 

Shenhar and Dvir´s dimensions of project success provide useful method of assessing 
projects, project management success and business success of projects. The assessment of 
the Harpa project reveals total failure associated with the project efficiency at the deliverance 
of the building. Despite effective and focused project management in the implementation of 
the building it suffered overruns both in time and budget, but the impact on the customer 
seems to be a success. This approach should never be ignored in the initiative and planning 
phases of new projects. 

The  usefulness  of  the  Diamond  concept  is  more  controversial.  Despite  its  utility 
identifying key dimensions of projects, the universality somewhat prevents the applicability 
on construction projects in line with concert halls and operas. The scale is so vast that even 
project of significant novelty and technical complexity intend to score low on the Diamond 
scale so they appear simpler than they actually are, seen from inside the respective project. It 
is understandable when comparing them to totally different breakthrough and super high‐

39 
tech  projects,  but  it  leaves  us  with  too  little  difference  to  distinguish  between  projects  of 
similar character. The same applies for the calculation of the Risk factor as represented by 
Shenhar and Dvir, an interesting, and useful way of assessing risk in some types of projects. 
The formula gives a highest risk score of 3,3 and the lowest risk score of 1, with Harpa scoring 
2,2 according to the assessment of the author of this paper. This does not make much sense 
in itself, as the upper and lower limits of the scale is so narrow, and the levels of each axis to 
few. This indicates that the scale and levels of the Diamond concept is more useful comparing 
different kind of projects rather than project of similar kind.  

The findings of this study suggest a useful conceptual framework for assessing concert 
halls  and  opera  projects,  and  demonstrates  how  the  Harpa  project  is  arranged  within  the 
framework.  

See the table (Framework) on the following page.   

40 
Attributes  Parameter  Harpa – Concert and Conference Hall, Iceland
General  Scope of project Concert Hall and Conference Centre 
Justification  Annual EBIDTA over Zero / Flourishing music 
scene / Poor existing facilities/ Lacking 
Planning, Design and Construction attributes 

residence for ISO / Other art forms have better 
conditions / Not in line with other countries 
and similar sized communities 
Time span of the  Antecedent period 1983‐1995 (13 years) 
project  Planning period  1996‐2004 (9 years) 
Design and construction period  2005‐2011 (6,7 years) 
Years under construction  4,8 
Excelled construction time according to plan  23 months 
Building Metrics   Total Area (sqm) 29.865
Increase of area from forecast (%)  29,8%, *(70,7%) 
Volume/Area, Ratio  8,34 
Auditoriums / Total Area, Ratio  0,15 
Construction   **Building costs without VAT (MUSD) 226,0
cost figures  Increase from forecast (%)  17,7%, *(77,8%) 
**Building cost pr. sqm (USD)   7.568 
**Building cost pr. m3 (USD)  908 
Increase of sqm‐cost from forecast (%)  ‐9,3%, *(8,0%) 
Seat Capacity  Auditorium A (seats) 1630‐1800
Total number of auditoriums  4 
Total number of auditorium seats  3.355 
Operational attributes 

Annual number of  Number of concerts and opera events (2013) 514


events  Total number of events (2013)  957 
Average (daily) load (%)  65,7% 
Annual number of concert guests (2013)  >325.000 
Annual number of guests (2013)  >1.300.000 
***Operating figures  EBIDTA (MUSD) (2013) ‐4,7
Operational cost pr. sqm (USD) (2013)  419 
Annual property tax (MUSD)  3,2 
Operational  Number of personnel  64,5
personnel   Sqm. pr. staff member  463 
****Fulfillment of   General  0,87
Context and 
Features 

Feature Objectives  Location  0,66 


(based on survey)  Buildings (Acoustics)  0,79 
Operation  0,77 
Cultural importance  0,74 
Project management  Internal quality management and control  ISO 9001
Management 

data  Number of certified Project managers (IPMA, PMI)  1 (IPMA B) 


Project 

Number of work tasks (WBS)  >5.000 
Registered official inspections / audits  1.640 
Number of drawings  Total number of drawings (excl. shop dwg´s) >20.000
Number of drawings pr. sqm.  0,67 
Flyvbjerg´s 7 planning  Planning horizons and interfaces? Long planning horizons and complex interfaces
problems causes  Technology?  Partly non‐standard technology 
Decision process, actors and interests?  Many actors and conflicting interests 
Project scope and ambition?  Changing scope & ambition level over time 
Specific assessment tools 

Budget contingencies?  (No) Inadequate budget contingencies 
Misinformation about cost, benefits & risks?  Consequent misinformation 
Possible overruns and/or benefit shortfalls?  Factual overruns and benefit shortfall 
# Project success  Project efficiency 1
factors  Impact on Customer  4 
Impact on Team  Not explored (No information) 
Business & direct success  2 
Preparation for future  4 
Diamond assessment ‐  Novelty  Platform
NTCP  Technology  Medium‐tech / (High‐tech) 
Complexity  System / (Array) 
Pace  Fast/Competitive  / (Time critical) 
## Risk  2,2 / (2,2) 

*   Increase compared to Descriptive Document no. 13571 for PFI Works Concession, 2004/2005;    **   Exchange rate USD 31.12.2011 =122,25;   


***  Exchange rate USD 30.04.2014 =112,2;    ****  The percentage of those who agree or strongly agree; 
#    Project success scale: 1 = Total failure, 2 = Mostly failure, 3 = 50/50 Failure/success, 4 = Mostly success, 5 = Total success; 
##    Risk = 0,2xN+0,15xT+0,5xC+0,15xP = 0,2*2+0,15*1+0,5*3+0,15*1 = 2,2 

Table 9: The conceptual framework, and arrangement of Harpa within the framework. 

41 
6.  CONCLUSIONS 

The  study  reveals  a  definition  and  structure  of  a  conceptual  framework,  providing  a 
method, an assessment tool, to evaluate success of concert halls and opera projects.  

The  assessment  tool  sheds  light,  both  on  the  failure  and  the  success  of  Harpa.  The 
failures, mainly rooted in the strategic decisions taken in the eight yearlong planning phase, 
and  success  rooted  in  the  efficient  project  management  of  the  contractor,  the  project 
outcome and positive influence within the community.  

The  combined  use  of  Flyvbjerg’s  and  Snowden´s  lenses  reveals  the  weakness  of  the 
decision making, due to possible entrained thinking and the desire to simplify complexity.  

Shenhar  and  Dvir´s  dimensions  of  project  success  helps  identifying  both  the  failing 
project  efficiency  and  lack  of  business  success,  as  well  as  the  success  due  to  the  positive 
impact on customer and preparation for the future. The Diamond concept provides a useful 
method identifying dimensions of projects, but needs a specific adaption to concert halls and 
opera projects, especially for assessment of risk.  

The study of the fulfilment of feature objectives through a survey provides important 
information,  that  helps  assessing  the  project  success  and  the  project  outcome,  and  the 
gathering of metric information revealed important attributes specific for concert halls. 

The study indicates that the method can be used to evaluate success of other Concert 
halls  and  Opera  projects.  It  can  help  describing  the  internal  development  of  a  project  and 
compare  the  project´s  different  stages.  It  can  help  make  sense  of  a  finished  project  in 
retrospect. It can help comparing different projects, and finally it provides basic information 
for defining a benchmark for new projects. As such the framework can provide to be a useful 
tool in the initiating and planning phase of new concert halls and opera projects.  

7. LIMITATIONS AND FURTHER WORK 

The author of this paper considers it appropriate to draw attention to the following: The 
author is a practising architect. His firm participated in the Harpa project and therefor the 
inferences drawn from the study may be coloured by the involvement and closeness to the 
project.  It  should  be  considered  that  the  questionnaire  is  composed  by  the  surveyor,  and 

42 
presented  as  statements  as  if  the  objectives  had  been  met.  This  may  have  coloured  the 
responses. 

Studying specific cases in retrospect have certain limitations due to the fact that only a 
part of the background data is accessible and open to public. This limits the big picture of the 
of the strategic decision process and may bias the conclusion. New information may lead to 
further studies.  

The results of the questionnaire survey has only partially been discussed in this paper 
and need further analyses. 

As the strategic decisions, that have the biggest influence on the project efficiency, are 
taken  in  the  planning  phase  of  projects,  further  studies  might  help  to  a  provide  a  better 
understanding  of  the  decision  making  process  and  suggest  methods  for  improvements. 
Combing  the  lenses  of  Flyvbjerg  and  Snowden,  with  regard  to  the  diamond  framework  of 
Shenhar and Dvir can point the way to an improved assessment tool. 

8. ACKNOWLEDGEMENT 

The author gratefully acknowledges the guidance and support of Dr. Helgi Thor Ingason, 
associate professor at Reykjavík University in Iceland as a supervisor for this thesis. The author 
also thanks Helgi Thor and Michael Young for proposing an idea that led to the research. The 
research would not have been able, if not for the tolerance and support from my partners in 
Batteriid  architects,  especially  Sigurður  Einarsson,  the  responsible  architect  for  Harpa, 
Sigurður Harðarson architect, for reading over and making suggestions for improvements as 
well  as  Guðmundur  Osvaldsson  for  his  suggestions  for  improvements.  Thanks  to  my  good 
colleague, Halldor Eiriksson, architect and lecturer at Iceland Academy of the Arts, for his good 
advices,  for  reading  and  correcting.  The  author  would  also  thank  Sigurður  R.  Ragnarsson, 
programme manager and Dr. Ríkharður Kristánsson, design manager for the Harpa project, 
for their consulting interviews that provided a deeper understanding of the subject. Thanks to 
Halldór Guðmundsson, director of Harpa for important and useful information. Thanks to all 
the  248  respondents  that  offered  time  answering  the  questionnaire  survey.  Finally  I  am 
grateful  to  Anna,  my  wife  and  lifelong  partner  for  her  continuous  support,  tolerance  and 
guidance. 

   

43 
9. REFERENCES 

Austurhöfn‐TR  ehf.  (2003).  Information  Memorandum,  Proposed  concert  hall,  conference 


centre and hotel complex Reykjavik. Memorandum, The Government of Iceland and 
the City of Reykjavik, Reykjavik. 

Austurhöfn‐TR;  Ríkiskaup;  VST;  Landwell.  (January  2005).  The  Icelandic  National  Concert  & 
Conference Centre in Reykjavík‐PFI Works Concession Contract. Reykjavík: Ríkiskaup. 

CNN Staff. (2014, 03 03). CNN Style; World's 15 most beautiful concert halls. Retrieved 03 04, 
2014,  from  CNN:  http://edition.cnn.com/2014/03/02/travel/beautiful‐concert‐
halls/index.html?hpt=hp_mid 

Einarsson, S. (2014, 04 23). About Harpa ‐ development of project, cost and scope. 

Emporsis. (2014, February 06). Emporsis/Press Releases 2014/Music to the Eyes: The World's 
Most  Spectacular  Concert  Halls  .  Retrieved  Match  04,  2014,  from  Emporsis: 
http://www.emporis.com/pdf/Pressrelease_20140206_ENG.pdf 

Emporsis.  (n.d.).  Emporsis  Standards.  Retrieved  March  04,  2014,  from  Emporsis: 
http://www.emporis.com/building/standards/ 

Emporsis. (n.d.). The most expensive buildings in the world. Retrieved March 04, 2014, from 
Emporsis: http://www.emporis.com/statistics/most‐expensive‐buildings 

Flyvbjerg, B. (2007). Policy and planning for large‐infrastructure projects: problems, causes, 
cures. Planing and Design, 34, 578‐597. 

Fundació  Mies  van  der  Rohe.  (2013,  June  06). 


http://www.miesarch.com/images/stories/3PressReleaseENG.pdf.  Retrieved  March 
04,  2014,  from  Mies  Arch  European  Union  Prize  2013  Web  site: 
http://www.miesarch.com/index.php?option=com_content&view=article&id=7&Ite
mid=4&lang=en 

Guðmundsson,  H.  (2014,  04  28).  Re:  Til  upplýsingar  og  ósk  um  upplýsingar  vegna 
meistaraverkefnis  Jóns  Ólafs  í  MPM  við  HR.  Email  communication  with  attached 
document. 


Harold Kerzner, P. (2009). Project Management, A System Approach to Planning, Scheduling 
and Controlling (Tenth Edition ed.). Hoboken, New jersy, USA: John Wiey & Sons Inc.,. 

Harpa, tónlistar‐ og ráðstefnuhús ohf. (2013, 04 29). Ársreikningur samstæðu 2012 (Annual 
finanical  statement  2012),  23.  (V.  R.  Gíslason,  Ed.)  Reykjavík,  Iceland: 
Pricewaterhousecoopers ehf. 

Harpa, tónlistar‐ og ráðstefnuhús ohf. (2014, 04 25). Ársreikningur samstæðu 2013 (Annual 
financial  statement  2013),  20.  (V.  R.  Gíslason,  Ed.)  Reykjavík,  Iceland: 
Pricewaterhousecoopers ehf. 

IAV.  (2013).  Harpa  ‐  We  built  Harpa  (1st  ed.).  (R.  Kristjánsson,  S.  R.  Ragnarsson,  G.  B. 
Hólmsteinsson, Eds., & Ó. Eldjárn, Trans.) Reykjavík, Iceland: IAV. 

Iceland  Symphony  Orchestra.  (2014,  January  06).  Retrieved  March  04,  2014,  from 
http://en.wikipedia.org/wiki/Iceland_Symphony_Orchestra 

IPMA. (2006). ICB ‐ IPMA Competence Baseline Vesion 3.0 (ICB Version 3.0, June 2006 ed.). (G. 
Caupin,  H.  Knoepfel,  G.  Koch,  K.  Pannenbäcker,  F.  Pérez‐Polo,  &  C.  Seabury,  Eds.) 
Nijkerk, The Netherlands: International Project Management Association. 

Jónsdóttir,  B.  (2003,  09  23).  Sér  fyrir  endann  á  aldargömlum  hugmyndum.  (Morgunblaðið) 
Retrieved  04  28,  2014,  from  Morgunblaðið: 
http://www.mbl.is/frettir/innlent/2005/09/23/ser_fyrir_endann_a_aldargomlum_hu
gmyndum/ 

Judgev, K., & Müller, R. (2005, December). A Retrospective look at our evolving understanding 
of Project success. Project Management Journal, 36(4), 19‐31. 

Kristjánsson, R. (2014, 04 25). About the Harpa project. (J. Ó. Ólafsson, Interviewer) 

Morgunblaðið. (2005, 09 21). Portus Group með vænlegasta tilboðið í tónlistarhús. Retrieved 
05  07,  2014,  from  Morgunblaðið: 
http://www.mbl.is/frettir/innlent/2005/09/21/portus_group_med_vaenlegasta_tilbo
did_i_tonlistarhu/ 

Morgunblaðið. (2006, 03 09). Skrifað undir samninga við Portus‐hópinn um tónlistarhús. (s. a. 
Netúgáfa fréttar, Editor, & Morgunblaðið) Retrieved 04 28, 2014, from Morgunblaðið: 

ii 
http://www.mbl.is/frettir/innlent/2006/03/09/skrifad_undir_samninga_vid_portus_
hopinn_um_tonlist/ 

Munns, A. K., & Bjeirmi, B. F. (1996, April). The role of project management in achieving project 
success . International Journal of Project Management, 14(2), 81‐87. 

Nefnd  um  málefni  tónlistarhús.  (1997).  Álitsgerð  nefndar  um  tónlistarhús.  Ministry  of 
Education in Iceland. Ministry of Education in Iceland. 

Nilsen,  M.  (2013,  12  11).  The  Cynefin  framework.  Retrieved  04  22,  2014,  from 
http://www.scrumsense.com: http://www.scrumsense.com/blog/cynefin‐framework 

Project  Management  Institute.  (2012).  Project  Management  Body  of  Knowledge  (PMBOK 
Guide) (Fifth Edition ed.). Nwwtown Square, Pennsylvania, USA: Project Management 
Institute. Inc. 

Project  Mangement  Institute.  (2012).  Project  Management  Body  of  Knowledge  (PMBOK 
Guide) (Fifth Edition ed.). Newtown Square, Pennsylvania, USA: Project Mangement 
Institute. Inc. 

Ragnarsson, S. R. (2014, 04 10). About the Harpa project. (J. Ó. Ólafsson, Interviewer) 

Reykjavíkurborg og íslenska ríkið. (2002, 04 11). Samkomulag um byggingu tónlistarhúss og 
ráðstefnumiðstöðvar í Reykjavík. Reykjavík, Iceland. 

Samtök um  tónlistarhús. (n.d.). Samtök um tónlistarhús 1983‐2002. Retrieved 02 04, 2014, 
from Samtök um tónlistarhús: http://www.fih.is/sut/sagasut/sagasut.html 

Shenar,  A.  J.,  Dvir,  D.,  Levy,  O.,  &  Maltz,  A.  C.  (2001,  December  6).  Project  Success:  A 
Multidimensional Strategic Concept. Long Range Planning, 34(6), 699‐725. 

Shenhar, A. J., & Dvir, D. (2007). Reinventing Project Management: the diamond approach to 
successful  growth  and  innovation.  Boston,  Massachusetts,  USA:  Harvard  Business 
School Publishing. 

Smith,  A.,  &  von  Krogh  Strand,  I.  (2011,  1).  Oslo's  new  Opera  House:  Cultural  flagship, 
regeneration tool or destination icon? Eropean Urban and Regional Studies, 18(1), 93‐
110. 

iii 
Snowden, D. J., & Boone, M. E. (2007, November). A Leader´s Framework for Decision Making. 
Harvard Business Review. 

The  Cognitive  Edge  Network.  (n.d.).  Cognitive  Edge  Network.  Retrieved  03  04,  2014,  from 
Cognitive Edge Network: http://cognitive‐edge.com/library/methods/ 

VSÓ  Ráðgjöf.  (1998).  Tónlistarhús  og  ráðstefnumiðstöð,  Nýtingar  og  hagkvæmismat. 


Feasability  study  and  cost  estimation,  Stýrihópur  um  tónlistar‐  og  ráðstefnuhús, 
Reykjavík. 

Wikipedia. (2014, March 04). Retrieved March 05, 014, from Wikipedia: List of concert halls: 
http://en.wikipedia.org/wiki/List_of_concert_halls 

iv 

You might also like